Loading...
HomeMy WebLinkAboutItem 08 Consideration of Charge Order #3 with Master Site Development, Inc. for the Ocoee Crown Point PUD Phase I Infrastructure Project A tex of Good Z, AGENDA ITEM COVER SHEET Meeting Date: June 21, 2005 Item # 8 Reviewed By: Contact Name: David Wheeler Department Director: Contact Number: 407-905-3100 ext 1504 City Manager: Subject: Change Order No. 3 with Master Site Development, Inc. for the Ocoee Crown Point PUD Phase 1 Infrastructure Project Background Summary: The project as bid did not include a electrical service drop to provide power to the irrigation system and the fountain, irrigation on the high school side of Ocoee Crown Point Parkway, nor maintenance of the landscaping until the project is accepted by the City. These items are necessary to provide a complete project that meets the expectations of the City. Details of the • proposed changes are included in the attached copy of the Change Order No. 3. The amount of the change order is an increase of$78,063.00, with an increase in contract time of 14 days. Issue: The Engineering Department has proposed a change to the Ocoee Crown Point PUD Phase 1 Infrastructure project and requests the City Commission approve Change Order No. 3 with Master Site Development, Inc. in the amount of an increase of $78,063.00, with an increase of 14 days in contract time. Recommendations The Engineering Department recommends that the City Commission approve Change Order No. 3 for the additional work and increase the construction contract by $78,063.00, with an increase of 14 days in contract time, and authorize the Mayor and City Clerk to execute the change order. Attachments: 1) Change Order No. 3 between the City of Ocoee and Master Site Development, Inc. Financial Impact: This change order will be funded by the City of Ocoee from the Ocoee Crown Point PUD project fund. According to the agreement with the Orange County Public Schools they are not participating in the landscape/hardscape cost in the overall project. Type of Item: ❑ Public Hearing For Clerk's Dept Use: ❑ Ordinance First Reading ❑ Consent Agenda O Ordinance First Reading ❑ Public Hearing ❑ Resolution ❑ Regular Agenda ® Commission Approval ❑ Original Document/Contract Attached for Execution by City Clerk ® Original Document/Contract Held by Department for Execution Reviewed by City Attorney ® N/A Reviewed by Finance Dept. //1‘1.50 — ❑ N/A Reviewed by ( ) ❑ N/A Mayor „s:tveCeitet of Good L1 Commissioners S. Scott Vandergrift 4, Danny Howell, District 1 Scott Anderson, District 2 City Manager Rusty Johnson, District 3 Robert Frank Nancy J. Parker, District 4 STAFF REPORT TO: The Honorable Mayor and City Commissioners FROM: David A. Wheeler, P.E., City Engineer DATE: June 10, 2005 RE: Approval of Change Order No. 3 With Master Site Development, Inc. For Ocoee Crown Point PUD Phase 1 Infrastructure Project ISSUE The Engineering/Public Utilities Department requests that the City Commission approve Change Order No. 3 with Master Site Development, Inc. on the Ocoee Crown Point PUD Infrastructure Project for the installation an electrical drop to provide power to the irrigation system and the fountain, installation of irrigation around pond 8 and on the high school side of Ocoee Crown Point Parkway, and for the maintenance of the landscaping until the project is accepted by the City in the amount of an increase of$78,063.00, with an increase of 14 days in contract time. BACKGROUND/DISCUSSION The Ocoee Crown Point PUD Phase 1 Infrastructure project will install the roadway and utilities for the first phase of the development. That first phase is for the new Ocoee High School. The water main extension into the Ocoee Crown Point PUD development was to connect to the water main installed for the Westyn Bay development. The water main from Ocoee-Apopka Road to Westyn Bay Boulevard was constructed as a 20- inch diameter pipeline and the pipeline that turned into the Westyn Bay development was a 12-inch pipeline. Based upon a review of the plans it was assumed that the pipeline across Westyn Bay Boulevard was a 20-inch pipeline; the drawings did not label this pipeline, they only showed the pipeline to be constructed. The original bid for the phase 1 infrastructure did not include a design or bid item for the electrical service for the irrigation system and fountain. The service drop could not be tied into the lift station electrical service because the lift station is operated by Orange County Utilities. The new service drop was placed near the lift station so that the landscaping could be used as a screen for the transformer and control boxes. The original bid did not show landscaping and irrigation on the high school side of the road because it was envisioned that the Orange County Public Schools would be including that area in there landscaping and irrigation plan. This was an incorrect assumption. Therefore, the City needed to add in as a minimum, irrigation for the sod within the road right-of-way and to size it appropriately if the City decided to install other landscaping after the school is completed and/or when future phases of the development come along. The original bid had line items for furnishing and installing the landscaping but there was no mention of maintenance of the landscaping until the entire project is accepted by the City. It would not be a good idea to have the City start tiittintaining the landscaping until the contractual obligations for the entire project have been met. The total cost for these three items is $78,063.00 with an increase in contract time of fourteen days. The change order is attached for review. �8ce center of Good Lip CITY OF OCOEE Engineering/Utilities 150 North Lakeshore Drive Ocoee, Florida 34761-2258 CHANGE ORDER NO. #3 CITY OF OCOEE Ocoee Crown Point PUD—Phase 1 Infrastructure DATE: June 6,2005 CONTRACTOR:Master Site Development,Inc. AGREEMENT DATE:March 2,2004 The following changes are hereby made to the CONTRACT DOCUMENTS. Original CONTRACT PRICE $2,496,811.50 Current CONTRACT PRICE ADJUSTED by previous CHANGE ORDER $2,612,354.50 Net Increase Resulting from this CHANGE ORDER $ 78,063.00 The current CONTRACT PRICE including this CHANGE ORDER $2,690,417.50 ORIGINAL CONTRACT TIME: 420 Consecutive Calendar Days from Notice to Proceed Date: May 16,2005 Current CONTRACT TIME adjusted by previous CHANGE ORDERS Date: May 16,2005 Net Increase Resulting from this CHANGE ORDER Days: 14 Days Current CONTRACT TIME Including this CHANGE ORDER Date: June 14,2005 00842-1 CHANGES ORDERED: I. GENERAL This change order is issued pursuant to the applicable provisions of the Contract Documents and is intended to provide an equitable adjustment in the Contract Sum to accommodate an unprecedented market condition. II. REQUIRED CHANGES Item A: Provide and electrical service for the fountain and the irrigation controller. Item B: Provide irrigation for the school side of Ocoee Crown Point Parkway including road crossings. Item C: Provide maintenance of the landscaping after installation up to acceptance of the project. III. JUSTIFICATION Item A: The project plans and specifications did not include a design for the electrical service drop for the irrigation controls and the fountain. Item B: It as envisioned that the high school project would include landscaping and irrigation along their side of Ocoee Crown Point Parkway. The high school plans did not address landscaping or irrigation off-site. Therefore provisions needed to be made to sod and irrigate the high school side of the road right-of-way. Item C: The project plans and specifications did not include maintenance of the landscaping until the project was accepted by the City IV. NARRATIVE OF NEGOTIATIONS All three items were negotiated based upon required work,materials,equipment,and manpower needed. Based upon the estimated scope,the work was reduced to provide only the minimum required. V. PAYMENT Change Order Description Net Increase Unit Unit Price Net Increase Item No. (Decrease)Quantity (Decrease)Price Item A Install electrical service drop for irrigation LS 10,911.30 controller and fountain Install irrigation on the high school side of Item B Ocoee Crown Point Parkway including road LS crossings 58,315.95 Provide maintenance of landscaping to Item C project completion LS 8,835.75 Total Net Increase Change Order No. #2 $78,063.00 00842-2 VI.APPROVAL AND CHANGE AUTHORIZATION This proposed change to the Contract is to be approved by the Ocoee City Commission. Acknowledgements: The aforementioned change,and work affected thereby,is subject to all provisions of the original contract not specifically changed by this Change Order;and, It is expressly understood and agreed that the approval of the Change Order shall have no effect on the original contract other than matters expressly provided herein. CONTRACTOR acknowledges, by its execution and acceptance of this Change Order, that the adjustments in Contract Price and Time shown hereon constitute full and complete compensation and satisfaction for all costs and modifications of performance time incurred by the CONTRACTOR as a result of this Change Order and/or relating to or arising out of the reasons and justifications for this Change Order.. No other claim for increased costs of performance or modifications of time will be granted by the OWNER for the Work covered by this Change Order. Nothing contained in this action by the City shall be deemed to constitute a waiver or an estoppel to assert its rights or remedies under the Contract Documents nor shall it be deemed to set a precedent for an equitable adjustment for any other materials required by the Work. The CONTRACTOR hereby waives and releases any further claims for cost or time against the OWNER arising from or relating to the matters or Work set forth or contemplated by this Change Order and/or relating to or arising out of the reasons and justifications for this Change Order. RECOMMENDED BY: ACCEPTED BY: CITY OF OCOEE,FLORIDA MASTER SITE DEVELOPMENT,INC. By: By: Signature Signature Date: Date: Title: Title: APPROVED BY: CITY OF OCOEE,FLORIDA By: S. Scott Vandergrift,Mayor Date Attest: Beth Eikenberry,City Clerk FOR USE AND RELIANCE ONLY BY THE APPROVED BY THE OCOEE CITY CITY OF OCOEE,APPROVED AS TO FORM COMMISSION IN A MEETING HELD ON AND LEGALITY THIS DAY OF ,2005 UNDER ,2005. AGENDA ITEM NO. FOLEY&LARDNER By: City Attorney 00842-3 CITY OF OCOEE REQUEST FOR PROPOSAL Engineering Department FOR PROPOSED CHANGE 150 North Lakeshore Drive (407)905-3100 ext. 1505 (RFP) Ocoee, Florida 34761-2258 (407)656-7835 -fax NO. THREE PROJECT DATA: NAME: Ocoee Crown Point PUD—Phase 1 Infrastructure Proiect PROJECT NO: LOCATION: On Ocoee Crown Point Parkway at the Lift Station DATE: April 11 2005 OTHER: REFERENCE: TO(CONTRACTOR): Master Site Development,Inc. Please provide the undersigned a proposal for the following change in the work within seven(7)calendar days after receipt of this request. The written proposal must clearly delineate the scope of the proposed change in the work providing an itemized estimate of the time and all material and labor(by trade),subcontract and overhead costs and fees. Any amount claimed for subcontracts must be similarly supported. DESCRIPTION of change in work: Install electrical service for the fountain and the irrigation system for the landscaping in the road right-of-way The electrical service will be located at 1960 Ocoee Crown Point Parkway,with the physical location to be at the northwest corner of lift station tract. Change Order Type: d Deletion d Addition d Revision d Other:( Constraints of Change: Initiated by: d Changes in Owner Requirements d Unforeseen Conditions d Others:( ) Proposal must be received by: ATTACHMENTS(Listing of attached documents that support description): 1. Contractor Request for Information No. 4. 2. Plan Revisions: 5. 3. 6. d OWNER: David Wheeler,Ocoee d CONTRACTOR: Curt Noblitt, Master Site d ENGINEER: Joe Kolb,VHB, Inc. d FIELD: Otis Patton,Ocoee d CONSTRUCTION ADMINISTRATOR: d OTHER: d SUBCONSULTANT: Date Received From Contractor: Date Returned to Contractor With Comments: Date Returned to City: 00847-1 PRICING INFORMATION: Method of Pricing: A. d Established Contract Unit Price(s) B. d Negotiated Unit Price(s)(including Overhead and Profit) C. d Negotiated Lump Sum(including Overhead and Profit) D. d Actual Cost of Work plus Fixed Percent for Overhead and Profit E. d A combination of A,B,C, D DESCRIPTION OF WORK: d By General Contractor d By Subcontractor ITEM OF WORK QUANTITY PRICE TOTAL Attach additional pages if necessary. NET TOTAL COST OF THIS CHANGE PROPOSAL $ EXTENSION OF CONTRACT TIME: As part of this Change Proposal the Contractor requests an extension of the contract time in the amount of SEVEN additional days. Provide thorough documentation in support of the request for additional time: Additional Time Required for permitting and Progress Energy,Inc. A requirement of this Change Proposal will be to provide record drawing information for all of the affected items of work RECOMMENDATION BY ENGINEER/CONSTRUCTION ADMINISTRATOR: Comments: Signature of Engineer/Construction Administrator: Date: ACCEPTANCE BY OWNER: Comments: Signature: Date: 1 ,of agree to the costs and terms of RFP (Name) (Company) (No.) this day of ,199 . (day) (month) (year) 00847-2 CITY OF OCOEE REQUEST FOR PROPOSAL Engineering Department FOR PROPOSED CHANGE 150 North Lakeshore Drive (407)905-3100 ext. 1505 (RFP) Ocoee, Florida 34761-2258 (407)656-7835-fax NO. FOUR PROJECT DATA: NAME: Ocoee Crown Point PUD—Phase 1 Infrastructure Project PROJECT NO: LOCATION: On Ocoee Crown Point Parkway DATE: April 11 2005 OTHER: REFERENCE: TO(CONTRACTOR): Master Site Development, Inc. Please provide the undersigned a proposal for the following change in the work within seven(7)calendar days after receipt of this request. The written proposal must clearly delineate the scope of the proposed change in the work providing an itemized estimate of the time and all material and labor(by trade),subcontract and overhead costs and fees. Any amount claimed for subcontracts must be similarly supported. DESCRIPTION of change in work: Install additional irrigation to cover areas not shown on the original drawings. The two areas not shown on the original drawing were the backside of pond 8 and the high school side of Ocoee Crown Point Parkway within the road right-of-way. Work will also include the crossing of Ocoee Crown Point Parkway. Change Order Type: d Deletion d Addition d Revision d Other: ( Constraints of Change: Initiated by: d Changes in Owner Requirements d Unforeseen Conditions d Others:( ) Proposal must be received by: ATTACHMENTS(Listing of attached documents that support description): 1. Contractor Request for Information No. 4. 2. Plan Revisions: 5. 3. 6. d OWNER: David Wheeler,Ocoee d CONTRACTOR: Curt Noblitt,Master Site d ENGINEER: Joe Kolb,VHB,Inc. d FIELD: Otis Patton,Ocoee d CONSTRUCTION ADMINISTRATOR: d OTHER: d SUBCONSULTANT: Date Received From Contractor: Date Returned to Contractor With Comments: Date Returned to City: 00847-1 PRICING INFORMATION: Method of Pricing: A. d Established Contract Unit Price(s) B. d Negotiated Unit Price(s)(including Overhead and Profit) C. d Negotiated Lump Sum(including Overhead and Profit) D. d Actual Cost of Work plus Fixed Percent for Overhead and Profit E. d A combination of A,B,C,D DESCRIPTION OF WORK: d By General Contractor d By Subcontractor ITEM OF WORK QUANTITY PRICE TOTAL Attach additional pages if necessary. NET TOTAL COST OF THIS CHANGE PROPOSAL $ EXTENSION OF CONTRACT TIME: As part of this Change Proposal the Contractor requests an extension of the contract time in the amount of Fourteen additional days. Provide thorough documentation in support of the request for additional time: Additional Time Required for design and permitting. A requirement of this Change Proposal will be to provide record drawing information for all of the affected items of work RECOMMENDATION BY ENGINEER/CONSTRUCTION ADMINISTRATOR: Comments: Signature of Engineer/Construction Administrator: Date: ACCEPTANCE BY OWNER: Comments: Signature: Date: I ,of agree to the costs and terms of RFP (Name) (Company) (No-) this day of ,199 . (day) (month) (year) 00847-2 CITY OF OCOEE REQUEST FOR PROPOSAL Engineering Department FOR PROPOSED CHANGE 150 North Lakeshore Drive (407)905-3100 ext. 1505 (RFP) Ocoee, Florida 34761-2258 (407)656-7835 -fax NO. FIVE PROJECT DATA: NAME: Ocoee Crown Point PUD—Phase 1 Infrastructure Project PROJECT NO: LOCATION: On Ocoee Crown Point Parkway DATE: May 11 2005 OTHER: REFERENCE:_ TO(CONTRACTOR): Master Site Development, Inc. Please provide the undersigned a proposal for the following change in the work within seven(7)calendar days after receipt of this request. The written proposal must clearly delineate the scope of the proposed change in the work providing an itemized estimate of the time and all material and labor(by trade),subcontract and overhead costs and fees. Any amount claimed for subcontracts must be similarly supported. DESCRIPTION of change in work: Maintenance of landscaping from the time of installation to acceptance of the proiect Change Order Type: d Deletion d Addition d Revision d Other:( Constraints of Change: Initiated by: d Changes in Owner Requirements d Unforeseen Conditions d Others:( ) Proposal must be received by: ATTACHMENTS(Listing of attached documents that support description): 1. Contractor Request for Information No. 4. 2. Plan Revisions: 5. 3. 6. d OWNER: David Wheeler,Ocoee d CONTRACTOR: Curt Noblitt,Master Site 4 ENGINEER: Joe Kolb,VHB,Inc. 4 FIELD: Otis Patton,Ocoee 4 CONSTRUCTION ADMINISTRATOR: 4 OTHER: 4 SUBCONSULTANT: Date Received From Contractor: Date Returned to Contractor With Comments: Date Returned to City: 00847-1 PRICING INFORMATION: Method of Pricing: A. 4 Established Contract Unit Price(s) B. 4 Negotiated Unit Price(s)(including Overhead and Profit) C. 4 Negotiated Lump Sum(including Overhead and Profit) D. d Actual Cost of Work plus Fixed Percent for Overhead and Profit E. 4 A combination of A, B,C,D DESCRIPTION OF WORK: 4 By General Contractor 4 By Subcontractor ITEM OF WORK QUANTITY PRICE TOTAL Attach additional pages if necessary. NET TOTAL COST OF THIS CHANGE PROPOSAL $ EXTENSION OF CONTRACT TIME: As part of this Change Proposal the Contractor requests an extension of the contract time in the amount of Fourteen additional days. Provide thorough documentation in support of the request for additional time: Additional Time Required for design and permitting. A requirement of this Change Proposal will be to provide record drawing information for all of the affected items of work RECOMMENDATION BY ENGINEER/CONSTRUCTION ADMINISTRATOR: Comments: Signature of Engineer/Construction Administrator: Date: ACCEPTANCE BY OWNER: Comments: Signature: Date: I ,of agree to the costs and terms of RFP (Name) (Company) (No.) this day of ,199 . (day) (month) (year) 00847-2 06/08/2005 13:43 4078910575 MASTER PAGE 03 MASTER S TIE D EVJ LOPMENT, I NC 1203 Florida Avcnac•Wirt Cloud.Florida 34749 •(407)891-0700 • (407)891-0575—Fax Request For Change Order To: City Of Ocoee Project: Crown Point PUD Phase I Attention: Dave Wheeler Date: 9-Feb-05 Re•uest No. 3 REV Phone: 407-905-3100 Fax: Comments: Description Quantity Unit Unit Total Price 1 Electric Service To Fountain:(1) 100 amp 3 Phase 480 Volt 1 Ea $ 9,262.00 $ 9,262.00 On Concrete Post With 45 KVA Pad-Mounted Transformer For(1)7 1/2 HP Floating Fountain Pump w/(2)2"PVC Empty Conduits Extended 20'Into Pond w/Pull Strings. 2 Additional Irrigation Around Pond#8 And Along South Side 1 Pa $ 49,500.00 $ 49,500.00 Of Crown Pointe Parkway Including Directional Bores And All Additional Slaves 3 Landscape Maintenance 3 Ea $ 2,500.00 $ 7,500.00 Administration Estimator Hr $ 50.00 $ Subtotal $ 66,262.00 Overhead 10% $ 6,626.20 Subtotal $ 72,888.20 Profit 5% $ 3,644.41 Subtotal $ 76,532.61 Bond 2% $ 1,530.39 Total $ 78,063.00 Note: This Additional Scope Of Work Will Add 14 Calender Days To The Contract Authorized Signature: 06/08/2005 15:22 4078910575 MASTER PAGE 02 MASTER SITE DEVELOPMENT, INC. L r 1203 Florida Avenue *St Cloud,FL 34769 407491-0700(Office) *407-891-0575(Fax) June 8,2005 David Wheeler City Of Ocoee 150 North Lakeshore Dr. Ocoee,FL 34761 Re: Ocoee Crown Point COR#3 David, The original scope of work involving Crown Point Parkway on the bid set of drawings designated the irrigation only to be installed in an area on one side of the highway. During construction of the project,we noticed new trees,shrubs, and landscaping were being installed on the opposite side of the street as well. We sent an RFI to the City of Ocoee concerning this issue and were instructed to meet the requirements of irrigating the new landscape design. We proceeded with the work and submitted for an increase in our contract amount on change order request#3 as "additional irrigation". Sincerely, Curt Noblitt MASTER Site Development, Inc.