Loading...
HomeMy WebLinkAboutItem 06 Consideration of Change Order No. 2 with Master Site Development, Inc. for the Ocoee Crown Point PUD Phase 1 Infrastructure Project Cet►tet of Good j S AGENDA ITEM COVER SHEET Meeting Date: May 3, 2005 Item # �Q Reviewed By: Contact Name: David Wheeler Department Director: • 14 Contact Number: 407-905-3100 ext 1504 City Manager: . ,,P_ ,,, 4,1159 Subject: Change Order No. 2 with Master Site Development, Inc. for the Ocoee Crown Point PUD Phase 1 Infrastructure Project Background Summary: The Ocoee Crown Point PUD Phase 1 Infrastructure project includes the installation of the roadway and utilities for the first phase of the development. The water main extension into the development connects to the water main installed for the Westyn Bay development. When the contractor was installing the new pipeline, it was discovered that the pipeline across the entrance to Westyn Bay was only 12 inches in diameter. Staff and VHB, Inc., the design engineer, determined that the short section of 12-inch pipeline would not allow for meeting fire flow requirements at the new school. Therefore it was determined that the 140 linear feet of 12-inch pipeline needed to be replaced. Details of the proposed changes are included in the attached copy of the Change Order No. 2. The amount of the change order is an increase of $55,360.00, with an increase in contract time of 14 days. Issue: The Engineering/Public Utilities Department has proposed a change to the Ocoee Crown Point PUD Phase 1 Infrastructure project and requests the City Commission approve Change Order No. 2 with Master Site Development, Inc. in the amount of an increase of $55,360.00, with an increase of 14 days in contract time. Recommendations The Engineering/Public Utilities Department recommends that the City Commission approve Change Order No. 2 for the additional work and increase the construction contract by $55,360.00, with an increase of 14 days in contract time, and authorize the Mayor and City Clerk to execute the change order. Attachments: 1) Change Order No. 2 between the City of Ocoee and Master Site Development, Inc. Financial Impact: This change order will be funded in part by the City of Ocoee from the Ocoee Crown Point PUD project fund and Orange County Public Schools in accordance with the agreement between both parties. The Ocoee share is 51.8% or $28,576.48 and the OCPS share is 48.2% or$26,683.52. Type of Item: ❑ Public Hearing For Clerk's Dept Use: ❑ Ordinance First Reading 0 Consent Agenda ❑ Ordinance First Reading 0 Public Hearing ❑ Resolution 0 Regular Agenda ❑ Commission Approval ❑ Discussion &Direction ❑ Original Document/Contract Attached for Execution by City Clerk 0 Original Document/Contract Held by Department for Execution Reviewed by City Attorney ® N/A Reviewed by Finance Dept. „go/ ``„ a "tom ; ❑ N/A Reviewed by ( ) ❑ N/A Mayor centei of Good£j . Commissioners S. Scott Vandergrift Danny Howell, District 1 Scott Anderson, District 2 City Manager Rusty Johnson, District 3 Robert Frank Nancy J. Parker, District 4 STAFF REPORT TO: The Honorable Mayor and City Commissioners FROM: David A. Wheeler, P.E., City Engineer& Director of Public Utilities DATE: April 19, 2005 RE: Approval of Change Order No. 2 With Master Site Development, Inc. For Ocoee Crown Point PUD Phase 1 Infrastructure Project ISSUE The Engineering/Public Utilities Department requests that the City Commission approve Change Order No. 2 with Master Site Development, Inc. on the Ocoee Crown Point PUD Infrastructure Project for the installation of 140 linear feet of 16-inch water main to replace a 12-inch water main in the amount of an increase of $55,360.00, with an increase of 14 days in contract time. BACKGROUND/DISCUSSION The Ocoee Crown Point PUD Phase 1 Infrastructure project will install the roadway and utilities for the first phase of the development. That first phase is for the new Ocoee High School. The water main extension into the Ocoee Crown Point PUD development was to connect to the water main installed for the Westyn Bay development. The water main from Ocoee-Apopka Road to Westyn Bay Boulevard was constructed as a 20- inch diameter pipeline and the pipeline that turned into the Westyn Bay development was a 12-inch pipeline. Based upon a review of the plans it was assumed that the pipeline across Westyn Bay Boulevard was a 20-inch pipeline; the drawings did not label this pipeline, they only showed the pipeline to be constructed. Since this pipeline was in the Orange County Utilities service area, contact was made with OCU and they basically stated that it was a 20-inch diameter pipeline. When the contractor was installing the new pipeline was when it was discovered that the pipeline across the entrance to Westyn Bay was only a 12-inch pipeline. Staff and VHB, Inc., the design engineer, determined that the short section of 12-inch pipeline would not allow for meeting fire flow requirements at the new school. Therefore it was determined that the 140 linear feet of 12-inch pipeline needed to be replaced. Staff and VHB, Inc. determined that using 20-inch diameter pipe would meet fire flow requirements. The installation of the 20-inch pipeline cost $55,360.00 with an increase in contract time of 14 days. The change order is attached for review. Centex of Good Lr°COE v • CITY OF OCOEE Engineering/Utilities 150 North Lakeshore Drive Ocoee, Florida 34761-2258 CHANGE ORDER NO. #2 CITY OF OCOEE Ocoee Crown Point PUD—Phase 1 Infrastructure DATE: April 11,2005 CONTRACTOR: Master Site Development,Inc. AGREEMENT DATE: March 2,2004 The following changes are hereby made to the CONTRACT DOCUMENTS. Original CONTRACT PRICE $2,496,811.50 Current CONTRACT PRICE ADJUSTED by previous CHANGE ORDER $2,556,994.50 Net Increase Resulting from this CHANGE ORDER $55,360.00 The current CONTRACT PRICE including this CHANGE ORDER $2,612,354.50 ORIGINAL CONTRACT TIME: 420 Consecutive Calendar Days from Notice to Proceed Date: May 16,2005 Current CONTRACT TIME adjusted by previous CHANGE ORDERS Date: May 16,2005 Net Increase Resulting from this CHANGE ORDER Days: 14 Days Current CONTRACT TIME Including this CHANGE ORDER Date: May 30,2005 00842-1 CHANGES ORDERED: I. GENERAL This change order is issued pursuant to the applicable provisions of the Contract Documents and is intended to provide an equitable adjustment in the Contract Sum to accommodate an unprecedented market condition. II. REQUIRED CHANGES Item A: To replace the existing 12-inch water main across the entrance to the Westyn Bay subdivision with a 20-inch water main,which is required. III. JUSTIFICATION Item A: The water main installed across Westyn Bay Boulevard as part of the Westyn Bay development was assumed to be a 20-inch pipeline. This information was based upon plan review and discussions with Orange County Utilities, who operates the water main. The water main was installed as a 12-inch diameter pipeline. Because of the fire flow requirements for the new high school the 140 linear feet of 12-inch pipeline needed to be replaced to meet the fire demand. IV. NARRATIVE OF NEGOTIATIONS Item A: Bid amounts were used where applicable and pay items not on the original bid schedule were negotiated. V. PAYMENT Change Order Description Net Increase Unit Unit Price Net Increase Item No. (Decrease)Quantity (Decrease)Price Item A Install 140 LF of 20-inch water main on LS 55,360.00 Ocoee Crown Point Parkway across Westyn Bay Boulevard Total Net Increase Change Order No. #2 $55,360.00 VI. APPROVAL AND CHANGE AUTHORIZATION This proposed change to the Contract is to be approved by the Ocoee City Commission. 00842-2 Acknowledgements: The aforementioned change,and work affected thereby,is subject to all provisions of the original contract not specifically changed by this Change Order;and, It is expressly understood and agreed that the approval of the Change Order shall have no effect on the original contract other than matters expressly provided herein. CONTRACTOR acknowledges, by its execution and acceptance of this Change Order, that the adjustments in Contract Price and Time shown hereon constitute full and complete compensation and satisfaction for all costs and modifications of performance time incurred by the CONTRACTOR as a result of this Change Order and/or relating to or arising out of the reasons and justifications for this Change Order.. No other claim for increased costs of performance or modifications of time will be granted by the OWNER for the Work covered by this Change Order. Nothing contained in this action by the City shall be deemed to constitute a waiver or an estoppel to assert its rights or remedies under the Contract Documents nor shall it be deemed to set a precedent for an equitable adjustment for any other materials required by the Work. The CONTRACTOR hereby waives and releases any further claims for cost or time against the OWNER arising from or relating to the matters or Work set forth or contemplated by this Change Order and/or relating to or arising out of the reasons and justifications for this Change Order. RECOMMENDED BY: ACCEPTED BY: CITY OF OCOEE,FLORIDA MASTER SITE DEVELOPMENT,INC. By: By: Signature Signature Date: Date: Title: Title: APPROVED BY: CITY OF OCOEE,FLORIDA By: S. Scott Vandergrift,Mayor Date Attest: Beth Eikenberry,City Clerk FOR USE AND RELIANCE ONLY BY THE APPROVED BY THE OCOEE CITY CITY OF OCOEE,APPROVED AS TO FORM COMMISSION IN A MEETING HELD ON AND LEGALITY THIS DAY OF ,2005 UNDER ,2005. AGENDA ITEM NO. FOLEY&LARDNER By: City Attorney 00842-3 CITY OF OCOEE REQUEST FOR PROPOSAL Public Works Department FOR PROPOSED CHANGE 150 North Lakeshore Drive (407) 905-3100 ext. 1505 (RFP) Ocoee, Florida 34761-2258 (407)656-7835-fax NO. TWO PROJECT DATA: NAME: Ocoee Crown Point PUD—Phase 1 Infrastructure Project PROJECT NO: LOCATION: On Ocoee Crown Point Parkway at Westyn Bay Boulevard DATE: April 11 2005 OTHER: REFERENCE: TO(CONTRACTOR): Master Site Development, Inc. Please provide the undersigned a proposal for the following change in the work within seven(7)calendar days after receipt of this request. The written proposal must clearly delineate the scope of the proposed change in the work providing an itemized estimate of the time and all material and labor(by trade),subcontract and overhead costs and fees. Any amount claimed for subcontracts must be similarly supported. DESCRIPTION of change in work: Install 140 linear feet of 20-inch DIP water main and all necessary connections,fittings,etc.required to replace the 140 linear feet of 12-inch water main installed at this location. This work will include the replacement of asphalt pavement and brick pavers affected by the construction and the coordination with Orange County Utilities for service outages. Change Order Type: d Deletion d Addition d Revision d Other:( Constraints of Change: Initiated by: d Changes in Owner Requirements d Unforeseen Conditions d Others:( ) Proposal must be received by: ATTACHMENTS(Listing of attached documents that support description): 1. Contractor Request for Information No. 4. 2. Plan Revisions: 5. 3. 6. d OWNER: David Wheeler,Ocoee d CONTRACTOR: Curt Noblitt,Master Site d ENGINEER: Joe Kolb,VHB, Inc. d FIELD: Otis Patton,Ocoee d CONSTRUCTION ADMINISTRATOR: d OTHER: d SUBCONSULTANT: Date Received From Contractor: Date Returned to Contractor With Comments: Date Returned to City: 00847-1 PRICING INFORMATION: Method of Pricing: A. d Established Contract Unit Price(s) BQ d Negotiated Unit Price(s)(including Overhead and Profit) C. d Negotiated Lump Sum(including Overhead and Profit) D. d Actual Cost of Work plus Fixed Percent for Overhead and Profit E. d A combination of A,B,C,D DESCRIPTION OF WORK: d By General Contractor d By Subcontractor ITEM OF WORK QUANTITY PRICE TOTAL Sty A,h# €.A 4,of Es 1:414 i Attach additional pages if necessary. NET TOTAL COST OF THIS CHANGE PROPOSAL $ SSS 3 6o.i° EXTENSION OF CONTRACT TIME: As part of this Change Proposal the Contractor requests an extension of the contractratime in the amount of /67/ additional days. Provide thorough documentation in support of the request for additional tip e: dap y D7 N L *Cr Dl e'$15f) /frd e 11°1. 6/IA de�. � Cow" LA Ve s c-.of Fe0eP A requirement of this Change Proposal will be to provide record drawing information for all of the affected items of work RECOMMENDATION BY ENGINEER/CONSTRUCTION ADMINISTRATOR: Comments: Signature of Engineer/Construction Administrator: Date: ACCEPTANCE BY OWNER: Comments: Pt DG df3 G.c C D 412 r : ,�j.. //l Date: Signature: j`!�'� 1 of agree to the costs and terms of RFP (Name) (Company) (No.) this day of ,199 . (day) (month) (year) 00847-2 00+99 VIS 3N11 HOiVVi 90001.33HS 33S z•-• i , ' ' Li- I 4 i ,-- I D )- 0 A i 1 f 1 , 1 , 03 ; 4 di ' P I— I 1 D X T. 0 0 , 4, . 1, 00 ' CN i .0 - ' WI / \• 0- o k-- w z zt,Lo w 1, , ., QD1--- wo , -- -.-"o _ i. 7 5?-i2 1-122 4 0 A V.:.t 1. 4• 4-, -5-‹ -a. U.I — 63 % -• \V*1 > ., 0 . , \ _ , ._. 0 ‘,k vk 0,7 \ ea - 11-.I:-Arirtt4"- ., g \ 't".9'.----•APO4oPt*. ..,,,,, ' Ilk ---olotAttsl t 1 . \ ,v• s •; f ''' 4% 2.' (6. "4404111 t .a 0' 1 10 So 75 *e‘3 ,,,, 48 S$ oco 't te, s ..—d •insrt \\ .\ -', 4: or..S.p ip ay. -.. 9_, -,, , ,„ N 7 ,- \ \ 0 > ” I— 6 w ...., F- - 4., 0 i 1.0 ill 1— Z ° i 1'0 10 Cl- 1.i OG A La 0 La 8 r...., 04/19/2005 09:16 4078910575 MASTER PAGE 02 • - MASTER S ITE DEVELOPMENT, INC. 1203 floc da Aveae•Saint Cloud,Florida 34769 •(407)B91-0700 • (407)591.0575—Pax Request For Change Order To: City Of Ocoee Project: Crown Point PUD Phase 1 Attention: Dave Wheeler Date: 23-Aug-04 Request No. 2a Phone: 407-905-3100 Fax: Comments: Description Quantity Unit Unit Total Price 1 Demo Exisiting 12"Water Main -1 Ea $ 3,650-00 $ (3,650.00) la Caps For Demo Existing Main 2 Ea $ 700.00 $ 1,400.00 2 Install 20"DIP 140 Lf $ 45.34 $ 6,347.60 3 Install 20"Gate Valve 1 Ea $ 11.,064.00 $ I1,064.00 4 Install 16"Gate Valve 1 Ea $ 3,859.00 $ 3,859.00 5 install 20"X 16"Reducer 1 Ea $ 1,455.00 $ 1,455.00 6 Open Road Cut&Repair(Curb,Asphalt,Saw-Cutting) 1 Ea $ 9,810.00 $ 9,810.00 7 Install DI Fast Grip Gasket 6 Ea $ 495.00 $ 2,970.00 8 Install 20"MJ C153 Long Sleeve w/pvcml 1 Ea $ 1,745.00 $ 1,745.00 9 Install 20"45 Degree Fittings(conflicts With Existing Utiliti 6 Ea $ 2,155.00 $ 12,930.00 Administration Estimator fir $ 50.00 $ _ - Subtotal $ 47,930.60 Overhead 1 0% $ 4,793.06 Subtotal $ 52,723.66 Profit 5% $ 2,636.34 Total $ 55,360.00 Note: This Additional Scope Of Work Will Add 14 Calender Days To The Contract Authorized Signature: