HomeMy WebLinkAboutIII (C) Approval and Authorization for Mayor and City Clerk to Execute Add No 95-2 to PSI Proposal for Hydrogeologic Evaluation at Forest Lake Golf Course I • „ _ AGENDA 6-20-95
Item III C
0
0
%<<or 1)00`tea?9 JAMES W.SHIRA,P.E.
CITY ENGINEER/UTILITIES DIRECTOR
150 N.LAKESHORE DRIVE•OCOEE,FLORIDA 34761
PHONE(407)656-2322 EXT.142•FAX(407)656-7835
MEMORANDUM
DATE: June 13, 1995
TO: The Honorable Mayor and Board of City Commissioners
FROM: James W. Shira,P.E.
City EngineerfUtiliti s irector
SUBJECT: Addendum to Previous Proposal- Hydrogeologic Evaluation at Golf Course
On March 7, 1995 the City Commission authorized PSI to begin work on a hydrogeologic
evaluation and load test program at the Forest Lake golf course and the wastewater treatment
plant to determine the capacity of these sites for effluent disposal. This determination was
required so that the Florida Department of Environmental Protection could issue a permit to the
city for effluent disposal.
In discussing this project with FDEP, it was decided that some of the planned deeper auger
borings would not be required, but that there was a need for several additional shallow piezometer
borings. I authorized PSI to continue with the work in order to expedite determination of the
effluent disposal capacity of these two sites, and have been in contact with PSI and FDEP to see if
the total number of borings could be further reduced as more information was gathered.
The Department of Environmental Protection remains firm in their desire to have data collected
from the fifteen shallow piezometers that were not anticipated in PSI's original proposal, but they
have also agreed that the scope of the deep borings can be reduced from 210 feet to 100 feet. The
total cost to the City for this additional work is $4,350.00 as outlined in the attached Addendum
Proposal. This amount will be paid for from the Wastewater Reserve for Contingency account
which has a balance of$263,331.50 as of June 13, 1995.
I recommend that the City Commission authorize the Mayor and City Clerk to execute Addendum
No. 95-2 in the not-to-exceed amount of$4,350.00 in accordance with their proposal number
757-55049 dated April 27, 1995.
ITHEiPRIDE OF WEST ORANGE
~v� Environmental
Geotechnical
Construction
• Consulting • Engineering • Testing
April 27, 1995
Project No. 757-55049
TO: City of Ocoee
150 North Lakeshore Drive
Ocoee, Florida 34761
Attention: Mr. Jim Shira, P.E.
SUBJECT: Addendum Proposal
Hydrogeologic Evaluation/Load Test of
City of Ocoee Waste Water Treatment Plant Site
and Forest Lake Golf Course, Ocoee, Florida
Dear Mr. Shira:
This letter is addressing the Plan of Study that has been developed for the load test
monitoring and effluent disposal capacity evaluations for the City of Ocoee Wastewater
Treatment Plant (WWTP) site and Forest Lakes Golf Course, as discussed in our last
meeting with you and PEC.
As previously discussed this Plan of Study is based upon our evaluation of the available
data, site visits and meeting with the Florida Department of Environmental Protection
(FDEP) for their review and approval prior to implementation. Therefore, in accordance
with our report entitled "Recommended Plan of Study for City of Ocoee Wastewater
Treatment Plant and Forest Lakes Golf Course, Ocoee, Florida" dated April 10, 1995, as
accepted and approved by FDEP, it is necessary to add 13 piezometer boring installations,
not previously listed in our Addendum No. 95-1. These 13 piezometer borings were
approved in our last meeting with PEC and yourself, and are herein presented as an
addition to Addendum No. 95-1. Note should be taken that Addendum No. 95-1 shows 210
lineal feet of proposed Auger Borings. However, currently we only require 1 deep boring
to 100 feet below existing grade, for groundwater modeling purposes. Please note that we
are crediting you with the difference in unused drilling footage, i.e. $715.00 as shown in the
following price attachment.
Furthermore, as per FDEP's latest request in accordance to their letter OCD-DW-95-0371,
dated April 25, 1995, two additional piezometers will need to be installed as a condition of
final approval of our "Submitted Plan of Study" discussed previously. The costs incurred
for this undertaking are also reflected in our price attachment. The total number of shallow
aquifer piezometers required by FDEP is fifteen (15).
PSI•1675 Lee Road•Winter Park,FL 32789•Phone 407/645-5560•Fax 407/645-1320
City of Ocoee -2-
Project No. 757-55056
Below is a detailed breakdown of all costs that will need to be incurred:
• Laying out piezometer location $ 175.00
(Actual survey control and ground
elevation to be performed by PEC.)
• Fifteen (15) Piezometer Installations @ $14.00/LF $4,200.00
(Assumed 300 Lineal Feet of PVC Pipe with Materials)*
• Engineering (layout, meetings, site visits, etc.)
8 Hours @ $65.00/Hour $ 520.00
• CADD Graphics, 4 Hours @ $30.00/Hour $ 120.00
• Technical Secretarial, 2 Hours @ $25.00/Hour $ 50.00
Total: $5,065.00
• Auger Borings (Credit from original scope)
(210-100) = 110 Lineal Feet @ $6.50/LF - Credit:
< 715.00>
TOTAL INCREASE IN BUDGET: $4,350.00
* The necessary and exact footage will be substituted upon completion of the field
installation program, which will be reflected in final pricing.
PSI will start these piezometer installations on May 1, 1995, as discussed and approved. As
also conveyed in FDEP's letter of April 25, 1995, the load test monitoring is to be extended
through the rainy season,therefore,the actual monitoring period may exceed the 4± months
we recommended.
jai
City of Ocoee -3-
Project No. 757-55056
Should you have any questions concerning these additional services, please do not hesitate
to call the undersigned at (407) 645-5560. For your convenience, we have attached a
completed Addendum form similar to our original Agreement with the City of Ocoee.
Sincerely,
PSI
Christian C. Steputat, P.E. Dan u or., P.r.
Project Engineer Senior Vice President
Attachment
• Addendum No. 95-2
e7i
ADDENDUM NO. 95-2 TO
AGREEMENT FOR CONSULTING ENGINEERING SERVICES
HYDROGEOLOGIC EVALUATION/LOAD TEST
FOREST LAKE GOLF COURSE & CITY OF OCOEE WWTP SITE
This Addendum No. 95-2 hereinafter called the Addendum as of this day of
1995, shall constitute an Addendum to the Agreement for
Professional Geotechnical Engineering &Testing Services between the City of Ocoee, Florida
(the CITY) and PSI, 1675 Lee Road, Winter Park, Florida (the CONSULTANT) dated the
27th April 1995, hereinafter referred to as the AGREEMENT.
WHEREAS, the CITY and CONSULTANT entered into an AGREEMENT whereby the
CITY retained the CONSULTANT to provide professional engineering services as required
from time to time, and WHEREAS the CONSULTANT will perform consulting engineering
services for the CITY defined.
NOW THEREFORE, in consideration of the mutual covenants and promises hereinafter set
forth on the part of both parties to be kept and performed, the parties do mutually agree as
follows:
Section 1 - Services of the Consultant
1.1 The CONSULTANT shall perform the engineering services as outlined in the attached
proposal #757-55049 dated April 27, 1995 relative to the provision of consulting services
to the CITY.
Section 2 - Compensation
2.1 Compensation by CITY for engineering services provided under this Addendum shall
be computed under Section II of the AGREEMENT utilizing the Payroll Cost Times
a Factor Method of Compensation with the compensation for this additional
authorization not to exceed $4,350.00 as outlined in the attached proposal, without
further authorization from the CITY.
Section 3 - Time of Completion
3.1 The CONSULTANT shall provide the services as outlined in the attached proposal.
IN WITNESS WHEREOF, the parties have executed this Addendum No. 95-1 the day and
year hereinafter set forth.
CITY CONSULTANT
CITY OF OCOEE PSI
BY: BY: _1 I ��/�.���
Mayor S. Scott Vandergrift Dan Fulf f,rd, P.E.
Sr. Vice 'resident
ATTEST: ATTEST:
Jean Grafton, City Clerk
FOR USE AND PELIANCE ONLY
BY THE CfTY CP CCCEE.
APPROVED AS TO FORM AND LEGALITY
Offs day of 19
FOLEY&LARDNER
By
C;;�. .y