MEMORANDUM
DATE: March 12, 1996
TO: The Honorable Mayor and Board of City Commissioners
FROM: James W. Shira, P.E.
City Engineer/Utilities Director
SUBJECT: Presentation Regarding Drainage Basin Studies
Attached for your review are copies of letters received from Professional Engineering
Consultants, Inc. (PEC)transmitting final submittals for two of the drainage basin studies that
have been authorized. Each of you has been provided with a copy of the three volumes which
comprise each report.
The Spring Lake/Lake Johio basin study, and the Starke Lake/Lake Olympia basin study have
both been completed, and final reports have been delivered to the City. In the final reports, PEC
has analyzed the conditions within each basin, identified problem areas, and has developed a
recommended program of capital improvements to correct the various deficiencies.
to
PEC
PEC will discuss each of these studies at the City Commission meeting on April z', 1996, and will
answer any questions you might have.
THE PRIDE OF WEST ORANGE di
PEC
PROFESSIONAL ENGINEERING CONSULTANTS, INC.
February 21, 1996 0E-188
1-1.0
Mr. Ellis Shapiro
City Manager
City of Ocoee
150 North Lakeshore Drive
Ocoee, Florida 34761
RE: Spring Lake/Lake Johio Drainage Basin Study
"FINAL"Submittal
Dear Mr. Shapiro:
It is with great pleasure that PEC/Professional Engineering Consultants is able to transmit
with this letter the "FINAL"Engineering Report for the aforementioned project. As part of this
"FINAL"submittal, please find enclosed the following documents:
• Volume I (Introduction, Existing Conditions, Recommended improvements, Capital
Improvement Program, and Water Budget Analysis); and
• Volume II (Valence, adICPR analysis, Project Survey, Supporting Documentation, and
Project Correspondence).
It is recommended that PEC/Professional Engineering Consultants "update/amend" the
existing conditions computer model contained within this basin study, based on any
proposed development submitted to the City of Ocoee Engineering Department for review
and approval (e.g., Spring Lake Oaks and/or Lake Johio Shores Subdivision).
Updating/amending of this master analysis will better determine the impact of the proposed
development on the Basin as a whole, and will utilize the most accurate and up to date
information currently available for this area.
Per your direction, we have not transmitted copies of the "FINAL"Engineering Report to City
Commissioners at this time, and will wait for your instruction as to how copies will be
provided in the near future. Furthermore, at the City's request, PEC/Professional Engineering
Consultants will conduct one (1) public workshop or presentation to the City Commission,
or City staff, of the existing conditions analysis and recommended improvements which are
contained within the "FINAL"submittal of the Spring Lake/Lake Johio Drainage Basin Study.
engineers
planners
surveyors 200 East Robinson Street • Suite 1560 • Orlando, Florida 32801 • 407/422-8062 • FAX 407/849-9401
Letter To Mr. Ellis Shapiro February 21, 1996
OE-188.L02 Page 2
At this time we would like to thank the City staff for their continued assistance and
cooperation relative to the development of the subject Engineering Report, and look forward
to our continued relationship with the City regarding the ongoing development of the City of
Ocoee Master Drainage Basin Study. If you have any questions, please do not hesitate to
contact me directly at 422-8062.
Sincerely,
PROFESSIONAL ENGINEERING CONSULTANTS, INC.
W UAtSC.k..
David W.' stra, P.E. Lynette L. Wuensch, E.I.
Stormwater Department Manager Project Engineer
cc: Jim Shim, City of Ocoee (with enclosure)
Montye Beamer, City of Ocoee (with enclosure)
Russ Wagner, City of Ocoee (with enclosure)
Dr. M. Krishnamurthy, Orange County(with enclosure)
Mary Brabham, SJRWMD (with enclosure)
Craig Batterson, PEC (w/o enclosure)
Ken Hooper, PEC (w/o enclosure)
PEC/PROFESSIONAL ENGINEERING CONSULTANTS
PEC
PROFESSIONAL ENGINEERING CONSULTANTS, INC.
March 4, 1996 OE-208
1-1.0
Mr. Ellis Shapiro
City Manager
City of Ocoee
150 North Lakeshore Drive
Ocoee, Florida 34761
RE: Starke Lake/Lake Olympia Drainage Basin Study
Work Order No. 8 "FINAL"Submittal
Dear Mr. Shapiro:
It is with great pleasure that PEC/Professional Engineering Consultants is able to transmit
with this letter the "FINAL"Engineering Report for the aforementioned project. As part of this
"FINAL"submittal, please find enclosed the following documents:
• Volume I (Engineering Report);
• Volume ll (adICPR Analysis); and
• Volume Ill (Supporting Documentation).
It is recommended that PEC/Professional Engineering Consultants "update/amend" the
existing conditions computer model contained within this basin study, based on any
proposed development submitted to the City of Ocoee Engineering Department for review
and approval. Updating/amending of this master analysis will better determine the impact
of the proposed development on the Basin as a whole, and will utilize the most accurate and
up to date information currently available for this area.
Per your direction, we have not transmitted copies of the "FINAL"Engineering Report to City
Commissioners at this time, and will wait for your instruction as to how copies will be
provided in the near future. Furthermore, at Jim Shire's request, PEC/Professional
Engineering Consultants is prepared to present the results of the existing conditions analysis
and the recommended improvements to the City Commissioners on Tuesday, March 19,
1996. It is anticipated that the presentation will include the Starke Lake/Lake Olympia
Drainage Basin Study and the Spring Lake/Lake Johio Drainage Basin Study.
engineers
planners
surveyors 200 East Robinson Street • Suite 1560 • Orlando, Florida 32801 • 407/422-8062 • FAX 407/849-9401
Letter To Mr. Ellis Shapiro March 4, 1996
0E-208.G01 Page 2
At this time we would like to thank the City staff for their continued assistance and
cooperation relative to the development of the subject Engineering Report, and look forward
to our continued relationship with the City regarding the ongoing development of the City of
Ocoee Master Drainage Basin Study. If you have any questions, please do not hesitate to
contact me directly at 422-8062.
Sincerely,
PROFESSIONAL ENGINEERING CONSULTANTS, INC.
David W Hamstra, P.E.
Stormwater Department Manager
cc: Jim Shira, City of Ocoee (with enclosure)
Montye Beamer, City of Ocoee (with enclosure)
Russ Wagner, City of Ocoee (with enclosure)
Dr. M. Krishnamurthy, Orange County(with enclosure)
Mary Brabham, SJRWMD (with enclosure)
Craig Batterson, PEC (w/o enclosure)
Ken Hooper, PEC (w/o enclosure)
PEC/PROFESSIONAL ENGINEERING CONSULTANTS