HomeMy WebLinkAboutVI(H) Discussion/ Action Re: Change Order #1 For Continuing Horizontal Construction Services Capital Improvements Projects No. 1 & 6 (Georgetown). AGENDA 11-05-96
Ocoee Item VI H
1f4 o Goo
O
JAMES W. SHIRA,P.E.
CITY ENGINEER/UTIL1"1'1bS DIRECTOR
150 N.LAKESHORE DRIVE a OCOEE,FLORIDA 34761
PHONE(407)656-2322 EXT.142•FAX(407)656-7835
MEMORANDUM
DATE: October 31, 1996
TO: The Honorable Mayor and Board of City Commissioners
FROM: David Wheeler, P.E.
Assistant City Engineer/Utilities Director
SUBJECT: Continuing Horizontal Construction Services
Capital Improvements Projects No. 1 and 6
Change Order Request No. 1
Attached for your review is Change Order Request No. 1 on the Continuing Horizontal
Construction Services Capital Improvements Projects No. 1 and 6. This change order request
was initiated by City staff due to PEC's oversight in not including the one property that has the
worst drainage problem on Dovetail Court. This oversight was discovered after PEC had
completed the design and the City was in receipt of the bids for this stormwater improvements
project.
This additional construction request was initiated not only due to the oversight; but also due to
additional subsurface investigations by the subconsultant employed to inspect the underdrain
installation for these initial horizontal construction projects. This change order request was
further enhanced by the excessive rainfall from tropical storm Josephine and the results
witnessed by staff and its consultants. The excessive rainfall occurred during the same time
period that Dr. Seereeram, P.E. and his soils technician performed additional soils investigation
in the backyards of the Fergus and Murray properties. The original design solved the drainage
problems along the rear and side lot lines and partially assisted in the drainage problems behind
the Murray house. Since the initial investigations by PEC which prompted the design were
performed,the drainage problems have become worse and warrant the additional underdrains and
surface drains in both properties.
The contractor for this project and City staff have negotiated the scope and cost for the change
order to ensure that the City is only incurring reasonable costs for the additional construction.
Had this additional work been included in the original design project, staff feels certain that the
costs would have been the same.
I recommend that the City Commission approve Change Order No. 1 by increasing the contract
amount by$34,492.00, with an extension in contract time of fourteen calendar days, and
authorize the Mayor and City Clerk to execute Change Order No. 1.
Attachment
THE PRIDE OF WEST ORANGE
SECTION 00842
*Adjustment as of " Coventry Subdivision Lots 100 and 101
Change Order No.
Underdrain Changes and Additions
(Short title of Change Order)
CHANGE ORDER FORM
CITY OF OCOEE
PROJECT: CONTINUING-HORIZONTAL CONSTRUCTION SERVICES
CAPITALIMPROYEMENT PROJECTs40;4 ORO
CHANGE ORDER NO. 1
DATE: October 17. 1996 CONTRACTOR: Georgetown Enterprises
OWNER: CITY OF OCOEE. FLORIDA AGREEMENT DATE: June 27, 1996
AMENDMENT DATE: September 13, 1996
•
The following changes are hereby made to the CONTRACT DOCUMENTS:
Original CONTRACT PRICE $ 149,735.30
Current CONTRACT PRICE ADJUSTED by previous CHANGE ORDER* $ -0-
Net(Increase)(Decrease) Resulting from this CHANGE ORDER $ 34,492.00
The current CONTRACT PRICE including this CHANGE ORDER $ 184,227.30
ORIGINAL CONTRACT TIME: Sixty (60) Days Date December 6, 1996
Current CONTRACT TIME adjusted by previous CHANGE.ORDERS* Date December 6, 1996
Net(Increase)(Decrease) Resulting from this CHANGE ORDER Days -14
Current CONTRACT TIME Including this CHANGE ORDER Date December 20, 1996
CHANGES ORDERED:
Provide changes to comply with City of Ocoee review comments regarding additional rear yard underdrains for
Coventry Subdivision Lots 100 and 101, and review comments by the project geotechnical engineer(Devo Seereeram,
Ph.D., P.E.)regarding the addition of a swale and alternative trench material on the rear yard underdrain detail. These
changes are represented on two(2)construction plans:
• a site plan provided as a Supplemental Drawing; and
. • a revised standard detail sheet.
00842(1)-1 C:\WORK\W P61\0E-25711-1 A6\00842(1)
I. GENERAL
This Change Order is necessary to cover changes in the Work to be performed under this Contract. The
GENERAL CONDITIONS, SUPPLEMENTARY CONDITIONS, SPECIFICATIONS and all parts of the
Project Manual listed in Article 1, Definitions, of the GENERAL CONDITIONS apply to and govern all work
under this Change Order.
Change Order No. 1
II. REQUIRED CHANGES
Provide changes to comply with City of Ocoee review comments regarding additional rear yard underdrains for
Coventry Subdivision Lots 100 and 101, and review comments by the project geotechnical engineer(Devo Seereeram,
Ph.D., P.E.)regarding the addition of a swale and alternative trench material on the rear yard underdrain detail. These
changes are represented on two (2) construction plans:
• a site plan provided as a Supplemental Drawing; and
• a revised standard detail sheet.
•
III. JUSTIFICATION
The current project geotechnical engineer (Devo Seereeram, Ph.D., P.E.) was made,a part of the project team
following bidding of the project, due to PEC/Professional Engineering Consultants (Engineer) concern with regard
to the lack of direction/guidance provided by the previous project geotechnical engineer. Therefore, this change order
is predicated on a very detailed review and investigation conducted by the current project geotechnical engineer (Devo
Seereeram, Ph.D., P.E.)at the request of the Engineer, and is based entirely upon the site specific conditions prevalent
at Coventry Subdivision Lots 100 and 101 at the time of this investigation.
IV. PAYMENT
Following Change Order approval, additional compensation will be provided to the Contractor based upon the
percentage completion of the described Work up to the Lump Sum Value of$34,492.00, via the Periodic Estimate for
Partial Payment (00861).
V. NARRATIVE OF NEGOTIATIONS
Following completion of the construction plans which depict the proposed revisions as previously discussed, a meeting
was conducted between representatives of the City of Ocoee (Owner), PEC/Professional Engineering Consultants
(Engineer) and Georgetown Enterprises(Contractor). Upon comparison and review of the Engineer's and Contractor's
Estimate(s), the proposal from the Contractor dated October 11, 1996 in the amount of$34,492.00 was verbally
accepted by the Owner.
Proposal from Contractor dated October 11, 1996 in the amount of$34,492 attached.
VI. APPROVAL AND CHANGE AUTHORIZATION
This proposed change to the Contract is to be approved by the Ocoee City Council.
00842(1)-2 C:\WORK\W P61\OE-25T1-1A6\00842(1)
•
•
Acknowledgments:
The aforementioned change, and work affected thereby, is subject to all provisions of the original contract not
specifically changed by this Change Order; and,
It is expressly understood and agreed that the approval of the Change Order shall have no effect on the original
contract other than matters expressly provided herein.
CONTRACTOR acknowledges, by its execution and acceptance of this Change Order, that the adjustments in
Contract Price and Time shown hereon constitute full and complete compensation and satisfaction for all costs and
modifications of performance time incurred by the CONTRACTOR as a result of this Change Order. No other
claim for increased costs of performance or modifications of time will be granted by the OWNER for the Work
covered by this Change Order. The CONTRACTOR hereby waives and,releases any further claims for cost or time
against the OWNER arising from or relating to the matters or Work set forth or contemplated by this Change Order. •
Change Order Request by: City of Ocoee, Florida
Change Order Prepared by: Greg A. Teague. P.E,
RECOMMENDED BY: ACCEPTED BY:
PROFESSIONAL ENGINEERING
CONSULTANTS. INC. / 44.7G
Engineer Contra
By: -ticcl .k.. �a�.�4¢. By: . / `Y
Signature Signature
Greg A. Teague, P.E. Tlitgmas . arlow
Date: ►b(ls /� _
94, Date: /(D
Title: Project Engineer/Associate Title: President
APPROVED BY:
• City of Ocoee. Florida
Owner
By:
Signature Date
Change Order No. 1
END OF SECTION
•
00842(1)-3 c:\WORK\WP61\oE-257\1-1A6100842W
GEORGETOWN ENTERPRISES INC.
P.O. BOX 547163
ORLANDO, FL 32854-7163
(407) 843-3445
FAX (407) 423-1644
CITY OF OCOEE
BID 1-1A6
REQUESTED CHANGES
10/11/96
DESCRIPTION QTY UNIT PRICE EXTENSION
1.1 6" UNDERDRAIN 168 LF $ 38.00 $ 6,384.00
10" UNDERDRAIN 92 LF $ 39.00 $ 3,588.00
12" NON PERFORATED CPEP 124 LF $ 40.00 $ 4,960.00
18"STRIP DRAIN 534 LF $ 20.00 $ 10,680.00
18"YARD DRAIN 1 EA $ 600.00 $ 600.00
12"YARD DRAIN 1 EA $ 500.00 $ 500.00
24"YARD DRAIN 3 EA $ 700.00 $ 2,100.00
GRADE SWALE OVER UNDERDRAIN 460 LF $ 8.00 $ 3,680.00
$ 32;492.00
12" NON PERFORATED TO BE MEASURED AFTER INSTALLATION
SOD--AS NEEDED 500 SY $ 3.00 $ 1,500.00
12" FLARED END 1 EA $ 500.00 $ 500.00
IF3* `i-12..o0
•
T;-17;77;71;1
OCT 1111 1996-
; gg
10/11/96 2:11 PM Ocoeel-6 Sheet2