MEMORANDUM
DATE: July 24, 1997
TO: The Honorable Mayor and Board of City Commissioners
FROM: James W. Shira, P.E.
City Engineer/Utilif s irector
SUBJECT: Water System Improvements
Design Services Contract with Professional Engineering Consultants, Inc.
The 1997 Water and Sewer Utility Bond issue included $3,123,000 for water distribution system
improvements and $649,000 for engineering and inspection services related to water system
projects. In meeting with Professional Engineering Consultants, Inc. (PEC), we have been able
to fine-tune the proposed water distribution network, taking into account those water lines which
have been or will be installed by developers. By removing these from the list of proposed water
lines used in the bond issue, we have been able to lower the estimated construction cost from
$3,123,000 to $ 2,500,700, a 20% reduction.
Attached for your review and action is a proposal from PEC for the design services required for
this project, and Addendum No. 97-3 to their contract. PEC's proposal is based on a fee of 7%
of the actual cost of construction. The anticipated fee is $175,100 based on the estimated
construction cost of$2,500,700.
Your approval of this Addendum will allow us to proceed with design of this important project.
Design services will be complete in late January 1998, and we should be ready to advertise for
bids in early March 1998.
I recommend that the City Commission authorize the Mayor and City Clerk to execute
Addendum No. 97-3 to Professional Engineering Consultants, Inc.'s contract in the not-to-exceed
amount of 7% of the construction cost of the water distribution system improvements.
THE PRIDE OF WEST ORANGE
ADDENDUM NO. 97-3 TO
AGREEMENT FOR CONSULTING ENGINEERING SERVICES
INCLUDING
ENGINEERING DESIGN AND PERMITTING SERVICES FOR EXPANSION OF
POTABLE WATER DISTRIBUTION SYSTEM
This Addendum No. 97-3 hereinafter called the Addendum, as of this 5th day of
August, 1997, shall constitute an Addendum to the Agreement for Consulting
Engineering Services between the City of Ocoee, Florida (the CITY) and Professional
Engineering Consultants, Inc., 200 East Robinson Street, Suite 1560, Lake Eola Centre,
Orlando, Florida(the CONSULTANT), dated the 21st day of August, 1984, hereinafter
referred to as the AGREEMENT.
WHEREAS, the CITY and CONSULTANT entered into an AGREEMENT whereby
the CITY retained the CONSULTANT to provide professional engineering services as
required from time to time, and WHEREAS the CONSULTANT will perform'
consulting engineering services for the CITY as herein defined.
NOW THEREFORE, in consideration of the mutual covenants and promises hereinafter
set forth on the part of both parties to be kept and performed, the parties do mutually
agree as follows:
Section 1 - Services of the Consultant
1.1 The CONSULTANT shall perform the Engineering services as outlined in the
attached proposal P-7036R2, revised as of July 7, 1997 relative to the provision
of consulting engineering services to the CITY.
Section 2 - Compensation
2.1 Compensation by CITY for engineering services provided under this Addendum
shall be computed under Paragraph 6.1.2.3 of the Agreement, utilizing the
Percentage of Construction Value (Lump Sum) Method of Compensation with
the compensation for this authorization not-to-exceed 7% of the cost of
construction of the water system improvements as outlined in the attached
proposal, without further authorization from the CITY. The estimated design
and permitting fee is $175,100.
Section 3 - Time of Completion
3.1 The CONSULTANT shall provide the services within six (6) months as
described in the attached proposal.
IN WITNESS WHEREOF, the parties have executed this Addendum No. 97-3 the day
the year hereinabove set forth.
By:
ATTEST: enneth R. Hooper, Pri cipal
Date: ,,./fr , / 77
BOARD OF CITY COMMISSIONERS
CITY OF OCOEE, FLORIDA
By:
ATTEST: S. Scott Vandergrift, Mayor
Date:
For the use and reliance
of City of Ocoee only.
Approved as to form and
legality this
day of , 1997.
City Attorney
G:\cler\env\oe\ocoee\97-3.ADN -2- OE(05/09/97)
PEC
PROFESSIONAL ENGINEERING CONSULTANTS, INC.
May 9, 1997 P-7036R2
July 7, 1997 Revised
Mr. James W. Shira, P.E.
City Engineer/Utilities Director
City of Ocoee
150 North Lakeshore Drive
Ocoee, Florida 34761
Re: Proposal for Engineering Design Services
Water System Distribution Improvements
Dear Jim:
We are pleased to present the attached revised proposal for the engineering design and
permitting services related to expansion of the City's potable water distribution system.
This proposal has been revised to reflect the changes discussed in our meeting June 19,
1997. These changes include the deletion of several pipeline alignments and an increase
in the pipeline diameter along several segments. The changes are summarized in
Attachment A for your reference.
The City has planned for the expansion of the water distribution system through the
Series 1997 Water and Sewer Revenue Bonds. The Engineer's Report for the 1997
Bond Issue describes the proposed water distribution system improvements consisting
of three (3) phases or levels of service and provides a construction cost estimate of
$3,123,000. All three (3) phases will be designed under this scope of work. As
discussed during our meeting, the revenue committed for this Bond issue is the Water
Connection Fees (Impact Fees). Because the outlying undeveloped areas (Phase 3) are
presently more costly to serve than other established areas within the City, we
concluded that the Connection Fees should vary to reflect the cost of providing water
service to these areas. Water Service Districts would be established which would
reflect the cost of providing water service, i.e., the outlying undeveloped areas would
require a higher Connection Fee.
Based on the pipeline alignment and pipeline size changes made during our meeting, the
total linear footage of pipe has decreased from 70,020 LF to 56,050 LF while 7,300 LF
increased in size form 12-inch to 16-inch near the South WTP. The following table
summarizes the construction cost impact of these changes:
engineers
planners
surveyors 200 East Robinson Street • Suite 1560 • Orlando, Florida 32801 • 407/422-8062 • FAX 407/849-9401
Mr. James W. Shira, P.E.
July 7, 1997
Page 2
Phase I $ 970,000
Phase II $ 1,020,000
$ 800,000 $ 828,187
Phase III $ 1,353,000
$ 652,500
TOTAL $ 3,123,000 $ 2,500,687
Our engineering and permitting fee estimates have also changed based on the new
pipeline alignment and size changes and are summarized as follows:
Scope of Services Previous Estimate Revised Estimate **
Basic Design & Permitting $ 95,340 $74,000
Basic Survey * $ 81,250 $ 65,000
Geotech & Corrosion Survey $ 9,150 $ 8,100
Aerial Raster Imagery $ 32,870 $ 28,000
TOTAL $ 218,610 $ 175,100-
* Does not include surveying services on private land for possible easement requirements.
** Estimate based on pipeline lineal footage reduction of 20 percent
Also, as you have requested, we have revised Exhibit 1 which depicts the modified
alignment of the proposed water distribution system improvements and the existing
water distribution system. The background of this exhibit now uses an aerial raster
image dated about April, 1997 of the Ocoee planning area The alignments are still
preliminary as we discussed in our meeting, and additional preliminary engineering
analysis and evaluation will be necessary to select specific cost effective pipeline
alignments for the identified segments.
Our fee proposal is based on a not-to-exceed amount of 7% of the cost estimate for
construction of the water distribution system improvements. It is our understanding that
the fee for preliminary design, final design and permitting will not exceed 7% of the
actual cost of construction of the water distribution system improvements. The 7% fee
is based on an average complexity of design. Our estimate of the maximum design and
permitting fee is $ 175,100. This proposal does not include fees for bidding assistance
or construction phase services. At a later date the City may request a proposal for
services of PEC to provide bidding phase services and construction administration.
This proposal does not include eminent domain assistance by PEC. If any eminent
domain or acquisition assistance is necessary PEC will provide the services on a parcel
by parcel basis as authorized by the City of Ocoee.
Please review this proposal and provide comments as necessary.
Mr. James W. Shira, P.E.
July 7, 1997
Page 3
Very truly yours,
PROFESSIONAL ENGINEERING CONSULTANTS, INC.
Ke eth R. Hooper
Project Manager
KRH/bk
Mr. James W. Shira, P.E.
July 7, 1997
Page 4
ATTACHMENT A
SUMMARY OF PIPELINE ALIGNMENT & SIZE CHANGES
Seg- Description of Changes
ment
1 Deleted
2 Deleted - Changed to 9,000 LF 12 inch loop running north on Clarke Road to
Clarocona Ocoee Road
3 No Change
4 Deleted
5 Deleted
6 No Change
7 No Change
8 No Change
9 No Change
10 No Change
11 Deleted
12 Relocated along City owned property - 1600 LF 12-inch
13 Deleted
14 Changed to 100 LF 8-inch interconnection under large Drainage Ditch on Geneva
Road. Also, possible 12-inch loop alternate between Maguire Road and Old Main
Street by developer.
15 East end of alignment is "S" shaped and unknown at this time.
West end alignment will conform to re-alignment of Old Main Street by Developer.
16 North of S.R. 50 deleted. Approx. 1400 LF
17 No Change
18 No Change
19 Change from 12-inch to 16-inch.
20 "S" shape change to east road alignment by developer. Change from 12-inch to 16-
inch.
21 Shift to access road to South WTP. Change from 12-inch to 16-inch.