Item VII G
"CENTER OF GOOD LIVING-PRIDE OF WEST ORANGE" MAYOR•COMMISSIONER
S. SCOTT VANDERGRIFT
( fiJ) (407)656-2322 NANCY J.PARKER
rEP of G00� CITY MANAGER
ELLIS SHAPIRO
MEMORANDUM
DATE: April 10, 2000
TO: The Honorable Mayor and Board of City Commissioners
FROM: James W. Shira, P.E., City Engineer/Utilities Director
SUBJECT: Proposal from Burton & Associates
At the February 1, 2000 City Commission meeting, Mr. Michael Burton was asked to
provide us with a proposal to perform a water usage analysis. This analysis will provide
information about actual water consumption patterns in the city, and this information
will be used to help determine appropriate water and reclaimed water rates.
Attached is a proposal provided by Mr. Burton to perform the water usage analysis.
Also attached is a schedule for the completion of this work and the development of
proposed water and reclaimed water rates.
The proposed fee of $14,020.00 will be funded by a transfer from the Wastewater
Reserve for Contingency account, which has a current balance of $80,000.00.
I recommend that the City Commission authorize Burton & Associates to proceed with
the work outlined in their proposal dated March 7, 2000 for a not-to-exceed fee of
$14,020.00, and authorize the transfer of $14,020.00 from Wastewater Reserve for
Contingency to the appropriate operating account.
JWS/jbw
Attachments
POW!'#rrtet Oof!e_c Water Resourrt:,
BURTON &
ASSOCIATES
March 7, 2000
Mr. Jim Shira, P.E. MAR I 3 M000
Director of Engineering and Utilities
City of Ocoee
150 N. Lakeshore Drive
Ocoee, FL 34761-2258
Re: Water and Wastewater Rate Study - Additional Services Authorization
Dear Mr. Shira:
As requested, I have prepared this proposed Additional Services Authorization request to perform
the above referenced analysis. This analysis is necessary to determine an accurate water usage
profile for the City's water customers in order to properly construct the reclaimed water rate
system included in the water and wastewater rate study. This information is also necessary to
evaluate the appropriate water rate structure for the City with regard to its overall water
conservation program.
I have included a Project Workplan & Cost Estimate schedule for these additional services. This
schedule shows that successful completion of this additional work will require approximately 120
hours for an estimated fee of$12,745 plus a 10% contingency allowance for unforeseen issues
regarding the data analysis required of$1,275 for a total estimated additional cost of$14, 020.
This additional work will be performed as part of the ongoing water and wastewater rate study
and as such is necessary to successfully complete that project in such a way as to be accurate and
to properly structure the reclaimed water rate program and water rates.
If you have any questions, please do not hesitate to call me at (904) 247-0787.
Vcry truly your
Michael E. Burton
President
MEB/cs
Enclosure
440 Osceola Avenue • Jacksonville Beach, Florida 32250 • 904/247-0787
City of Ocoee, _Florida
Water & Sewer System
Determination of Household Consumption
PROJECT WORKPLAN& COST ESTIMATE
I Burton Associates) inc. — —
i 1I�!►i�1.��" ESTIMATED MANHOUR8
ell 11 =t._ PROJECT TASKS PROJECT PROJECT TOTAL
DIRECTOR STAFF ASSOCIATE PROJECT
TASK Subtask Description hearty.... 3150 S125 $85
COSTS
A in t .te project $250 - _2 - 2
_
1 Meet with staff to discuss sco.e of work and confirm tasks to be performed. _________ i $2501 - 2 - _ 2
B Doterm/ne Consumption Statistics by CmatomoL C/aas $4,soo L 2 36 - 38
I Set up bill frequency data In model to prepare for analysis. $2,000 - 16 - 16
2 Compare revenue calculated from billing data to recorded revenue to confirm data. $1,000 - 8 - 8
3 Calculate consumption by customer class and meter size. $500 - 4 - 4
4 Pre.are memorandum report of results, with comprehensive schedules. $1, 00 2 8 - 10
C Test ne/ghbomood dam $3,415 1 3 34 38
—
1 Meet with staff to determine data collection approach. $420 - 2 2 4
2 Extract data from billing record for sample of neighborhoods included in previous study. $1,360 - - 16 16
3 Calculate average household consumption and compare to previous study. $680 - - 8 8
4 Prepare memorandum report of results, with comprehensive schedules. _ $955 1 1 8 10
D Prepare ne3port and make presentations, $4,280 6 8 28 42
1 Review memorandum reports with staff and management. S720 2 2 2 6
2 Prepare combined report for City Commission. $1,760 1 2 16 19
3 Revise report based on staff/management review. $540 0.5 1 4 5.5
4 Present report to City Commission. $720 2 2 2 6
5 Finalize report based on City Commission comments. _ — $540 0.5 _ 1 4 5.5
TOTAL PROJECT ESTIMATED MANHOURS 9 49 62 120
TOTAL PROJECT ESTIMATED CONSULTING FEES $1,350 $6,125 $5,270 $12,745
REIMBURSEABLE EXPENSES AS REQUIRED,96 FEES NOT TO EXCEED - -
CONTINGENCY AT % FEES 1o.0% $1,275
— — -- -- =E-tTiMgrtrr OS j S14,020'
SOURCE:BURTON&ASSOCIATES 03106/2000
03/30/00 09: 43 Z 9042411%0u .
t • c4 G
Bl 1 R'I'(.)N &
ASSOCIATES 1
March 28, 2000 re/
Mr. Jim Shira, P.E.
Director of Engineering and Utilities
City of Ocoee
150 N. Lakeshore Drive
Ocoee, FL 34761-2258 •
Re: Water and Wastewater Rate Study
Dear Jim:
It was good to speak with you today regarding the status of the above referenced project. This
letter will summarize the status of the various elements of the project and set forth a proposed
schedule for its completion.
On February 1, 2000, we presented the results of the revenue sufficiency analysis portion of the
project to your City Commission. If you will recall, the results of that analysis indicate that the
City can fund its proposed capital improvement program(exclusive of reclaimed water capital
projects) and its projected operations and maintenance costs for the next five years(FY 2000 -
FY 2004)with no increases in its water and sewer rates.
During that inecting we also discussed the need to conduct a water usage profile analysis to
determine the water usage profiles of Ocoee's water customers. This analysis is necessaty to
determine an accurate water usage profile for the City's water customers in order to properly
construct the City's reclaimed water rate system, including the impact upon water usage in the
form of loss of water billing units and the resultant impact upon the water rates to remain revenue
neutral. This irillimation is also necessary to evaluate the appropriate water rate structure for the
City with regard to its overall water conservation program. Dr. Don Brandes, of the St. Johns
River Water Management.District also spoke to this issue and strongly recommended that the
City proceed with such a water usage profile analysis to accurately access these water usage
issues.
We subsequently sent you a proposal to conduct a water usage profile analysis and arc awaiting
approval to proceed. in the meantime, as we discussed today, we can and will develop draft
reclaimed water rates and projections of the impact of reuse substitution upon potable water rates
using industry standard potable and irrigation water usage data. We will use water usage profile
data from other cities in Florida where we have developed reclaimed water rates as industry
standard data. Upon completion of the above referenced water usage profile analysis, we can
substitute Ocoee water usage profile data to determine the final reclaimed water rates.
440 Osceola Avenue • Jacksonville Beach,Florida 32250 ■ 904/247.0787
V
Mr. Jim Shira, P. E.
March 28, 2000
Page 2
We can complete the development of the draft reclaimed water rate program using industry
standard data by the end of April, 2000, We can complete the water usage profile analysis within
approximately 45 days of receipt of a notice to proceed. Upon completion of the water usage
profile analysis, we can complete the final reclaimed water rates and develop a recommended
water conservation potable water rate structure within approximately 30 days.
Therefore, assuming receipt of an authorization to proceed with the water usage profile analysis
by mid April, the remaining project milestones would be as follows:
Task Completion pate
Develop draft reclaimed water rates using industry
standard data April 28, 2000
Receive authorization to proceed with water usage profile
analysis April 18,2000
Complete water usage profile analysis May 31, 2000
Develop final reclaimed water rates with Ocoee water
usage profile data Juno 30,2000
Develop conservation rate structure for potable water rates June 30,2000
I trust that this project status summary will serve to provide an acceptable framework and plan for
completion of the study. if this plan is acceptable to the City, please contact me and we can
schedule specific dates for the staff work sessions and City Commission workshops that will be
necessary to complete the above referenced tasks and present the results to your City
Commission.
}-
I look forward to working with you during the completion of this important project. If you have
any questions, please do not hesitate to call me at(904) 247-0787.
Very truly yo s
Michael E. Burton
President