DATE: May 21, 1997
TO: The Honorable Mayor and Board of City Commissioners
FROM: James W. Shira, P.E.a
City Engineer/Utilities Director
SUBJECT: Phase I and Phase 2 Reclaimed Water System
The 1997 Water and Sewer Revenue Bond Issue included capital funding for the design,
permitting and construction of a reclaimed water system which will allow us to provide treated
wastewater for irrigation purposes.
Professional Engineering Consultants, Inc. has submitted the attached proposal for design
services for Phases 1 and 2. These phases include the storage facilities, pumps and pipelines
required to make reclaimed water available to the Clarke Road corridor.
Professional Engineering Consultants, Inc. proposes to design the required facilities for a not-to-
exceed fee of$159,250.00 which is 6.5%of the estimated cost of construction. If the actual cost
of construction is less than the estimated $2,450,000.00, PEC's fee will be reduced
proportionately.
I recommend that the City Commission authorize the Mayor and City Clerk to execute
Addendum 97-2 in the not-to-exceed amount of$159,250.00.
JWS/jbw
oG•-
THE PRIDE OF WEST ORANGE e<3
PEC
PROFESSIONAL ENGINEERING CONSULTANTS. INC.
May 7, 1997 P-6175R
Mr. James W. Shira, P.E.
City Engineer/Utilities Director
City of Ocoee = '
150 North Lakeshore Drive /t, ,
Ocoee, Florida 34761
8 -
Re: Phase 1 and Phase 2
Reclaimed Water Program
Dear Jim: .�
We are pleased to present this modified proposal for engineering and permitting services
related to the design of the Phase 1 and Phase 2 Reclaimed Water Program. Capital
funding for the design and construction of the Reclaimed Water Program was included
in the Series 1997 Water and Sewer Revenue Bond Issue. The initial phases of the
Reclaimed Water Program includes the following components:
I. 3.0 - 4.0 million gallon reclaimed water ground storage tank;
2. Reuse high service pumps and/or low lift pump station:
3. 16,300 L.F. of 16-inch reclaimed water main and 2,500 L.F. of 12-inch
reclaimed water main east along A.D. Mims Road and north and south along
Clarke Road.
The estimated cost of construction of Phases 1 and 2 Reclaimed Water Improvements
as defined in the Engineer's Report of the recent Water and Wastewater Revenue Series
1997 Bond Issue is $2.450,000 (Phase I - S1.600.000 and Phase 2 - $850.000). The
estimated cost of the storage pumping and control system is $1.300,000 and the
estimated cost of the distribution system is Si,L50.000. The reclaimed water ground
storage tank and reuse high service pumps are to be located on the City-owned
wastewater treatment site on A.D. Mims Road. The specific location will be
determined after completion of the preliminary engineering report. The reclaimed water
distribution system will be placed east along A.D. Mims Road to Clarke Road and
continue north and south along Clarke Road. These proposed improvements will allow
the City to supply reclaimed water to new developments along Clarke Road from
Clarcona-Ocoee Road south to S.R. 50. Examples of areas to be served reclaimed
water include: Prairie Lake PD; Lake Johio Shores; Whitehill property; Mulrey
property: Lake Lona Center, West Oaks Mall and the medians along Clarke Road.
As we have discussed, we propose an innovative approach to value the cost of
preliminary design, final design, and permitting for this reclaimed water project.
Previously we have developed a scope of work and estimated the number of hours
necessary to complete the various tasks associated with the design of a capital project.
srgmees
panes
surveyors FCC =__. ;cbirscn street • Suite 'SSC • Orlarcc. =area 32E01 • 407122-3062 • FAX 407.849.9401
Mr. James W. Shira. RE.
May 7, 1997
Page '_
We have entered into professional services contracts based on an estimated number of
manhours multiplied by an hourly rate resulting in a not-to-exceed amount as the
maximum fee for providing the engineering services. Our proposed new methodology
is based on a fixed percentage of the construction cost with an absolute ceiling of the
design cost. For the level of complexity of this design, we propose to complete the
preliminary design, final design, preparation of contract drawing and specifications for
a guaranteed maximum of 7.0% of the cost of construction of the storage and pumping
facilities and 5.5% of the cost of the construction of the distribution system. The
proposed design fee for the storage and pumping facility is $91,000 and the proposed
design fee for the distribution system is $63,250. A not-to-exceed amount of $5,000
is requested for the FDEP permitting requirement for a total fee of $159,250.00. In
preparation of the Engineers Report for the Series 1997 Issue, we projected a total
engineering cost for the Reclaimed Water Project(including design, permitting, bidding,
and construction) of $340.000. This proposal does not include fees for construction
phase services which the City may or may not want to engage the services of PEC.
Under the proposed methodology the maximum fee for design services is $159,250.00.
This methodology will result in a savings to the City of approximately 15% of the
design fee_
In summary. we propose to complete the design of the Phase I and Phase 2 Reclaimed
Water Program for a lump-sum fee not-to-exceed 7% of the construction value of the
storage and pumping facility and 5.5% of the construction value of the distribution
system. Including the $5,000 fee for permitting, we estimate the total engineering fee
to be 3159.250.00.
Please review this proposal and provide comments as necessary.
Very truly yours,
PROFESSIONAL ENGINEERING CONSULTANTS, INC.
Kenneth R. Hooper
Project Manager
KRH/bk
g:\c ler\env\pro97\p-6175 R.Itr
ADDENDUM NO. 97-2 TO
AGREEMENT FOR CONSULTING ENGINEERING SERVICES
INCLUDING
DESIGN AND CONSTRUCTION OF THE PHASE I AND PHASE 2
RECLAIMED WATER PROGRAM
This Addendum No. 97-2 hereinafter called the Addendum. as of this 7th day of May,
1997, shall constitute an Addendum to the Agreement for Consulting Engineering
Services between the City of Ocoee, Florida (the CITY) and Professional Engineering
Consultants. Inc., 200 East Robinson Street, Suite 1560, Lake Eola Centre, Orlando,
Florida (the CONSULTANT), dated the 21st day of August, 1984, hereinafter referred
to as the AGREEMENT.
WHEREAS, the CITY and CONSULTANT entered into an AGREEMENT whereby
the CITY retained the CONSULTANT to provide professional engineering services as
required from time to time, and WHEREAS the CONSULTANT will perform
consulting engineering services for the CITY as herein defined.
NOW THEREFORE, in consideration of the mutual covenants and promises hereinafter
set forth on the pan of both patties to be kept and performed, the patties do mutually
agree as follows:
Section 1 - Services of the Consultant
1.1 The CONSULTANT shall perform the Engineering services as outlined in the
attached proposal P-6175R, dated May 7, 1997 relative to the provision of
consulting engineering services to the CITY.
Section 2 - Compensation
2.1 Compensation by CITY for engineering services provided under this Addendum
shall be computed under Paragraph 6.1.2.3 of the Agreement, utilizing the
Percentage of Construction Value (Lump Sum) Method of Compensation with
the compensation for this additional authorization not-to-exceed $159,250.00 as
outlined in the attached proposal, without further authorization from the CITY.
Section 3 - Time of Completion
3.1 The CONSULTANT shall provide the services within six (6) months as
described in the attached proposal.
IN WITNESS WHEREOF, the panes have executed this Addendum No. 97-2 the day
the year hereinabove set forth.
ATTEST:
PROFESSIONAL—ENGINEERING CONSULTA.'TS, INC.
• F
-- BILE. LIt�!i_ By: .
Kenneth R. Hooper, Principal ri
Date: /�y�� /J / 2
ATTEST: BOARD OF CITY COMMISSIONERS
CITY OF OCOEE. FLORIDA
By:
S. Scott Vandererift. Mayor
Date:
For the use and reliance
of City of Ocoee only.
Approved as to form and
legality this
day of , 1997.
City Attorney
G4Icr cnv1oelococc 97-2.ADN -2- OE(04I08I97)