HomeMy WebLinkAboutIII (F) Approval and Authorization to Award a Contract with Prime Construction Group Inc. Agenda 4-20-99
"CAN"I'ER OF GOOD LIVING-PRIDE OF WEST ORANGE" MAYYORR•CCOMII MISSIONFR
S. SCOTT VANDERGRIET
Ocoee
` CITY OF OCOEE ONY OWE
ODANNY HONFRS
O
4i �� SCO'1'1'ANDERSON
l.• — ISO N. LARFSHORB DRIVE
Q RUSTY IOHRCI
\s„..........
00OF.9, 07)656 34761-2258NA STY 1. PARKER
��� (407)656-2322�, Cl3 ,� QIY NANAGFR
f*OF 6000�` ELIAS SI IAPIRO
MEMORANDUM
DATE: April 16, 1999
TO: The Honorable Mayor and Board of City Commissioners
FROM: David Wheeler,Assistant City Engineer/Utilities Director,,(YOn4/
SUBJECT: Phase 3 Water Distribution Mains Project
Award of Construction Contract
On Tuesday,April 13, 1999, bids were received for the Phase 3 Water Distribution Mains Project.
This phase of the water distribution mains projects was bid in two contracts. The attached figure
shows the general layout of the two projects. The work in this project generally includes:
Part1:
This contract allows for the installation of a new 12 inch water main along Ocoee-Apopka Road from
north of Silver Star Road to Fuller's Cross Road. The new pipeline will connect to the existing 12 inch
water main on Ocoee-Apopka Road at the Sobik's Sub Shop and run north to Fuller's Cross Road to
connect to the new water main to be constructed under the Part 2 contract.
Part 2:
This contract allows for the installation of a new 12 inch water main along Fuller's Cross Road and
Clarcona-Ocoee Road. The new pipeline will connect to the new water main constructed under the
Part 1 contract at the intersection of Fuller's Cross Road and Ocoee-Apopka Road and run cast to
Clarcona-Ocoee Road and then south along Clarcona-Ocoee Road to Wurst Road to connect to the new
12 inch water mains being constructed under the Phase I contract.
Four of the five contractors prequalified under Continuing Horizontal Construction Services program
submitted bids on these projects. 'their bids were:
CONTRACTOR PHASE 3/Part 1 WATER MAINS
Prime Construction Group, Inc. $348,840.00
Wharton-Smith, Inc. $427,000.00
Georgetown Enterprises, Inc. $436,825.00
Phillips& Jordan, Inc. $612,681.33
Engineer's Estimate $453,555.00 6 )7
CONTRACTOR PHASE 3/Part 2 WATER MAINS
Prime Construction Group, Inc. $297,775.00
Wharton-Smith, Inc. $338,000.00
Georgetown Enterprises, Inc. $391,325.00
Phillips& Jordan, Inc. $566,854.45
Engineer's Estimate $373,767.00
Fossitt Groundwork, Inc. has requested a release from the program due to contractual obligations with
another entity and therefore will not be bidding any future work.
The water pipelines were identified in the Water Master Plan as vital to the City's ability to meet
current and projected future demands on the City's water system. This project will enhance the water
system's ability to provide adequate pressure and flow to our customers during high demand periods
and to aide in minimizing reduction in pressure and flow at times when repairs are required within the
distribution system.
The attached letter from PEC, Inc. is a recommendation to award both contracts to Prime Construction
Group, Inc. in accordance with the base bid option. The project will be funded from the 1997 Utility
Bond Issue. The Engineering Staff concurs with PEC's recommendation to award the Phase 3 Water
Main Projects Parts 1 and 2 to Prime Construction Group, Inc. in the amounts of$348,840.00 and
$297,775.00, respectively. This construction cost of these projects is approximately 21.84 percent
lower than the engineer's estimate.
The intent is to secure bonds and insurance certificates, execute contract documents, and issue the
Notice To Proceed about the middle of May. The construction schedule requires the contractor to be
completed within 150 days.
Action Items:
1. I recommend that the City Commission authorize the Mayor and City Clerk to execute a contracts
with Prime Construction Group, Inc. in the amount of$348,840.00 for the Phase 3 Water
Distribution Main Project Part 1 and $297,775.00 for the Phase 3 Water Distribution Main Project
Part 2 in accordance with the following steps:
• Authorize the Engineering Department to execute the Notices of Intent To Award and
secure executed contract documents,bonds and insurance from the contractor.
• Authorize the Mayor and City Clerk to execute the contracts with Prime Construction
Group, Inc. at such time as the contract documents are reviewed for compliance by staff and
legal counsel, as needed.
DAW/jbw
Attachments
PEC
PROFESSIONAL ENGINEERING CONSULTANTS, INC.
April 15, 1999 OE-293-2.3.1/1.0
Mr. James W. Shim, P.E.
City of Ocoee
150 N. Lakeshore Drive
Ocoee, FL 34761
SUBJECT: City of Ocoee
Water Distribution Mains - Phase III, Part 1
RE: Recommendation of Award
Dear Mr. Shira:
On Tuesday, April 13, 1999, the City received sealed bids for the referenced project from
four (4) contractors. The attached tabulation of bids represents a summary of unit prices
provided by each of the bidders. The bid tabulation indicates Prime Construction Group,
Inc. as the apparent low bidder with a total bid price of$348,840.00. The second apparent
low bidder is Wharton-Smith, Inc. with a total bid price of $427,000.00, and the third
apparent low bidder is Georgetown Enterprises, Inc., with a total bid price of$436,825.00.
The highest total bid price is $612,681.33 (corrected from $557,975.98 due to a
mathematical error) submitted by Phillips and Jordan, Inc. The engineer's construction
estimate was $453,555.00. The bid proposals of the three (3) apparent low bidders are
complete and properly executed (except as noted on the attached Bid Checklist forms).
They have acknowledged receipt of the addendum and have submitted proposals to comply
with other City bidding requirements. While these special requirements must be verified
by the City, we believe that these bid proposals axe in conformance in all material respects
to the invitation for bids and are therefore responsive bids.
Based upon our review of the submittals from each of the bidders, and with the
understanding that these contractors have been pre-qualified for the City's Continuing
Construction Services Program, we recommend that the above referenced construction
contract be awarded to Prime Construction Group, Inc.
engineers
planners
surveyors 200 East Robinson Street • Suite 1560 • Orlando, Florida 32801 • 407;422-8062 • FAX 407;849-9401
Mr. James W. Shim, P.E.
April 15, 1999
Page 2
If you have any questions or comments, please contact me at your earliest convenience.
Sincerely,
PROFESSIONAL ENGINEERING CONSULTANTS, INC.
Arthur R. Austin, P.E., Principal
Manager - Environmental Department
ARA/cs
Attachments: Bid Tabulation
Bid Checklists
Original Bid Proposals
c:\...OS7D.ROA
cc: Mr. David Wheeler, P.E., City of Ocoee (w/o Bid Proposals)
Mr. Ken Hooper, PEC (w/o Bid Proposals)
Mr. Geoff Hennessy, PEC (w/o Bid Proposals)
PEC
PROFESSIONAL ENGINEERING CONSULTANTS, INC.
April 15, 1999
0E-293-2.3.2/1.0
Mr. James W. Shim, P.E.
City of Ocoee
150 N. Lakeshore Drive
Ocoee, FL 34761
SUBJECT: City of Ocoee
Water Distribution Mains - Phase III, Part 2
RE: Recommendation of Award
Dear Mr. Shira:
On Tuesday, April 13, 1999, the City received sealed bids for the referenced project from
four(4) contractors. The attached tabulation of bids represents a summary of unit prices
provided by each of the bidders. The bid tabulation indicates Prime Construction Group,
Inc. as the apparent low bidder with a total bid price of$297,775.00. The second apparent
low bidder is Wharton-Smith, Inc. with a total bid price of $338,000.00, and the third
apparent low bidder is Georgetown Enterprise, Inc. with a total bid price of$387,500.00
(corrected from $391,325.00 due to an extension mathematical error). The highest total
bid price is $566,854.45 (corrected from $513,380.01 due to a mathematical error)
submitted by Phillips and Jordan, Inc. The engineer's construction estimate was
$373,767.00. The bid proposals of the three (3) apparent low bidders are complete and
properly executed (except as noted on the attached Bid Checklist forms). They have
acknowledged receipt of the addendum and have submitted proposals to comply with other
City bidding requirements. While these special requirements must be verified by the City,
we believe that these bid proposals are in conformance in all material respects to the
invitation for bids and are therefore responsive bids.
Based upon our review of the submittals from each of the bidders, and with the
understanding that these contractors have been pre-qualified for the City's Continuing
Construction Services Program, we recommend that the above referenced construction
contract be awarded to Prime Construction Group, Inc.
engineers
planners
surveyors 200 East Robinson Street • Suite 1560 • Orlando,Florida 32801 • 4071422-8062 • FAX 407/849-9401
Mr. James W. Shira, P.E.
April 15, 1999
Page 2
If you have any questions or comments, please contact me at your earliest convenience.
Sincerely,
PROFESSIONAL ENGINEERING CONSULTANTS, INC.
Arthur R. Austin, P.E., Principal
Manager - Environmental Department
ARA/cs
Attachments: Bid Tabulation
Bid Checklists
Original Bid Proposals
G\_.\W1D.ROA
cc: Mr. David Wheeler, P.E., City of Ocoee (w/o Bid Proposals)
Mr. Ken Hooper, PEC (w/o Bid Proposals)
Mr. Geoff Hennessy, PEC (w/o Bid Proposals)
Ms. Cynthia K. Malone (w/o Bid Proposals)