Loading...
HomeMy WebLinkAboutIII (G) Approval and Authorization for Mayor and City Clerk to Execute Change Order No. 1 and Final for Reflections Subdivision Groundwater Seepage Improvements Agenda II-19-2002 Centel of Good Li Item 111 G S.oe .. __Mayor , Commissioners S. Scott Vandergrift Danny Howell, District 1 p�(� r Scott Anderson, District 2 City Manager ! ')�y M 1 Rusty Johnson, District 3 Jim Gleason �, ' 999��/////���. �MMM_e/ 7 Nancy J. Parker, District 4 MEMORANDUM DATE: November 8, 2002 TO: The Honorable Mayor and Board of City Commissioners FROM: David A. Wheeler, P.E. Director of Public Works SUBJECT: Reflection Subdivision Groundwater Seepage Improvements Project Change Order No. I and Final With Schuller Contractors,Inc. Attached for your review is Change Order Request No. 1 on the Reflection Subdivision Groundwater Seepage Improvements Project with Schuller Contractors, Inc. This change order request was initiated by City Staff to adjust unit quantities on a few construction items and resolve a existing utility conflict issue that lengthened the contractors schedule. The project included the installation of underdrains on Cool Springs Circle and Sparkling Water Road. In all unit price construction projects, a change order is required to adjust quantities from the estimated contract amount to the actual installed amount and adjust the associated costs to perform that work, to make them equal so that the contract is 100% complete and does not appear as if there is still work to be performed. This change order is performing that task of adjusting quantities and final the contract between the City and Schuller Contractors, Inc. There were 18 items of work required under this contract on this project. There were no work items that were over the estimated contract quantity and 3 work items that were under the estimated contract quantity which had a value of$3,701.17 to the City. At the Pre-construction conference, Schuller submitted a work schedule that showed that they would complete the underdrain installation in one week. Because of the size the underdrain envelope and the location of existing utilities, including the City's water main, Schuller was not able to meet the proposed schedule. They were required to perform hand excavation around some portions of the gas main that was not exactly where it had been shown on the drawings. Utility locates are only accurate to two feet left or right of the actual location. The existing utilities were not excavated to verify location, this is not a standard practice. The actual installation took over two weeks. The City of Ocoee• 150 N Lakeshore Drive•Ocoee. Florida 3476] phone:(407)905-3100• fax: (407)656-8504•www.ci.ococc flus contractor only requested one additional week of equipment and labor. The cost of this additional work is $8,003.71, with no adjustment in contract time. The attachment is a copy of Change Order No. 1, which is the final change order for this project. The original construction contract cost was $55,436.32. This change order increased the contract amount by $4,302.54, to a final contract amount of$59,738 86. The overall contingency usage was 7.76%of the original construction cost. This contract increase will be paid for out of the Stormwater Capital Fund, which is the funding source for the entire project. I recommend that the City Commission approve Change Order No. 1 with Schuller Contractors, Inc. by increasing the contract amount by $4,302.54, with no extension in contract time, and authorize the Mayor and City Clerk to execute Change Order No. 1. Attachment 1) Change Order No. I DAW/jbw Ocoee CITY OF OCOEE Engineering/Utilities 6 pa ,o 150 North Lakeshore Drive ?/ Ocoee, Florida 34761-2258 CHANGE ORDER NO. #1 CITY OF OCOEE Reflections Subdivision Groundwater Seepage Improvements DATE: October 30,2002 CONTRACTOR:Schuller Contractors, Inc. AGREEMENT DATE: May 15,2001 The following changes are hereby made to the CONTRACT DOCUMENTS, Original CONTRACT PRICE $ 55,436.32 Current CONTRACT PRICE ADJUSTED by previous CHANGE ORDER S 55,436,32 Net Increase Resulting from this CHANGE ORDER $ 4,30254 The current CONTRACT PRICE including this CHANGE ORDER $ 59,738.86 ORIGINAL CONTRACT TIME: 90 Consecutive Calendar Days from Notice to Proceed Date: October I, 2001 Current CONTRACT TIME adjusted by previous CHANGE ORDERS Date: October I, 2001 Net Increase Resulting from this CHANGE ORDER Days: 0 Days Current CONTRACT TIME Including this CI IANGE ORDER Date: October 1, 2001 00842-I CHANGES ORDERED: I. GENERAL This change order is necessary to cover changes in the work to be performed under this Contract. The GENERAL CONDITION,SUPPLEMENTARY CONDITIONS, SPECIFICATIONS and all parts of the Project Manual listed in Article I, Definitions. of the GENERAL CONDITIONS apply to and govern all work under this change order. II. REQUIRED CHANGES Item A: Deleted pay item 2d—Remove and Replace Landscaping in ROW. Item B: Reduce pay item 4—Construction Permit Allowance. Item C: Reduce pay item 10- Remove and Replace Concrete Sidewalks Item D: Additional cost due to working around existing utilities which were near the underdrain envelope III. JUSTIFICATION Item A: The extra landscaping in place at the time of the design had already been removed by the home owners. Item B: Reduced to actual permit cost from Ocoee Building Department. Item C: Reduced to actual quantity installed. Item D: The existing gas main and water main were in close proximity to the location of the underdrain envelope(3 foot by 3 foot cross section). In many places the underdrain installation required hard excavation and physically holding the other utilities out of the way while the underdrain was installed. The original work schedule showed one week of underdrain installation and the actual installation was over two weeks. IV. NARRATIVE OF NEGOTIATIONS Item A, R,& C: Prices were per the bid prices. Item D: Price was negotiated. V. PAYMENT Change Order Description Net Increase Unit Unit Price Net Increase Item Nn. (Ikcreasc)Quantity (Decrease)Price Item A Delete Remove it Replace Landscaping I S I 21161 90 (21161 90) Item 10 Reduce Construction Permit Allowance IS I 345.25 (3452) Item C Reduce Remove k Replace Concrete SY 40.35 32(17 (1294.(12) Driveways Item I) Additional cost ler working around existing IS I X.(103]1 8.002.7I utilities 'final Net Increase Change Order No. XI $4,3t)254 VI. APPROVAL AND CHANCE AUTHORIZATION 00842-2 This proposed change to the Contract is to be approved by the Ocoee City Commission. Acknowledgements: The aforementioned change,and work affected thereby, is subject to all provisions of the original contract not specifically changed by this Change Order; and, It is expressly understood and agreed that the approval of the Change Order shall have no elect on the original contract other than matters expressly provided herein. CONTRACTOR acknowledges, by its execution and acceptance of this Change Order,that the adjustments in Contract Price and Time shown hereon constitute full and complete compensation and satisfaction for all costs and modifications of performance time incurred by the CONTRACTOR as a result of this Change Order. No other claim for increased costs of performance or modifications of time will be granted by the OWNER for the Work covered by this Change Order. The CONTRACTOR hereby waives and releases any further claims for cost or time against the OWNER arising from or relating to the matters or Work set forth or contemplated by this Change Order RECOMMENDED BY: ACCEPTED BY: CITY OF OCOEE,FLORIDA SCHULLER CONTRACTORS, INC. By: By: Signature Signature Date: Date: title: Title' APPROVED BY: CITY OF OCOEE, FLORIDA By: S. Scott Vandergri R, Mayor Date Attest: .lean Grafton,City Clerk FOR USE AND RELIANCE ONLY BY TIIE APPROVED BY THE OCOEE CITY CITY OF OCOEE, APPROVED AS TO FORM COMMISSION IN A MEETING I IELD ON AND LEGALITY THIS DAY OF .2002 UNDER ,2002. AGENDA ITEM NO. FOLIEY &LARDNER By: City Attorney 00842-3 Contract Amounts Change Order No. 1 Adjustments Final Adjusted Quantities Item No. Description Quantity Unit Unit Price Total Price Quantity Unit Unit Price Total Price Quantity Unit Unit Price Total Price 1 Mobilization,Demobilization. Bonds,and Permits 1 LS $1 762.54 $1 76254 $0.00 1 LS $1 76254 $1,762.54 2 General Requirements-Division 1 1 LS $2,551.22 82,561 22 $000 1 LS $2,561.22 $2,561.22 a. Color Audio-Video Preconstruction Record 1 LS $572.75 $57275 $0.00 1 LS $572 75 $572.75 b. Field Engineering and Exploratory Excavation 1 LS $572.75 $572.75 $000 1 LS $57275 $57275 c. Utility Coordination 1 LS $572.75 $572.75 1 LS $572.75 $57275 d. Removal and Replace Landscaping in ROW 1 LS $2,061 90 $2,061.90 1 LS -$2051.90 -$2,061.90 1 LS $0.00 $000 e Record Drawing Preparation 1 LS $2.06190 $2,061.90 $0.00 I LS $2,061.90 $206190 f Traffic Control and Signage 1 LS $2,863 75 $2,863.75 1 LS $2,863.75 $2,863.75 3 Indemnification 1 LS $1,145.50 $1,14550 $0.00 1 LS $1,145.50 $1,145 50 4 Construction Permits Allowance 1 ALL. $572.75 $57275 1 ALL. -$345.25 -$345.25 1 ALL. $227.50 $22750 5 Clearing and Grubbing 1 LS $2,291.00 $2.291.00 $000 1 LS $2,291 00 $2,291.00 6 Furnish,Install Maintain&Remove Silt Fence 435 LF $2.29 $996.15 $000 435 LF $229 $996.15 7 Install 6 inch diameter Underdrain System 1,245 LF $20.62 $25.671.90 $000 1,245 LF $2062 $25,671.90 8 Connect Underdrain to Existing Drainage Structures 14 EA $57.28 $801.92 $000 14 EA $57.28 $801.92 9 Remove&Replace Concrete Driveways 133 SY $34.37 $4,571.21 $0.00 133 EA $34.37 $4571.21 Allowance for Removing& Replacing Concrete 10 Sidewalk 50 SY $32.07 $1,603.50 -40.35 SY $32.07 -$1,294.02 9.65 SY $32.07 $309.45 11 Remove&Replace Sod 1000 SY $2.29 $2,290.00 $0.00 1,000 LF $2.29 $2,290.00 12 Work not included but required, Etc. 1 LS $2.46283 $2,462.83 $0.00 1 EA $2,462.83 $2462.83 $55 436.32 -53.701.17 $51 735.15 Additional Work Because of Conflicts with Existing Utilities $8,003.71 Total Construction Cost $59,738.86 ���l_1 i.�chuller (, G Contractors Incorporated October 22, 2001 David A. Wheeler, P.E. Assistant City Engineer/Utilities Director City of Ocoee Florida 150 Lakeshore Drive Ocoee,Florida 34761 RE: Reflections Subdivision Groundwater Seepage Improvements Dear Mr. Wheeler, As I am sure that you are aware Schuller Contractors Incorporated is encountering conflicts with numerous utilities on the above referenced project. These conflicts,particularly with regards to the gas line,are delaying our progress on the project. The project plans do not show the conflict and in fact indicate that the existing gas line was not going to interfere with our installation of the underdrain. We are currently hand digging and moving the gas line in order to install the underdrain. This is not a part of our contract with the City. It is not the responsibility of Schuller Contractors Incorporated to relocate the existing utilities which conflict with the underdrain installation. Your office needs to immediately address this issue or we will be forced to demobilize from the project until these issues can be resolved. We look forward to hearing from you. Should you have any questions regarding this issue do not hesitate to contact me. Sincerely, Tim Schuller President /TS Att. 8046A Presidents Drive,Orlando,Florida 32809 407/855-55I2 407/85554922 ,„ �huller GContractors Incorporated October 24, 2001 David A. Wheeler, P.E. Assistant City Engineer/Utilities Director City of Ocoee Florida 150 Lakeshore Drive Ocoee,Florida 34761 RE: Reflections Subdivision Groundwater Seepage Improvements Dear Mr. Wheeler, We believe that the additional time that the utility conflicts have cost our company is $8,003.71. The cost breakdown is as follows: Supervisor @ $15.00/hr 45hrs/wk +benefits = $ 926.25/wk Pipe Layer @ $12.00/hr 45hrs/wk +benefits = $ 741.00/wk 3 Laborers @ $10.00/hr 45hrs/wk +benefits = $1,852.00/wk Loader @ $42.00/hr 40hrs/wk = $1,890.00/wk Backhoe @ $30.00/hr 40hrs/wk = $1,350.00/wk Truck Rental _ $ 200.00/wk $6,959.75/wk +15%oh & profit = $8,003.71 Thank you for your swift attention to this issue. Sincerely, Tim Schuller President ITS Att. 11046A Presidents Drive,Orlando,Florida 32809 407/855-5572 407/855-1922