HomeMy WebLinkAboutV (F) Progress Energy Upgrades on Old Winter Garden Road and Professional Parkway Agenda 7-15-2003
Mayor �e Center of Gas('fm, Commissioner', V F
S. Scott. Vandergrift . ni„ Uanm I luwell, Distil
ct
/�/'+ Scott Anderson. District 2
Cite Manager t Sr .1{i Husky .Johnson. District 3
Jim Gleason ([` 1 `� A Nancy 1 Parker. District 4
STAFF REPORT
TO: The Honorable Mayor and City Commissioners
FROM: David A. Wheeler, P.E., Director of Public Works
DATE: July 7, 2003
RE: Progress Energy upgrades on Old Winter Garden Road and Professional
Parkway
ISSUE
The City of Ocoee is in the process of finalizing the design plans for the improvements to Old
Winter Garden Road and Professional Parkway. As a part of those improvements the City will
be impacting some underground facilities located in a private right-of-way (ROW) owned by
Progress Energy, requiring Progress Energy to relocate its above ground facilities throughout
most of the project area, and replacing sonic aboveground facilities in another portion of the
project area.
BACKGROUND/DISCUSSION
Progress Energy has aboveground power distribution facilities along Professional Parkway and
Old Winter Garden Road from Hemple Road to Blackwood Avenue. These facilities are
distribution "power" poles located just inside the original right-of-way. They have underground
facilities along Old Winter Garden Road from Blackwood Avenue to approximately Professional
Parkway; these facilities are located within a private right-of-way obtained by Progress Energy.
To widen the road to four lanes, including drainage systems and sidewalks, the City had to obtain
additional right-of-way along the entire length of the project. Some of this ROW was given to
the City as part of adjacent development and the remainder was or is being purchased.
In the portion of the road along the Oak Forest Apartment complex where Progress Energy owns
a private ROW for there underground facilities, the City is requiring Progress Energy to relocate
some of their facilities at the Blackwood Avenue end of their ROW. Staff along with PEC, Inc.
avoided impacting the majority of the private ROW and the Progress Energy facilities but was
unable to completely avoid them. The cost for Progress Energy to purchase additional ROW and
relocate their facilities is estimated to cost $43,072.32. This cost is unavoidable and would be
paid for according to the proportional formula by Ocoee and Orange County per the Interlocal
Agreement.
In the portion of Old Winter Garden Road from Division Avenue to Blackwood Avenue,
Progress Energy's distribution poles will not be in conflict with the road widening and related
facilities. These eight poles are wooden type poles.
Throughout the rest of the project area, the aboveground wooden poles need to be moved back to
the edge of the new ROW line because they are in conflict with the road widening and related
facilities. There are 46 wooden poles that need to be moved. There is no cost to the City to
relocate the wooden poles.
The City's position on electrical power facilities in new developments has been to require that
they be underground. However, this is not new development but improvements affecting
existing facilities. Staff asked about the possibility of placing the electrical power in this area
underground. Progress Energy's position is that they will relocate or move aboveground
facilities at their cost but that should it be required that those facilities be moved and changed to
underground then the requesting entity must pay for that change from aboveground to below
ground. Progress Energy does not install underground facilities in public ROW, they purchase
private ROW so they can be the controlling party. There are also additional construction costs
associated with underground installations versus aboveground facilities. The cost to the City to
have the facilities changed to belowground is estimated to be at least $750,000 and probably
higher. Staff did not feel that this change from aboveground to belowground was warranted
based upon cost.
In attempting to follow the Land Development Code and the Activity Center Special
Development Plan requirements, staff looked at upgrading the distribution poles from wood to
gray concrete and upgrading the street lights from the standard gray "cobra head" type fixtures to
the black "deco roadway" type fixtures. Progress Energy does not paint or "color" distribution
poles. If the City was to require the distribution poles to be "colored", the City would have to
pay the up front cost to paint them and then the cost to repaint them each time they were
repainted. There is also a possible issue of maintenance and safety for the Progress Energy
employees because of electricity and paint. Progress Energy has never "colored" distribution
poles, so they did not have an estimated cost.
Because the distribution poles would be along the outside of the ROW, staff chose to place light
fixtures on these poles as opposed to the median type design used on Maguire Road. The Old
Winter Garden Road corridor is predominately commercial. The portion of Old Winter Garden
Road going east into Orange County has the distribution poles along the outside edge of the
ROW, the poles are wooden not concrete, and much of the area is not lighted. This is Orange
County's standard.
The City will probably be required to pay the total cost for the upgrade for the pales from wood
to concrete since it is an upgrade according to Orange County standards. Progress energy has
calculated the cost differential for wood poles versus concrete poles. For the 46 poles that need
to be relocated,the City's cost to upgrade them to concrete poles would be $32,115.99. For the 8
poles that do not need to be relocated and are wood, the City's cost to have them replaced with
concrete poles to be uniform throughout the project area would be $22,208.44. The total cost to
use concrete poles throughout the project area is $54,324 43_
Additionally, to have the entire roadway corridor lighted with the "deco roadway" fixtures the
upfront capital cost is estimated to not exceed $55,000. The light fixtures would be attached to
the distribution poles where available and additional poles would be installed in the areas where
there were no distribution poles. Because Orange County does not light their roadways, the City
would probably be required to bear the entire cost of the lighting.
RECOMMENDATION
Staff provides the following recommendation:
• Accept the proposal for the modifications as required within the Progress Energy ROW
to relocate their facilities to conflict with the roadway improvements for the cost of
$43,072.32 and authorize staff to execute the documents with Progress Energy. These
costs would be split between Ocoee and Orange County in the 46/54% respective share
arrangement.
• Authorize staff to proceed with the proposal to have Progress Energy install concrete,
instead of wooden, poles throughout the project limits for the amount of$54,324.43 and
authorize staff to execute the documents with Progress Energy. This cost would be paid
entirely by Ocoee.
• Authorize staff to proceed with the proposal to have Progress Energy install the black
"deco roadway" fixtures on the distribution poles and install additional concrete poles for
the remainder of the light poles for the not to exceed amount of $55,000 and authorize
staff to execute the documents with Progress Energy. This cost would be paid entirely by
Ocoee.
"the total cost for all three proposals is $152,396.75. The breakdown is Orange County's share is
approximately $23,259.05 and Ocoee's share is $129,137.70, to be paid from Transportation
Bond Funds earmarked for the Old Winter Garden Road/Professional Parkway Roadway
Improvements Project.