STAFF REPORT
TO: The Honorable Mayor and Board of City Commissioners
FROM: David A. Wheeler, P.E., Director of Public Works ,,&),Q4/
DATE: December 8, 2003
SUBJECT: Proposal for Engineering Services—Reuse Water Main Design and --
Construction Services for the Old Winter Garden Road/Professional
Parkway Project with Professional Engineering Consultants, Inc.
ISSUE
Should the Mayor and City Commissioners approve the Addendum to the Agreement for
Consulting Engineering Services with Professional Engineering Consultants, Inc. (PEC). The
addendum is for the design and construction services for the reuse main on Old Winter Garden
Road and Professional Parkway from Maguire Road to Blackwood Avenue.
BACKGROUND/DISCUSSION
As part of the expansion of the reuse system within the Ocoee service area, the Old Winter
Garden Road and Professional Parkway area falls within the guidelines for the expansion. The
area is a growing commercial corridor that uses lots of potable water for irrigation and the entire
right-of-way will be torn up during the roadway improvements project. The timing could not be
better to extend the backbone of the Ocoee reuse system.
The reuse project will include the installation of a 16 inch pipeline within the right-of-way and
stubouts to all the existing customers and proposed developments along the corridor. The
extension of the reuse pipeline from Maguire Road towards Clarke Road allows for the ultimate
connection of those two pipelines that make up backbone of Ocoee's reuse system at this time.
PEC has performed the design of the reuse water main in the subject area and included that
design in the roadway plans. PEC's cost to the City is $17,950 for the design and $8,704 for the
construction services. Attached is a copy of the proposal from PEC. This cost plus the
construction of the pipeline will be paid for by the 2003 Utility Bond Fund. The total cost of the
addendum is $26,654.00.
RECOMMENDATION
Staff recommends that the City Commission approve Addendum 03-03 to the Agreement for
Consulting Engineering Services with Professional Engineering Consultants, Inc. for the design
and construction services for the reuse water main along Professional Parkway and Old Winter
Garden Road from Maguire Road to Blackwood Avenue in the amount of $26,654.00 and
authorize the Mayor and City Clerk to execute the addendum.
ADDENDUM NO. 03-03 TO
AGREEMENT FOR CONSULTING ENGINEERING SERVICES
INCLUDING
ENGINEERING SERVICES FOR
CONSTRUCTION ADMINISTRATION/INSPECTION SERVICES FOR
CITY OF OCOEE
RECLAIMED WATER UTILITY DESIGN
This Addendum No. 03-03 hereinafter called the Addendum, as of this day of
2003, shall constitute an Addendum to the Agreement for Consulting Engineering
Services between the City of Ocoee,Florida(the CITY)and Professional Engineering Consultants,
Inc., 200 East Robinson Street, Suite 1560, Lake Eola Centre, Orlando, Florida (the
CONSULTANT),dated the 21st day of August, 1984,hereinafter referred to as the AGREEMENT.
WHEREAS, the CITY and CONSULTANT entered into an AGREEMENT whereby the CITY
retained the CONSULTANT to provide professional engineering services as required from time to
time, and WHEREAS the CONSULTANT will perform consulting engineering services for the
CITY as herein defined.
NOW THEREFORE, in consideration of the mutual covenants and promises hereinafter set forth
on the part of both parties to be kept and performed, the parties do mutually agree as follows:
Section 1 - Services of the Consultant
1.1 The CONSULTANT shall perform the Engineering Services as outlined in the attached
proposal(P-3069R1) dated June 24,2003 relative to the provision of design phase services
and construction administration services to the CITY.
Section 2 - Compensation
2.1 Compensation by CITY for engineering services for the Reclaimed Water Booster Pumping
Facility and Construction Administration/Inspection Services is provided under this
K:\ENV\DOCUMENT\OE\OCOEE\2003ADN\03-03ADN.wpd 1
Addendum shall be computed under Paragraph 6.1.2.3 of the Agreement,utilizing the Lump
Sum Method of Compensation with the compensation for this authorization not-to-exceed
$17,950 (for Design) and authorization not-to-exceed $8,704 (for Construction
Administration Services)as outlined in the attached proposal(P-3069R1)and manhour fee.
Section 3 - Time of Completion
3.1 The CONSULTANT shall provide the construction administration services within a 365
calendar day period(12 months) from the notice-to-proceed for construction as outlined in
the attached proposal.
IN WITNESS WHEREOF, the parties have executed this Addendum No. 03-03 the day the year
her=' . ••ve set • • .
ii
/
_ By: ��`7�J 20 )/7/17,4
Attest: i Kenneth R. Hoo er,Princi
Date: !Y/k 6
BOARD OF CITY COMMISSIONERS
CITY OF OCOEE, FLORIDA
By:
S. Scott Vandergrift,Mayor Date
Attest:
Jean Grafton, City Clerk
FOR THE USE AND RELIANCE ONLY BY APPROVED BY THE OCOEE CITY
THE CITY OF OCOEE, APPROVED AS TO COMMISSION IN A MEETING HELD ON
LEGALITY THIS DAY OF , 2003 UNDER
, 2003. AGENDA ITEM NO.
FOLEY&LARDNER
By:
City Attorney
K:\ENV\DOCUMENT\OE\OCOEE\2003ADN\03-03ADN.wpd 2
y 4'w
PROFESSIONAL ENGINEERING CONSULTANTS, INC.
June 24, 2003 P-3069R1
OE/MK-04
EC LE WE
Mr. David A. Wheeler, P.E.
AI
Public Works Director JUN 3 0 20O3
City of Ocoee
150 N. Lakeshore Drive
Ocoee, FL 34761
SUBJECT: Old Winter Garden Road/Professional Parkway
Water Main and Force Main Relocation Plans
RE: Proposal for Engineering Services - Reclaimed Water Utility Design
Dear Mr. Wheeler:
We are pleased to present the attached proposal for Engineering Services related to the above
referenced project. The Engineering Services include design and construction administration
services for a reclaimed water main within the Professional Parkway improvement program.
The proposed 16-inch reclaimed water main will extend along Professional Parkway from
Maguire Road to Blackwood Avenue. The project estimate(including engineering fees)for
this segment is $550,000.
The proposed reclaimed water main is a primary segment that will allow the future
interconnection of the City's reclaimed water system with reclaimed water from the County's
Consery II facility. In addition,the City will be able to provide reclaimed water service along
the Professional Parkway corridor to Blackwood Avenue. Bidding for this road widening
project is scheduled for August,2003. The short lead time for this Old Winter Garden Road/
Professional Parkway Reclaimed Water Utility Project requires an escalated design schedule.
We propose to perform the design engineering services described herein based on an hourly
not-to-exceed compensation method not-to-exceed $17,950 and the Construction
Administration Services not-to-exceed$8,704 without further authorization from the Owner.
Enclosed for your review are engineering design man-hour estimates included in Attachment
A and a cost estimate shown in Attachment B. Also included are Construction
Administration Services man-hour estimates included in Attachment C and a cost estimate
shown in Attachment D. We are prepared to complete this reclaimed water system
assignment in conformance with the roadway design schedule.
engineers "Engineering Our Community"
planners
surveyors 200 East Robinson Street°Suite 15600 Orlando,Florida 32801 407/422-8062 o FAX 407/849-9401
Mr. David Wheeler, P.E. P-3069R1
June 24, 2003 OE/MK-04
Page 2
We appreciate the opportunity to provide our services for this assignment. If you have any
questions or require additional information,please do not hesitate to contact the undersigned.
Sincerely,
PROFESSIONAL ENGINEERING CONSULTANTS, INC.
Kenneth R. Hooper
Principal
KRH/CKM/cs
K:\...\OE\PRO03\P-3069R 1
Enclosures:
(1) Attachment A-Design Engineering Man-hour Estimates
(2) Attachment B-Design Engineering Fee Estimate
(3) Attachment C-Construction Administration Services Man-hour Estimates
(4) Attachment D-Construction Administration Services Fee Estimate
cc: Tom Kelley P.E., PEC
Cynthia Malone, P.E.,PEC
Mr. David Wheeler, P.E. P-3069R1
June 24, 2003 OE/MK-04
Page 3
Professional Parkway Utility Design
ATTACHMENT"A"- MAN-HOUR ESTIMATES
Task Description/ Labor Classification/Hours
No Scope of Services P.M. Sr.E. Engr. CAM CAD WP Total
A PRELIMINARY DESIGN
1. Review City Utility Maps and other pertinent information to be made available by the 0 2 1 0 0 0 3
City.
2. Meet with the City to assist with identification of potential reclaimed water customers. 0 3 4 0 0 1 8
3. Prepare preliminary alignment for City's approval. 1 2 2 0 2 0 7
4. Prepare preliminary cost estimate. 1 4 1 0 0 1 7
5. Prepare and meet with City staff to review preliminary engineering data and estimates 1 3 3 0 2 1 10
before proceeding with final design.
SUBTOTAL TASK A-Preliminary Design 3 14 11 0 4 3 35
Mr. David Wheeler, P.E. P-3069R1
June 24,2003 OE/MK-04
Page 4
Professional Parkway Utility Design
ATTACHMENT "A"-MAN-HOUR ESTIMATES
Task Description/ Labor Classification/Hours
No Scope of Services P.M. Sr.E. Engr. CAM CAD WP Total
B FINAL DESIGN
1. Prepare Contract Drawings(11"X 17")as follows: 8 15 45 0 40 0 108
7-Single Frame Plan Sheets at 1"=40'scale
7-Single Frame Profile Sheets at 1"=40'scale
1 -Detail Sheet
15-Sheets Total
2. Prepare additional Technical Specifications in CSI format and Review/Edit the 1 4 10 0 0 8 23
completed Final Technical Specifications.
3. Submit 100%completion level construction documents. 0 0 3 0 2 2 7
4. Meet with City staff at 100%completion level to review the construction documents. 0 3 6 0 3 1 13
Respond to City review comments and revise accordingly.
5. Prepare and submit Final Engineering Cost Estimate. 1 1 6 0 0 1 9
6. Prepare and submit Final Construction Documents to be provided to the Contractor as 1 2 4 0 4 2 13
a Change Order.
7. Notify FDEP concerning expansion of Reclaimed Water Main within the City's 0 0 1 0 0 0 1
Permitted Reclaimed Water Service Area as part of the final Wastewater Certification
of Completion.
SUBTOTAL TASK B-Final Design 11 25 75 0 49 14 174
Mr. David Wheeler, P.E. P-3069R1
June 24, 2003 0E/MIC-04
Page 5
Professional Parkway Utility Design
ATTACHMENT"B" - COST ESTIMATES
Raw Hourly TASK A TASK B LABOR
LABOR CLASS Hourly Rate @ Prelim. Final COST
Rate 2.92 Mult. Design. Design
Direct Labor
Project Manager $43.60 $127.31 3 11 14 $1,782
Senior Engineer $36.00 $105.12 14 25 39 $4,100
Engineer $27.00 $78.84 11 75 86 $6,780
Const.Adm.Mgr. $36.00 $105.12 0 0 0 $0
CADD $19.50 $56.94 4 49 53 $3,018
Word Processor $14.00 $40.88 3 14 17 $695
Sub-Total Hours 35 174 209
Sub-Total Labor $3,071 $13,304 $16,375
Avg.Hrly Rate $87.75 $76.46
Sub:Consultant Services
Sub-Total Sub-Consultant Services $0 $0 $0
Other Direct Costs
Reproduction/Printing $75 $100 $175
Computer Support/Plotting $200 $1,000 $1,200
Telephone $25 $25 $50
Mileage $30 $30 $60
Postage $20 $40 $60
Fax $15 $15 $30
Sub-Total ODC $365 $1,210 $1,575
Total Costs
Total Costs $3,436 $14,514 $17,950
Mr. David Wheeler, P.E. P-3069R1
June 24, 2003 OE/MK-04
Page 6
Professional Parkway Utility Design
ATTACHMENT "C"-MAN-HOUR ESTIMATES
Task Description/ Labor Classification/Hours
No Scope of Services P.M. Sr.E. Engr. CAM CAD WP Total
C CONSTRUCTION ADMINISTRATION(no additional contract time)
1. Schedule and administer periodic progress meetings throughout progress of work. 0 0 0 0 0 0 0
Progress meetings will be held weekly. Number of progress meetings estimated at four
(4)with an average duration of four(4)hours.
2. Make visits to the site at intervals appropriate to the various stages of construction in 0 0 0 0 0 0 0
order to observe the progress and quality of Contractor's executed Work. One(1)visit
per week with and average visit duration of approximately four(4)hours. Provide
construction observation report for each visit.
3. Review and approve Shop Drawings, Product Data and Samples and Equipment 1 4 10 4 0 10 29
O&M's.
4. Review and recommend Contractor's Change Order Time Impact Analysis schedule. 0 0 0 4 0 2 6
5. Review field questions and/or problems and provided interpretation of Contract 0 1 .4 2 0 2 9
Documents. Issue written clarifications or interpretations of Contract Documents as-
necessary. Number of RFI's estimated at two(2).
6. Review and provide comments/recommendations concerning results of materials tests 0 0 0 4 0 2 6
and observations performed by project Quality Control Consultant.
7. Review,recommend and assist in negotiations of Contract Modification. 0 4 4 8 2 4 22
8. Observe piping system testing. 0 0 0 4 0 0 4
9. Upon written request by Contractor, conduct an inspection to determine if Work is 0 2 2 4 0 1 9
Substantially Complete and prepare and distribute a Punch List of items to be
addressed. Upon written request by Contractor,conduct a re-inspection to confirm that
Substantial Completion Punch List items have been addressed. Provide written
recommendation with respect to Project Substantial completion acceptance.
10. Upon written request by Contractor, conduct an inspection to determine if Work is 0 2 2 4 0 1 9
fmally complete and prepare and distribute a Punch List of items to be addressed.
Upon written request by Contractor, conduct a re-inspection to confirm that Final
Completion Punch List items have been addressed. Provide written recommendation
with respect to project Final Completion acceptance.
11. Provide mylar reproducible set of record drawings based upon field data provided by 0 1 1 2 4 1 9
the Contractor,Subcontractor(s),RPR,Subconsultant(s)and upon information obtained
directly during periodic site visits.
SUBTOTAL TASK C-Construction Administration 1 14 23 36 6 23 103
Mr. David Wheeler, P.E. P-3069R1
June 24, 2003 OE/MK-04
Page 7
Professional Parkway Utility Design
ATTACHMENT "D" - COST ESTIMATES
Raw Hourly TASK C LABOR
LABOR CLASS Hourly Rate @ Const. COST
Rate 2.92 Mult. Svcs.
Direct Labor
Project Manager $43.60 $127.31 1 1 $127
Senior Engineer $36.00 $105.12 14 14 $1,472
Engineer $27.00 $78.84 23 23 $1,813
Const.Adm.Mgr. $36.00 $105.12 36 36 $3,784
CADD $19.50 $56.94 6 6 $342
Word Processor $14.00 $40.88 23 23 $940
Sub-Total Hours 103 103
Sub-Total Labor $8,479 $8,479
Avg.Hrly Rate $82.32
Sub-Consultant Services
Sub-Total Sub-Consultant Services $0 $0
Other Direct Costs
Reproduction/Printing $50 $50
Computer Support/Plotting $100 $100
Telephone $10 $10
Mileage $30 $30
Postage $20 $20
Fax $15 $15
Sub-Total ODC $225 $225
Total Costs
Total Costs $8,704 $8,704
Mr. David Wheeler,P.E. P-3069R1
June 24, 2003 OE/MK-04
Page 8
PROPOSAL CONDITIONS
1. PEC shall provide Project Quality Control Consultant services by this proposal.
2. This Construction Administration/Construction Observation services proposal is based on a not-to-exceed
28 calendar day construction period with PEC office staff personnel normal 40 hour work weeks and on-site
personal normal 40 hour work weeks. PEC office staff working hours are from 8:00 a.m. to 5:00 p.m.
Monday through Friday.
3. The Owner shall provide additional compensation for construction phase services preformed by PEC in
connection with contract time extension beyond the stated not-to-exceed 28 calendar day construction
period. Said additional services shall be reimbursed by the Owner to PEC on an hourly basis for time
worked at the given rates as provided in this proposal and/or by any future amendments and/or modifications
thereto.
4. PEC shall not provide construction related surveying services by this proposal. Contractor shall be required
to perform referenced construction related surveying services.
5. The Owner shall provide additional compensation for construction phase services preformed by PEC in
connection with additional Owner requested services either beyond that estimated by this proposal or not
addressed within the scope of this proposal. Said additional services shall be reimbursed by the Owner to
PEC on an hourly basis for time worked at the given rates as provided in this proposal and/or by any future
amendments and/or modifications thereto.
6. This proposal provides for very limited PEC review of Contractor Proposed Changes and or Contractor
Value Engineering Proposals. However, as it is not possible to forecast time required to perform such
reviews or the number of possible proposals that may submitted,cost of such review should be covered by
the Contractor. PEC recommends that Owner's Specifications address reimbursement cost for Engineer's
review of Contractor Proposed Changes and or Contractor Value Engineering Proposals by the Contractor
as part of such proposals.