Background Summary:
The metal stormwater drainage pipe on Ocoee Hills Road between Apricot Drive and Flewelling Avenue
has deteriorated to the extent the line must be replaced. The current Public Works Stormwater budget
included a $100,000 capital item for this project. The City designed the pipe replacement in-house and
solicited pricing from the City's Continuing Contract for Small Construction Services vendors. The City
received three (3) responses with the low bid from Schuller Contractors at $103,700.00. Public Works
is requesting Commission approval to award the work to Schuller and reallocate Stormwater funds from
the General Stormwater System Improvements Capital line to cover the additional costs of the project
and any unanticipated change orders which may be required for completion.
Issue:
Request the City Commission to award the Ocoee Hills Road Pipe Repair Project to Schuller
Contractors and reallocate Stormwater funds as needed to complete the project.
Recommendations:
Recommend the City Commission approve the award of the Ocoee Hills Road Pipe Repair Project to
Schuller Contractors for $103,700.00, approve to reallocate $3,700.00 Public Works General
Stormwater System Improvements Capital funds to the project and recommend the City Manager and
staff be authorized to approve change orders to this contract up to the limit of his purchasing authority
for each change order, with funding from the General Stormwater System Improvements Capital line.
Attachments:
Project Site Plan
Schuller Contractors' bid.
Financial Impact:
The project and budget reallocation is adequately funded within the Public Works Stormwater Division.
Type of Item: (please mark with an x')
Public Hearing For Clerk's Dept Use:
Ordinance First Reading X Consent Agenda
Ordinance Second Reading Public Hearing
Resolution Regular Agenda
X Commission Approval
Discussion& Direction
Original Document/Contract Attached for Execution by City Clerk
Original Document/Contract Held by Department for Execution
Reviewed by City Attorney N/A
Reviewed by Finance Dept. N/A
Reviewed by ( ) N/A
2
° dY
.- ONSTRUCT NEW INLET TOP
, Not
i s :
{CAST-IN-PLACE FD
,.•
i�� { CURB INLET TOP o 1
s E, F TRANSITION GUTTE j
REMOVE AND REPLACE ji • ""'i� '7R f
PLACEFDOT ' R
FLEWELLING AVENUE 40'
—, • 1".40
it ,' '., �. SCALE
i,� .• s P 1 sA i �s• MOVE ACE J
+ „ �.., ' . ASPHALT' NT EDGE LL
(2"SP-9.5.2-Lifts a7 F
_*-^- ' CONSTRUCTION NOTES: p
CUT +• a e ,r: I 1. PRIOR TO CONSTRUCTION,CONTRACTOR RESPONSIBLE TO VERIFY DEPTH OF u.8
" ':; C'"' l ti EXISTING STORM STRUCTURES FOR SHOP DRAWING SUBMITTAL. v '9.
71'— ' 2. PRIOR TO CONSTRUCTION,CONTRACTOR RESPONSIBLE FOR INSTALLING EROSION 3°�;
•
h I a /, i �" CONTROL MEASURES,INCLUDING INLET PROTECTION AND SILT FENCE. - •?
„ : °' ET T c 3. CONTRACTOR RESPONSIBLE TO PROVIDE TEMPORARY TRAFFIC CONTROL PLAN E
w .~ a ? PRIOR TO CONSTRUCTION.
I 7, "" 4. CONTRACTOR RESPONSIBLE TO REMOVE AND HAUL OFF ALL DEMOLITION ITEMS. „.��
y -'V + .- 5. CONTRACTOR RESPONSIBLE FOR DEWATERING ACTIVTIES. CONTRACTOR SHALL USE °
I17 TTAL.AND REPLACE I A SILENCE PUMP FOR DEWATERING OPERATION. /
4'WIDE CONCRETE . 6. CITY OF OCOEE WILL PROVIDE COMPACTION TESTING.
SIDEWALK(3000PSI) I• 7. ANY DAMAGES TO PRIVATE FENCING AND ITEMS WITHIN CONSTRUCTION LIMITS WILL
•EMOVE CORRUGATED BE REPAIRED AT CONTRACTORS EXPENSE.
4In PIPE SYSTEM
4 ••';�r "" I 1 8. CITY OF OCOEE CAN PROVIDE FILL MATERIAL,IF REQUIRED. o
"• ' SILT PENCE o ai
' I ,,, firil
a .,4
R,
x
•
a_ w Y 7 UQ
•EMOVE AND REPLACE o
i . ASPHALT PAVEMENT EDG: ! Won 61
(2"SP-9.5,2-Lifts) ° .,k.o-
• ~• ° 0.44
III . ° X 3 .0 iYPE'D'INLET I 'EMOVE CONCRETE BOX $ i : *Idd /
a ft
-ETICULINEGRATE) 22,_ ST RE • �f PROJECT' �U °' + "~'�4
XISTING ELEVATIONS I ,-4' Nopr +"' "`- r c
';. AND INVERTS , LOCATION PO. OF va.W.0. a e
1
. -. ...,,4,,..44,,•,4..•' EX.PI' '.„ 1 A c..wm ca.a i iQ 0
. t ' ROVI'EAD ` ! E
w
TRUN''TED M! LA Fp °
4111 REMOVE ANL REPLACE MAT 7 V I """" rnw�m.Dr r ® OP 44E". ,
CONCRETE FLUME AND ---- -.....L.• .1 z r �'z
HANDRAIL 1 ,,°+,� ■y s ! li I �)CIrcM O
* w w n
"elaillitiiii ;AO
O O E Silver Sts Rd O
WwTp�'c%^4 I.I.I
dii
1111 ^ AutoZone Auto Pals 9
CITY OF OCOEE
OCOEE HILLS ROAD DRAINAGE IMPROVEMENTS PROJECT
OPINION OF PROBABLE CONSTRUCTION COST
BID NO.:
DATE OF OPENING:December 13,2019
SCHULLER CONTRACTORS INC. CENTRAL FLORIDA ENV.CORP RMS CONSTRUCTORS GROUP,LLC.
Item# Quantity Unit Item Description Unit Price Extensions Unit Price Extensions Unit Price Extensions
IMPROVEMENTS
1.01 1 LS Mobilization/Execution of General Requirements(10%Max.of Base Bid) $9,000.00 $9,000.00 $11,555.00 $11,555.00 $10,000.00 $10,000.00
1.02 1 LS Erosion Control(Silt Fencing/Inlet Protection) $2,000.00 $2,000.00 $2,025.00 $2,025.00 $7,500.00 $7,500.00
1.03 1 LS Temporary Traffic Control $4,500.00 $4,500.00 $8,713.00 $8,713.00 $12,500.00 $12,500.00
Demolition and Removal(Pipe/Concrete
1.04 1 LS Box/Sidewalk/Flume/Handrail/Pavement) $10,800.00 $10,800.00 $20,713.00 $20,713.00 $30,000.00 $30,000.00
1.05 200 LF Furnish and Install ADS HD Pipe(30"Pipe)Jincludes Dewatering) $195.00 $39,000.00 $230.25 $46,050.00 $140.00 $28,000.00
1.06 1 EA Furnish and Install FDOT Type'D'DBI(<10-ft) $5,400.00 $5,400.00 $5,467.00 $5,467.00 $8,500.00 $8,500.00
1.07 1 EA Construct Curb Inlet Top(FDOT Type 4) $2,400.00 $2,400.00 $2,562.00 $2,562.00 $10,000.00 $10,000.00
1.08 1 EA Construct Curb Inlet Top(FDOT Type 3) $2,400.00 $2,400.00 $1,966.00 $1,966.00 $10,000.00 $10,000.00
1.09 100 SY Asphalt Pavement Edge Repair(2"SP-9.5,2-Lifts) $80.00 $8,000.00_ $71.45 $7,145.00 $100.00 $10,000.00
1.10 100 SY Construct 4"Concrete Sidewalk(4'Wide) $50.00 $5,000.00 $68.85 $6,885.00 $60.00 $6,000.00
1.11 20 LF Construct Transitional Curbing $60.00 $1,200.00 $17.25 $345.00 $50.00 $1,000.00
1.12 1 EA Storm Pipe Connection/FDOT Collar $1,800.00 $1,800.00 $1,245.00 $1,245.00 $2,500.00 $2,500.00
1.13 1 LS Concrete Flume $3,000.00 $3,000.00 $4,961.00 $4,961.00 $3,500.00 $3,500.00
1.14 20 LF FDOT Two Tier Handrail $100.00 $2,000.00 $121.50 $2,430.00 $140.00 $2,800.00
1.15 1 EA Ramp with ADA Mat $1,200.00 $1,200.00 $1,451.00 $1,451.00 $1,500.00 $1,500.00
1.16 3000 SF Sodding(Bahia) $2.00 $6,000.00 $1.20 $3,600.00 $1.00 $3,000.00
TOTAL BASE BID=_ $103,700.00_ $127,113.00 $146,800.00
CITY OF OCOEE
OCOEE HILLS ROAD DRAINAGE PIPE REPAIR PROJECT
Submitted by:Schuller Contractors Incorporated
DATE:December 13,2019 by COB
Item# Quantity Unit Item Description Unit Price Extensions
IMPROVEMENTS
1.01 1 LS Mobilization/Execution of General Requirements(10%Max.of Base Bid) $9,000.00 $9,000.00
1.02 1 LS Erosion Control(Silt Fencing/Inlet Protection) $2,000.00 $2,000.00
1.03 1 LS Temporary Traffic Control $4,500.00 $4,500.00
1.04 1 LS Demolition and Removal(Pipe/Concrete Box/Sidewalk/Flume/Handrail/Pavement) $10,800.00 $10,800.00
1.05 200 LF Furnish and Install ADS HD Pipe(30"Pipe) $195.00 $39,000.00
1.06 1 EA Furnish and Install FOOT Type'D'DBI(<10-ft) $5,400.00 $5,400.00
1.07 1 EA Construct Curb Inlet Top(FOOT Type 4) $2,400.00 $2,400.00
1.08 1 EA Construct Curb Inlet Top(FOOT Type 3) $2,400.00 $2,400.00
1.09 100 SY Asphalt Pavement Edge Repair(2"SP-9.5,2-Lifts) $80.00 $8,000.00
1 10 100 SY Construct 4"Concrete Sidewalk(4'Wide) $50.00 $5,000.00
1.11 20 LF Construct Transitional Curbing $60.00 $1,200.00
1.12 1 EA Storm Pipe Connection/FOOT Collar $1,800.00 $1,800.00
1.13 1 LS Concrete Flume $3,000.00 $3,000.00
1.14 20 LF Furnish and Install FOOT Two Tier Handrail $100.00 $2,000.00
1.15 1 EA Ramp with ADA Mat $1,200.00 $1,200.00
1.16 3000 SF Sodding(Bahia) $2.00 $6,000.00
$103,700.00
TOTAL BASE BID= $103,700.00
CITY OF OCOEE
OCOEE HILLS ROAD DRAINAGE PIPE REPAIR PROJECT
Central Florida Environmental,Corp.
DATE: December 13,2019
Item# Quantity Unit Item Description Unit Price Extensions
IMPROVEMENTS
1.01 1 LS Mobilization/Execution of General Requirements(10%Max.of Base Bid) $11,555.00 $11,555.00
1.02 1 LS Erosion Control(Silt Fencing/Inlet Protection) $2,025.00 $2,025.00
1.03 1 LS Temporary Traffic Control $8,713.00 $8,713.00
1.04 1 LS Demolition and Removal(Pipe/Concrete Box/Sidewalk/Flume/Handrail/Pavement) $20,713.00 $20,713.00
1.05 200 LF Furnish and Install ADS HD Pipe(30"Pipe) (includes dewatering) $230.25 $46,050.00
1.06 1 EA Furnish and Install FDOT Type'D'DBI(<10-ft) $5,467.00 $5,467.00
1.07 1 EA Construct Curb Inlet Top(FDOT Type 4) $2,562.00 $2,562.00
1.08 1 EA Construct Curb Inlet Top(FDOT Type 3) $1,966.00 $1,966.00
1.09 100 SY Asphalt Pavement Edge Repair(2"SP-9.5,2-Lifts) $71.45 $7,145.00
1.10 100 SY Construct 4"Concrete Sidewalk(4'Wide) $68.85 $6,885.00
1.11 20 LF Construct Transitional Curbing $17.25 $345.00
1.12 1 EA Storm Pipe Connection/FDOT Collar $1,245.00 $1,245.00
1.13 1 LS Concrete Flume $4,961.00 $4,961.00
1.14 20 LF Furnish and Install FDOT Two Tier Handrail $121.50 $2,430.00
1.15 1 EA Ramp with ADA Mat $1,451.00 $1,451.00
1.16 3000 SF Sodding(Bahia) $1.20 $3,600.00
$127,113.00
TOTAL BASE BID= $127,113.00
RMS Constructors Group,LLC.
CGC No: 1507424
CITY OF OCOEE
OCOEE HILLS ROAD DRAINAGE PIPE REPAIR PROJECT
DATE:12/13/19
Item# Quantity Unit Item Description Unit Price Extensions
IMPROVEMENTS
1.01 1 LS Mobilization/Execution of General Requirements(10%Max.of Base Bid) $10,000.00 $10,000.00
1.02 1 LS Erosion Control(Silt Fencing/Inlet Protection) $7,500.00 $7,500.00
1.03 1 LS Temporary Traffic Control $12,500.00 $12,500.00
1.04 1 LS Demolition and Removal(Pipe/Concrete Box/Sidewalk/Flume/Handrail/Pavement) $30,000.00 $30,000.00
1.05 200 LF Furnish and Install ADS HD Pipe(30"Pipe) $140.00 $28,000.00
1.06 1 EA Furnish and Install FDOT Type'D'DBI(<10-ft) $8,500.00 $8,500.00
1.07 1 EA Construct Curb Inlet Top(FDOT Type 4) $10,000 00 $10,000.00
1.08 1 EA Construct Curb Inlet Top(FDOT Type 3) $10,000.00 $10,000.00
1.09 100 SY Asphalt Pavement Edge Repair(2"SP-9.5,2-Lifts) $100.00 $10,000.00
1.10 100 SY Construct 4"Concrete Sidewalk(4'Wide) $60.00 $6,000.00
1.11 20 LF Construct Transitional Curbing 550.00 $1,000.00
1.12 1 EA Storm Pipe Connection/FDOT Collar $2,500.00 $2,500.00
1.13 1 LS Concrete Flume $3,500.00 $3,500.00
1.14 20 LF Furnish and Install FDOT Two Tier Handrail $140.00 $2,800.00
1.15 1 EA Ramp with ADA Mat $1,500.00 $1,500.00
1.16 3000 SF Sodding(Bahia) $1.00 $3,000.00,
TOTAL BASE BID= $146,800.00