HomeMy WebLinkAboutItem 11 Approval of Project Budget and Exhibit A – Amendment to the Design-Build Agreement with Wharton-Smith for Construction of the New City Hallr;; ; Ocoee AGENDA ITEM COVER Meeting Date: October 20, 2020 Item # Reviewed By Contact Name: J. Croteau Department Director: J. Croteau , Contact Number: 407-905-3159 City Manager: Robert Frank Subject: Approval of Project Budget and Exhibit A — Amendment to the Design -Build Aareement with Wharton -Smith for Construction of the New Citv Hall Background Summary: On January 15, 2019, the City Commission approved an Agreement with Wharton -Smith to provide Design -Build Services for the new City Hall. On October 15, 2019, the City Commission selected an exterior design concept and authorized Staff to continue with the design process allowing the internal specifics of the building to fall to the City Manager for approval. In August, the Design -Build team completed the building design and Wharton -Smith began soliciting bids from subcontractors. The bids were due back to Wharton -Smith on October 1, 2020. Since that time Wharton -Smith has been compiling the bids, reviewing the scope with their subcontractors and negotiating for better pricing. For the approximately 46,000 square feet, three-story structure, Wharton -Smith has provided a Guaranteed Maximum Price (GMP) of $17,255,537, The GMP includes a 5% fee, $821,692, for Wharton -Smith and a 3%, $478,656, in Design -Builder Contingency. The Contingency can be used by Wharton -Smith to cover items such as subcontractor defaults, cost overruns not covered by allowances, and scope gaps between subcontractors. It cannot be used for the removal and replacement of any deficient work. The use of the contingency requires verification and agreement by the City. It also requires that any savings incurred during subcontractor buyouts go into the Design - Builder Contingency. If at the end of the contract there is money left in the Design -Builder Contingency then Wharton -Smith would be entitled to 25% of the Contingency amount. The remaining amount would be returned to the City. Along with the GMP, the total project budget of $21,993,942, includes a 7.5% project contingency ($1.53 mil), 15% for furniture fixtures and equipment ($2.6 mil), and 3.5% miscellaneous amount that covers a variety of items needed to complete the building such as testing services, permitting, consultants, attorneys' fees, etc. The City and Wharton -Smith will be following the guidelines for the Owner's Direct Purchase Program, which should provide the City with approximately $150,000 in sales tax savings. Staff is requesting: A. Approval of the Project Budget; and B. Approval of Exhibit A — Amendment to the Design -Build Agreement with Wharton -Smith for Construction of the New City Hall; and C. The City Manager be authorized to approve use of the Design -Builder Contingency; and D. The City Manager be authorized to approve contracts and spending up to the amount of the Project Budget. Recommendations: A. Approve the Project Budget B. Approve Exhibit A — Amendment to the Design -Build Agreement with Wharton -Smith for Construction of the New City Hall C. Authorize the City Manager to approve use of the Design -Builder Contingency D. Authorize the City Manager to approve, and the Mayor to sign, contracts and spending up to the amount of the Project Budget Attachments: Exhibit A — Amendment to the Design -Build Agreement with Wharton -Smith Financial Impact: $21,993,942 Type of Item: (please mark with an "x ) Public Hearing Ordinance First Reading Ordinance Second Reading Resolution Commission Approval 4— Discussion & Direction Original Document/Contract Attached for Execution by City Clerk Original Document/Contract Held by Department for Execution Reviewed by City Attorney Reviewed by Finance Dept. Reviewed by Rebecca Roberts 10-14-20 For Clerk's Dept Use: Consent Agenda Public Hearing Regular Agenda 2 AIA Document ♦, I 20141 Exhibit A Design -Build Amendment This Amendment is incorporated into the accompanying AIA Document A141T"h-2014, Standard Form of Agreement Between Owner and Design -Builder dated the ((fifteenth N; day of ((January)) in the year a 2019»', (the "Agreement") (In words, indicate day, month and year.) for the following PROJECT: (Nance and location or address) RFP #18-001 Design -Build Services for New Ocoee City Hall THE OWNER: (Name, legal status and address) THE DESIGN -BUILDER: (Nance, legal status and address) The Owner and Design -Builder hereby amend the Agreement as follows. TABLE OF ARTICLES A.1 CONTRACT SUM A.2 CONTRACT TIME A.3 INFORMATION UPON WHICH AMENDMENT IS BASED AA DESIGN -BUILDER'S PERSONNEL, CONTRACTORS AND SUPPLIERS A.5 COST OF THE WORK ARTICLE A.1 CONTRACT SUM § A.1.1 The Owner shall pay the Design -Builder the Contract Sum in current funds for the Design -Builder's performance of the Contract after the execution of this Amendment. The Contract Sum shall be one of the following and shall not include compensation the Owner paid the Design -Builder for Work performed prior to execution of this Amendment: (Check the appropriate hox) [ a1 )i ] Stipulated Sum, in accordance with Section A.1.2 below author of this document has added information needed for its icompletion. The author may also have revised the text of the original AIA standard for.. A. Additions andl Deletions Report that notes added information as tell as revisions to the standard form text is available. from theauthor and should be reviewed. This document has important legal consequences. Consultation with an attorney is encouragedwith is completion or with respect to professional licensing requirements in the jurisdiction where the Project is located. ELECTRONIC COPYING of any portion of this AIA" Document to another electronic file is prohibited and constitutes a violation of copyright laws as set forth in the rooter of this document. Alk Document A14111- 2014 Exhibit A. Copyright G 2004 and 2014 by The eaerican Institnte of Architects. All rights reserved. Ishi.ING: tihis Au° at ' tod by 0.5. C p 'st d i t t' 2 T U .' .d d'.t' di t 'h 'f '}' AlA ar•ypo t..on of may '-'It i2 v v 1 a,d o - I p al ri _., and "411_ pcoeao..tea to he v ox. s t pe. <ialm under to 1— This draft was produced by AIA software at 17:53:49 on 09/06/2018 under Orden 110.4296692226 which expires . 09/06/2019, and is not for resale. User Notes: Error! Unknown document property name. (930172996) [ « >a ] Cost of the Work plus the Design -Builder's Fee, in accordance with Section A.1.3 below [ <<M> ] Cost of the Work plus the Design -Builder's Fee with a Guaranteed Maximum Price, in accordance with Section A.1.4 below (Based on the selection above, complete Section A.1.2, A.1.3 or A.1.4 below.) § § A.1.4 Cost of the Work Plus Design -Builder's Fee With a Guaranteed Maximum Price § A.1.4.1 The Cost of the Work is as defined in Article A.S, Cost of the Work. § A.1.4.2 The Design -Builder's Fee: (State a hinip sum, percentage of Cost of the ff/ork or other provision for determining the Design -Builders Fee and the metliod for adjustment to the Fee for changes in the fork.) , § A.1.4.3 Guaranteed Maximum Price § A.1.4.3.1 The sum of the Cost of the Work and the Design -Builder's Fee is guaranteed by the Design -Builder not to exceed a Seventeen Million Two Hundred Fifty-five Thousand Five Hundred Thirty-seven Dollars and No Cents ($ 17,255,537.00), subject to additions and deductions for changes in the Work as provided in the Design -Build Documents. Costs that would cause the Guaranteed Maximum Price to be exceeded shall be paid by the Design -Builder without reimbursement by the Owner. (Insert speck provisions if the Design -Builder is to participate in any savings.) § A.1.4.3.2 Itemized Statement of the Guaranteed Maximum Price Provided below is an itemized statement of the Guaranteed Maximum Price organized by trade categories; allowances, contingencies, alternates, the Design -Builder's Fee, and other items that comprise the Guaranteed Maximum Price. (Provide information below, or reference an attachment.) " As shown on Attachment A Guaranteed Maximum Price Details attached hereto. § A.1.4.3.3 Alternates listed on the attachment are not included in GMP. Alternates to be accepted or declined no later than November 13, 2020. (Slate the numbers or other identification of accepted alternates. If the Owner is per mated to accept other aternates subsequent to the execution of this Amendment, attach a schedule ofsuch other alternates showing the change in the Cost of the ffrork and Guaranteed Maxim hot Price for each and the deadline by which the alternate must be accepted) § A.1.4.3.4 Unit Prices, if any: AIA Docoment A341M - 2014 Exhibit A. Copyright O' 2004 and 2014 by The American Institute of Architects. All rights roadrued. WARNING: Thi.c nIA" OieusorL t. t d by U 9. C py.:..h T- t G o P„. d 'tof thir AIA' [, oz . .. t cud c al L, ._ .i Lt boo 'ed to th sible under a e i " This 2 draft ... produced by AIA iseftvaarev at 1":53:49 on r09/06/2018 under Order No.4296692226, which expires on m 09/06/2019, and is not for Tocsin. User Notes: Error! Unknown decament property name. (930172996) (Identib, item, state the unit price, and state any applicable quantity limitations) Item Units and Limitations Price per Unit ($0.00) N/A N/A N/A' § A.1.4.3.5 Assumptions, if any, on which the Guaranteed Maximum Price is based: § A.1.5 Payments § A.1.5.1 Progress Payments § A.1.5.1,1 Based upon Applications for Payment submitted to the Owner by the Design -Builder, the Owner shall make progress payments on account of the Contract Sum to the Design -Builder as provided below and elsewhere in the Design -Build Documents. ----- § A.1.5.1.2 The period covered by each Application for Payment shall be one calendar monthending on the last day of the month, or as follows: § A=1.5.1.3 The Design -Builder shall submit each month's Application for Payment not later thanithe 25th day of the month. Payment by the Owner shall comply with the applicable portions of Florida Statute 218.735 Timely payment for purchases of construction services. (Federal, state or local lairs may require payment within a certain period of time) § A,1.5,1.4 With each Application for Payment where the Contract Sum is based upon the Cost of the Wok, or the Cost of the Work with a Guaranteed Maximum Price, the Design -Builder shall submit Waivers of Lien for Design -Builder and each potential bond clannant that was included in the previous month's pay application, payrolls, petty cash accounts, receipted invoices or invoices with check vouchers attached, and any other evidence required by the Owner to demonstrate that cash disbursements already made by the Design -Builder on account of the Cost of the Work equal or exceed (1) progress payments already received by the Design -Builder, less (2) that portion of those payments attributable to the Design -Builder's Fee; plus (3) payrolls for the period covered by the present Application forPayment. § A.1.5.1.5 With each Application for Payment where the Contract Sum is based upon a Stipulated Sum or Cost of tl Guaranteed Maximum Price, the Design -Builder shall submit the most recent schedule of values in accordance with Documents. Tine schedule of values shall allocate the entire Contract Sum among the various portions of the Work. ( design services, if any, shall be shown separately. Where the Contract Sum is based on the Cost of the Work with "a ( Price, the Design -Builder's Fee shall be shown separately. The schedule of values shall be prepared in such form am data to substantiate its accuracy as the Owner may require. This schedule of values, unless objected to by the Owner, e for reviewing the Design -Builder's Applications for Payment. § A.1.5.1.6 In tatting action on the Design -Builder's Applications for Payment the Owner shall be entitled to rely on completeness of the information furnished by the Design -Builder and shall not be deemed to have made a detailed ei arithmetic verification of the documentation submitted in accordance with Sections A.1.S.1.4 or A� 1.5.15, onother sr made exhaustive or continuous on -site inspections; or to have made examinations to ascertain how or for what put po has used amounts previously paid. Such examinations, audits and verifications, if required by die Owner, wilfbe pelf, auditors acting in the sole interest of the Owner. I § A.1,5.1.7 Except with the Owner's prior written approval, the Design -Builder shall not make advance payments materials or equipment which have not been delivered and stored at the site, ---- +1 Work with a e Design -Build mpensation for aranteed Maximum upported by such ill be used as a basis accuracy and iination, audit or orting data; to have the Design -Builder led by the Owner's for § A.1.5.4 Progress Payments —Cost of the Work Plus a Fee with a Guaranteed Maximum Price § A.1,5.4.1 Applications for Payment where the Contract Sum is based upon the Cost of the Work Plus a Fee with a Guaranteed(Maxi Price shall show the percentage of completion of each portion of the Work as of the end of one period covered by the Applidatiofi for Payment. The percentage of completion shall be the lesser of (1) the percentage of that portion of the Work which has actually been completed; or (2) the percentage obtained by dividing (a) the expense that has actually been it}eurred by the Design -Builder on accou that portion of the Work for which the Design -Builder has made or intends to make actual payment prior to the next Application for Payment by (b) the share of the Guaranteed Maximum Price allocated to that portion of the Work in the schedule of values. AIA Document A141n' - 2014 Exhibit A. Copyright 0 2004 and 2014 by The Nnerican Institute of Architects. Aft rights reserved, oSrm NG: M. ULU C t protected bv U.S.Copyrsqht Lau, Sui S C t I t: . UL.cL. 't t t "hi A1,- rSec rmc�t, o- 3 ay Ccrti.n o1 't, y x svlt V cai peuolt- , nd ✓'1 ae pr c ten n t - posoanie ,azr the i This draft was produced by AZA softwareat 1L53:49 on 09/06/2018 under Order No.4296692226 which expires on 09/06/2019, and is not for resale. User Notes: Essavl Unknown document property name. (930172996) of § A.1.5.4.2 Subject to other provisions of the Design -Build Documents, the amount of each progress payment shall be computed as follows: 1 Take that portion of the Guaranteed Maximum Price properly allocable to completed Work as determined by multiplying the percentage of completion of each portion of the Work by the share of the Guaranteed Maximum Price allocated to that portion of the Work in the schedule of values. Pending final determination of cost to the Owner of changes in the Work, amounts not in dispute shall be included as provided in Section 6.3.9 of the Agreement. .2 Add that portion of the Guaranteed Maximum Price property allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the Work, or if approved in advance by the Owner, suitably stored off the site at a location agreed upon in writing; .3 Add tine Design -Builder's Fee, less retainage of ten percent 110 %). The Design -Builder's Fee shall be computed upon the Cost of the Work at the rate stated in Section A.1.4.2 or, if the Design -Builder's Fee is stated as a fixed sum in that Section, shall be an amountthatbears the same ratio to that fixed -sum fee as the Cost of the Work bears to a reasonable estimate of the probable Cost of the Work upon its completion; A Subtract retainage of ten percent ( 10 %) from that portion of the Work that the Design -Builder self -performs; .5 Subtract the aggregate of previous payments made by the Owner; .6 Subtract the shortfall, if any, indicated by the Design -Builder in the documentation required by Section A.I.5.1.4 to substantiate prior Applications for Payment, or resulting from errors subsequently discovered by the Owner's auditors in such documentation; and .7 Subtract amounts, if any, for which the Owner has withheld or nullified a payment as provided in Section 9.5 of tine Agreement. .8 In accordance with Florida Statute 218.735, after 50%g of the construction services are completed and upon the request of the Design Builder, the retainage may be reduced to five percent (5%) of the work completed § A.1.5.4.3 The Owner and Design -Builder shall agree upon (1) a mutually acceptable procedure for review and approval of payments to the Architect, Consultants, and Contractors and (2) the percentage of retainage held on agreements with the Architect, Consultants, and Contractors; and the Design -Builder shall execute agreements in accordance with those terms. § A.1.5.5 Final Payment § A.1.5.5.1 Final payment, constituting the entire unpaid balance of the Contract Sum, shall be made by the Owner to the Design -Builder not later than 30 days after the Design -Builder has fully performed the Contract and the requirements of Section 9.10 of the Agreement have been satisfied, except for the Design -Builder's responsibility to correct non -conforming Work discovered after final payment or to satisfy other requirements, if any, which extend beyond final payment, § A.1.5.5.2 If the Contract Sum is based on the Cost of the Work, the Owner's auditors will review and report in writing on the Design -Builder's final accounting within 30 days after the Design -Builder delivers the final accounting to the Owner. Based upon the Cost of the Work the Owner's auditors report to be substantiated by the Design -Builder's final accounting, and provided the (other conditions of Section 9.10 of tine Agreement have been met, the Owner will, within seven days after receipt of the written report of the Owner's auditors, either issue a final Certificate for Payment, or notify the Design -Builder in writing of the reasons for withholding a certificate as provided in Section 9.5.1 of the Agreement. ARTICLE A.2 CONTRACT TIME § A.2.1 Contract Time, as defined in the Agreement at Section 1.4.13, is the period of time, including authorized adjustments, for Substantial Completion of the Work. § A.2.2 The Design -Builder shall achieve Substantial Completion of the Work not later than a » (t » ) days from the date of this Amendment, or as follows: (Insert number of calendar days. Alternatively, a calendar date may be used when coordinated with the date of commencement. If appropriate, insert requirements for• earlier Substantial Completion of certain portions of the Work) Portion of Work Substantial Completion Date , subject to adjustments of the Contact Time as provided in the Design -Build Documents. i (Insert provisions, ifany, for liquidated damages relating to failure to achieve Substantial Completion on tine orfor bonus pe early completion of the YPork) ATA Document A141- - 2014 Exhibit A. Copyright O 2004 and 2014 by The Americas Institute of Architects. All rights reserved. WArI4:NC: This AIA' D 1" or, f by 2h I 1 t_. t L 1"Ti L tL d p. d l'' t i t E t AIA U nI_ bx -y T.stl . oI t, try sdd It a -i c II and and w 11 b_ p d I. t � ti L� . This 4 draft was budneed by AIA seftbare at 10:53:49 on P09/06/2016 Insist Order No.4296692226 which expiresyanc09/06/2019,s and is rut for Tessin. User Notes: Error! Unknown document property name. (930172996( ARTICLE A.3 INFORMATION UPON WHICH AMENDMENT IS BASED § A.3.1 The Contract Sum and Contract Time set forth in this Amendment are based on § A.3.1.1 The Supplementary and other Conditions of the Contract: Document Title Date N/A` § A.3.1.2 The Specifications: (Either list the specifications here or refer to an exhibit attached to this Amendment.) § A.3.1.3 The Drawings: (Either list the dralvings here or refer to an exhibit attached to this Amendment.) § A.3.1.5 Allowances and Contingencies: (Identijj� an), agreed upon allowances and contingencies, including a statement of their basis.) .2 AID Document A141^ — 2014 Exhibit A. Copyright n 2004 and 2014 by The American Institute of Architects. All rights reserved. WRN'NG: Ths Y.IA° 0 t ,ot Iod hy] 9 4Y 4,ht Lon and I E.. 1 Tr­ti.. of thi. R k 5 —y Fort.., mqj Y v _ 1 _ Y_ i.erx 1 p a to .. .,., exttni po13. v de r c ]as. .Thi9 draft w s pr.dneed by AIA software at 17:53:49 on 09/06/2016 under Order No.4296692226 which expires do 09/06/2019, and is not for s eals. User Notes: Error[ Unknovn tlocumxnt property name. (930132996) the savings will be assigned to the Design -Builder Construction Contingency. At the completion of the Project, any amount not used in file Construction Contingency shall be subject to the shared savings provisions in paragraph A.1'4..3.1. § A.3.1.6 Design -Builder's assumptions and clarifications: § A.3.1.8 To the extent the Design -Builder shall be required to submit any additional Submittals to the Owner for review, indicate any such submissions below: ARTICLE A.4 DESIGN -BUILDER'S PERSONNEL, CONTRACTORS AND SUPPLIERS § A.4.1 The Design -Builder's key personnel are identified below: (Jdenti)� name, title and contact information.) .1 Superintendent James A. Jenkins, Project Superintendent, Wharton -Smith, Inc. E-mail: tienk ns(awhartonsmith.com Mobile: (407) 739-9565 .2 Project Manager Randall Ellington, Senior Project Manager, Wharton -Smith, Inc. E-mail: relhneton i�whartonsmitin.cosii Mobile: (407) 640-0441 .3 Others Rick Bundy, Jr., Project Executive, Wharton -Smith, hie. E-mail: rbunl �uharionsmith,corn Mobile: (407) 948-9910 Trent Mayberry, Assistant Project Manager, Wharton -Smith, Inc e-mail: hnayben a+whartansmith col Mobile: (407) 257-7447 Alex McBride, Assistant Superintendent, Wharton -Smith, Inc. - e-mail: amebride@whartonsrnitlr.com Mobile: (407)I256-4685 The Owner reserves the right to approve all Design -Builder's personnel, contractors and suppliers working on the project, an approval shall not be unreasonably withheld, If the Owner requests that any Design -Builder personnel, contractor, or supplie removed from the project, the Design -Builder will immediately remove that party without impact to the Owner or the project schedule. The Owner's direction to remove a party can be with or without written explanation.` § A.4.2 "flre Design -Builder shall retain the following Consultants, Contractors and suppliers, identified below: this be cost or Alk Document A141m - 2014 Exhibit A. Copyright 0 2004 and 2014 by The American institute of Architects. All right. reserved. S9iRNT.G, 'Thin .ASA` D p ky U S I. , '.g i S 1 R t Uc,,oLUoe .d: t d tr T' th At1 L. ry, ac y yawasop of r m.ay ,: vso ., . I o aundea, r d ..l.I ba 9 I. expires � 9/0 /2 19,.:a d i r cfo 1. resale. This thndra6 User was produced by nATAow software at property 9 on 09/O6/2010 under Order No.91.96692226 which expires on 09/06/2019, antl is not for r sale. Geer Notes: Errorl Unknown document property name. J930112996) (List name, discipline, address and other information) G131IaAAE l34Zid1MIAi:ISTAilti, § A.5.1 Cost To Be Reimbursed as Part of the Contract Costs of the Work reimbursement outlined below, unless specifically stated to the contrary, are included in the Guaranteed Maximum Price (GNP) as outlined in A.1.43.1 above. No other costs will be allowed without the prior written approval of the Owner, § A.5.1.1 Labor Costs § A.5.1.1.1 Wages of construction workers directly employed by the Design -Builder to perform the construction of the Work at the site or, with the Owner's prior approval, at off -site workshops. § A.5.1.1.2 With the Owner's prior approval, wages or salaries of the Design -Builder's supervisory and administrative personnel when stationed at the site. (If it is intended that the wages or salaries of certain personnel stationed at the Design -Builders principal or other offices shall be included in the Cost of the II'ork,, identify below the personnel to be included, whetherfor all a)• only part of their time, and the rates at which their time will be charged to the Work) Person Included Rate (unit of § A.5.1.1.3 Wages and salaries of the Design -Builder's supervisory or administrative persorm road, in expediting the production or transportation of materials or equipment required for tl time required for the Work d at factories, workshops or on the but only for that portion of their AIA Document A141`x - 2014 Exhibit A. Copyright n 2004 and 2014 by The American Institute o£ Architects. 1,11 rights xe rved. 61>9S;,b=!?, L. G,_ t.rur­t to Cccte.t.d by U S C ' t t' _ m - t' t h t C th' ,. t— 7a_y ..o _ .n _t, ay 21 t r..tie_, —1 .� - Le pz rA to EI e m This draft o s produced by AIA softwa at 17:53:49 on 09/06/2010 under Order No.4296692226 which expires ou 09/06/2019, and is mt for r sale. User Netee: Error l Unknown document property name. (930172996) § A.5.1.1.4 Costs paid or incurred by the Design -Builder for taxes, insurance, contributions, assessments and benefits required by law or collective bargaining agreements and, for personnel not covered by such agreements, customary benefits such as sick leave, medical and health benefits, holidays, vacations and pensions, provided such costs are based on wages and salaries included in file Cost of the Work under Section A.5. L L § A.5.1.1.5 Bonuses, profit sharing, incentive compensation and any other discretionary payments paid to anyone hired by the Design -Builder or paid to the Architect or any Consultant, Contractor or supplier, with the Owner's prior written approval. § A.5.1.2 Contract Costs. Payments made by the Design -Builder to the Architect, Consultants, Contractors and suppliers in accordance with the requirements of their subcontracts. § A.5.1.3 Costs of Materials and Equipment Incorporated in the Completed Construction § A.5.1,3.1 Costs, including transportation and storage, of materials and equipment incorporated on to be incorporated in the completed construction. § A.5.1,3.2 Costs of materials described in the preceding Section A.513.1 in excess of those actually installed to allow for reasonable waste and spoilage. Unused excess materials, if any, shall become the Owner's property at the completion of the Work or, at the Owner's option, shall be sold by the Design -Builder. Any amounts realized from such sales shall be credited to the Owner as a deduction from the Cost of the Work. § A,5.1.4 Costs of Other Materials and Equipment, Temporary Facilities and Related Items § A.5.1.4.1 Costs of transportation, storage, installation, maintenance, dismantling and removal of materials, supplies, temporary facilities, machinery, equipment and hand tools not customarily owned by construction workers that are provided by the Design -Builder at the site and fully consumed in the performance of the Work. Costs of materials, supplies,temporary facilities, machinery, equipment and tools that arenot fully consumed shall be based oil the cost or value of the item at the time it is first used on the Project site less the value of the item when it is no longer used at the Project site, Costs for items not fully consumed by the Design -Builder shall mean fair market value. § A.5.1.4,2 Rental charges for temporary facilities, machinery, equipment and hand tools not customarily owned by construction workers that are provided by the Design -Builder at the site and costs of transportation, installation, minor repairs, dismantling and removal. The total rental cost of any Design -Builder -owned item may not exceed the purchase price of any comparable item. Rates of Design -Builder -owned equipment and quantities of equipment shall be subject to the Owner's prior written approval. § A.5.1.4.3 Costs of removal of debris from the site of the Work and its proper and legal disposal § A.5.1,4,4 Costs of document reproductions, electronic communications, postage and parcel delivery charges, dedicated data and communications services, teleconferences, Project websites, extranets and reasonable petty cash expenses of the site office. § A.5.1.4.5 Costs of materials and equipment suitably stored off the site at a mutually acceptable location, with the Owners prior written approval. § A.5.1.5 Miscellaneous Costs § A.5.1.5.1 Premiums for that portion of insurance and bonds required by the Design -Build Documents that can be directly attributed to the Contract. With the Owner's prior written approval self-insurance for either full or partial amounts of the coverages required by the Design -Build Documents. Bond requirements, as outlined in §3.1,16 of the Agreement between the Owner and Design -Builder, shall be modified as follow: the Design -Builder shall furnish the Owner with a 100% Performance Braid — AIA A312-2010 Performance Bond, The Design -Builder shall furnish the Owner with a Public Construction Payment Bond in the form attached hereto. As shown on Attachment H AIA A312-201 Performance Bond attached hereto As shown on Attachment I Public Construction Payment Bond attached hereto § A,5.1.5.2 Sales, use or similar taxes imposed by a governmental authority that are related to the Work and for which the r is liable. AIA Document A14Ve - 2014 Exhibit A. Copyright 0 2004 and 2014 by The Noe dean Institute of Architects. All rights reperved. WAPNI i3 th:a AIF°' by 1 .!. l _ 1 I th _P 1, ,t 'h Y t ALA J nt or } .t Bey z <_b 6t'6/ Ire c d., e d NN ie to o pes .rb_e de the law. This User w e purred! by AIA software at property ne 09/06/2018 under Order No.9296692226 which expires on 09/06/2019 and is not for r sale. User Notes: Error! Unknown document pxopeity name. 19301"]2996) § A.5.1.5.3 Fees and assessments for the building permit and for other permits, licenses and inspections for which the Design -Builder is required by the Design -Build Documents to pay. § A.5.1.5.4 Fees of laboratories for tests required by the Design -Build Documents, except those related to defective or nonconforming Work for which reimbursement is excluded by Section 15.5.3 of the Agreement or by other provisions of the Design -Build Documents, and which do not fall within the scope of Section A.5.1.6.3. § A.5.1.5.5 Royalties and license fees paid for the use of a particular design, process or product required by the Design -Build Documents; the cost of defending suits or claims for infringement of patent rights arising from such requirement of the Design -Build Documents; and payments made in accordance with legal judgments against the Design -Builder resulting from such suits or claims and payments of settlements made with the Owner's consent. However, such costs of legal defenses, judgments and settlements shall not be included in the calculation of the Design -Builder's Fee or subject to the Guaranteed Maximum Price. If such 'i`oyalties, fees and costs are excluded by the second to last sentence of Section 3.1.13.2 of the Agreement or other provisions of the Design -Build Documents, then they shall not be included in the Cost of the Work. § A.5.1.5.6 With the Owner's prior written approval, costs for electronic equipment and software directly related to the Work. § A.5.1.5.7 Deposits lost for causes other than the Design -Builder's negligence or failure to fulfill a specific responsibility in the Design -Build Documents. § A.5.1.6 Other Costs and Emergencies § A.5.1.6.1 Other costs incurred in the performance of the Work if, and to the extent, approved in advance in writing by the Owner. § A.5.1.6.2 Costs incurred in taking action to prevent threatened damage, injury or loss in case of an emergency affecting the safety of persons and property. § A.5.1.7 Related Party Transactions § A.5.1.7.1 For purposes of Section A.5.1.7, the term "related party" shall mean a parent, subsidiary;affiliate or, other entity having common ownership or management with the Design -Builder; any entity in which any stockholder in, or management employee of, the Design -Builder owns any interest in excess of ten percent in the aggregate; or any person of entity .which has the right to control the business or affairs of the Design -Builder. The term "related party" includes any member of the immediate family of any person identified above. - I. § A.5.1.7.2 If any of the costs to be reimbursed arise from a transaction between the Design -Builder and a related party, the '. Design -Builder shall notify the Owner of the specific nature of the contemplated transaction, including the identity of the related party and the anticipated cost to be incurred, before any such transaction is consummated or cost incurred. If the Owner, after: such notification, authorizes the proposed transaction, then the cost incurred shall be included as a cost to be reimbursed, and the Design -Builder shall procure the Work, equipment, goods or service from the related party, as a Contractor,' according to the terms of Section A.5.4. If the Owner fails to authorize the transaction, the Design -Builder shall procure the Work, equipment, goods or service from some person or entity other than a related party according to the terms of Section A.5.4. § A.5.2 Costs Not to Be Reimbursed as Part of this Contract The Cost of the Work shall not include the items listed below: .1 Salaries and other compensation of the Design -Builder's personnel stationed at the Design -Builder's principal office or offices other than the site office, except as specifically provided in Section A.S.1.1; --- .2 Expenses of the Design -Builder's principal office and offices other than the site office; .3 Overhead and general expenses, except as may be expressly included in Section A.S.1;..,, ---- .4 The Design -Builder's capital expenses, including interest on the Design -Builder's, capital employed for the Work; .5 Except as provided in Section A.5.1.63 of this Agreement, costs due to the negligence or failure of the Design -Builder, Contractors and suppliers or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable to fulfill a specific responsibility of the Contract; .6 Any cost not specifically and expressly described in Section A.5.1; and .7 Costs, other than costs included in Change Orders approved by the Owner, that would cause the Guaranteed Maximum Price to be exceeded. AIA Document A141M - 2014 Exhibit A. Copyright O 2004 and 2014 by The American Institute of Architects. All rights reserved..mnulnc; 2:us nlnn U t t t d 'r U 9 1.11,ht t- -t 1 _ Una,ilot z d t'_ _ d t_' t 1his ATA D it, or any 1 rtion of it, ney r. u1t _)ait z nal Pena Wed to o - Cio..e � cde.. th. . This 9 draft w s produced by AIA softwareat 17�:53:49 on o9/06/2018 antler Order No.4296692226 which expires onR09/06/2019, and is not for resale. User Notes: Error[ Oak— document property name. (930172996) § A.5.3 Discounts, Rebates, and Refunds § A.5.3.1 Cash discounts obtained on payments made by the Design -Builder shall accrue to the Owner if (1) before making the payment, the Design -Builder included them in an Application for Payment and received payment from the Owner, or (2) the Owner has deposited funds with the Design -Builder with which to make payments; otherwise, cash discounts shall accrue to the Design -Builder. Trade discounts, rebates, refunds and amounts received from sales of surplus materials and equipment shall accrue to the Owner, and the Design -Builder shall make provisions so that they can be obtained. § A.5.3.2 Amounts that accrue to the Owner in accordance with Section A.53.1 shall be credited to the Owner as a deduction from the Cost of the Work. § A,5.4 Other Agreements § A.5.4.1 When the Design -Builder has provided a Guaranteed Maximum Price, and a specitie bidder (1) is recommended to the Owner by the Design -Builder; (2) is qualified to perform thatportion of the Work; and (3) has submitted a bid that conforms to the requirements of the Design -Build Documents without reservations or exceptions, but the Owner requires that another bid be accepted, then the Design -Builder may require that a Change Order be issued to adjust the Guaranteed Maximum Price by the difference between the bid of the person or entity recommended to the Owner by the Design -Builder acid the amount of the subcontract or other agreement actually signed with the person or entity designated by the Owner. § A.5.4.2 Agreements between the Design -Builder and Contractors shall conform to the applicable payment provisions of the Design -Build Documents, and shall not be awarded on the basis of cost plus a fee without the prior consent of the Owner. If an agreement between the Design Builder and a Contractor is awarded on a cost plus a fee basis, the Design -Builder shall provide in the agreement for the Owner to receive the same audit rights with regard to the Cost of the Work performed by the Contractor as the Owner receives with regard to the Design -Builder in Section A.5.5, below. § A.5.4.3 The agreements between the Design -Builder and Architect and other Consultants identified in the Agreement shall. be in writing. These agreements shall be promptly provided to the Owner upon the Owner's written request. § A.5.5 Accounting Records The Design -Builder shall keep full and detailed records and accounts related to the cost of the Work and exercise such controls as may be necessary for proper financial management under the Contract and to substantiate all costs incurred. The accounting and control systems shall be satisfactory to the Owner. The Owner and the Owner's auditors shall, during regular business hours ands, upon reasonable notice, be afforded access to, and shall be permitted to audit and copy, the Design -Builder's records and accounts, including complete documentation supporting accounting entries, books, correspondence, instructions, drawings; receipts, subcontracts, Contractor's proposals, purchase orders, vouchers, memoranda and other data relating to the Contract. The Design -Builder shall preserve these records for a period of ten (10) years after final payment, or for such longer period as may be required by law... PUBLIC RECORDS COMPLIANCE: The City of Ocoee (City) is a public agency subject to Chapter 119, Florida Statutes: The Contractor agrees to comply with Florida's Public Records Law. Specifically, the Contractor shall:.. 1. Keep and maintain public records required by the City to perform the service. 2. Upon request from the City's custodian of public records, provide the City with a copy of the requested records or allow the records to be inspected or copied within a reasonable time at a cost that does not exceed the cost providedfin chapter 119, Florida Statutes, or as otherwise provided by law. 3. Ensure that public records that are exempt or confidential and exempt from the public records disclosure requirements are not disclosed except as authorized by law for the duration of the contract term and following completion of the contract if the Contractor does not transfer the records to the City. 4. Upon completion of the contract, Contractor agrees to transfer at no cost to the City all public records in possession of Tile Contractor or keep and maintain public records required by the City to perform the service. If the Contractor- transfers all public record to the City upon completion of the contract, the Contractor shall destroy any duplicate public records that are exempt or confidential and exempt from public records disclosure requirements. If the Contractor keeps and maintains public records upon completion of the contract, the Contractor shall meet all applicable requirements for retaining public records. All records stored electronically must be provided to the City, upon request from the City's custodian of public records, in a format that is compatible with the information technology systems of the City. 5. A Contractor who fails to provide the public records to City within a reasonable time may be subject to penalties under °section 119.10, Florida Statutes. IF THE CONTRACTOR HAS QUESTIONS REGARDING THE APPLICATION OF CHAPTER 119, FLORIDA STATUTES, TO THE CONTRACTOR'S DUTY TO PROVIDE PUBLIC RECORDS RELATING TO TERS CONTRACT, CONTACT THE CUSTODIAN OF PUBLIC RECORDS AT 407-905-3100, EXTENSION 1022, CCDL a ci.ococe.fl.us, WITH AN OFFICE LOCATED AT 150 NORTH LAKESHORE DRIVE, OCOEE, FLORIDA 34761. ATA Document A14Vx - 2014 Exhibit A. Copyright O 2004 and 2014 by The American Institute o£ Architects. A11 rights se seed. wP m_mG: a. a A!, ° T P C 1 Y G C P} h t Z I' 1. 1 6 h .. _ d f c' L d - E 2 t f L h IA 0 nt, .1 } }ortw, o -' cad v i P`nz - nd .ail Le F'o muted to th. L p',s bi_ �d— th. La This l� a. draft , s produc,d by AIA seft,—eatc 1y:53:49 on 09/06/2018 under Order No.4296692226 which expires on 09/06/2019, and is not for x sale. User Notes: Excoil Unknovn document property name. (930172996) § A.5.6 Relationship of the Parties The Design -Builder accepts the relationship of trust and confidence established by this Agreement and covenants with the Owner to exercise the Design -Builder's skill and judgment in furthering the interests of the Owner; to furnish efficient construction administration, management services and supervision; to furnish at all times an adequate supply of workers and materials; and to perform the Work in an expeditious and economical manner consistent with the Owner's interests. This Amendment to the Agreement entered into as of the day and year first written above. Signature page follows. Are, Document A14rs - 2014 Exhibit A. Copyright Q 2004 and 2014 by The American Institute of Architects. All rights reserved. WACN?NG: This A'rpa Dt t is C,yt,i by, U,C. c av ', r z d 1 t t' -1 tit t f ch' 11. any 4>u t of .1.v'l. and c al penel t_e ,.il,b - pr wd to th exicv ­,I—t n ender the I—, This draft w so prodr,od by AIA'software at 17:53:49 on 09/06/2018 ender Order No.4296692226 iabich expires of 09/06/2019, and in not for r sale. User Notes: Errorl Unknown document property name. (930172996( CITY OF OCOEE SIGNATURE PAGE FOR DESIGN -BUILD SERVICES FOR NEW OCOEE CITY HALL DESIGN -BUILDER: WHARTON-SMITH, INC. SIGNATURE: PRINT NAME TITLE: WITNESSES: NAME: TITLE: OWNER: CITY OF OCOEE, FLORIDA ATTEST: APPROVED: BY: BY: Melanie Sibbitt, City Cleric (SEAL) FOR USE AND RELIANCE ONLY BY THE CITY OF OCOEE, FLORIDA APPROVED AS TO FORM AND LEGALITY this _ day of 201_ SHUFFIELD, LOWMAN & WILSON, P.A. BY: Scott A. Cookson, City Attorney Rusty Johnson, Mayor APPROVED BY CITY OF OCOEE COMMISSION AT A MEETING HELD on under Agenda Item _ AlA Document A141- - 2014 Exhibit A. Copyright Ci 2004 and 2014 by The lan rican Institate of Amhitectn. All rights rrserved. WARN NM : - s Al. o _d bl t S Y fig. V L t U th _P t 1 .b [. t A A D t, or 12 �y n;ort.on oP f, mnyle—It 1' n � ltL - �d x 11 be o .,led bo tde . e tee 1--bin under .. e lay. Thin draft w s produced by AIA software at 1):53:49 on r09/06/201B under order Ne.4296692226 which expires a 09/06/2019, and is not for x sale. Over Notes: Error! Unknown document property name. (9301)2996) Attachment A Estimating Worksheet Summary Wwme A- ossx LINE DESCRIPTION $/SF % Cost 2 Direct Costs 3 General Requirements $9.72 2.35%', $405,758 4 Structural Concrete & Stair Concrete $11.58 312%. $538,985 5 Site Concrete $6.63 1.79%', $308,529 6 Masonry $43.96 11,86%: $2,046,509 7 Structural & Miscellaneous Steel $24.14 6.51%', $1,123,564 8 Caulking & Waterproofing $1.53 0.41%$71,292 9 Roo0ng : $5.04 1,36%. $234,791 10 Frames, Doors & Hardware Supply $5.09 1.37%; $236,752 11 Windows & Glazing $15.88 4.28%. $739,359 12 Overhead Coiling Doors $0.34 0.09%. $15,673 13 Framing, Drywall & Stucco $27.77 7.49%' $1,292,758 14 Hard Tile, Resilient Flooring and Carpet $7.59 2.05%: $353,316 15 Acoustical Ceilings & Wall Panels - $3.60 0.97%'. $167,593 16 Painting $1.93 0.52%, $89,750 17 Specialties $1.83 0.49%: $85,060 18 Signage $1.06 0.29% $49,496 19 Operable Partition $0.28 '., 0.08%, $12,997 20 Site furnishings & amenities $1.01 0.27%' $47,225 21 Glass canopy $1.74 0.47%j $81,000 22 Casework $8.45 2.28% $393,207 23 Elevator $4.16 1.12%. $193,571 24 Fire Suppression System $2.76 0.74%. $128,338 25 Plumbing $9.65 2.60%. $449,192 26 HVAC $30.07 8.11%.. $1,399,732 27 Electrical $61.14 16.50%, $2,846,388 28 Earthwork, Paving & Site Utilities $11.83 3.19%. $550,522 29 Fencing & Gates $1.19 0.32% $55,567 30 Landscaping & Irrigation $4.65 1.25% $216,334 31 TOTAL DIRECT COSTS $303.60 81.91%'. $14,133,259 32 Indirect Costs 33 Value Engineering 34 General Conditions $28.44 7,67%. $1,323,938 35 Construction Administration services $5.37 1.45%. $250,000 36 Bond $2.55 0.69%. $118,834 37 General Liability Insurance $2.11 0.57%. $98,357 38 Builder's Risk insurance $0.66 0.18%. $30,801 39 Design Contingency $0.00 0.00% $0 40 Escalation Contingency $0.00 0.00%. $0 41 SUBOTAL $342.74 92,46%''. $15,955,189 42 CM Contingency $10.28 ',. 3.00%''. $478,656 43 CM Fee $17.65 5,00%'. $821,692 44 TOTAL $370.67 T 100,00% $17,255,537 Page 1 of 1 Attachment li 1. Spec Section 012300: Sound -Absorbing Ceiling Units............................................................. ADD ...$24,400 2. Aluminum Trellis @ Patio ........ ..................................................... ....... .................................. Deduct ... $37,800 3. Alternate Lighting Fixture ..................................................................................................... Deduct ... $35,000 4. MCBranchCabling................................................................................................................ Deduct ...$55,000 4. Delete Paver Band @Plaza................................................................................................... Deduct ... $3,500 Amounts shown are 'Direct Cost", with no applicable "Indirect Costs" applied. Page 1 of 1 Attachment C 1. Permits and Fees associated with Permits are to be provided byOwner. 2. Impact Fees of any kind assessed by any governmental entity are not included 3. FFE is to be provided by Owner and to be coordinated by WSI team. F F & E installation shall be in accordance with the F F & E contract. 4. The depth of the existing pool to be removed expected to be no greater than 10'deep. 5. Contingent upon Design -Builder completing all prerequisite items, Notice to Proceed by Owner is expected to be received by October 27th, 2020 which would result in a substantial completion date of 03/22/2022. 6. Work hours are anticipated to be standard 40hr work weeks, M-F (1" Shift), extensive overtime, night or weekend work is not included. 7. Dewatering pumps and generators will need to be allowed to run 24/7 at certain times during construction. 8. It is assumed that occasional nighttime concrete pours will be allowed, at the Design -Builders discretion and with the Owner's prior written approval, to make up for inclement weather, maintain the Project Schedule or accelerate the work. 9. It is assumed that occasional overtime or weekend work will be allowed, at the Design -Builders discretion and with the Owner's prior written approval, to make up for inclement weather, maintain the Project Schedule or accelerate the work. 10. Assuming construction vehicles will be allowed on adjacent roads to access the site during construction. Construction access routes shall be reviewed with the Owner prior to start of work. 11. Assuming Wharton -Smith job trailer yard and on -site parking will be in accordance with previously submitted site logistic plan. 12. Additional parking locations, as required will be coordinated the Owner and be within %+/- mile of the site. Parking fees are not included in the GMP. 13. The GMP includes a mechanically fastened roof substrates and fully adhered TPO membrane system in accordance with the manufacture's recommendations. 14. The UV light included in the GMP is to help control microbes on the NVAC Fan Coil per direction from Trane and Matern Engineering and not the larger UV lights units used to treat the supply air. 15. The removal and disposal of any unforeseen unsuitable or contaminated soils is not included in the GMP. 16. No Remediation for sink holes is included, however per the soil report sink holes are unlikely because no evidence of soil raveling present. 17. The GMP does not include Item #24 arm -less chairs and 42" square dining table @ patio because these are to be Owner provided. 18. Independent Construction Materials Testing services, if required or desired, are not included in the GMP. 19. Per the Building Department, threshold inspections are not required and therefore not included in the GMP. 20. Design -Builder will coordinate with Duke Energy to have permanent power to be provided to site no later than August 2021. 21. Cost for primary power conductor and transformer on the project site are not included in the GMP. 22. Road closure fees are not included in the GMP. 23. Repair of pre-existing damage of existing roadways is not included. Damage, outside of normal wear and tear caused by Design -Builder, contractors, subcontractors, orsuppliers shall be repaired by the Design - Builder. Page 1 of 2 Attachment C 24. The GIMP anticipates unrestricted delivery hours, subject to prior written approval of the Owner. 25. Data/ethernet TV utilities to be brought to the site by others. 26. This GIMP does not include any cost for unforeseen circumstances, such as material shortages or government shutdowns, associated with the COVID Virus pandemic. Costs, if reasonable and approved by the Owner, shall be deducted from Design -Builder Construction Contingency. Page 2 of 2 Attachment D 007300 Supplementary Conditions HKS O8/26/2020 2 011000 Summary 08/26/2020 3 012300 Alternates 08/26/2020 2 012500 Substitution Procedures 08/26/2020 4 • Attachment — HKS Substitution Request Form 012500 1 012600 Contract Modification Procedures 1 08/26/2020 2 • Attachment — Architect's Supplemental Instruction 1 e Attachment— HKS-714 Construction Change Directive 1 012900 Payment Procedures 08/26/2020 S 013100 Project Management and Coordination 08/26/2020 9 e Attachment— Request for Information 1 013200 Construction Progress Documentation 08/26/2020 8 013300 Submittal Procedures 08/26/2020 10 014000 Quality Requirements 08/26/2020 9 014200 References 08/26/2020 4 014323 Special Inspections 08/26/2020 2 014339 i Visual Mock -Up Requirements 08/26/2020 3 014516 Field Test for Water Leakage 08/26/2020 5 015000 Temporary Facilities and Controls 08/26/2020 7 016000 Product Requirements 08/26/2020 6 016050 Installer's Warranties 08/26/2020 2 017300 Execution 08/26/2020 10 017419 Construction Waste Management and Disposal 08/26/2020 5 017700 Closeout Procedures 08/26/2020 6 017823 Operations and Maintenance Data 08/26/2020 7 017839 Project Record Documents 08/26/2020 4 017846.13 Extra Stock& Maintenance Materials - Architectural 08/26/2020 3 017900 Demonstration and Training 08/26/2020 4 031100 Concrete Forming 08/26/2020 7 032000 Concrete Reinforcing 08/26/2020 4 033000 Cast -In -Place Concrete 08/26/2020 23 034500 Precast Architectural Concrete 08/26/2020 9 040513 Masonry Mortaring 08/26/2020 3 040516 Masonry Grouting 08/26/2020 3 040523 ' Masonry Accessories 08/26/2020 5 042100 1 Masonry Veneer 08/26/2020 21 042200 Concrete Unit Masonry 08/26/2020 14 Page 1 of 7 Attachment D 047500 Adhered Masonry Veneer 08/26/2020 13 051200 Structural Steel Framing 08/26/2020 10 051213 Architecturally Exposed Structural Steel Framing 08/26/2020 8 052100 Steel Joists Framing 08/26/2020 5 053100 Steel Decking 08/26/2020 6 054000 Cold -Formed Metal Framing 08/26/2020 5 055000 Metal Fabrications 08/26/2020 10 055100 Metal Stairs 08/26/2020 10 055213 Pipe and Tube Railings 08/26/2020 11 057000 Ornamental Metal 08/26/2020 6 057360 Exterior Metal Railings 08/26/2020 6 061053 Miscellaneous Rough Carpentry 08/26/2020 7 061643 Exterior Gypsum Sheathing 08/26/2020 6 064023 Interior Architectural Woodwork 09/23/2020 18 066400 Plastic (FRP) Paneling 08/26/2020 4 066813 Plastic Gratings 08/26/2020 3 07 1326 Sheet Waterproofing 09/23/2020 13 071900 Water Repellents 08/26/2020 5 072100 Thermal Insulation 08/26/2020 8 072423 Defs for Soffits 08/26/2020 4 072617 Below Slab Vapor Retarders 08/26/2020 5 072716 Self -Adhering Air and Water Barriers 08/26/2020 12 075013 Single -Ply Membrane Roofing 09/23/2020 14 076200 Sheet Metal Flashing and Trim 08/26/2020 17 077200 Roof Accessories 08/26/2020 12 078116 Sprayed Fire -Resistive Materials 08/26/2020 10 078413 Penetration Firestopping 08/26/2020 8 078446 Fire Resistive Joint Firestopping 08/26/2020 9 079200 Joint Sealants 08/26/2020 12 081113 Hollow Metal Doors and Frames 08/26/2020 13 081416 Prefinished Flush Wood Doors 08/26/2020 9 083113 Access Doors and Frames 08/26/2020 8 083323 Overhead Coiling Doors 08/26/2020 10 084128 Interior All -Glass Entrances and Storefronts 09/23/2020 6 084400 Glazed Aluminum Framing Systems 09/23/2020 17 084430 Glass Canopies 08/26/2020 10 085656 Bullet -Resistive Windows 08/26/2020 7 087100 Door Hardware 09/23/2020 33 Page 2 of 7 Attachment D 088000 Glazing 092423 Cement Plaster 092900 Gypsum Board Assemblies 093000 Tiling 095113 Acoustical Panel Ceilings 096500 Resilient Flooring 096513 Resilient Base and Accessories 096800 Carpeting 097723 Fabric Wrapped Panels 098400 Sound -Absorbing Ceiling Units (Alternate) 098433 1 Acoustical Wall Panels 09 8453 Specialty Wood Wall Systems 099000 Painting for Cement Plaster 099100 Painting 099663 Textured Acrylic Coatings 101100 102113 102213 102223 102613 102641 102813 104116 104400 107516 112400 122413 123661 124843 142400 211300 220013 220500 220510 220519 220523 220529 220553 Visual Display Boards Toilet Compartments Wire Mesh Partitions Accordion Folding Partitions Wall and Corner Guards Bullet -Resistant Panels Toilet Accessories Emergency Key Cabinets Fire Protection Specialties Building Maintenance Equipment Roller Window Shades Simulated Stone Countertops Entrance Floor Mats Hydraulic Elevators Fire Suppression Systems - Performance Plumbing Systems Common Work Results for Plumbing Systems Basic Materials and Methods for Plumbing System Meters and Gauges for Plumbing Piping General Duty Valves for Plumbing Piping Hangers and Supports for Plumbing Piping and Equipment Identification for Plumbing Piping and Equipment Page 3 of 7 08/26/2020 20 08/26/2020 3 08/26/2020 27 09/23/2020 16 08/26/2020 7 08/26/2020 10 08/26/2020 6 08/26/2020 7 08/26/2020 3 08/26/2020 4 08/26/2020 4 08/26/2020 4 08/26/2020 3 09/23/2020 14 08/26/2020 9 08/26/2020 6 08/26/2020 4 08/26/2020 6 08/26/2020 5 08/26/2020 5 08/26/2020 2 09/23/2020 10 08/26/2020 3 08/26/2020 5 08/26/2020 3 09/23/2020 9 08/26/2020 8 08/26/2020 5 08/26/2020 5 08/26/2020 16 08/26/2020 8 08/26/2020 4 08/26/2020 4 08/26/2020 3 08/26/2020 4 08/26/2020 4 08/26/2020 8 08/26/2020 4 Attachment D 220576 Facility Drainage Piping Cleanouts 08/26/2020 2 220577 Facility Plumbing Drains and Accessories 08/26/2020 2 220700 Plumbing insulation 08/26/2020 7 22 1116 Domestic Water Piping 08/26/2020 7 221117 Disinfection of Domestic Water Lines 08/26/2020 4 221123 Domestic Water Pumps 08/26/2020 2 221316 Sanitary Drain, Waste and Vent Piping 08/26/2020 6 221317 Rain Leader Piping 08/26/2020 6 223300 Electric Water Heaters and Accessories 08/26/2020 3 224200 Plumbing Fixtures and Trim 08/26/2020 2 230500 Common Work Results for HVAC Systems 08/26/2020 5 230510 Basic Materials and Methods for HVAC Systems 08/26/2020 9 230513 Common Motor Requirements for HVAC Equipment 08/26/2020 5 230517 Adjustable Frequency Drives 08/26/2020 6 230518 Control Wiring 08/26/2020 3 230519 Meters, Gauges and Accessories for HVAC Piping 08/26/2020 4 230523 General Duty Valves for HVAC Piping 08/26/2020 5 230529 Hangers and Supports for HVAC Piping and Equipment 08/26/2020 8 230548 Vibration and Seismic Controls for HVAC 08/26/2020 7 230553 Identification for HVAC Piping and Equipment 08/26/2020 4 230580 Air Control and Accessories 08/26/2020 5 230593 Testing, Adjusting and Balancing for HVAC 08/26/2020 12 230700 HVAC Insulation 08/26/2020 10 230800 Commissioning of HVAC Systems 09/23/2020 10 230923 Instrumentation and Control Devices for HVAC O8/26/2020 35 230993 Sequence of Operations 08/26/2020 4 23 2113 Hydronic Piping 08/26/2020 10 23 2123 HVAC Pumps 08/26/2020 4 232500 HVAC Water Treatment 08/26/2020 4 233100 HVAC Ducts and Casings 08/26/2020 10 233101 Shop Fabricated Ductwork 08/26/2020 6 233300 Air Duct Accessories 08/26/2020 11 233400 HVAC Fans 08/26/2020 4 233600 Air Terminal Units 08/26/2020 4 233713 Diffusers, Registers and Grilles 08/26/2020 2 234113 Active Harmonic Filter 08/26/2020 6 236428 Air Cooled Liquid Chillers 08/26/2020 6 237300 Packaged Air Handling Units 08/26/2020 10 Page 4 of 7 Attachment D 238125 j Mini Split Air Conditioning Systems 08/26/2020 4 260100 Operation and Maintenance Manuals 08/26/2020 5 a Attachment — Project Information Sheet • Attachment —Check Out Memo • Attachment —Conductor Insulation Resistance Test • Attachment— DC High Voltage Cable Test •Attachment — Ground Test Information • Attachment — Motor Test Information • Attachment — Voltage and Amperage Readings (Tabulation Data) • Attachment — Progress and Record Drawing Certification • Attachment —Spare Parts / Maintenance Stock Certification •Attachment — Binder Examples for Submittals 260500 Common Work Results for Electrical 08/26/2020 10 260503 Equipment Wiring Systems 08/26/2020 3 260506 Demonstration of Completed Electrical Systems 08/26/2020 2 • Attachment — Check Out Memo 1 260507 Submittals 08/26/2020 4 • Attachment —Title Page • Attachment — Binder Examples for Submittals 260508 Substitutions 08/26/2020 3 260509 Reference Standards and Regulatory Requirements 08/26/2020 4 260510 Electrical Symbols and Abbreviations 08/26/2020 4 260519 Building Wire and Cable 08/26/2020 5 260523 Power System Study with Arc Flash Analysis 08/26/2020 11 260526 Grounding and Bonding 08/26/2020 14 260529 Hangers and Supports 08/26/2020 3 260533 Conduit 08/26/2020 10 260534 Outlet Boxes 08/26/2020 5 260535 Pull and Junction Boxes 08/26/2020 3 260537 Surface Raceways 08/26/2020 4 260538 Floor Boxes 08/26/2020 6 260553 Identification for Electrical Systems 08/26/2020 4 260800 Commissioning of Electrical Systems 09/23/2020 8 260813 Tests and Performance Verification of Electrical System 08/26/2020 3 260923 Occupancy Sensors 08/26/2020 8 260934 Dimming System 08/26/2020 7 262100 Utility Service Entrance 08/26/2020 4 262213 Dry Type Transformers 08/26/2020 7 Page 5 of 7 Attachment D 262416 Panelboards 08/26/2020 14 262417 Distribution Panelboards 08/26/2020 5 262713 Electrical Metering 08/26/2020 5 262716 Cabinets and Enclosures 08/26/2020 4 262726 Wiring Devices 08/26/2020 6 262819 Enclosed Disconnect Switches 08/26/2020 3 262913 Motor Control 08/26/2020 4 263213 Exterior Diesel Emergency Generator With Subbase Fuel Tank 08/26/2020 10 263623 Automatic Transfer Switch 08/26/2020 4 264113 Lightning Protection System 08/26/2020 5 264300 Surge Protective Devices 08/26/2020 8 26 5113 Interior Lighting Fixtures, Lamps and Ballasts 08/26/2020 7 265213 Emergency Lighting Equipment 08/26/2020 4 265561 Television Lighting 08/26/2020 3 265600 Exterior Luminaires 08/26/2020 5 270500 Common Work Results for Communications Systems 08/26/2020 9 270507 Submittals for Communications Systems 08/26/2020 14 • Attachment —Title Page 270526 Grounding and Bonding for Communications Systems 08/26/2020 5 270529 Hangers and Supports for Communications Systems 08/26/2020 3 270533 Conduit and Backboxes for Communications Systems 08/26/2020 15 270553 Identification for Communications Systems 08/26/2020 3 271000 Premise Distribution Wiring System 08/26/2020 42 274000 Television System 08/26/2020 15 274129 Audio/Video System 08/26/2020 44 280500 Common Work Results for Electronic Safety and Security 08/26/2020 9 280507 Submittals for Electronic Safety and Security 08/26/2020 10 • Attachment —Title Page 28 OS26 Grounding and Bonding for Electronic Safety and Security 08/26/2020 5 280529 Hangers and Supports for Electronic Safety and Security 08/26/2020 3 280533 Conduit and Backboxes for Electronic Safety and Security 08/26/2020 15 281300 Access Control System (ACS) 08/26/2020 15 282300 Closed Circuit Television (CCTV) System 08/26/2020 10 283100 Addressable Fire Alarm/Detection System 08/26/2020 44 311000 Site Clearing 08/26/2020 3 312000 Earthwork 08/26/2020 8 312319 Dewatering 08/26/2020 2 32 1216 Asphalt Paving 08/26/2020 2 Page 6 of 7 Attachment D 32 1313 Concrete Paving 32 1313 Concrete Paving (Landscape) 321316 Integral Color Concrete Paving 328400 Irrigation System 329200 Sodding 329300 Landscape 33 1100 Water Utility Distribution Piping 333100 Sanitary Utility Sewerage Piping 334100 Storm Utility Drainage Piping Page 7 of 7 08/26/2020 14 08/26/2020 3 08/26/2020 4 08/26/2020 8 08/26/2020 4 08/26/2020 12 08/26/2020 6 08/26/2020 6 08/26/2020 5 Attachment E A0.00 Cover 08/26/2020 A0.01 Sheetlndex 08/26/2020 C000 Boundary & Topographic Survey 12/28/2016 Cool General Notes 08/26/2020 C100 Site Plan 08/26/2020 C200 Demolition & Erosion Control Plan 08/26/2020 j C201 Demolition & Erosion Control Details 08/26/2020 C300 Geometry & Striping Plan 08/26/2020 C400 Grading & Drainage Plan 09/23/2020 1 C500 Utility Plan 08/26/2020 C600 Site Details 09/23/2020 1 C601 FDOT Details 08/26/2020 C700 Grading & Drainage Details 08/26/2020 C800 City Utility Details 08/26/2020 C801 City Utility Details 08/26/2020 - C802 City Utility Details 08/26/2020 C803 City Utility Details 08/26/2020 C804 City Utility Details 08/26/2020 1-001 Hardscape Material Schedule 08/26/2020 1100 Hardscape Callout Plan 09/23/2020 1 L101 Hardscape Dimension Plan 09/23/2020 1 L102 Hardscape Concrete Jointing Plan 09/23/2020 1 L200 Hardscape Details 08/26/2020 L201 Hardscape Details 08/26/2020 L202 Hardscape Details 08/26/2020 L203 Hardscape Details 08/26/2020 L204 Hardscape Details 08/26/2020 L205 Hardscape Details 08/26/2020 L206 Hardscape Details 08/26/2020 L207 Hardscape Details 08/26/2020 L208 Hardscape Details 08/26/2020 L209 Hardscape Details 08/26/2020 L210 Hardscape Details 08/26/2020 L300 Landscape Plan 09/23/2020 1 L301 Plants List & Notes 09/23/2020 1 L302 Landscape Details 09/26/2020 L400 Irrigation Plan 09/23/2020 1 L401 Irrigation Legend & Schedules 09/23/2020 1 Page 1 of 6 Attachment E L402 Irrigation Notes & Details 08/26/2020 L403 Irrigation Details 08/26/2020 A1.00 Project Information 09/23/2020 1 A1.01 Site Plan 08/26/2020 ALES Life Safety Plan 09/23/2020 1 A2.01 Floor Plan Level 1 09/23/2020 1 A2.02 Floor Plan - Level 2 09/23/2020 1 A2.03 Floor Plan - Level 3 09/23/2020 1 A2.04 Roof Plan 08/26/2020 A2.05 Single Ply Roofing Details 08/26/2020 L A3.00 Partition Types 01 08/26/2020 A3.03 i Partition Framing Details 08/26/2020 A3.04 Gyp Bd Details 08/26/2020 A3.10 Metal Fabrications 08/26/2020 A3.20 Enlarged Restroom Plans 09/23/2020 1 A3.21 Restroom Elevations I 09/23/2020 1 A3.23 Florida Toilet Layouts and Std Accessories 09/23/2020 1 A3.24 Shower Details - Without Slab Depression 09/23/2020 1 A3.31 Door, Safety Glazing and Louver Information 09/23/2020 1 A3.32 Door Schedule and Door Details 09/23/2020 1 A3.50 Cabinet Details 08/26/2020 A3.51 Interior Elevations Level 09/23/2020 1 A3.52 Interior Elevations - Level 2 09/23/2020 1 A3.53 Interior Elevations - Level 3 09/23/2020 1 A3.60 Millwork Enlarged Plans, Elevations, and Details 09/23/2020 1 A3.61 Millwork Enlarged Plans, Elevations, and Details 09/23/2020 1 A3.62 Millwork Enlarged Plans, Elevations, and Details 08/26/2020 A3.63 - Millwork Enlarged Plans, -Elevations, and Details li 08/26/2020 A3.64 Millwork Enlarged Plans, Elevations, and Details 09/23/2020 1 A3.70 Interior Enlarged Plans and Details 09/23/2020 1 A4.01 Reflected Ceiling Plan -Level 01 g I 09/23/2020 1 A4.02 Reflected Ceiling Plan - Level 02 08/26/2020 A4.03 Reflected Ceiling Plan - Level 03 09/26/2020 A4.04 Ceiling Details 09/23/2020 1 A5.01 Elevations 09/23/2020 1 A5.02 Elevations 09/23/2020 1 A5.10 Window Legend and Enlarged Elevations 09/23/2020 1 A5.11 Enlarged Elevations 09/23/2020 1 Page 2 of 6 Attachment E A5.12 Enlarged Elevations 09/23/2020 1 A6.01 Building Sections 08/26/2020 A6.10 Wall Sections 09/23/2020 ! 1 A7.11 Brick Details - Batt Insulation 01 09/23/2020 1 A7.12 Brick Details - Batt Insulation 02 09/23/2020 !, 1 A7.13 Brick Details - Batt Insulation 03 08/26/2020 A7.14 Precast & Masonry Veneer Details 09/23/2020 1 A7.15 Soffit and Balcony Details 09/23/2020 1 A7.21 Plan Details 09/23/2020 1 A7.32 Interior Adhered Masonry Details 08/26/2020 A8.01 Stair Plans and Sections 08/26/2020 A8.10 Steel Stair Plans, Sections, And Details 01 08/26/2020 A8.20 Elevator Details 08/26/2020 A9.00 Room Finish Schedule and Details 09/23/2020 ! 1 A9.01 Finish Floor Plan - Level 1 09/23/2020 1 A9.02 Finish Floor Plan - Level 2 09/23/2020 1 A9.03 Finish Floor Plan - Level 3 09/23/2020 1 A9.04 Furniture Plan - Levell 08/26/2020 A9.05 Furniture Plan - Leve12 08/26/2020 A9.06 Furniture Plan - Leve13 08/26/2020 A11.0107 ULAssemblies —HW-D-0107 08/26/2020 A11.411 UL Assemblies — U411 08/26/2020 A11.419 ULAssemblies —U419 08/26/2020 A11.420 ULAssemblies —U420 08/26/2020 A11.465 ULAssemblies —U465 08/26/2020 A11.469 ULAssemblies —U469 08/26/2020 A11.497 ULAssemblies U497 08/26/2020 A11.586 ULAssemblies —G586 08/26/2020 MA1.01 Mock Up Plan, Sections, and Elevations 08/26/2020 S1.01 Structural General Notes & Wind Schedule 08/26/2020 S1.02 Structural General Notes 08/26/2020 S1.03 Structural General Notes 08/26/2020 S1.04 Structural General Notes 08/26/2020 S1.05 Structural General Notes 08/26/2020 S2.01 Foundation Plan 08/26/2020 - S2.01A First Floor Edge of Slab Dimension Plan 08/26/2020 S2.02 Second Floor Framing Plan 09/23/2020 : 1 S2.02A Second Floor Edge of Slab Plan 08/26/2020 Page 3 of 6 Attachment E S2.03 Third Floor Framing Plan 08/26/2020 S2.03A Third Floor Edge of Slab 08/26/2020 S2.04 Roof Framing Plan 08/26/2020 S2.04A Roof Edge of Slab Plan 08/26/2020 S3.01 Foundation Sections and Details 08/26/2020 S3.02 Foundation Sections and Details 08/26/2020 S3.03 Foundation Sections and Details 08/26/2020 S4.01 Floor Framing Sections and Details 09/23/2020 1 S4.02 Floor Framing Sections and Details 08/26/2020 S5.01 Roof Framing Sections and Details 08/26/2020 S6.01 Schedules 08/26/2020 S6.02 Schedules 08/26/2020 MS1.01 Mock Up Plan, Sections, and Details 08/26/2020 M0.01 General Notes, Legend, Abbrev & Sheet Index 08/26/2020 M2.01 First Floor Plan 08/26/2020 M2.02 Second Floor Plan 08/26/2020 M2.03 Third Floor Plan 08/26/2020 M2.04 Roof Plan 08/26/2020 M2.0S Enlarged Mechanical Rooms 08/26/2020 M5.01 Controls 08/26/2020 M5.02 Controls 08/26/2020 M5.03 Controls 08/26/2020 M5.04 Controls 08/26/2020 M5.05 Controls 08/26/2020 M6.01 Schedules 08/26/2020 M6.02 Schedules 08/26/2020 M9.01 Details 08/26/2020 M9.02 Details 08/26/2020 M9.03 Details 08/26/2020 M9.04 Details 08/26/2020 30.01 General Notes, Fixture Schedule & Sheet Index 08/26/2020 P2.01 First Floor Plan 09/23/2020 1 P2.02 Second Floor Plan 09/23/2020 j 1 P2.03 Third Floor Plan 09/23/2020 1 P2.04 Roof Plan 08/26/2020 P5.01 Enlarged Plans 08/26/2020 P6.01 Schedules 08/26/2020 P7.01 Riser Diagrams Core Toilets 08/26/2020 Page 4 of 6 Attachment E P7.02 Water Riser Diagram 09/23/2020 1 P7.03 Waste Riser Diagram 09/23/2020 1 137.04 Storm Riser Diagram 09/23/2020 1 FP0.01 General Notes & 61-G15 Compliance Notes 08/26/2020 FP2.01 First Floor Plan 09/23/2020 1 FP2.02 Second Floor Plan 09/23/2020 1 FP2.03 Third Floor Plan 09/23/2020 ! 1 E0.01 General Notes, Symbol Legend, & Sheet Index 08/26/2020 E0.02 .Abbreviations & LightingFixture Schedule 08/26/2020 E1.01 Site Plan 08/26/2020 E2.01 First Floor Plan - Power 08/26/2020 E2.02 Second Floor Plan - Power 08/26/2020 E2.03 Third Floor Plan - Power 08/26/2020 E2.04 Roof Plan -Power 08/26/2020 E4.01 First Floor Plan - Lighting 08/26/2020 E4.02 Second Floor Plan - Lighting 08/26/2020 E4.03 Third FloorPlan- Lighting 08/26/2020 E5.01 Electrical Exterior Lighting Elevation 08/26/2020 E6.01 Mechanical Feeder Schedules 08/26/2020 E6.11 Panelboard Schedules 08/26/2020 �I E6.12 Panelboard Schedules 08/26/2020 E6.13 Panelboard Schedules 08/26/2020 E6.14 Panelboard Schedules 08/26/2020 E7.01 Riser Diagram & Feeder Schedule 08/26/2020 E9.01 Details 08/26/2020 E9.02 Details 08/26/2020 E9.03 Details 08/26/2020 E9.05 Details 08/26/2020 E9.06 Details 08/26/2020 E9.11 Powerlinl< Details 08/26/2020 E9.21 Chambers Lighting Control Details 08/26/2020 I_ E9.22 Chambers Lighting Control Details 08/26/2020 TA0.01 General Notes, Fixture Schedule & Sheet Index 08/26/2020 TA1.01 SitePlan-Systems 08/26/2020 TA2.01 First Floor Plan -Systems 08/26/2020 TA2.02 Second Floor Plan -Systems 08/26/2020 TA2.03 Third Floor Plan - Systems 08/26/2020 TA5.01 Enlarged Plans 08/26/2020 Page 5 of 6 Attachment E TA7.01 Block Diagram —Audio 08/26/2020 TA7.02 Block Diagram —Video j 08/26/2020 TA7.03 Block Diagram Control 08/26/2020 TA8.01 RiserDiagrams— Systems 08/26/2020 TA9.01 Details 08/26/2020 TA9.02 Details 08/26/2020 TA9.03 Details 08/26/2020 TA9.04 Details 08/26/2020 TA9.05 Details — AV 08/26/2020 TA9.06 Details — AV 08/26/2020 TS0.01 _ Symbol Legend 08/26/2020 TS1.01 Site Plan —Fire Security 08/26/2020 TS2.01 First Floor Plan Fire Security /_ 08/26/2020 I TS2.02 Second Floor Plan Fire Security 08/26/2020 TS2.03 Third Floor Plan — Fire Security 08/26/2020 TS6.01 Schedules 08/26/2020 TS8.01 Riser Diagram — Fire Security 08/26/2020 TS9.01 Details - Fire Security 08/26/2020 TS9.02 Details - Fire Security 08/26/2020 TS9.03 Details -ACS 08/26/2020 TS9.04 Details -ACS 08/26/2020 L TS9.0S Details -CCTV 08/26/2020 Page 6 of 6 Attachment F • Request for Information Response No. 001, dated September 18, 2020. • Request for Information Response No. 002, dated September 21, 2020. o Matern Engineering Response, dated September 21, 2020 o Response RFI 2.1— Finishes selections and clarifications • Request for Information Response No. 003, dated September 28, 2020. • Request for Information Response No. 004, dated September 29, 2020. • Request for Information Response No. 005, dated September 29, 2020. Attachment G • Addendum No. 01, dated September 23, 2020 Page 1 of 1 Attachment H Document A312TM .2010 Performance Bond CONTRACTOR: SURETY: (Mahe, legal slams and address) (Name, legal slants and princleal place WhntlonSmil6, he• ojbaslness) al Inlh ""'" "`""f 140- "' nu,una;. Hama naa n u; mie wn Upcumpmp pprubaleJ by US.6opyiIH11L wend lntamaUon ITrcaUea. Unaulhpaxad nprodudlon yJlattl4ullpp o(Ihls gl0.°OosuinOnf, of any portivn oP ,� p,maywsHll in¢aypre.I'll I'd atiMln Ipanaig a, PA wlll lrepfo p<olad to the rdaalmum wot pcealull, unJarlt'. I.W. T. repwtcopyAHM I ylolnilons ORA Uonimol Ooeenwnd...mell The Mullein imlilala ofNdJlods' IOUul comuol, mpyelghl®siamrg. Page 1 of 4 halt. Attachment H § 1 The Contractor and Surely,jointly and severally, bind themselves, their bolls, executors, adminiatrntors, successors and assigns to the Ohmor for Ilia perfo nu co of the Construction Contract, which Is Incorporated herein by reference. § 2If the Contractor performs the Construction Contract, the Surety and ilia Contractor shall have no obligation under this Bond, except when applicable to participate in a conference as provided in Section 3. § 3 If them is no Owner Default under the Construction Contract, Ilia Surety's obligation under this Bond shall arise after .1 the Owner first provides notice to ilia Contractor and the Surely that tie Owner is considering declaring a Contractor Default. Such notice shall Indicate whetter One Owner is requesting a conference unrong tiro Owner, Contractor mid Surety to discuss the Contractors performance. If Ilse Ovmer does not request a conference, the Surety may, within live (5) business days after receipt ?f the Ownpr's notice, request such a conference. If the Surety timely requests a conference, tine Onvnor shall all edd. it o9s� Ilto Osvner agmas otherwise, ahy conference regncsted undordfhls'Seelion 3.1 nshnil ba llc1d within to (10) business days of the Suroly's receipt of fileOwner's notiee.If the Owner, the Codtmolor add t�o Surety agree, Ilia Contractor shall be alloyed a maeonable time to perfomm the Conshuullon Canino, but such on agreement shall not waive ilia Owner's right, if any, subsequently to declare n Contractor Default; ,2 the Owner declares a Contractor Default, maralnutos the Construction Contract and notifies ilia Surety; and .3 Wo Owner has agreed to pay ilia Balmneo of Ilia Commol i't ce to accordance,yyvrith Ilia learns of the Construction Contract to lie Surety or to fl Cmlifaetef 80�Ce�ed to perform lje construclhon Contract, § 4 Failure on the part of the Owner (o comply with ilia notice requirement in Section 3.L'ahyylI not constitute a failure to comply with a condition precedent to the Surety's obligations, or release the Surely fl`omlis obligations, except to Iihe extent ilia Slimly demonstrates actual prejudice. § 6 When the Owner has sutisfed tiro conditions of Sccti¢nh3, Ilia Slimly shall promptly and at ilia Suroty's expense lake cola of the following notions: ..., § 6.1 Arrange for the Contractor, with We consent of Ilia Owner, to perform and complete the Combination Contract; § 6.2 Undertake to perform and complete ilia Coal etion Commit lisolf, iluough its agents or independent contractors; § 6.3 Obtain bids or negotiated proposals from qualified eoutraomrs acceptable to Ilse Owner for a coal met for performance and completion of the ConstnwAon.Contract, arrange for a controat to be prepared for execution by the Owner and n contractor scicoti;Qwith the Owner's conourroaco, to be seemed wi0t porfomenco and payment bonds executed by n gnatifed surely Cgtj'ivolont to Ilia bonds issued on the Construction Contract, and pay to the Olmer the amount of damages as describild in Section 9 In o>)`oc� s of Ilia Salience of the Contract price inoolrcd by the Omer a result of the Contractor Defanit; or I , § 6A Waive Ila right to perform mad edmpleto, orrpiigo for completion, or obtain a new contractor and with reasonable prompinoss,under We circmnslances. union Afar investigation, determine the eon at for which it may be liable to ilia Owner and, as soon as practicable afar the amount is determined, make payment to the owner; or Deny liability In tvilolopr in part and notify tine Owner, outing ilia ronsons for don lol. § 61f ilia Surely does not proceed as provided in Section 5 with reasonable promptness, the Solely shad be deemed to be In default oil Oils Bond seven days after receipt of an additional written notice from the Owner to ilia Surety demanding that the Surely fortatm its obligatlols under Oils Bond, and ilia Owner shall be entitled to enforce any romedy available to Ilia Owii4. If rho Solely proceeds as provided In Section 5.4, and the Owner refuses the payment or Iho Surety has denied liability, in whole or in part, without father notice the Owner shall be entitled to anfoee any remedy available to Ilia Owner. Page 2 of 4 Attachment H § 7If ilia Surely elects to not under 8cction 5.1, 5.2 or 5.3, then the responsibilities of the Surety to the Owner shall not be greater porn those of Ilia Contrncor under Ilia CmtsWction Contract, and Ilia responsibilities of the Owner to the Surely shot not be greater than those of the Owucr under lire Construction Contract. Subject to tiro commitment by the Owner to pay the Balance of the Contract Price, Ilia Surely is obligated, without duplication, for .1 lite responsibilities of the Contractor for correction of defective work and completion of tiro Construction Contract; .2 additional legal, design professional unit delay costs resulting from the Contractor's Default, and resulting from Wo actions or failure to not of Ilia Surety under Section 5; and .3 liquidated damages, orifno liquidated damages are specified in Ilia Construction Contract, actual damages caused by delayed performance or non-perfonnanm of the Contractor. § 81f the Surety elects to act under Section 5.1, 5.3 or SA, the Surely's liability is § 0 The Surety shell not be liable to Ilia Owner or others for obligations of the Co, Construction Contract, and pre Balance of the Contract Price shall not be reduced unrelated obligations. No right of action shut[ accme un this Bond to any person c India, executors, administration, successors mid assigns. § 10'Die Surety hereby wolves notice of any change, including changes related subcontracts, purchase orders and other obligations, § 12 Notice to the Surety, the Owner or on which their signature appears. its or to shown on the page § 14 Definitions - 1 § 14.1 Balance of the Coafloat Pirleq. Tha tidal, umount payable by lite Owner to the Contractor under ilia Construction Contract after all proper ndjUsti nonis have@doll mica, Including allowance to the Contractor of any antowds received or to be received by Zile Ow or in set 11 eht of insurance or other clahns for damages to which the Contractor is entitled, reduced by all valid rand proper psynnonts isade to or on behalf of the Conlmclorundrr de Construction Contract,.>. ' § 14.2 Construction Conlraot.'fhe ugreemenl bahvceti the Owner mid Contractor identified on the cover page, including hit Contract Decontrols Tid.'chmges made to ilia agreement and the Contract Documents. § 14.3 Contractor Didaull. Fatima yf the Contractor, which ties not been remedled or waived, to perform or otherwise to comply with smateriel term of the Construction Contract. § 14.4 Owner Default Failure of the Owner, which Ins not been remedied or waived, to pay file Contractor as required under die Construction Contract or to perform and complete or comply wipn pre other material tents of the Construction Contract. § 14.6 Contract Documents. All the documents that comprise ilia agreement between the Owner and Contractor. § 18I€dlds-Bond-ioissuad-ferentngreernaut-between-n F3ontraatorandreulreerrlmWor—ttoe-lemrCohlwatartintlis-Bond ahn�rocdeem�dieve-Bubcomertetornndtlx:tetn9wnerslmHte�emmediabc6muractor. Page 3 of 4 Attachment H § 16 Modifications to this bond am as follows: Reference § 11 Delete in Its entirely and replace with the following: "Any proceeding, legal or equitable, under Ibis Bond may be insi inlcd In any competent jurisdiction In the location in which tiro Project is located and shall he instituted wHIlln 11 governing statute of lhlllm ions" Reference § 13 Delete in its entirely and replace with the following: "Any provision in this ]load conflicting with Pin. Sint. 255.05 sting he deemed deleted herefrona and provisions conforudug to that statute shall be deemed Incorporated herein, Tit intent is Aat this Bond shall be construed as a statutory bond in compliance with Fla. Shut. 255,05 and not as n common law bond." Reference §15 Delete tit its entirety. r , r (4ace is provided below for addidmial slgnalures ofadded parlies, odlel, tlmn those appeothigon the cover page.) CONTRACTOR AS PRINCIPAL SURETY Company: _... (Coipomte Seal) Company: (Coipyaram Seal) Signature: Name and Title: Address Intl. Slgnntum: Name and Title: Address Page 4 of 4 Attachment I BOND NO.: «pp_bond_bond_number» EXHIBIT 2 PUBLIC CONSTRUCTION PAYMENT BOND BY THIS BOND, We, Wharton -Smith, Inc., 750 Monroe Road, Snaford, FL 32771, as Principal and osurety_name», asurety_addressly, asurety_6ty», asurety_state _cd» asurety_zip»«surety_phone number» , a corporation, as Surety, are bound to the City of Ocoee, 150 N. Lakeshore Drive, Ocoee, FL 34761, herein called Owner, in the sum of «pp_bond_contract_price», for payment of which we bind ourselves, our heirs, personal representatives, successors, and assigns, jointly and severally. THE CONDITION OF THIS BOND is that if Principal: Performs the contract dated January 15, 2019, between Principal and Owner for construction of RFP 418-001, Design -Build Services for New Ocoee City Hall located at I North Bhiford Ave., Ocoee, FL 34761 the contract being made a part of this bond by reference, at the times and in the manner prescribed in the contract; and 2 Promptly makes payments to all claimants, as defined in Section 255.05(1), Florida Statutes, supplying Principal with labor, materials, or supplies, used directly or indirectly by Principal in the prosecution of the work provided for in the contract; and 3. Pays Owner all losses, damages, expenses, costs, and attorneys' fees, including appellate proceedings, that Owner sustains because of a default by Principal under the contract; and Any action instituted by a claimant under this bond for payment must be in accordance with the notice and time limitation provisions in Section 255.05(2) and 255.05(10), Florida Statutes. Any changes in or under the contract documents and compliance or noncompliance with any formalities connected with the contract or the changes does not affect Surety's obligation under this bond. Page 1 of 2 Attachment I DATED otodays_date_month» «todays_date _day», otodays_dateyear». aWharton-Smith, Inc. incipal) BY: «surety name» (Surety) BY: upp_bond_attorney_in_fact)> Attorney In Fact & Florida Licensed Resident Agent Inquiries: (407) 834-0022 Page 2 of 2