HomeMy WebLinkAboutItem 05 Approval of Stormwater Capital Projects with American In-Line Inspection, Inc. ocoee
florida
AGENDA ITEM COVER SHEET
Meeting Date: December 15, 2020
Item # O5
Reviewed By:
Contact Name: Stephen C. Krug Department Director:
Contact Number: 6002 City Manager:
Subject: Stormwater Capital Projects with American In-Line Inspection, In .
Background Summary:
The approved Stormwater Division budget includes four Capital Improvement projects for repairs and
upgrades to existing infrastructure. These projects involve lining existing failed pipelines. Public Works
has determined an epoxy-based lining system will provide the most economical repair to these pipes
draining to environmentally sensitive areas. Few vendors provide this type of lining and only local
vendor, American In-Line Inspection, Inc., responded to requests for pricing. Other lining systems
utilize toxic curing byproducts that would not be conducive for the project locations.
The projects included in the Stormwater budget are as follows:
1. Clarke Road at Ocoee Vista Parkway, $59,400.00.
2. 2700 Kemos Landing, Waterside Subdivision, $52,456.00.
3. City Pond #7 Outfall, Coventry Subdivision, $43,300.00.
4. 2006 Nancy Ann Terrace, $15,900.00.
Public Works is requesting Commission approval to utilize American In-Line Inspection, Inc. to complete
the projects as incorporated in the Stormwater Capital Improvement budget. Public Works has been in
contact with other municipalities to verify the pricing is in line with the scope of work.
Issue:
Contract with American In-Line Inspection, Inc, to complete the pipe lining projects included in the
Stormwater Capital Improvement budget.
Recommendations:
Recommend approval to issue a purchase order to American In-Line Inspection, Inc. for the pipe lining
of; 1) Clarke Road at Ocoee Vista Parkway for $59,400.00, 2) 2700 Kemos Landing, Waterside
Subdivision for $52,456.00, 3) City Pond #7 Outfall, Coventry Subdivision for $43,300.00 and 4) 2006
Nancy Ann Terrace for $15,900.00, and authorize the City Manager and staff to approve and execute
change orders to the work in accordance with the limits established in the Purchasing Code.
Attachments:
American In-Line Inspection, Inc. Quotations.
Financial Impact:
The work is adequately funded in the Stormwater Division Capital Improvement budget.
Type of Item: (please mark with an 'k )
Public Hearing
Ordinance First Reading
Ordinance Second Reading
Resolution
X Commission Approval
Discussion & Direction
Original Document/Contract Attached for Execution by City Clerk
Original Document/Contract Held by Department for Execution
For Clerk's Dept Use:
Consent Agenda
Public Hearing
Regular Agenda
Reviewed by City Attorney N/A
Reviewed by Finance Dept. N/A
Review ed by ) N/A
QUOTATION
1CAN IN -LINE INSPECTIONj1
415 Timaquan Trail Phone (386) 409-5446
Edgewater, FL, 32132 Fax (386) 957-4919
Proposal Sinn acted To: The City of Ocoee
Phone: 407 905-3170
Date: 10/29/2020
Street: 301 Maguire Road
Job Name: Clark Rd. Existing Storm CIPP Repair
City, state; ilp,coae: Ocoee FL 32778
nob Location: Clark Rd. City of Ocoee, FL
ATTN: Mr. Russell Oliver, 407-427-3760
Fax: Roliver@ci.ocoee.fl.us
We propose to perform the following:
Pre Clean & Pre & Post CCTV/Video One (1) Separate Run approx. 350 +/- of 24" Existing RCP Storm Pipe,
before Installing C.I.P.P. manhole to manhole liner system, using the NLC-115-18 100% epoxy lamination system.
Our price includes all labor, material, equipment, and workmanship to complete the project, along with a clear
typed report and video before & after the repairs. (DVD/VHS) Additional copies are $25.00 each.
Day Rate of 12-hrs for Vac Truck & Crew to Clean One (01) Run of 24" Existing RCP Storm Pipe @ $200.00 per hr.......... $ 2,400.00
***Vne Truck On Site To Assist CIPP Liner Installation***
(Additional hours @ $200.00 per hour if needed)
Day Rate of 6-hrs for CCTV/Video & Crew to video Existing Storm Drainage Pipe @ $150.00 per hr,.......(Pre & Post) ....... $ 900.00
(Additional hours @ $185.00 per hour if needed)
Engineering Design Calculation Spec's by Manufacture, Per Line Segment @ $1,500.00 each ............. (I -Run) ................. $ If Needed
Install approx. 350+/- LF of 24" 6mm CIPP M/H to M/H Liner r@ $158.00 per LF.......................................................$ 55,300.00
Plus 20 LF of 24" Dry Bag Included .... ............................................................................................................. $ N/C
***Exact Liner Footage Will Be Billed Upon Completion***
Confined Space Reinstate Two (2) Inverts, one in each manhole structure or out -fall @ $150.00 ea .................$ N/C
Mobilization, Set up & Demobilization @ $800.00 per site...........................(Estimated 1-Visit)................................... $ 800.00
**Vac Truck, CCTV Track, Reefer Truck, Boiler Truck & Trailer & Cutter Truch**
Estimated Total Price $ 59,400.00
To be provided by others/The Hiring Contractor: Stabilized access to the site to perform duties requested, permits,
MOT/traffic control, water meter or clean water source, any bypass pumping, up -stream plugging & dewatering
the system as needed, along with a suitable dump site for debris or Transportation & Environmental Disposal
Charges will apply.
We appreciate this opportunity to serve The City of Ocoee
Note: This proposal may be withdrawn by as if not accepted within 30 days.
Please contact our main office for any scheduling needs
Payment terms are Net 30 days
REPRESENTATIVE: Walt Kush Position: Service Rep.
Authorized Signature: Date: 10/29/2020
Acceptance of Proposal ... The above prices, specifications, and conditions are satisfactory and are hereby accepted. You are authorized to do
the Wa rk as specified. Payment will be made as outlined above. We understand that attorney fees and collection costs will be recovered if
contract is not paid in full.
Authorized Signature: Date:
QUOTATION
AMERICAN IN -LINE INSPECTION, Inc
415 Timaquan Trail Phone (386) 409-5446
Edgewater, FL 32132 Fax (386) 957-4919
Proposal smmnatea To: The City.oflococe
Phone: 407 905-3170
Dale; 10/29/2020
sired: 301 Maguire Road
Job Name: Kemos Landing CIPP MH to MH Install
City, State, Zip Code; Ocoee FL 32778
Job Location: 2700 Kemos Landing, Ocoee FL
ATTN: Mr. Russell Oliver Cell # 407-427-3760
Fax: Roliver@ci.ocoee.fl.us
We propose to perform the following:
City of Ocoee's Municipality to Cofferdam @ (The Lake), Then Plug (The Retention Pond) & Dewater (The Storm
Drainage System), Prior to AIL Pre -Cleaning & Pre-CCTV/Video Inspection One (1) Separate Run approx. 197
+/- of Existing 30" CMP Storm Pipe, before Installing C.I.P.P. manhole to manhole liner system, using the NLC-
115-18 100% epoxy lamination system. Our price includes all labor, material, equipment, and workmanship to
complete the project, along with a clear typed report and video before & after the repairs. (DVD/VHS) Additional
copies are $25.00 each.
Day Rate of 8-firs for Vac Truck & Crew to Clean One (01) Run of Existing 30" CMP Storm Pipe @ $200.00 per fir ...............$ 1,600.00
(Additional hours @ $200,00 per hour if needed)
Day Rate of 6-firs for CCTVNideo & Crew to video Existing Storm Drainage Pipe @ $150.00 per hr.......... (Pre & Post) .......... $ 900.00
(Additional hours @ $150.00 per hour if needed)
Install approx. 197 +/- LP of 30" 6mm CIPP M/H to MID Liner @ $248,00 per LF..............(MES-Lake to Roadway) ............. $ 48,856.00
Plus 20 LF of 30" Dry Sag Included......................................................................................................................$ N/C
Confined Space Reinstate Two (2) Inverts, one in each drainage structure & Mitered End Outfall @ $150,00 ea .....................$ 300.00
Mobilization, Set up & Demobilization @ $800.00 per site...........................(Estimated 1-Visit)...................................... $ 800.00
Total Price $ 52,456.00
To be provided by others/the hiring municipality: Stabilized Access to the Site to Perform Duties Requested,
Cofferdam (The Lake), Plug (The Retention Pond) & Dewater (The Pipe Ram), MOT/Traffic Control, Water
Meter or Clean Water Source and Suitable Dump Site for Debris or Transportation & Environmental Disposal
Charges will apply.
We appreciate this opportunity to serve The City of Ocoee
Note: This proposal may be withdrawn by us if not accepted within 30 days.
Please contact our main office for any scheduling needs
Payment terms are Net 20 days
REPRESENTATIVE: Wolt Kush Position: Service Rep.
Authorized Signature: Date: 10/29/2020
Acceptance of Proposal ... The above prices, specifications, and conditions are satisfactory and are hereby. accepted. You are authorized to do
the work as specified. Payment will be made as -outlined -above. We understand that attorney fees and collection costs will be recovered if
contract is not paid in iulL
Authorized Signature: Date:
QUOTATION
415 Timaquan Trail Phone (386) 409-5446
Edgewater, FL 32132 Fax (386) 957-4919
Proposal Submitted To: The City of Ocoee
Pima.: 407 905-3170
Date: 10/29/2020
street: 301 Maguire Road
Job Name: Pond #17 CIPP MH to MH Install
aty,state,zip ode; Ocoee FL 32778
Job Location: Pond # 7 Ocoee FL
ATTN: Mr. Russell Oliver Cell # 407-427-3760
Fax: Roliver@ci.ocoee.fl.us
We propose to perform the following:
Pre Clean & Pre & Post CCTV/Video One (1) Separate Run approx. 110 +/- of 36" Existing CMP Storm Pipe,
before Installing C.I.P.P. manhole to manhole liner system, using the NLC-115-18 100% epoxy lamination system.
Our price includes all labor, material, equipment, and wo•lunanship to complete the project, along with a clear
typed report and video before & after the repairs, (DVD/VHS) Additional copies are $25.00 each.
Day Rate of 12-hrs for Vac Truck & Crew to Clean One (01) Run of 36" Existing CMP Storm Pipe @ $200.00 per hr.......... $ 2,400.00
***Vac Truck On Site To Assist CIPP Liner Installation***
(Additional hours @ $200.00 per hour if needed)
Day Rate of 6-firs for CCTV/Video & Crew to video Existing Sturm Drainage Pipe @ $150.00 per hr........ (Pre & Post) ....... $ 1,110.00
(Additional hours @ $185.00 per hour if needed)
Engineering Design Calculation Spec's by Manufacture, Per Line Segment @ $1,500.00 each ............. (1-Run)................. $ If Needed
Install approx. 110 +/- LP of 36" 6mm CIPP M/H to M/H Liner @ $345.00 per LP .... ................................................... $ 37,950.00
Plus 20 LP of 36" Dry Bag Included .............................................. ................................................................... $ N/C
***Exact Liner rootage Will Be Billed Upon Completion***
Confined Space Reinstate Two (2) Inverts, one in each manhole structure or out -fall @ $150.00 ea .................$ 300.00
Mobilization, Special Set up & Demobilization @ $1,500.00 per site .....................(Estimated 1-Visit)........................... $ 1,500.00
**Vac Truch, CCTV Truck, Reefer Truch, Boiler Truck & Trailer & Cutter Truck**
Estimnted Total Price $ 43,300.00
To be lnrovided by others/T he Hiring Co1fi actor: Stabilized access to the site to perform duties
requested, permits, MOT/traffic control, water meter or clean water source, any bypass pumping, up-
stream plugging & dewatering the system as needed, along with a suitable dump site for debris or
Transportation & Environmental Disposal Charges will apply.
We appreciate this opportunity to serve The City of Ocoee
Note: This proposal may be withdrawn by us if not accepted within 30 days.
Please contact our main office for any scheduling needs
Payment terms are Net 20 days
REPRESENTATIVE: Walt Kush Position: Service Rep.
Authorized Signature: Date: 10/29/2020
-Acceptance of Proposal ... The above prices, specifleations, and conditions are satisfactory and are hereby accepted, You are authorized to do
the wok as specified. Payment will be made as outlined above, We understand that attorney fees and collection costs will be recovered if
contract is not paid in full,
Authorized Signature: Dater
QUOTATION
415 Timaquan Trail Phone (386) 409-5446
Edgewater, FL 32132 Fax (386) 957-4919
Proposal sulnuitted:To: The.City of Ocoee
Phoae: 407 905-3170
Date: 10/29/2020
Street 301 Maguire Road
JobNmue: CIPP MH to MH Liner Install Repair
City, Slide, zip Code: Ocoee FL 32778
Job Loomion: 2006 Nane Ann Terrace, Ocoee, FL
ATTN: Mr. Russell Oliver, 407-427-3760
Fax: Roliver@ci.ocoee.fl.us
We propose to perform the following; 2002 Nancy Ann Terrace MH to MH
Pre Clean & Pre & Post CCTVNideo One (1) Separate Run approx. 100 +/- of 15" Existing RCP Storm Pipe,
before Installing C.I.P.P. manhole to manhole liner system, using the NLC-115-18 100% epoxy lamination system.
Our price includes all labor, material, equipment, and workmanship to complete the project, along with a clear
typed report and video before & after the repairs. (DVD/MS) Additional copies are $25.00 each.
Day Rate of 8-hrs for Voc Truck & Crew to Clean One (01) Run of 15' RCP Storm Pipe @ $200.00 per hr.......................$ 1,600.00
***Vac Truck On Site To Assist CIPP Liner Installution***
Day Rate of 4-hrs for CCTV/Video & Crew to video Existing Storm Drainage Pipe @ $150.00 per hr........(Pre & Post) ....... $ 600.00
Pre Plug Up -Stream Inverts......................................................... (As Needed) ....... .... .... .... I ... I .............. ......I .... $ 400.00
Install approx. 100+/- LF of 15 6nun CIPP M/H to M/H Liner @ 12,500.00 Minimum Charge .......................................$ 12,500.00
Plus 30 LF of 15' Dry Bag Included.................................................................................................................$ N/C
Confined Space Reinstate Two (2) Inverts, one in each manhole structure or out -fall @ $150.00 ea .................................$ N/C
Mobilization, Set up & Demobilization @ $800.00 per site...........................(Estimated 1-Visit)................................. $ 800.00
**Vnc Truck, CCTV Truck, Reefer Trucit' Boiler Truck & Trailer & Cutter Truck**
Estimated Total Price $ 15,900.00
To be provided by others/The Hiring Contractor: Stabilized access to the site to perform duties requested, permits,
MOT/traffic control, water meter or clean water source, any bypass pumping, up -stream plugging & dewatering
the system as needed, along with a suitable dump site for debris or Transportation & Environmental Disposal
Charges will apply.
We appreciate this opportunity to serve 'file Cify of Ocoee
Note: This proposal may be withdrawn by us if not accepted within 30 days.
Please contact our main office for any scheduling needs.
Payment terms are Net 30 days.
REPRESENTATIVE: Walt Kush Position: Service Rep.
Authorized Signature: Date: 10/29/2020
Acceptance of Proposal ... The above prices, specifications, and conditions are satisfactory and are hereby accepted. You are authorized to do
the Work as specified. Payment will be made as outlined above. We understand that attorney fees and collection costs will be recovered if
contract is not paid in full,
Authorized Signature: Date: