AGENDA ITEM COVER SHEET
Meeting Date: August 16, 2022
Item #
Reviewed By:
Contact Name: TJ Tomlinson, P.E. Department Director: Jamie Cr
Contact Number: (407) 905-3159 City Manager: Robert Frank
Subject: Waiving of Procurement MethodRequirements for Emergency Projects
Background Summary:
The Utilities Department has multiple projects that require a Purchase Order prior to the new 2022/2023
fiscal year (October 1, 2022) due to their urgent nature and end of the year time constraints.
• Orlando Health Central Hospital has a malfunctioning meter that needs to be replaced. Due to
the hospital having one service line, the City will require the assistance of EA Tapping and J.
Malever Construction to keep the hospital in service while switching the meter and adding a
bypass to ensure redundancy. City staff has been working diligently to coordinate with the
Hospital on this matter. Staff received two quotes, J. Malever was the least costly of the two
contractors.
• An 8-inch force main on Palm Dr is flowing below required cleansing velocity conditions which
results in clogging of the pipe and backup of connected developments. The City will need the
assistance of Prime Construction to clean the pipe and construct preventative measures to
maintain unconstructed flow. Prime Construction is working in the area and is of the few
contractors who was willing and able to do the work.
• Utilities has 17 areas that need concrete work due to emergency utility repairs impacting City
sidewalks. Due to limited staff available to perform concrete work, the City needs assistance
from Buffalo Concrete to pour and form new concrete sidewalk panels in these areas.
City staff has done extensive research to pick the contractors that they have confidence in to get the job
done quickly and efficiently. One of these contractors includes J. Malever Construction which was
awarded for RFQ22-005 for small construction projects under $500K and is awaiting a contract. The
use of the specified contractors to complete this urgent repair work will need the required purchasing
code waived.
As an additional step, Utilities discussed the projects and pricing with the Public Works Director who
concurred that the pricing and approach is consistent with today's market.
Issue:
Should the Honorable Mayor and City Commission waive the purchasing requirements so that Utilities
can quickly move forward with these repairs?
Recommendations:
Staff recommends the Honorable Mayor and City Commission waive the purchasing requirements so
that Utilities can quickly move forward with these repairs?
Attachments:
1. J. Malever Construction Estimate
2. EarthTrades Estimate
Financial Impact:
The construction to fix the meter and add a bypass for the future is in the amount of $16,950.00 for EA Tapping
which shall come from account number 401-533-10-3400 and $51,500.00 for J. Malever Construction which shall
come from account number 408-533-10-6302.
The construction to clean the 8-inch force main on Palm Dr and add new preventative measures is in the amount
of $22,458.39 for Prime Construction which shall come from account number 408-535-10-6302.
The construction to pour and form multiple concrete sidewalks is in the amount of $18,400.00 for Buffalo Concrete
which shall come from account number 407-535-00-6302.
Type of Item: (please mark with an 'Y)
Public Hearing
Ordinance First Reading
Ordinance Second Reading
Resolution
x Commission Approval
Discussion & Direction
Original Document/Contract Attached for Execution by City Clerk
Original Document/Contract Held by Department for Execution
Reviewed by City Attorney
Reviewed by Finance Dept.
Reviewed by
For Clerk's Dept Use:
Consent Agenda
Public Hearing
Regular Agenda
N/A
N/A
N/A
2
J. Malever Construction Company
301 Sampey Rd., Groveland, FL 34736
Phone:352-429-9507 Fax:452-429-8705
Contract / Proposal
Date August 10, 2022
Name/Owner: City of Ocoee - Utility Dept
1800 A.D. Mims Rd
Ocoee, FL 34761
Job Name: Health Central Hospital - Ocoee - Water Service Bypass
Engineer City of Ocoee
Plan Date Field Drawing
Estimate No 22111
I/We the undersigned do hereby authorize and direct J. Malever Construction Company
hereinafter "Malever") to perform construction work to the above -described property in
accordance with the Scope of Work outlined below. This Contract is subject to the Standard
Terms and Conditions below.
ACCORDING TO FLORIDA's CONSTRUCTION LIEN LAW (SECTIONS 713.001-713.37, FLORIDA STATUES), THOSE WHO
WORK ON YOUR PROPERTY OR PROVIDE MATERIALS AND SERVICES AND ARE NOT PAID IN FULL HAVE A RIGHT TO
ENFORCE THEIR CLAIM FOR PAYMENT AGAINST YOUR PROPERTY. THIS CLAIM IS KNOWN AS A CONSTRUCTION LIEN. IF
YOUR CONTRACTOR OR A SUBCONTRACTOR FAILS TO PAY SUBCONTRACTORS, SUB -SUBCONTRACTORS, OR MATERIAL
SUPPLIERS, THOSE PEOPLE WHO ARE OWED MONEY MAY LOOK TO YOUR PROPERTY FOR PAYMENT, EVEN IF YOU
HAVE ALREADY PAID YOUR CONTRACTOR IN FULL. IF YOU FAIL TO PAY YOUR CONTRACTOR, YOUR CONTRACTOR MAY
ALSO HAVE A LIEN ON YOUR PROPERTY. IF A LIEN IS FILED, YOUR PROPERTY COULD BE SOLD AGAINST
YOUR WILL TO PAY FOR LABOR, MATERIALS OR OTHER SERVICES THAT YOUR CONTRACTOR OR SUBCONTRACTOR MAY
HAVE FAILED TO PAY. TO PROTECT YOURSELF, YOU SHOULD STIPULATE IN THIS CONTRACT THAT BEFORE ANY
PAYMENT IS MADE, YOUR CONTRACTOR IS REQUIRED TO PROVIDE YOU WITH A WRITTEN RELEASE OF LIEN FROM
ANY PERSON OR COMPANY THAT HAS PROVIDED YOU A "NOTICE TO OWNER." FLORIDA's CONSTRUCTION LIEN LAW
IS COMPLEX, AND IT IS RECOMMENDED THAT YOU CONSULT AN ATTORNEY.
STANDARD TERMS AND CONDITIONS
I Malever's Scope of Work. The scope of work of this Contract/Proposal (hereinafter "Scope of Work") is to
furnish the labor and materials necessary to:
A
1 Scope per attached proposal breakdown.
B Notes
1 Includes one mobilization
2 This is a labor & equipment quote only - City to provide all materials - see additional items on proposal
3 Does Not Include any Asbuilts
Print date: 8/11/2022 1 of 3 Toms ocoee oakland water rev 2
Ocoee dater Service at Hospital - labor & eauin quote - REV 8/8
ITEM DESCRIPTION
Mobilization and General Conditions
UNIT
LS
QTY
1
Clearing & Demo
LS
1
Labor to Install 8" Pipe & Fittings
LS
1
install 6' wide x 4" Thick Sidewalk
SY
55
1
All Material to be provided by the City - Add the following
1
City to Schedule & Install (inc excavation) all necessary wet
taps / line Stops / EZ Valve needed for bypass
City to coordinate with the Hospital on all landscape and plant
removal before work starts. Hospital to reinstall all landscape
City to take and run 2 day Bac T samples on new pipe
1
Add 2 - 12 long sleeve w/acc
1
1 - 8" Long sleeve w/acc
1
2 - 8" 22 bends with acc
1
4 valve boxes
1
1 jumper asembly with meter for 12" pipe
1
Hyd Meter to fill the pipe
1
1
The per day change for labor and equipment - remove and
reset new water meter at old backflow is $4,400 per day
Day
2
Totals
1
$51,550.00
Comir EARTHTFRADES
City of Ocoee Water
Time & Materials Work Order Proposal 7/18/2022
Main Bi Pass
Bill To Totals
City of Ocoee Utilities Department Equipment
and Labor $120,785.00
1800 A.D. Mims Road Materials: $0.00
Ocoee, FL 34761-4001 O&P $9,058.88
ATIention: Gary Gleason Invoice Total: $129,843.88
Equipment and Labor Only Does not Inlude Materials
Equipment and Materials Description
Quantity or Hours
Cost Per Item
Total
Notes
Excavate and Expose 12" Line Stop, 12" EZ
3
$5,230.00
$15,690.00
Excavation and soft digging for the Installation of EZ Valves and Wet
Valve, 8" EZ Valve, 8"x8" Wet Tap,
Tap's Estlnated 3 days Crew on site during Taps and Line stops
Pipe Crew to Excavte trenches for pipe
Pipe Crew rate Includes all Labor, Equipment, Tolls ect. Necesssary to
Instalations install and assemble Backflow
12
$5,230.00
$62,760.00
complete the proposed socpe of waor as required
Replace Sidewalk as Required
600
$9.75
$5,850.00
Includes unit cost piece to sunbrade, Form Pour and Finish 4" sidewalk
replacement Including Pump for concrete due to location
Equipment Mobilization
1
$2,200.00
$2,200.00
Mobilize Equipment as required
SURVEYING FIELD CREW
8
$175.00
$1,400.00
This Deos not Include Certified as builds or record drawings we will
provide Digital Red Line as builds
CAD WORK SURVEYING
8
$125.00
$1,000.00
This Deos not Include Certified as builds or record drawings we will
provide Digital Red Line as builds
Demo Concrete Sidewalk and Curbs as
600
$6.25
$3,750.00
Cost per Sq. Ft may increase or decrease as required
Required
12" Line Stop Fitting
1
$8,905.00
$8,905.00
See attached Quote from CFT Included Equipment Labor and
Materials 3 week lead time on materials
8" EZ Insert Valve
1
$9,775.00
$9,775.00
See attached Quote from CFT Included Equipment Labor and
Materials 3 week lead time on materials
12" EZ Insert Valve
1
$8,905.00
$8,905.00
See attached Quote from CFT Included Equipment Labor and
Materials 3 week lead time on materials
8" Test &Tap
1
$550.00
$550.00
See attached Quote from CFT This does not Include the tapping Sleeve
and Valve
PLATETAMP 4 hour min
$35.00
$0.00
Street Sweeper 4 hour min
$75.00
$0.00
Roller 4 hour min
$210.00
$0.00
Loader 4 hour min
0
$230.00
$0.00
SOIL STABALIZER/Mixer 4hour min
$285.00
$0.00
Motor Grader 4 hour min
$260.00
$0.00
7000R D-6 K Bulldozer hour min
$285.00
$0.00
650 OR D5 Bulldozer 4 hour min
$225.00
$0.00
100,000 LB Size Excavator 4 hour min
$325.00
$0.00
70,000 LB Size Excavator 4 hour min
$250.00
$0.00
50000 LB Size Excavator 4 hour min
$220.00
$0.00
Mini Excavator 4 hour min
0
$120.00
$0.00
Skid Steer 4 hour min
$135.00
$0.00
END Dump Truck OFF ROAD Hauling 4
$285.00
$0.00
hour min
Dump Truck ON ROAD Hauling 4 hour min
$185.00
$0.00
CLEARING / DIRT CREW / FINISH GRADE
$4,771.00
$0.00
"LABOR AND EQUIPMENT" DAILY RATE
PIPE CREW "LABOR AND EQUIPMENT"
0
$5,230.00
$0.00
DAILY RATE
TOTAL
I
fltlgtlnifflgfttl
Payee Signature
Payer Sin nature
"Building Partnerships" P.O. Box 521279 CU C055705
Longwood, FL 32752-1279 CB C045652
Central FloridaTapping & Phone: 407-834-8271 CONT. V 13942900011997
Construction Services, Ine. Fax: 407-834-3859
CFT will furnish Technician(s), Material and Equipment to perform One (1) 12" Line
Stop on PVC Pipe containing water at 60 PSI. Included in the service price is a period of
one (1) 8-hour continuous calendar day with no overtime, per operation. Line Stops are to
be performed during normal working hours.
Base price includes one (1) day or less, per Line Stop, when Line Stop is in place. Daily
charge thereafter will be at a rate of $500.00 per day. Service and Material for this quote
will be as follows. CFT will furnish and install material for the Line Stops only.
Item No. Description Quantitv Unit Unit Price Total
1 12" Line Stop 1 EA $ 8,905.00 $ 8,905.00
Total $ 8,905.00
• Quote valid for 30 days.
• Payment terms are net 30 days from invoice date
• Unpaid invoices beyond 30 days incur 1-1/2% per month carrying charge
• Florida Sales Tax on Material is included.
• No Retainage
Central Florida Tapping Acceptance:
Rick Bullington
2
"Building Partnerships" P.O. Box 521279 CU C055705
Longwood, FL 32752-1279 CB C045652
Central FloridaTapping & Phone: 407-834-8271 CONT. V 13942900011997
Construction Services, Inc. Fax: 407-834-3859
July 19, 2022
Todd Henderson
Earthtrades
3307 Clarcona Road
Apopka, Fl. 32703
Re: Ocoee Hospital By Pass
Todd,
We propose the following,
Item No. Description
1 8" EZ Insert Valve
2 12" EZ Insert Valve
3 8" Test & Tap
Tota
Quanti Unit' Unit Price Total
1 EA $ 9,775.00 $ 9,775.00
1 EA $ 18,400.00 $ 18,400.00
1 EA $ 550.00 $ 550.00
$ 28,725.00
An accurate OD and pipe type will need to be verified by others prior to ordering the
valves. Also please note the manufacture, nor CFT, can guarantee a 100% shut down and
these valves cannot be tested against. Additionally a dry, safe work pit is to be supplied.
Please call with any questions you might have.
Sincerely,
Rick Bullington
Accepted by,