STAFF REPORT
Meeting Date: October 15, 2024
Item #: 10
Contact Name: Trent Hopper Department Director: Jen Bolling
Contact Number: Ext. 4306 City Manager: Craig Shadrix
Subject: Approval to Rebuild Bar Screen #1 at the City of Ocoee Wastewater Treatment Plant
(WWTP). (Acting Utilities Director Bolling)
Background Summary:
The approved City of Ocoee Budget for Fiscal Year 2024-2025 includes $115,000.00 to rebuild Bar Screen #1
at the WWTP. Staff contacted FilterONE USA, Inc., a division of Parkson Corporation, the original
manufacturer and sole source vendor for the current bar screen, and obtained a quote of $89,817.00 for the
rebuild.
Issue:
Should the Honorable Mayor and City Commissioners approve to rebuild Bar Screen #1 at the WWTP with
Parkson Corporation, at a cost of $89,817.00?
Recommendations:
Staff recommends that the Honorable Mayor and City Commissioners authorize the City Manager to cause the
rebuild of Bar Screen #1 at the WWTP by contracting with Parkson Corporation, at a cost of $89,817.00, and
to approve Parkson Corporation as the Sole Source Vendor for bar screen parts and repairs at the
WWTP. Staff also recommends that the City Manager be authorized to approve changes to this contract up to
the limit of his purchasing authority for each change order.
Attachments:
1. Quote
2. Sole Source Vendor Form
Financial Impacts:
None as this purchase is adequately funded in the FY 24-25 budget.
Type of Item: Consent
Page 84 of 122
Quotation
NUMBER: B02011597 Rev 1 DATE: September 11, 2024
TO: Ocoee WWTF
Attn: Bruce Chiesa
Tel: 407-353-6417
Fax:
E-Mail: bchiesa@ocoee.org
REF.: Project Name: Ocoee WWTF
Project Location: Ocoee, FL
Original Serial #: 2014050
Rebuild #: n/a
Specification Sec.: n/a
Parkson Corporation proposes the reconditioning of your existing Aqua Guard® Continuous Self-
Cleaning Bar/Filter Screen and is pleased to provide this Rebuild/Retrofit Quotation for the following:
ITEM 1 AQUA GUARD SELF-CLEANING BAR/FILTER SCREEN
# Existing Units: 1
Unit #: 2014050
Model: Inflomax
1.A Existing Equipment:
Description
Screen Width: 2’-10.5”
Solids Discharge Height: 8 ft.
[as measured from the bottom of the channel to the discharge point]
Screen Angle: 75 º
Screen Opening: 6 mm
Application / Industry: Municipal
Materials of Construction
Elements: high impact polycarbonate alloy
Frame: 304 SS
Conveyor Chain: 304/410
Filter Element Shafts: 304 SS
Side Plate: high impact phenolic
Page 85 of 122
1.B The following parts are recommended for replacement on one (1) unit:
2014050 Inflomax B02011597
Ocoee WWTF
AG-MN-A 2'-10-1/2"x8'DH, 304ss, 6mm
Item Description Quantity
Crane 2
Motor, Baldor, 2HP 1
Rotating Brush 1
Rotating Guide Rail 1
Upper Guide Rail, 304ss 2
Lower Guide Rail, 304ss 2
Rail, front 6
Rail, rear 4
Discharge Chute Pan Seal, UHMW 1
Side Seals , Neoprene 2
Flange Bearing, Brush 2
Bearing, Rotating Rail 2
Flange Bearing, Drive shaft 1
Front Seal Brushes 1A-6262
Brush, 2" 1
Brush, 3" 1
Clips
Nameplates & Labels set 1
Crane 2
Screen Assembly
Side Plates 1A-5766 160
Spacer Washer 160
Conveyor Chain 160
Filter Shaft, solid, (total 80 shafts) 80
Snap Rings 3/4 160
Filter Elements 6mm 3280
Page 86 of 122
ITEM 2 OFFERINGS - PURCHASE PRICE
2.A Parkson Certified On-site Rebuild with OEM Parts & Technicians (Per Unit)
………………………………………………………………………………………$89,817.00 USD
1. Customer/owner is responsible for thoroughly cleaning, pressure washing and
disinfecting the unit prior to rebuild.
2. All parts listed in [1B] above.
3. Parts will be shipped F.O.B. Factory, freight included to jobsite.
4. Removal and reinstallation of the unit in the channel is included.
5. Parkson to supply crane.
6. Customer to disconnect electrical prior to rebuild.
7. Work performed by Parkson authorized field technicians, who will test run equipment at
completion of rebuild.
8. Taxes excluded.
Rebuild / Start-Up Assistance - Included
Parkson will furnish one certified crew as required to rebuild unit, provide start -up and
operator training. Dates of service to be scheduled upon receipt of Buyer’s written request.
Additional start-up service can be purchased for $1,400 per day plus travel and living
expenses.
ITEM 3 OPTIONS FOR EXISTING UNITS(S) ONLY
1. ………………………………………………. Add/Deduct……. USD
ITEM 4 SCHEDULE, VALIDITY, PAYMENT TERMS
4.A Schedule
• Submittal Phase not required on this project.
• Parts availability: 14-16 weeks following receipt of acceptable written Purchase
Order. The Parkson Project Manager will coordinate shipment of the unit to and from
the factory with the customer for factory rebuilds.
• Field/on-site rebuild will be accomplished within 4 – 6 weeks after parts are delivered
• to customer, but in no event later than 90 days.
• Rebuild must be completed within 90 days after parts arrive on-site.
4.B Validity:
Price is valid for sixty (60) calendar days from Quotation date, for shipment of Equipment
within the timetable stated above.
Page 87 of 122
4.C Payment Terms:
20% net 30 days upon approved PO, 70% net 30 days upon shipment of parts to site,
10% upon rebuild completion, not to exceed 90 days after shipment of parts should
rebuild be delayed by other than Parkson. Payment terms for parts only without any
factory labor or field service is 100% net 30 days from shipment.
ITEM 5 WARRANTY, DRAWINGS & MANUALS
5.A Mechanical Warranty:
1. As defined in Section XVI (see attached link under terms and conditions) Standard
Conditions of Sale, Parkson offers a one (1) year mechanical warranty for all new
parts installed on the Aqua Guard screen by an on-site certified rebuild.
2. Installation labor of parts or parts not ordered as part of a rebuild package have a 90-
day warranty.
5.B Drawings and Installation, Operation and Maintenance (IO&M) Manuals:
1. Approval Drawings: Not required
2. Certified Drawings: Not required
3. IO&M Manuals: Not required
TERMS AND CONDITIONS:
This Quotation is governed by and subject to Parkson’s Standard Conditions of Sale, which are
incorporated by reference and accessible at: http://www.parkson.com/files/documents/AFRM-
terms.pdf
PATENTS:
The Equipment and/or process quoted herein may operate under one or more U.S. patents. The
Purchase Price includes a one-time royalty payment (if any), which provides the Buyer with
immunity to operate the Equipment specified in the Quotation under any applicable patents.
CLARIFICATIONS AND EXCEPTIONS:
Parkson is not in receipt of any plans and specifications. The equipment quoted above is based
upon Parkson’s current standards and may or may not comply with any specification that may exist.
Parkson reserves the right to revise this quotation upon receipt of any plans and specifications.
Page 88 of 122
BUYER / OWNER RESPONSIBILITY UNLESS OTHERWISE STATED:
Getting the Unit ready for the Rebuild/Retrofit
• Upon disassembly on-site, if any unforeseen parts or structural repairs are discovered,
Parkson Corporation will notify the customer prior to commencement of any repairs which will
be beyond the originally quoted scope. The costs for these items and any time extension will
be added to the scope of work.
• Disassembling from adjoining equipment / electrical / controls
• Disconnecting shower water connections and water supply
• Disconnecting controls / electrical connection and interconnecting wiring removal (including
any of the following, but not limited to: E-stop button, solenoids, motors, interlock switches,
wiring and conduit from each unit-mounted electrical device to a terminal box or control panel
• Removing piping connections, platforms, gratings and railings unless stated otherwise
• Removing any other auxiliary equipment or service not detailed above
• Readiness of the equipment before requesting [rebuild or start-up] service. Non-readiness
may result in additional charges.
Getting the Site ready for the Rebuild/Retrofit (Personnel Safety is of utmost importance)
• Provide a safe work area around the equipment.
1. If the rebuild is performed with the unit in the channel; customer/owner to cover the
channel with minimum ¾” plywood and ensure it is properly secured.
2. If unit is tilted out of the channel customer/owner to supply a brace (spanning the channel)
sufficient enough to support the weight of the unit while it is being rebuilt.
3. Whenever possible, unit should be staged away a safe distance away from any currently
utilized equipment and/or work areas.
• Provide proper ventilation inside the building
• Care and storage of rebuild components upon receipt at customer site.
• Unloading of replacement parts when they arrive on site.
• Delivered material needs to be stored at the same elevation and within 10 feet of the screen (if
applicable)
• Redirect channel flow.
• Provide clean, dry channel.
• Old parts weighing 50 lbs or more should be loaded on a customer supplied forklift (or equal)
in order to place them in a customer supplied dumpster.
Customer must Provide
• At a minimum a forklift.
• Manlift, ladders
• Dumpster for all old parts [on-site rebuild only].
NOTE REGARDING PREVALING WAGES: Parkson, as the original equipment manufacturer,
will be servicing/reconditioning its own proprietary equipment, which service may contain our
proprietary trade secrets and knowhow. No craft or trade would be appropriate for apprentices
related to this work. If the awarding body requires apprenticeship coverage, then Parkson
would need to amend its quoted pricing and completion time
Page 89 of 122
• Please return one signed copy of this quotation and Purchase Order to Parkson Corporation
at the address below. Refer to this quotation, date, and related correspondence.
Issued By: Carlos Robaina Accepted By: (Herein called the Buyer)
PARKSON CORPORATION
1401 West Cypress Creek Road, Ste. 100
Fort Lauderdale, FL 33309
Name: Marty Unger
Title: Regional Sales Manager
Phone: 954 383-1757
E-Mail: munger@parkson.com
Fax: 954-252-3775
Title:
Date:
Date: 9-11-2024
Local Rep:
cc: Edna Sugden
Aqua Guard Rebuild 9/26/2018 supersedes 06/09/17
Page 90 of 122
Page 1
Fort Lauderdale ♦ Chicago ♦ Montreal ♦ Mumbai
www.parkson.com
technology@parkson.com
Rev 4 AF-008
1401 West Cypress Creek Road
Suite 100
Fort Lauderdale FL 33309-1969
Phone 1.888.PARKSON
Fax 954.974.6182
Sole Source Letter
To: Bruce Chiesa Date: September 12, 2024
Company: Ocoee WWTF
1810 A D Mims Rd
Ocoee, FL 34761
From: Marty Unger
Tel: 407-353-6417 Tel: 954-383-1757
Fax: Fax: 954-252-3775
Email: BChiesa@ocoee.org Email: munger@parkson.com
# Pages: 1 Cc:
Subject Project: Inflomax
This document is to confirm that Parkson Corporation is the sole source provider for parts for the
subject product. Parkson Corporation is the original manufacturer/supplier of the subject product and is
the only source for OEM replacement parts. In addition, Parkson is the only company with certified
technicians capable of rebuilding/working on the subject product.
If I can be of further assistance or should you have any questions, please feel free to contact me.
Sincerely,
Marty Unger
Parkson Corporation