HomeMy WebLinkAboutItem 12 Approval to Piggyback Sourcewell Cooperative Purchasing Contract to Purchase Generators for Lift Station 21 (Pioneer Key II) and Lift Station 14 (Lake Olympia)
City of Ocoee ▪ 1 N. Bluford Avenue ▪ Ocoee, Florida 34761
Phone: (407) 905-3100 ▪ www.ocoee.org
STAFF REPORT
Meeting Date: December 3, 2024
Item #: 12
Contact Name: Trent Hopper Department Director: Jen Bolling
Contact Number: Ext. 4306 City Manager: Craig Shadrix
Subject: Approval to Piggyback Sourcewell Cooperative Purchasing Contract to Purchase
Generators for Lift Station 21 (Pioneer Key II) and Lift Station 14 (Lake Olympia). (Acting
Utilities Director Bolling)
Background Summary:
As part of the ongoing hurricane critical infrastructure resilience program, the Utilities Department identifies
opportunities to strengthen backup systems and emergency redundancies at wastewater lift stations. During a
hurricane, the Utilities Department deploys mobile generators to combat power outages at the wastewater lift
stations and avoid catastrophic failures. Staff has identified Lift Station 21 (Pioneer Key II) and Lift Station 14
(Lake Olympia) as locations where permanent generators are needed, as these locations experience
consistent power failures and are extremely difficult to reach during extreme weather events. Sourcewell is a
cooperative purchasing program that the City of Ocoee is a member of. The permanent generators are
available for purchase under Sourcewell Contract #09222-CAT at a total cost of $200,075.00.
Issue:
Should the Honorable Mayor and City Commissioners approve to piggyback the Sourcewell Cooperative
Purchasing Contract to purchase generators for Lift Station 21 (Pioneer Key II) and Lift Station 14 (Lake
Olympia)?
Recommendations:
Staff recommends that the Honorable Mayor and City Commissioners authorize the City Manager to purchase
generators for Lift Station 21 (Pioneer Key II) and Lift Station 14 (Lake Olympia) from Ring Power CAT utilizing
Sourcewell Contract #09222-CAT. Staff also recommends that the City Manager be authorized to approve
changes to this contract up to the limit of his purchasing authority for each change order.
Attachments:
1. MB24-149-Ocoee LS 21-30kw
2. MB24-150-Ocoee LS 14 80kw Turnkey
3. 120617-CAT - Pricing Information (1)
Financial Impacts:
None, as this purchase is fully funded by utilizing the remaining funds for Job#P000298A (Generator and
Repiping for Palm Drive)
City of Ocoee ▪ 1 N. Bluford Avenue ▪ Ocoee, Florida 34761
Phone: (407) 905-3100 ▪ www.ocoee.org
Type of Item: Consent
Your North and Central Florida Caterpillar Dealer
ST. AUGUSTINE TALLAHASSEE OCALA ORLANDO TAMPA
500 World Commerce Prkwy 4752 Capital Circle NW 6202 N US 301/441 9901 Ringhaver Dr. 9797 Gibsonton Dr
St. Augustine, FL 32092 Tallahassee, FL 32303 Ocala, FL 34475 Orlando, FL 32824 Riverview, FL 33569
904-737-7730 850-562-1622 352-732-4600 407-855-6195 813-671-3700
SALES SERVICE PARTS LEASING RENTALS
QUOTATION / SALES AGREEMENT / SECURITY AGREEMENT
Quotation Accepted By: ______________________________Date: ___________Tax No.: ________________________________
Customer: __________________________________Salesman's Signature: Mark Barbarulo
Mark Barbarulo, EPG Sales. Central Florida
TERMS
• This quotation is valid for 30 days. Due to the fluctuating costs associated with key materials
such as steel, aluminum, and copper, and other manufacturer delays beyond Ring Power’s control,
we reserve the right to review quotation pricing at the time of order and again at time of equipment
release. If material costs increase by greater than 2%, Ring Power will update our quotation
accordingly. We appreciate your understanding during this volatile time and look forward to
partnering with you as we work through it together.
• All quoted prices are subject to change without notice. Those in effect on the date of shipment shall prevail.
• Subject to credit approval.
• Used equipment is subject to prior sale.
• A 25% restocking fee will be assessed for all canceled orders or returned materials.
• No retainage to be withheld. Ring Power Systems is an equipment supplier and is not a sub-contractor. Our terms are Net 10 days.
• No sales tax is included.
• Buyer grants to seller a security interest in all equipment as described in this agreement until such time as payment is made in full
in accordance with the terms and conditions of this agreement and in accord with the seller’s credit application.
• Ring Power requires a purchase order to secure this sales agreement.
Page 1 of 4
DATE: 11/7/2024 QUOTATION NO: MB24-149
CUSTOMER NAME: Ocoee
ADDRESS:
CITY/STATE/ZIP: , FL
CONTACT: Bruce C
PHONE:
ESTIMATED SHIPPING LEAD TIME: 30 weeks-
changes weekly or depending on stock
SHIPPING VIA/FOB:
ESTIMATED SUBMITTAL LEAD TIME: 12+ Weeks
JOBSITE ADDRESS:
CITY/STATE/ZIP: FL
PROJECT NAME: LS 21
TERMS: Full payment is due from buyer within 10 days of delivery or pickup of the equipment.
DESCRIPTION OF MATERIAL UNIT PRICE EXTENSION
Please ensure the quote meets your expectations.
For your reference, your Sourcewell Member ID is 75029
One (1) New Caterpillar Diesel Generator – Model 2.2 Rated 30
KW standby at 0.8 PF, 240 Volts, 3 Phase, 4 Wire, 60 Hz at 1800
RPM, with following options:
DESCRIPTION OF MATERIAL UNIT PRICE EXTENSION
Page 2 of 4
• Main UL circuit breaker 100-amp
• Control panel with safety shutdowns, Engine controls and
gauges
• Voltage regulator
• Governor
• PMG excitation
• Jacket water heater
• Battery charger UL 10 amp
• 2 Year / 1000-hour Caterpillar limited warranty
• Start up and Commissioning
• Includes 4-hour load test
• Batteries and cables
• Introduction and training to personnel
• Freight to customer site
• Factory sound steel enclosure
• 68-gallon fuel tank 24 hr run at 100%
300 Series, Automatic Open
Transition Transfer Switch 104-amp 3 pole N4X
- PROVIDE ENGINEERING, PERMIT AND INSPECTION
- SITE PREPARATION:
- INSTALL CONCRETE PAD (~3'X8')
- RIGGING/CRANE NEW GENERATOR
- INSTALL NEW 30KW DIESEL GEN 120/240V 3PH
- INSTALL NEW 100A ATS 120/240V 3PH
- PROVIDE/INSTALL NEW GENERATOR FEEDERS
- PROVIDE AND INSTALL NEW STAINLESS STEEL 100A
FUSED DISCO
- TESTING
- FINAL INSPECTION
NOTES:
- DIESEL FUEL BY OTHERS
- BOLLARDS ADDER $1200 EACH
- NO REMOTE ANNUNCIATOR
Total NET for above $87,160.00
Exceptions & Clarifications:
DESCRIPTION OF MATERIAL UNIT PRICE EXTENSION
Page 3 of 4
***If video recording any training is necessary, a Ring Power form
will need to be signed before any taping is to be performed. ***
NOTE:
******DUE TO THE VOLATILITY OF THE MATERIALS
MARKET, ALL PROJECTS WILL BE RE-PRICED AT TIME OF
RELEASE TO PRODUCTION.
ANY INCREASE OR DECREASE WILL BE ASSESSED AND
APPLIED AT THAT TIME.
BASED ON RECENT MATERIAL COSTING, ESTIMATED
PRICING ESCALATION IS 10% INCREASE PER MONTH ON
ENCLOSURES,TANKS AND GENERATORS.*******
NOTE:
1. The above price includes start-up, testing, and customer training.
2. No fuel is included.
3. No third party testing or NETA testing included and is by others.
4. No sales tax included
5. Training that is to be videotaped, requires Ring Power approval in advance. RPC “Video
Recording Agreement” / waiver signed by the customer / end-user in advance. Videographer /
Recording Equipment to be provided by others.
6. In some cases the enclosure, tank and exhaust are shipped loose, installation is by others.
7. Work to be done during normal business hours 8am to 4pm.
8. Proposal is based on information supplied by the Customer.
9. Generators that come with an 800 amp breaker or larger are supplied with buss bar, Lugs are by
others.
10. No specifications, drawings, or diagrams were received or reviewed. General exception is taken
to any other specifications and drawings not available at time of quotation. Equipment supplied will
be limited to that described in this proposal.
11. Ring Power will be supplying equipment as described in the attached documentation.
12. For fuel tanks over 550 Gallons, it is the Contractor or Owners responsibility to notify the
appropriate State, and/or local regulatory agencies prior to delivery of the fuel storage tank so that
it can be inspected prior to fueling. The FDEP Registration form will be provided in the Ring Power
Submittal. Per FDEP Breach of Integrity Testing Guidance, tanks will ship from the factory with a
vacuum/gauge installed. On-site testing is not included.
13. Ring Power will not release equipment for production until we have received the signed
sales agreement and signed and approved submittal from our customer. This is done to
insure that we are providing quality equipment that fits our customer’s needs. If you need
any assistance, please contact your sales representative.
DESCRIPTION OF MATERIAL UNIT PRICE EXTENSION
Page 4 of 4
14. Under no circumstances does Ring Power accept any flow down provisions without specific
written agreement between Ring Power and Buyer.
Thank you for considering Ring Power Systems for your generator needs
Mark Barbarulo
Mark Barbarulo
Ring Power Systems, Generator Sales Central Florida,
407-472-6231 Office - 407-857-1592 Fax - 407-383-5840 Cell
Mark.barbarulo@ringpower.com
Your North and Central Florida Caterpillar Dealer
ST. AUGUSTINE TALLAHASSEE OCALA ORLANDO TAMPA
500 World Commerce Prkwy 4752 Capital Circle NW 6202 N US 301/441 9901 Ringhaver Dr. 9797 Gibsonton Dr
St. Augustine, FL 32092 Tallahassee, FL 32303 Ocala, FL 34475 Orlando, FL 32824 Riverview, FL 33569
904-737-7730 850-562-1622 352-732-4600 407-855-6195 813-671-3700
SALES SERVICE PARTS LEASING RENTALS
QUOTATION / SALES AGREEMENT / SECURITY AGREEMENT
Quotation Accepted By: ______________________________Date: ___________Tax No.: ________________________________
Customer: __________________________________Salesman's Signature: Mark Barbarulo
Mark Barbarulo, EPG Sales. Central Florida
TERMS
• This quotation is valid for 30 days. Due to the fluctuating costs associated with key materials
such as steel, aluminum, and copper, and other manufacturer delays beyond Ring Power’s control,
we reserve the right to review quotation pricing at the time of order and again at time of equipment
release. If material costs increase by greater than 2%, Ring Power will update our quotation
accordingly. We appreciate your understanding during this volatile time and look forward to
partnering with you as we work through it together.
• All quoted prices are subject to change without notice. Those in effect on the date of shipment shall prevail.
• Subject to credit approval.
• Used equipment is subject to prior sale.
• A 25% restocking fee will be assessed for all canceled orders or returned materials.
• No retainage to be withheld. Ring Power Systems is an equipment supplier and is not a sub-contractor. Our terms are Net 10 days.
• No sales tax is included.
• Buyer grants to seller a security interest in all equipment as described in this agreement until such time as payment is made in full
in accordance with the terms and conditions of this agreement and in accord with the seller’s credit application.
• Ring Power requires a purchase order to secure this sales agreement.
Page 1 of 4
DATE: 11/7/2024 QUOTATION NO: MB24-150
CUSTOMER NAME: Ocoee
ADDRESS:
CITY/STATE/ZIP: , FL
CONTACT: Bruce C
PHONE:
ESTIMATED SHIPPING LEAD TIME: 30 weeks-
changes weekly or depending on stock
SHIPPING VIA/FOB:
ESTIMATED SUBMITTAL LEAD TIME: 12+ Weeks
JOBSITE ADDRESS:
CITY/STATE/ZIP: FL
PROJECT NAME: LS 14
TERMS: Full payment is due from buyer within 10 days of delivery or pickup of the equipment.
DESCRIPTION OF MATERIAL UNIT PRICE EXTENSION
Please ensure the quote meets your expectations.
For your reference, your Sourcewell Member ID is 75029
One (1) New Caterpillar Diesel Generator – Model 4.4 Rated 80
KW standby at 0.8 PF, 480 Volts, 3 Phase, 4 Wire, 60 Hz at 1800
RPM, with following options:
DESCRIPTION OF MATERIAL UNIT PRICE EXTENSION
Page 2 of 4
• Main UL circuit breaker 150-amp
• Control panel with safety shutdowns, Engine controls and
gauges
• Voltage regulator
• Governor
• PMG excitation
• Jacket water heater
• Battery charger UL 10 amp
• 2 Year / 1000-hour Caterpillar limited warranty
• Start up and Commissioning
• Includes 4-hour load test
• Batteries and cables
• Introduction and training to personnel
• Freight to customer site
• Weatherproof white steel enclosure
• 209-gallon fuel tank 24hr at 100% loaded
300 Series, Automatic Open
Transition Transfer Switch 200-amp 3 pole N4X
- PROVIDE ENGINEERING, PERMIT AND INSPECTION
- SITE PREPARATION:
- MODIFY EXISTING CONCRETE PAD
- RIGGING/CRANE NEW GENERATOR
- INSTALL NEW 80KW DIESEL GEN 120/240V 3PH
- INSTALL NEW 200A ATS 120/240V 3PH
- PROVIDE/INSTALL NEW GENERATOR FEEDERS
- PROVIDE AND INSTALL NEW STAINLESS STEEL 200A
FUSED DISCO
- TESTING
- FINAL INSPECTION
NOTES:
- DIESEL FUEL BY OTHERS
- BOLLARDS ADDER $1200 EACH
- NO REMOTE ANNUNCIATOR
Total NET for above $112,915.00
Exceptions & Clarifications:
DESCRIPTION OF MATERIAL UNIT PRICE EXTENSION
Page 3 of 4
***If video recording any training is necessary, a Ring Power form
will need to be signed before any taping is to be performed. ***
NOTE:
******DUE TO THE VOLATILITY OF THE MATERIALS
MARKET, ALL PROJECTS WILL BE RE-PRICED AT TIME OF
RELEASE TO PRODUCTION.
ANY INCREASE OR DECREASE WILL BE ASSESSED AND
APPLIED AT THAT TIME.
BASED ON RECENT MATERIAL COSTING, ESTIMATED
PRICING ESCALATION IS 10% INCREASE PER MONTH ON
ENCLOSURES,TANKS AND GENERATORS.*******
NOTE:
1. The above price includes start-up, testing, and customer training.
2. No fuel is included.
3. No third party testing or NETA testing included and is by others.
4. No sales tax included
5. Training that is to be videotaped, requires Ring Power approval in advance. RPC “Video
Recording Agreement” / waiver signed by the customer / end-user in advance. Videographer /
Recording Equipment to be provided by others.
6. In some cases the enclosure, tank and exhaust are shipped loose, installation is by others.
7. Work to be done during normal business hours 8am to 4pm.
8. Proposal is based on information supplied by the Customer.
9. Generators that come with an 800 amp breaker or larger are supplied with buss bar, Lugs are by
others.
10. No specifications, drawings, or diagrams were received or reviewed. General exception is taken
to any other specifications and drawings not available at time of quotation. Equipment supplied will
be limited to that described in this proposal.
11. Ring Power will be supplying equipment as described in the attached documentation.
12. For fuel tanks over 550 Gallons, it is the Contractor or Owners responsibility to notify the
appropriate State, and/or local regulatory agencies prior to delivery of the fuel storage tank so that
it can be inspected prior to fueling. The FDEP Registration form will be provided in the Ring Power
Submittal. Per FDEP Breach of Integrity Testing Guidance, tanks will ship from the factory with a
vacuum/gauge installed. On-site testing is not included.
13. Ring Power will not release equipment for production until we have received the signed
sales agreement and signed and approved submittal from our customer. This is done to
insure that we are providing quality equipment that fits our customer’s needs. If you need
any assistance, please contact your sales representative.
DESCRIPTION OF MATERIAL UNIT PRICE EXTENSION
Page 4 of 4
14. Under no circumstances does Ring Power accept any flow down provisions without specific
written agreement between Ring Power and Buyer.
Thank you for considering Ring Power Systems for your generator needs
Mark Barbarulo
Mark Barbarulo
Ring Power Systems, Generator Sales Central Florida,
407-472-6231 Office - 407-857-1592 Fax - 407-383-5840 Cell
Mark.barbarulo@ringpower.com
All Discounts listed are for "Standby Ratings only unless otherwise stated".
List Price Discount
60 HZ, 40 - 60 kW Diesel (Reference the "PSNA-EPG-F_C4.4LCABR" Caterpillar Price List)
D40 - 40 kW 31%
D50 - 50 kW 31%
D60 - 60 kW 31%
60 HZ, 80 - 100 kW Diesel (Reference the "PSNA-EPG-F_C4.4PGABR" Caterpillar Price List)
D80 - 80 kW 31%
D100 - 100 kW 31%
60 HZ, 125 - 175 kW Diesel (Reference the "PSNA-EPG-F_C7.1PGABR" Caterpillar Price List)
D125 - 125 kW 35%
D150 - 150 kW 35%
D175 - 175 kW 35%
D200 - 200 kW 36%
C9, 60 HZ, 200 - 300 kW Diesel (Reference the "PSNA-EPG-F_C9PGAM" Caterpillar Price List)
200 kW 33%
250 kW 37%
300 kW 37%
C9 GC, 60 HZ, 200 - 300 kW Diesel (Reference the "CP GCABR" Caterpillar Price List)
250 kW 31%
300 kW 31%
C13, 60 HZ, 350 - 400 kW Diesel (Reference the "PSNA-EPG-F_C13PGAM" Caterpillar Price List)
350 kW 37%
400 kW 37%
C13 GC, 60 HZ, 350 - 400 kW Diesel (Reference the "C13 GCABR" & "C13 GCAM" Caterpillar Price List)
350 kW 31%
400 kW 31%
C15, 60 HZ, 350 - 500 kW Diesel (Reference the "PSNA-EPG-F_C15PGAM" Caterpillar Price List)
350 kW 37%
400 kW 37%
450 kW 37%
500 kW 37%
C15 GC, 60 HZ, 350 - 500 kW Diesel (Reference the "C15 GCABR" & "C15 GCAM" Caterpillar Price List)
350 kW 31%
400 kW 31%
450 kW 31%
500 kW 31%
C18, 60 HZ, 550 - 750 kW Diesel (Reference the "PSNA-EPG-F_C18PGAM" Caterpillar Price List)
550 kW 37%
600 kW 37%
650 kW 33%
700 kW 33%
750 kW 33%
C18 GC, 60 HZ, 550 - 600 kW Diesel (Reference the "C18 GCAM" Caterpillar Price List)
550 kW 31%
600 kW 31%
C18, 60 HZ, EPA Tier 4f, - 455 KW Diesel (Reference the "PSNA-EPG-F_C18PKAM" Caterpillar Price List)
455 kW Prime Power 20%
500 kW 20%
C27, 60 HZ, 750 - 800 kW Diesel (Reference the "PSNA-EPG-F_C27PGBG" Caterpillar Price List)
750 kW 34%
800 kW 34%
C32, 60 HZ, 1000 - 1250 kW Diesel (Reference the "PSNA-EPG-F_C32PGDG" Caterpillar Price List)
1000 kW 34%
1250 kW 34%
3512C, 60 HZ, 1500 - 1750 kW Diesel
(EPA Tier 2 & CARB Emissions Certified (Nonroad); EPA Tier 2 Emissions Certified for Stationary Use)
Caterpillar Sourcewell Member Discounts
Stationary Diesel
#Caterpillar: Confidential Green
(Reference the "PSNA-EPG-F_3512PGFL" Caterpillar Price List)
1500 kW 37%
1750 kW 35%
3516C/3516E, 60 HZ, 2000 - 2750 kW Diesel
(EPA Tier 2 & CARB Emissions Certified (Nonroad); EPA Tier 2 Emissions Certified for Stationary Use)
(Reference the "PSNA-EPG-F_3516PGFL" Caterpillar Price List)
2000 kW 40%
2500 kW 38%
2750 kW 34%
3516C-HD, 60 HZ, 2000 - 2500 kW Diesel (EPA Tier 4)
(Reference the "PSNA-EPG-F_3516PGFL" Caterpillar Price List)
2000 kW 19%
2500 kW 19%
C175-16, 60 HZ, 3000 kW Diesel (EPA Tier 2 for Mobile and Stationary Use)
(Reference the "C175-PGAL" Caterpillar Price List)
3000 kW 30%
C175-16, 60 HZ, 3000 kW Diesel (EPA Tier 4)
(Reference the "C175-PGAL" Caterpillar Price List)
3000 kW 19%
C175-20, 60 HZ, 4000 kW Diesel (EPA Tier 2 for Mobile and Stationary Use)
(Reference the "C175-PGAL" Caterpillar Price List)
4000 kW 24%
50 - 60 kW Caterpillar Natural Gas (Reference the "PSNA-EPG-F_G80PGAM" Caterpillar Price List)
DG50 - 50 kW 31%
DG60 - 60 kW 31%
DG80 - 80 kW 31%
100 - 150 kW Caterpillar Natural Gas (Reference the "PSNA-EPG-F_G150PGAM" Caterpillar Price List)
DG100 - 100 kW 35%
DG125 - 125 kW 35%
DG150 - 150 kW 35%
175 - 300 kW Olympian Natural Gas (Reference the "PSNA-EPG-F_GASOLYGN" Caterpillar Price List)
G175 - 175 kW 26%
G200 - 200 kW 26%
G230 - 230 kW 26%
G250 - 250 kW 26%
G275 - 275 kW 26%
G300 - 300 kW 26%
175 - 300 kW Caterpillar Natural Gas (Reference the "PSNA-EPG-F-G14.2 PGAN" Caterpillar Price List)
DG175 - 175 kW 26%
DG200 - 200 kW 26%
DG230 - 230 kW 26%
DG250 - 250 kW 26%
DG275 - 275 kW 26%
DG300 - 300 kW 26%
300 - 450 kW Caterpillar Natural Gas (Reference the "PSNA-EPG-F-G21.9 PGAN" Caterpillar Price List)
DG350 - 350 kW 26%
DG400 - 400 kW 26%
DG450 - 450 kW 26%
G3412, 60 HZ, 375 - 500 kW Natural Gas
(Reference the "PSNA-EPG-F_G3412PGG" Caterpillar Price List)
375 kW 20%
450 kW 26%
500 kW 26%
G3512 60 HZ, 750 - 1000 kW Natural Gas
(Reference the "PSNA-EPG-F_G3512NL" Caterpillar Price List)
750 kW 17%
1000 kW 17%
G3516 60 HZ, 750 - 1000 kW Natural Gas, Landfill Gas, & Biogas (Ratings Depend on Selection)
(Reference the "PSNA-EPG-F_G3516AEPL" Caterpillar Price List)
All Ratings 17%
G3516C 60 HZ, 1500 kW Natural Gas
Stationary Natural Gas (Select LP Vapor Options with Derates)
#Caterpillar: Confidential Green
(Reference the "PSNA-EPG-F_G3516CTPL" Caterpillar Price List)
1500 kW 17%
G3516H 60 HZ, 1966 kW Natural Gas
(Reference the "PSNA-EPG-F_G3516HNL" Caterpillar Price List)
1966 kW 17%
G3520H 60 HZ, 2469 kW Natural Gas
(Reference the "PSNA-EPG-F_G3520HNL" Caterpillar Price List)
2469 kW 17%
G3520C 60 HZ, 1600 - 2055 kW Natural Gas
(Reference the "PSNA-EPG-F_G3520CPGL" Caterpillar Price List)
1600 kW 17%
2055 kW 17%
CG132, CG170, CG260 (custom)
Due to the customization and plethora of options, it is not feasible to provide a paper price list for these specific generator sets.
Each quote is custom for the specific application.
However, members will receive a 15% discount off of the configured list price from each member’s local dealer.
XQ35, 60 HZ, 35 kVA Prime Diesel (EPA Tier 4 Final & CARB Emissions Certified (Non-road))
(Reference the "PSNA-EPG-F_XQ35BM" Caterpillar Price List)
27 kW Prime Power 23%
30 kW 23%
XQ60, 60 HZ, 59 kVA Prime Diesel (EPA Tier 4 Final & CARB Emissions Certified (Non-road))
(Reference the "PSNA-EPG-F_XQ60BM" Caterpillar Price List)
48 kW Prime Power 23%
XQ125, 60 HZ, 125 kVA Prime Diesel (EPA Tier 4 Final & CARB Emissions Certified (Non-road))
(Reference the "PSNA-EPG-F_XQ125BM" Caterpillar Price List)
100 kW Prime Power 23%
110 kW 23%
XQ230, 60 HZ, 230 kVA Prime Diesel (EPA Tier 4 Final & CARB Emissions Certified (Non-road))
(Reference the "PSNA-EPG-F_XQ230BM" Caterpillar Price List)
200 kW Prime Power 23%
XQ425, 60 HZ, 425 kVA Prime Diesel (EPA Tier 4 Final & CARB Emissions Certified (Non-road))
(Reference the "PSNA-EPG-F_XQ425BM" Caterpillar Price List)
340 kW Prime Power 23%
XQ570, 60 HZ, 570 kVA Prime Diesel (EPA Tier 4 Final & CARB Emissions Certified (Non-road))
(Reference the "PSNA-EPG-F_XQ570BG" Caterpillar Price List)
455 kW Prime Power 23%
Switchgear (customizable)12%
Epic (Reference the "PSNA-EPG-F_CATEPICG" Price List)
Epic - Master Control Panel 10%
Epic - Generator Control Panel 10%
Epic - Utility Control Panel 10%
Supervisory Contol Panel (Reference the "PSNA-EPG-F_CATSCPN" Price List)
EMCP 4.4 SCP 10%
ATS (AUTOMATIC TRANSFER SWITCHES) (Reference the "ATS NJPA Pricing 11-29-17" Price List)
235 ATS's Available 20%
Due to the customization and plethora of options, it is not feasible to provide a paper price list for Cat switchgear.
However, members will receive a 12% discount off of the configured list price from each member’s local dealer.
Mobile Diesel (With Trailers)
Control Panels, Switchgear, Automatic Transfer Switches
15%
#Caterpillar: Confidential Green