STAFF REPORT
Meeting Date: August 19, 2025
Item #: 12
Contact Name: Stephen Krug Department Director: Stephen Krug
Contact Number: Ext. 6002 City Manager: Craig Shadrix
Subject: Approval of Change Order No. 1 for Contracted Sidewalk Repairs with APEC, LLC.
(Public Works Director Krug)
Background Summary:
The City Commission approved $300,000.00 in funding in the current budget to perform contracted sidewalk
repairs and awarded the work to APEC, LLC, at the May 6, 2025, Commission Meeting. The initial
$125,173.33 of work awarded allowed the replacements to begin while Public Works completed tabulating the
list of publicly submitted locations requiring replacement. The list included various areas throughout the City
as documented in the GovPilot work order system, along with the entire length of Sabinal St. and a major
portion of Sparkling Water Circle which replaces approximately 6,200 linear feet of sidewalk. The additional
cost to complete these items is $534,688.01, giving a total cost of $659,861.34 and includes the cost of
securing a payment and performance bond per State Statute for work totaling over $200,000.00. The current
City budget included $300,000.00 for this work and the additional $359,861.34 required is available as
remaining funds in various completed Streets' Division projects as summarized in the Financial Impact. Public
Works recommends approval of the attached budget transfers and change order. Additionally, the Public
Works Team is in the process of completing a digitized GIS sidewalk inventory of the City to determine the
magnitude of contracted replacement required in order for the Team to perform repairs with in-house crews on
an annual basis.
Issue:
Should the Honorable Mayor and City Commissioners approve Change Order No. 1 for contracted sidewalk
repairs with APEC, LLC?
Recommendations:
Staff recommends the Honorable Mayor and City Commissioners approve Change Order No. 1 for contracted
sidewalk repairs with APEC, LLC, utilizing the existing competitively bid City of Kissimmee contract IFB2022-
002, in the amount of $534,688.01, and required budget transfers, and authorize the City Manager and Staff to
approve change orders to this contract up to the limit of his purchasing authority for each change order, and
up to the budgeted amount for this project for all change orders.
Attachments:
1. Change Order No. 1
2. APEC Scope Summary
City of Ocoee ▪ 1 N. Bluford Avenue ▪ Ocoee, Florida 34761
Phone: (407) 905-3100 ▪ www.ocoee.org
Financial Impacts: The cost of this change order is adequately funded in the Streets' Division through the
following remaining available project funds:
A000511 Bucket Truck 24/25 $30,000
P000179 Traffic Calming 20/21 $24,150
P000357 Restriping Citywide 22/23 $25,000
P000394 Restriping Citywide 23/24 $25,000
P000406 Rebuild School Zone Signs
23/24
$4,600
P000407 Spare Signal Cabinet 23/24 $17,000
P000409 Respan Maguire/Story
23/24
$3,900
RR011-25 Respan Clarke/White 24/25 $5,240
RR012-25 Illuminated Street Signs
24/25
$6,100
RR013-25 Contracted Sidewalk
Replacement 24/25
$174,826
RR027-25 Restriping OCPP Round-
About 24/25
$99,119
RR021-25 Silver Bend Repairs 24/25 $120,000
Type of Item: Consent