STAFF REPORT
Meeting Date: April 7, 2026
Item #: 16
Contact Name: T'Jean Tomlinson Department Director: Jen Bolling
Contact Number: Ext. 4301 City Manager: Craig Shadrix
Subject: Approval of Change Order No. 1 for ITB #26-001 Flewelling 2-Inch Water Main
Replacement Project. (Utilities Director Bolling)
Background Summary: The Flewelling 2 Inch Water Main Replacement Project (also known as the
Orange, Jay, and Cardinal Watermain Replacement Project) was approved to address aging infrastructure
and improve water service reliability in the project area. The scope includes
• Installation of a 6-inch ductile iron water main along Jay Street, Cardinal Street, and Orange Avenue,
and
• Relocation of residential water meters from rear yard locations to the front of each property to improve
accessibility and maintenance efficiency.
These improvements will enhance water system reliability, increase system pressure, and provide improved
fire protection for the neighborhood.
Utility staff has worked with the Contractor, Schuller Contractors Incorporated, to make the following changes
to the ongoing project:
1. Installation of twenty-one 2-inch sleeves under the roadway to allow the City to perform future
maintenance or repairs on individual service lines without disturbing the newly paved roadway.
2. Adding plumbing services to the contract to allow the Contractor to install new plumbing from the newly
installed meters to the existing plumbing on each property to streamline the construction schedule.
Change Order No. 1 for plumbing services will require a contract modification allowing the Contractor to
provide the additional construction services, increasing the total project cost by $347,400.69.
Issue:
Should the Honorable Mayor and City Commission approve Change Order No. 1 for ITB #26-001 Flewelling 2-
Inch Water Main Replacement Project for plumbing services in the amount of $347,400.69?
Recommendations:
Staff recommends that the Honorable Mayor and City Commission approve Change Order No. 1 for ITB #26-
001 Flewelling 2-Inch Water Main Replacement Project in the amount of $347,400.69. Staff further
Page 506 of 812
City of Ocoee ▪ 1 N. Bluford Avenue ▪ Ocoee, Florida 34761
Phone: (407) 905-3100 ▪ www.ocoee.org
recommends authorization for the City Manager to approve change orders associated with this contract up to
the limits of his purchasing authority.
Attachments:
1. Change Order No. 1
Financial Impacts:
None, as the City has adequate funding for this change order in Job Number P000284 in the Capital
Improvements Fund (408-533-10-6302).
Type of Item: Consent
Page 507 of 812
Flewelling 2-Inch Water Main
Replacement Project
ITB #26-001
FORM 00842A
CITY OF OCOEE
1 N. Bluford Avenue
Ocoee, Florida 34761
*This Change Order requires action by the City Commission*
Flewelling 2-Inch Water Main
Replacement Project
ITB #26-001
CHANGE ORDER NO. 1
DATE: 3/16/2026 PURCHASE ORDER:1430809
The following changes are hereby made to the CONTRACT DOCUMENTS.
Original CONTRACT PRICE $1,084,134.00
Current CONTRACT PRICE ADJUSTED by previous CHANGE ORDERS $1,084,134.00
Net Increase (Decrease) Resulting from this CHANGE ORDER $347,400.69
The current CONTRACT PRICE including this CHANGE ORDER $1,431,534.69
Original CONTRACT COMPLETION DATE: 12/27/2026
Current CONTRACT COMPLETION DATE adjusted by previous
CHANGE ORDERS
12/27/2026
Net Increase Resulting from this CHANGE ORDER 60 days
Current CONTRACT COMPLETION DATE including this
CHANGE ORDER
02/25/2027
Page 508 of 812
Flewelling 2-Inch Water Main
Replacement Project
ITB #26-001
FORM 00842A
CHANGES ORDERED:
I. REQUIRED CHANGES
1. This change order will cause a net increase to the contract total in the amount of $347,400.69
2. Increase/Decrease in Pay Items to complete the project:
No. 2. Increase to General Requirements, Bonds, and Permits by Two Hundred Twenty-
Four Thousandths of One (1) Lump in the total amount of Eight Thousand Two
Hundred Fifty and 38/100 ($8,250.38) Dollars.
3. Added Pay Items to complete the project:
C01.01 Installation of 2-inch Sleeves by Twenty-One (21) Each in the total amount of
Nine Thousand Two Hundred Sixty-Four and 31/100 ($9,264.31) Dollars.
C01.02 Plumbing Connections by Sixty (60) Each in the total amount of Three Hundred
Twenty-Nine Thousand Eight Hundred Eighty-Six and 00/100 ($329,886.00)
Dollars
II. JUSTIFICATION
No. 2. Increase in the Bonds, Insurance, and other fees associated with the changes
outlined in this Change Order.
C01.01 Cost to cover all the expenses for the installation of Twenty-One 2-inch sleeves
for services in case of damage to ensure the City can effectively perform
maintenance or repairs without damaging the road.
C01.02 Cost to cover all additional costs for plumbing connections for the contractor to
complete plumbing work from the new meter to existing plumbing to the house as
to streamline construction schedule.
III. NARRATIVE OF NEGOTIATIONS
The Contractor has agreed to do the additional work to install 2-inch sleeves under the roadway and
to provide the plumbing connection for each house.
IV. PAYMENT
There is adequate funding for this Change Order in the amount of $347,400.69 in the Capital
Improvements Fund (408-533-10-6302) of Job Number P000284.
Page 509 of 812
Flewelling 2-Inch Water Main
Replacement Project
ITB #26-001
FORM 00842A
V. APPROVAL AND CHANGE AUTHORIZATION
The original project and funding allocation were established by issuance of a CITY purchase
order, subject to the terms and conditions contained in the CITY’s solicitation, Project Manual,
Drawings, Specifications, and/or the CONTRACTOR’s service and price proposal, which
collectively form the terms of an agreement between the CITY and the CONTRACTOR for the
performance of the Work. This proposed change to the agreement requires approval by the City
Commission under the CITY’s Purchasing Rules and Regulations and is consistent with any
prior action by the City Commission to award the Work to the CONTRACTOR. It is expressly
understood and agreed that the approval of the Change Order shall have no effect on the original
agreement other than matters expressly provided herein.
CONTRACTOR acknowledges, by its execution and acceptance of this Change Order, that the
adjustments in contract price and time shown hereon constitute full and complete compensation
and satisfaction for all costs and modifications of performance time incurred by the
CONTRACTOR as a result of this Change Order. No other claim for increased costs of
performance or modifications of time will be granted by the CITY for the Work covered by this
Change Order. The CONTRACTOR hereby waives and releases any further claims for cost or
time against the CITY arising from or relating to the matters or Work set forth or contemplated
by this Change Order.
[Balance of this page was left blank intentionally]
Page 510 of 812
Flewelling 2-Inch Water Main
Replacement Project
ITB #26-001
FORM 00842A
RECOMMENDED BY: ACCEPTED BY:
CITY OF OCOEE, FLORIDA Schuller Contractors Incorporated
By: By:
Signature Signature
Date: Date:
Title: Title:
APPROVED BY:
CITY OF OCOEE, FLORIDA
By: Date:
Rusty Johnson, Mayor
Attest:
Melanie Sibbitt, City Clerk
FOR USE AND RELIANCE ONLY BY THE APPROVED BY THE CITY OF OCOEE
CITY OF OCOEE, APPROVED AS TO FORM COMMISSION IN A MEETING HELD ON
AND LEGALITY THIS DAY OF , 20 UNDER
, 20 AGENDA ITEM NO. .
By:
Richard S. Geller, City Attorney
Page 511 of 812
PROJECT DATA:
NAME: PROJECT NO.: 26-001
LOCATION: DATE: 02/12/26
OWNER:
DESCRIPTION: STATION NO.
PRICING INFORMATION
1. DIRECT LABOR (includes 45% Burden )Labor HOURS RATE COST
Foreman 28 $36.25 $1,015.00
Operator 28 $25.00 $700.00
Laborer 28 $23.00 $644.00
Laborer 28 $23.00 $644.00
Laborer 28 $22.00 $616.00
45% Burden:$1,628.55
Total Subtotal (1) $5,247.55
2. MATERIALS QUANTITY UNIT PRICE COST
$0.00
$0.00
$0.00
$0.00
Subtotal (2)$0.00
3. EQUIPMENT Day
0 $200.00 $0.00
0 $400.00 $0.00
0 $0.00 $0.00
Subtotal (3) $0.00
4. SUBCONTRACTOR Cost
$2,543.10
$559.37
$0.00
SUBTOTAL (4)$3,102.47
5. MISCELLANEOUS COST
$270,000.00
$19,386.00
SUBTOTAL (5)$289,386.00
6. Maintance of Traffic COST
SUBTOTAL (6)$0.00
7. FEE STRUCTURE COST PERCENT FEE
1. Direct Labor: $5,247.55 15.00% $787.13
2. Material $0.00 15.00% $0.00
3. Equipment $0.00 15.00% $0.00
4. Subcontractors $2,543.10 5.00% $127.16
5. Miscellaneous $270,000.00 15.00% $40,500.00
6. Maintenance of Traffic per day $0.00 10.00% $0.00
7. Bond .297% of the total cost $277,790.65 2.97% $8,250.38
8. Insurance 7.18% of total Cost $297,736.02 0.00% $0.00
SUBTOTAL (7) $49,664.67
TOTAL COST OF THIS CHANGE PROPOSAL (All deductions shown in parentheses): TOTAL $347,400.69
Additonal Days = 60
Item - #1 - General Conditions/ bonds = $ 8,250.38
Item - #2 - Installation of 2" sleeves, 21 Each ($9,264.31) cost per each = $441.16
Item - #3 - Plumbing Connections, 60 Each ($329,886.00) cost per each = $5,498.10
Signed:
Title: Date:02/12/26
Contractor:Schuller Contractors Incorporated
Jonathan Jasiewicz
Total Cost
Pull 21 service lines through casings
DESCRIPTION
Description of Work
WA 200
Description of Work
Schuller Contractors Inc.
B&B underground - 2 inch sleeves for services
CHANGE ORDER # 1
Flewelling Avenue
Installation of 2" sleeves for long services and house connections to new watermain
President
PC 55
Insurance
Insurance
Plumbing Connections for each home 60 Homes x $4,500
Flewelling 2-inch watermain replacement
City of Ocoee
Description of Work