HomeMy WebLinkAboutItem #04 Approval of Change Order No. 1 for Pioneer Key Regional Stormwater Pond
AGENDA ITEM COVER SHEET
Contact Name:
Contact Number:
David Wheeler
407-905-3100,
ext. 1504
Meeting Date: March 18, 2008
Item # L/
Reviewed By:
Department Director:
City Manager:
~yt
~~
Subject: Change Order No. 1 with Southern Site Works for the Pioneer Key Regional Stormwater Pond
Project for a No-Cost Time Extension
Background Summary:
This project requires removal of more than 90,000 cubic yards of excess materials. When the contract
for this project was originally executed, the City was to utilize one-half of the excess fill material for
various planned City projects, and the contractor was to dispose of the other half. When the City
subsequently indicated that it had no application for any excess materials, the contractor accepted
responsibility for removal of all materials without a change in contract price. With the subsequent
reduction in construction activity, the volume of material to be removed became greater than what could
be absorbed by the local development community within the original contract time. Accordingly, the
contractor has requested a no-cost construction time extension of 60 days in order to find additional
consumers of the remaining fill material.
Issue:
The Engineering Department has proposed changes to the construction completion date and requests
that the City Commission approve Change Order No. 1 for this project.
Recommendations
The Engineering Department recommends that the City Commission approve Change Order No. 1 for
the additional contract time, with no adjustment to contract cost.
Attachments:
Change Order No. 1 between the City of Ocoee and Southern Site Works for the Pioneer Key Regional
Stormwater Pond project.
Financial Impact:
There is no financial impact resulting from this Change Order.
Type of Item: (please mark with an "x')
Public Hearing
Ordinance First Reading
Ordinance Second Reading
Resolution
_ Commission Approval
Discussion & Direction
For Clerk's DeDt Use:
_ Consent Agenda
_ Public Hearing
_ Regular Agenda
Original Document/Contract Attached for Execution by City Clerk
:= Original Document/Contract Held by Department for Execution
Reviewed by City Attorney
Reviewed by Finance Dept.
Reviewed by ( )
~ BMOdDIW};.;' ~F^ ~
N/A
N/A
N/A
1
SECTION 00842
center of Good L .
~~e ll'ilJe
CITY OF OCOEE
150 North Lakeshore Drive
Ocoee, Florida 34761
CITY OF OCOEE
CHANGE ORDER NO.1
PIONEER KEY REGIONAL STORMW ATER POND PROJECT
DATE: February 26, 2008
CONTRACTOR: Southern Site Works
AGREEMENT DATE: July 17,2007
The following changes are hereby made to the CONTRACT DOCUMENTS.
Original CONTRACT PRICE $794.545.65
Current CONTRACT PRICE ADJUSTED by previous CHANGE ORDER $794.545.65
Net Increase (Decrease) Resulting from this CHANGE ORDER $0.00
The current CONTRACT PRICE including this CHANGE ORDER $794.545.65
Original CONTRACT COMPLETION DATE: April 25. 2008
Current CONTRACT COMPLETION DATE adjusted by previous
CHANGE ORDERS April 25. 2008
Net Increase Resulting from this CHANGE ORDER 60 days
Current CONTRACT COMPLETION DATE including this
CHANGE ORDER June 24. 2008
Pioneer Key Regional Stormwater Pond Change Order #1
00842-1 030105
CHANGES ORDERED:
I. GENERAL
This change order is necessary to cover changes in the work to be performed under this Contract.
The GENERAL CONDITION, SUPPLEMENTARY CONDITIONS, SPECIFICATIONS and
all parts of the Project Manual listed in Article 1, Definitions, of the GENERAL CONDITIONS
apply to and govern all work under this change order.
II. REQUIRED CHANGES
Provide additional time for cost-effective disposal of excess fill materials.
III. JUSTIFICATION
The regional slowdown in construction has reduced the demand for fill materials. This no-cost
time extension allows additional time for material to be removed from the site, with no resulting
damages to the City.
IV. NARRATIVE OF NEGOTIATIONS
Change order is based on mutual agreement by the parties.
V. PAYMENT
Change Order Description Net Increase Unit Unit Price Net Increase
Item No. (Decrease (Decrease) Price
Ouantitv
I Extend 60 days Each $0.00 $0.00
construction
schedule
Total Net Increase (Decrease) Change Order No. 1 $0.00
VI. APPROVAL AND CHANGE AUTHORlZA TION
This proposed change to the Contract is to be approved by the City of Ocoee Commission.
Pioneer Key Regional Stormwater Pond Change Order # 1
00842-2
030105
Acknowledgements:
The aforementioned change, and work affected thereby, is subject to all provisions ofthe original
contract not specifically changed by this Change Order; and,
It is expressly understood and agreed that the approval of the Change Order shall have no effect on
the original contract other than matters expressly provided herein.
CONTRACTOR acknowledges, by its execution and acceptance of this Change Order, that the
adjustments in Contract Price and Time shown hereon constitute full and complete compensation and
satisfaction for all costs and modifications of performance time incurred by the CONTRACTOR as a
result of this Change Order. No other claim for increased costs of performance or modifications of
time will be granted by the OWNER for the Work covered by this Change Order. The
CONTRACTOR hereby waives and releases any further claims for cost or time against the OWNER
arising from or relating to the matters or Work set forth or contemplated by this Change Order.
RECOMMENDED BY:
ACCEPTED BY:
CITY OF OCOEE. FLORIDA
By:
By:
Signature
Signature
Date:
Date:
Title:
Title:
APPROVED BY:
CITY OF OCOEE. FLORIDA
Owner
By:
Date
Attest:
FOR USE AND RELIANCE ONLY BY THE
CITY OF OCOEE, APPROVED AS TO FORM
AND LEGALITY THIS DAY OF
,20_.
APPROVED BY THE CITY OF OCOEE
COMMISSION IN A MEETING HELD ON
, 20_ UNDER
AGENDA ITEM NO.
By:
City Attorney
END OF SECTION
Pioneer Key Regional Stormwater Pond Change Order #1
00842-3
030105