HomeMy WebLinkAboutItem #08 Approval of change Order No. 2 for the Pioneer Key Regional Stormwater Pond Construction Project AGENDA ITEM COVER SHEET Meeting Date: May 20, 2008 Item # ~ ~c.~ Mk'- --. Subject: Change Order No. 2 for the Pioneer Key Regional Stormwater Pond construction project to accommodate the discovery of unsuitable underground materials and to install a drip irrigation system for trees to be planted at the site. Contact Name: David Wheeler 407 -905-3100, ext. 1504 Reviewed By: Department Director: City Manager: Contact Number: Background Summary: Unsuitable underground material was discovered while excavating the southern end of the new stormwater pond in the Pioneer Key area. Project excavation work was halted while geotechnical inspections and re-engineering was completed to respond to the situation. It was ultimately determined that an old excavation existed on the site beneath and to the south of a small pond that was on the site when construction began. Much of the effected area was found to be filled with construction debris buried in the early part of this decade. The area was underlain by a 12-inch root mat. This area included the southern portion of the pond, the inflow channel, and the parking area. No pre-construction geotechnical test sites were located within the area where the unsuitable materials were discovered. The entrained groundwater was drained from the face of the excavation while geotechnical inspections were underway. The ultimate decision by City and project engineers was to fully excavate the affected area, remove the construction debris and other unsuitable materials, and fill the area with suitable material put into place with proper compaction. This work was accomplished by excavating down to the original soil at the location where the unsuitable material was initially discovered and proceeding to the limits of the area to the east, south, and west until all such material was removed. In addition, the southern slope of the pond was adjusted to 4: 1 and an intermediate shelf was constructed to prevent slope face collapse. Acceptable replacement material was acquired from elsewhere on the site The total cost of delay and remediation caused by the unsuitable materials was: $16,860.00 for Delay (Contract Section 00700, Article 12 for Compensable Delay) $14,459.50 for Remediation (cost of soil excavation, relocation, and placement) $31,319.50 Total Actual project time involved = 3 weeks (8 work days idle, 7 work days remediation) Requested change in Contract Time = 2 weeks During the two-week period of delay, work crews were significantly idle while Devo Engineering and PEC investigated the problem and decided on a course of action; however, some useful work did occur, so the actual delay reimbursement requested is only for five full days. The cost of remediation was based on 1 the actual number of hours required for equipment and labor. In addition to reflecting the financial and contract time impacts of the unsuitable materials, the change order includes $2,640.00 for a drip irrigation system that will sustain the trees being planted around the pond. This alternative system will provide direct moisture to the trees without requiring excessive use of the spray irrigation system, which could impact the viability of sod placed on pond slopes if enough water were to be broadcast over the entire site in order to ensure tree survival. Issue: The Engineering Department has proposed a mutually beneficial settlement regarding the issues of irrigation system design and unsuitable underground materials discovered at the Pioneer Key Regional Pond construction site and requests that the City Commission approve the proposed change order. The change order includes an increase of $33,959.50 in Contract Price and an increase of 14 days in Contract Time. Recommendations The Engineering Department recommends that the City Commission approve the proposed change order and authorize the Mayor and City Clerk to execute the required legal documents. To fund the change, staff recommends that the City Commission approve the reallocation of $33,959.50 from remaining funds budgeted for this project. Attachments: Proposed Change Order No.2. Financial Impact: The funding for this action will be financed by the existing allocation for the project. Type of Item: (please ma/1( with an "x'7 Public Hearing Ordinance First Reading Ordinance Second Reading Resolution Commission Approval Discussion & Direction For Cle/1('s Deat Use: _ Consent Agenda _ Public Hearing _ Regular Agenda Original Document/Contract Attached for Execution by City Clerk - Original Document/Contract Held by Department for Execution Reviewed by City Attorney Reviewed by Finance Dept. Reviewed by ( ) JM- N/A N/A N/A 2 SECTION 00842 center of Good L . ~~e It'j~ CITY OF OCOEE 150 North Lakeshore Drive Ocoee, Florida 34761 CITY OF OCOEE CHANGE ORDER NO.2 PIONEER KEY REGIONAL STORMW ATER POND PROJECT DATE: May 20, 2008 CONTRACTOR: Southern Site Works AGREEMENT DATE: July 17,2007 The following changes are hereby made to the CONTRACT DOCUMENTS. Original CONTRACT PRICE $794.545.65 Current CONTRACT PRICE ADJUSTED by previous CHANGE ORDER $794.545.65 Net Increase (Decrease) Resulting from this CHANGE ORDER $33.959.50 The current CONTRACT PRICE including this CHANGE ORDER $828.505.15 Original CONTRACT COMPLETION DATE: April 25. 2008 Current CONTRACT COMPLETION DATE adjusted by previous CHANGE ORDERS June 24. 2008 Net Increase Resulting from this CHANGE ORDER 14 days Current CONTRACT COMPLETION DATE including this CHANGE ORDER Julv 10. 2008 Pioneer Key Regional Stormwater Pond Change Order #2 00842-1 030105 CHANGES ORDERED: I. GENERAL This change order is necessary to cover changes in the work to be performed under this Contract. The GENERAL CONDITION, SUPPLEMENTARY CONDITIONS, SPECIFICATIONS and all parts of the Project Manual listed in Article 1, Definitions, of the GENERAL CONDITIONS apply to and govern all work under this change order. II. REQUIRED CHANGES Provide additional Contract Price and Time for delay associated with unsuitable materials discovered at the site and subsequent remediation of the problem. III. JUSTIFICATION Unsuitable materials were discovered in the southern area of the project site near the end of pond excavation. Project delay was experienced as geotechnical investigations were conducted and design engineers decided on a course of action. The ultimate decision was to fully excavate all unsuitable material and to replace it with acceptable materials. IV. NARRATIVE OF NEGOTIATIONS Change order is based on mutual agreement by the parties. V. PAYMENT Change Order Description Net Increase Unit Unit Price Net Increase Item No. (Decrease (Decrease) Price Ouantity I Extend 14 Day $0.00 $0.00 construction time 2 Tracked Backhoe 42.0 Hour $85.00 $3,570.00 3 Front-end Loader 41.5 Hour $62.50 $2,593.75 4 Bulldozer 43.0 Hour $72.50 $3,117.50 5 Off-road Dump 10.5 Hour $65.50 $687.75 Truck 6 Vibratory Roller 13.0 Hour $38.50 $500.50 7 Labor 14.0 Hour $27.50 $385.00 8 On-site Supervisor 51.5 Hour $70.00 $3,605.00 9 Delay Day 5.0 Day $3,372.00 $16,860.00 10 Drip Irrigation 1 Lump Sum $2,640.00 $2,640.00 System Total Net Increase (Decrease) Change Order No.2 $33,959.50 VI. APPROVAL AND CHANGE AUTHORIZATION This proposed change to the Contract is to be approved by the City of Ocoee Commission. Pioneer Key Regional Stormwater Pond Change Order #2 00842-2 030105 The aforementioned change, and work affected thereby, is subject to all provisions of the original contract not specifically changed by this Change Order; and, It is expressly understood and agreed that the approval of the Change Order shall have no effect on the original contract other than matters expressly provided herein. CONTRACTOR acknowledges, by its execution and acceptance of this Change Order, that the adjustments in Contract Price and Time shown hereon constitute full and complete compensation and satisfaction for all costs and modifications of performance time incurred by the CONTRACTOR as a result of this Change Order. No other claim for increased costs of performance or modifications of time will be granted by the OWNER for the Work covered by this Change Order. The CONTRACTOR hereby waives and releases any further claims for cost or time against the OWNER arising from or relating to the matters or Work set forth or contemplated by this Change Order. RECOMMENDED BY: ACCEPTED BY: CITY OF OCOEE. FLORIDA By: By: Signature Signature Date: Date: Title: Title: APPROVED BY: CITY OF OCOEE. FLORIDA Owner By: Date Attest: FOR USE AND RELIANCE ONLY BY THE CITY OF OCOEE, APPROVED AS TO FORM AND LEGALITY THIS DAY OF ,2008. APPROVED BY THE CITY OF OCOEE COMMISSION IN A MEETING HELD ON , 2008 UNDER AGENDA ITEM NO. By: City Attorney END OF SECTION Pioneer Key Regional Stormwater Pond Change Order #2 00842-3 030105