HomeMy WebLinkAboutItem #04 Approval of Change Order No. 3 for Phase 2 of Lakeshore Drive Improvement Project
I
center of Goocl L .
'\.~e . .. . J~~
~
AGENDA ITEM COVER SHEET
Meeting Date: December 2, 2008
Item#~
Reviewed By: /~
Department Director. ~ .~_ IJ./.JrJ!xdllr
City Manager: V
----...,
Subject: Approval of and authorization for the Mayor to execute Change Order No.3 for Phase 2 of the
Lakeshore Dr. Improvements Project to provide for adjustment of final quantities, and to authorize the
funds required to implement the change order.
Contact Name:
Contact Number:
David Wheeler
407-905-3100, ext. 1504
Background Summary:
As is normal City practice, the construction contract for improving Lakeshore Drive and adjacent Bill
Breeze Park is of the unit-price form. This means that a change order is expected at the end of the
project to reconcile the bid quantities with the installed quantities. This Agenda Item presents the
closeout change order for the project. There were increases in curbing, sidewalk, trees, shrubbery, and
sod above the bid quantities, and several items were added to the project to accommodate new
requirements, such as St. Augustine sod, a drip irrigation system for the new trees, and temporary
Founders' Day vendor electrical connections. Foundations and footers are also being provided for
lighted bollards lining the new shoreline sidewalk and the three new picnic shelters.
Issue:
The Engineering Department has proposed a change order to implement the project modifications
identified in cooperation with the Parks & Recreation Department and to reconcile installed and contract
quantities. All involved City departments have reviewed the proposed prices for new bid items and
believe them to be reasonable and comparable; other prices were established in the contract bid or
previous change order.
Recommendations
The Engineering Department recommends that the City Commission approve the proposed Change
Order No.3, authorize the Mayor and City Clerk to execute the required legal documents, and direct the
Finance Department to make the related fund allocations to the project budget and revise the purchase
order issued to the Contractor to reflect the increase in project budget.
Attachments:
Proposed Change Order NO.3.
Financial Impact:
The $41,944.25 in funding for this action will be derived from previously budgeted funds for the project.
1
Type of Item: (please mark with an 'x"
Public Hearing
_ Ordinance First Reading
_ Ordinance Second Reading
Resolution
_ Commission Approval
Discussion & Direction
For Clerk's Deat Use:
_ Consent Agenda
_ Public Hearing
_ Regular Agenda
~ Original Document/Contract Attached for Execution by City Clerk
_ Original Document/Contract Held by Department for Execution
Reviewed by City Attorney
Reviewed by Finance Dept.
Reviewed by ( )
~/l{f-
N/A
N/A
N/A
2
CITY OF OCOEE
150 North Lakeshore Drive
Ocoee, Florida 34761
CITY OF OCOEE
CHANGE ORDER NO.3
LAKE SHORE DRIVE IMPROVEMENTS - PHASE II
DATE: November 13,2008
CONTRACTOR: American Persian Engineers & Constructors, Inc. (APEC)
NOTICE TO PROCEED DATE: February 11,2008
The following changes are hereby made to the CONTRACT DOCUMENTS.
Original CONTRACT PRICE $599.517.00
Current CONTRACT PRICE ADJUSTED by previous CHANGE ORDER $851.349.61
Net Increase (Decrease) Resulting from this CHANGE ORDER $41.944.25
The current CONTRACT PRICE including this CHANGE ORDER $893.293.86
Original CONTRACT COMPLETION DATE: October 11. 2008
Current CONTRACT COMPLETION DATE adjusted by previous
CHANGE ORDERS
November 21.2008
Net Increase Resulting from this CHANGE ORDER
56 days
Current CONTRACT COMPLETION DATE including this
CHANGE ORDER
J anuarv 16. 2009
CHANGES ORDERED:
I. GENERAL
This change order is necessary to cover changes in the work to be performed under this Contract.
The GENERAL CONDITION, SUPPLEMENTARY CONDITIONS, SPECIFICATIONS and all
parts of the Project Manual listed in Article 1, Definitions, of the GENERAL CONDITIONS apply to
and govern all work under this change order.
II. REQUIRED CHANGES
The project was expanded through a series of field orders to provide additional improvements within
the project area. Several of these improvements were to accommodate Founder's Day needs for the
Lakeshore Drive parking area, the location of trees, increased sod coverage, and temporary electrical
service for vendors. This change order closes out the project by reconciling contract and installed
quantities.
III. JUSTIFICATION
In the course of planning the work with the Contractor, City Engineering staff identified several cost-
effective enhancements to the project. City staff and elected officials involved in Founders' Day
preparations also required certain changes to conduct that special event and to prepare for future
events of that nature.
IV. NARRATIVE OF NEGOTIATIONS
Change order is based on mutual agreement by the parties or contract unit prices. Negotiated prices
apply only to those items not included in the original bid list.
V. PAYMENT
Quantity
Change Order Increase Price Increase
Item No. Description (Decrease) Unit Unit Price (Decrease)
Expand picnic
I shelter slabs; add 3 Each $1,431.00 $5,724.00
post footers
2 Install concrete 8 Each $75.00 $600.00
bollard footers
3 Furnish & install I Each $1,800.00 $1,800.00
irrigation system
4 Ribbon curb 386 Linear Foot $18.00 $6,948.00
5 Type-D curb 95 Linear Foot $16.00 $480.00
Furnish & install
6 porous concrete 112 Square Yard $36.00 $4,032.00
pavers
7 6" wire-reinforced 14 Square Yard $42.00 $588.00
concrete
APEC Change Order #3
2
Quantity
Change Order Increase Price Increase
Item No. Description (Decrease) Unit Unit Price (Decrease)
8 Furnish & install 2 Each $500.00 $1,000.00
yard drain
9 3 gal. shrub 21 Each $10.56 $221.76
10 Furnish & install I Each $467.97 $467.97
65 l!:al. tabebuia
Furnish & install
II parking area I Lump Sum $550.00 $550.00
gravel
Furnish & install
12 decorative sign on 4 Each $1,126.63 $4,506.52
cast-metal post
13 Furnish & install 1,333 Square Yard $3.00 $3,999.00
Bahia sod
14 Furnish & install 2,164 Square Yard $4.00 $8,656.00
St. Augustine sod
15 Relocate tree 3 Each $100.00 $300.00
Furnish & install
16 additional I Lump Sum $2,068.00 $2,068.00
electrical services
Total Net Increase (Decrease) Change Order No.3 $41,944.25
VI. APPROVAL AND CHANGE AUTHORIZATION
This proposed change to the Contract is to be approved by the City of Ocoee Commission.
The aforementioned changes, and work affected thereby, are subject to all provisions of the original
contract not specifically changed by this Change Order; and,
It is expressly understood and agreed that the approval of the Change Order shall have no effect on
the original contract other than matters expressly provided herein.
CONTRACTOR acknowledges, by its execution and acceptance ofthis Change Order, that the
adjustments in Contract Price and Time shown hereon constitute full and complete compensation and
satisfaction for all costs and modifications of performance time incurred by the CONTRACTOR as a
result of this Change Order. No other claim for increased costs of performance or modifications of
time will be granted by the OWNER for the Work covered by this Change Order. The
CONTRACTOR hereby waives and releases any further claims for cost or time against the OWNER
arising from or relating to the matters or Work set forth or contemplated by this Change Order.
(The rest of this page is intentionally blank)
APEC Change Order #3
3
RECOMMENDED BY:
ACCEPTED BY:
CITY OF OCOEE. FLORIDA
AMERICAN PERSIAN ENGINEERS &
CONSTRUCTORS. INC.
By: ~ /Jdi::
Signature
Date: ;t/;vemw. ~ 2..008
Title: elf M~n~9e,,-
APPROVED BY:
CITY OF OCOEE. FLORIDA
Owner
By:
Signature
Date:
Title:
By:
Date
Attest:
FOR USE AND RELIANCE ONLY BY THE
CITY OF OCOEE, APPROVED AS TO FORM
AND LEGALITY THIS DAY OF
,2008.
APPROVED BY THE CITY OF OCOEE
COMMISSION IN A MEETING HELD ON
, 2008 UNDER
AGENDA ITEM NO.
By:
City Attorney
END OF CHANGE ORDER
APEC Change Order #3
4