AGENDA ITEM COVER SHEET
Meeting Date: February 3, 2009
Item # 3,
Contact Name:
Contact Number:
Stephen C. Krug
6002
Reviewed By:
Department Director:
City Manager:
~(
. .~
Subject: Pioneer Key Regional Stormwater Pond Post Design Services and Performance
Efficiency Evaluation with PEe I Professional Engineering Consultants, Inc.
Background Summary:
In the last fiscal year, the City completed the construction of the Pioneer Key Regional Stormwater
project as a regional wet detention pond to provide retrofit water quality treatment and flood attenuation.
This facility will provide treatment for the Pioneer Key mobile home communities as well as other
developed and undeveloped areas along the Northwest Ditch 123-acre drainage basin in the City prior to
discharge into Lake Apopka.
The Department of Environmental Protection grant that funded the project construction also includes a
monitoring phase to determine the effectiveness of the facility in reducing pollutant loadings that
ultimately discharge into Lake Apopka. The scope of this phase requires the installation of hydrologic
and water quality monitoring equipment that will collect data along with water sampling over a 6 month
period. At the end of the monitoring period, a complete hydrologic and pollutant budget will be
developed for the facility, and the overall performance efficiency of the system will be calculated for the
evaluated parameters described in the attached scope of services.
Issue:
Request the City Commission direct staff to proceed with the monitoring phase of the Pioneer Key
Regional Stormwater Facility Performance Efficiency Evaluation.
Recommendations
Recommend awarding the Pioneer Key Regional Stormwater Facility Performance Efficiency Evaluation
to PEC for a not to exceed amount of $99,957.02.
Attachments:
PEC Scope of Services.
Financial Impact:
This project is adequately funded in Stormwater and through grants.
Type of Item: (please mark with an "x')
Public Hearing
Ordinance First Reading
Ordinance Second Reading
Resolution
x Commission Approval
Discussion & Direction
For Clerk's Deot Use:
Consent Agenda
_ Public Hearing
Regular Agenda
Original Document/Contract Attached for Execution by City Clerk
Original Document/Contract Held by Department for Execution
Reviewed by City Attorney
Reviewed by Finance Dept.
Reviewed by ( )
~/5;+-
N/A
N/A
N/A
2
PEe
PROFESSIONAL ENGINEERING CONSUL TANTS, INC.
January 26, 2009
P-8128
Mr. Stephen C. Krug, P.E.
Public Works Director
City of Ocoee
301 Maguire Road
Ocoee, Florida 34761
Re: Pioneer Key Regional Stormwater Pond
Contract No. 0404
Subj: Post-Design Services and Performance Efficiency Evaluation
Dear Steve:
Per your request, please find enclosed two (2) revised copies of the following documents for your
review and approval associated with the above-referenced project:
. Scope of Work (Exhibit "A"); and
. Manhour and Fee Estimate (Exhibit "B").
We look forward to the opportunity to continue serving the City ofOcoee on this assignment. If you
have any questions regarding the enclosed documents, please contact me directly at 407-422-8062,
extension 194, or bye-mail atdwh@peconline.com.
Very truly yours,
ONSUL T ANTS, INC.
Da . mstra, P.E.
Ice President I Stormwater Department Manager
DWHlpv
Enclosures
cc:
David Wheeler, City ofOcoee (wi enclosures)
Harvey Harper, ERD (wi enclosures)
Devo Seereeram, Devo Engineering (wi enclosures)
Mike Bruegger, PEC (wi enclosures)
PEC Project File OE-416 (1-1.0)
engmeers
planners
surveyors
"Engineering Our Community"
200 East Robinson Street. Suite 1560. Orlando, Florida 32801 · 407/422-8062. FAX 407/849-9401
Pioneer Key Regional
Stormwater Pond Post-Design Services
and Performance Efficiency Evaluation
Exhibit "A"
Scope of Work
EXHIBIT" A"
SCOPE OF WORK
for
PIONEER KEY REGIONAL STORMW ATER POND
POST -DESIGN SERVICES AND PERFORMANCE EFFICIENCY EV ALVA TION
OBJECTIVE:
The City of Ocoee, Public Works Department, has requested that Professional Engineering
Consultants, Inc. (PEC) prepare a scope of work and fee estimate under Contract No. 0404 to
provide post-design services and for Environmental Research and Design, Inc. (ERD) to conduct a
performance efficiency evaluation associated with the Pioneer Key regional stormwater pond
improvements.
PROFESSIONAL ENGINEERING SERVICES:
Professional Engineering Consultants, Inc. (Consultant) shall provide the following post-design
services enumerated below:
1. Prepare for and attend the pre-construction meeting with the City of Ocoee.
2. Review and process shop drawings.
3. Coordinate with City staff and Devo Engineering to resolve the unsuitable materials located
at the south end of the pond / north end of the parking lot.
4. Coordinate and/or conduct meetings with the City ofOcoee to discuss the construction plan
modifications (e.g., diversion weir).
5. Conduct a "Final" inspection and compare completion of "Punch List" to the items identified
in the substantial completion review.
6. Prepare a set of record drawings based upon as-built construction plans provided by Southern
Site Works (Alan Peckham).
7. Prepare and submit an as-built certification form to the SJRWMD.
8. Coordinate with ERD during the course of the 12-month performance efficiency evaluation.
9. Coordinate with City staff and Florida Department of Environmental Protection (FDEP) to
implement the required public education signage and educational kiosks.
A- I
P-8128.sco
Pioneer Key Regional
Stormwater Pond Post-Design Services
and Performance Efficiency Evaluation
Exhibit "B"
Manhour and Fee Estimate
:!!
n
~
()
tJ
~
,.
'"
~
~
~
~
;ll
o
..
o
~
."
"
~
"
~
o-l
"
!.
t"'
c
a
."
'"
C
a
..,
~
~~~~ ~
~ ~ ~ [ ~
[fmi ~
f,l=']~ ~
~~~~ i
~ 8" <g: "" ;;J
E. ~ ~ ~ ~
! i ]. ~ 8~
~ ti1.rt
Cl E: 8
g' ~ ~. ~~
'!S. J"
f: ~
;J. ~
"
e
" ...; ...;
moo
Pi ...; ...;
~f:f:
...; r :r:
to ~ ~
r:;~G;
~ 8
~~
C'
IJ:
&.
18'8'il'ilg8'8Wl
a e, e, ] ] g- e, e. ~. ~
~ ~ ~ ~ ~ ; s ~ ~ ~
3 {Jo.~ ,.1lIr1lo.'"1
~ ~ ~ ~ a [ ~ ~ l [
. ~ m Ii' ~ ~ ~ >
g ~ ~ ~ ~. ~ ~ Q !f I
!!I :r: ,. '\)I li " .or '" ~
0. ~ ~ ~ A I I n
"'nto~"3: .,,1
~ ; ~ ~ [ ~ ~ i ~
~ ~ ~ ~ [~ ~ ~. ~
a 0. p. ~ 3 !i. '!S. '\)I ~
~ ! ~ , g ~n ~ !!Io. ~
"... ::l 0 tI1 - ~ ::I
~"""5 21'''[3:
;~6' ","" Eta
i I ~ g I i a ~
rra.o~ oa~OQ
~ ~ !f 0 e, ~. -
~~~g ~~
~~~i ~~
~. Sl. 6 ~ g.
~ ~ G. n
I ~ g ~
1:d: ~ ~.
~ o' ~ t:i"
1;; " 8-
;;
;
~
ti1
~
g ~. ~
[ W ~
if ~ W
~]~
~ J7~ ~r
j
...
w ~:C3:f
'" .
'" '" ~ ... 0 0 '" cl 3 ~
. -J '" ... '" co - 0
w '"
;,"..
. 0 8 i !l ~
'"
iZ ~~ 3: [f
w'
'" '" w '" co co '" 2 i 1
. '" '" ... '" '" '" '" '"
'" '" 0 ~gg
~ 8 8 n II
.:2,
...
~~ ~Clmil'
~ ~ N '" N '" '" '" '" '" '" '" 0 ~ [~. ~
'" 8eall
~ ... ... ~ iZ ... ... ~P ~ ...
w i '"
co W '" co '" '"
"" ... ~ v, 8 8 8 -J '" 8 n ....
:g ... ~ 00 '" ~ '" ~ 00 " IJ:
... w '" 8 '" 8 8 8 '" 8 Of
'" '" '" '-" 8 8 8 8 8 8 "'"
':'] co ~ '" 00
'" '" '"
.. 8 0 8 8
.... ....
II II II If II
g
i
n
!
III
i. ."
t~
III
01
om"
fI o;j 0
C ::Jcg.ct
:( ~~ ~
~ alii 0'
o :;] 5':;]
OJ i:it(O 9...
":l
15
~~
of:i
"'l><
8 ~ ~
Fl ~ go M
S ~ ~ ~
s ~ r::;
~ ":l M l:l:l
nO"
g ~ i'
e b ~
~ t'j ft
- '"
~qi
fZ
i;f'J
~ill:l
;:::i
n
M
rn
...
'" .w ... ~ i g
w'" w
'" 8 '" '" N '" '" ;;; '" '" .... '" '" :3 8' -.
;,".. 8!~ g'
. '"
'"
... ... ~ W
... '"
:,. 8 ;:; '" '" '" - '" '" '" - '" '" ~ ~ :e
~ 8 8 16 ~
f ~
...
8~ ~ '" w co w '" '" ... :;:; '" '" :r: ...; t
. 00 ... '" ~ IJ:
~ ~ "'"
'"
DEVO SEEREERAM, Ph.D., P.E.
CONSULTING GEOTECHNICAL ENGINEER
5500 ALHAMBRA DRIVE
ORLANDO, FLORIDA 32808-7004
. .. .
, Date................... April 28, 2008 !Invoice No. .. .. . .. . . .. MAR08G.55 I Project No. . .. .. .. .. .. 05-121.168 I
To:
Professional Engineering Consultants, Inc.
Stormwater Management Department
200 East Robinson Street, Suite 1560
Orlando, FL 32801
Phone: 407-422-8062 Fax: 407-849-9401
attention: DAvid HAMSTRA, P.E.
Ref:
MISCELLANEOUS GEOTECHNICAL ENGINEERING SERVICES
Pioneer Key Regional Drainage Improvements; City of Ocoee, Florida
.......................................
. .
. .
Services performed for the calendar month: 1...~~.~~.~....~?~.~...1
AMOUNT DUE THIS INVOICE: $1,180.00
PER ATTACHED ITEMIZATION
TERMS: NET 30 DAYS
PLEASE EMAIL ClAUO.l.(WDEVOENG.COMIF THERE ARE ANY QUESTIONS REGARDING THIS INVOICE.
THANK YOU.
FEE ITEMIZATION
billing period: Mar-DB I
name of project PiONHR KEy DR4iuGE IMpROVEMENTS
INVOICE #: MAROBG.55
TABLE 1. ENGINEERING & TECHNICAL SERVICES
Hours Hourly
..._.._~::!:~?;y------ Name Title Worked Rate Amoun
Z Devo Seereeram, Ph.D., P.E. (in office) I 0.00 $100.00 : $0.00
0 I I I
1-;::: Devo Seereeram, Ph.D., P.E. (out of office but in Orlando Metro) 0.00 $120.00 $0.00
...<
~~ DelIO Seereeram, Ph.D., P.E. (out of office - outside Oriando Metro) I 0.00 I $140.00 i $0.00
!:IS.... DelIO Seereeram, Ph.D., P.E. (out-of-court expert witness time) I 0.00 I $150.00 I $0.00
Z
0 I I I
U Devo Seereeram, Ph.D., P.E. (on the stand expert witness time) 0.00 $165.00 $0.00
I I
--'-"--'--'--'--'---' ! Principal Engineer I
Devo Seereeram, Ph.D., P.E. I 0.00 $95.00 I $0.00
David Kincaid, B.Se., P.G. I Senior Hydrogeologist I 0.00 $90.00 I $0.00
Robin Persad, B.Se. I Senior Project Manager I 3.00 I $90.00 $270.00
I
.... .... Robert Casper, M. Eng., E.!. :Lead Ground Water ModelerjEngineer 0.00 I $90.00 $0.00
... t;
w I Senior Project Manager I I
w G Vijay Boodhoo, B.Se. 0.00 $90.00 $0.00
ZallO
G .. Senior Drainage Engineer Senior Drainage Engineer 0.00 I $100.00 I $0.00
0
Z w
w .., Doug Hearn, P.G. :Senlor Consultant Reviewer (P.G.) I 0.00 $125.00 I $0.00
Richard McCormick, P.G. Associate Consultant (P.G.) 0.00 I $125.00 $0.00
Steve Berry, P.E. ISenior Consultant Reviewer (P.E.) 0.00 I $125.00 , $0.00
Carl Henriksen, P.E. I Senior Consultant Reviewer (p.E.) I 0.00 I $125.00 I $0.00
---"-'- ISenior-level CADDjGIS I I
.... Ahmed Zaghloul, B.Se. 0.00 I $65.00 $0.00
.... I
:: .... Samar Mady, B.Se. Senior-level CADDjGIS 0.00 I $65.00 I SO.OO
__all-
e ..,
... Sasy Zaghloul, B.Se. I Mid-level CADDjGIS I 0.00 I $50.00 I $0.00
-2-.._.._......
Charmaine Saith, B.Se. IAdministrative Principal I 0.00 I $45.00 I SO.OO
I
W Kasey Chenea Senior Technical Assistant I 0.00 I $35.00 I $0.00
>
;::: .. I Senior Technical Assistant I I I
< Claudia Callahan, B.Sc. 0.00 $35.00 $0.00
"" <
I- U ! Senior Technical Assistant I I
~1l/5= Carla Medford, B.Se. 0.00 $35.00 I $0.00
_ w
:z: .. Bibi Centko JuniorTechnical Assistant I 0.00 I $32.50 I $0.00
i: U
c Usa Khan !JuniorTechnical Assistant I 0.00 $32.50 I $0.00
...
Anushka Seereeram JuniorTechnical Assistant I 0.00 $30.00 I $0.00
--.--...-----.-.--..-- I Senior field technician
HenryTowns 0.00 S65.00 I $0.00
=.... Brian Van Hoose Senior field technician 0.00 $65.00 I SO.OO
S~ Premchan Su~an Senior field technician I 14.00 $65.00 I $910.00
all!:
CZ Davis Galbraith I Senior field technician 0.00 I S65.00 I SO.OO
..=
wU
- w Ravi Premchand Juniorfield technician I 0.00 I $50.00 $0.00
"'I-
Geshan Premchand Juniorfield technician I 0.00 S50.00 I $0.00
SUBTOTAL FOR ENGINEERING & TECH SERVICES (TABLE 1.1 ABOVE)................................................................................................. $1,lBO.OO
SUBTOTAL FOR REPORT PRINTING & COURIER EXPENSES (SEETABLE 1.2, SEPARATE PAGE)............................................................. $0.00
SUBTOTAL FOR EXPENSES (SEE TABLE 1.3, SEPARATE PAGE)............................................................................................................. $0.00
SUBTOTAL FOR RELD GEOTECHNICAL INVESTIGATION (SEETABLE 1.4A, SEPARATE PAGE)................................................................. SO.OO
SUBTOTAL FOR RELD ENVIRONMENTAL INVESTIGATION (SEETABLE 1.4B, SEPARATE PAGE).............................................................. SO.OO
SUBTOTAL FOR GEOTECH LAB ORATORY TESTING (SEETABLE 1.5A, SEPARATE PAGE)......................................................................... $0.00
SUBTOTAL FOR ENVIRONMENTAL LABORATORY TESTIN G (SEE TABLE 1.5B, SEPARATE PAGE)............................................................. so.oo
GRAND TOTAL............ .............. ... ... ... ..................... ............ ... ....... ........... ....... ..... $1,180.00
L
PIONEER KEY REGIONAL STORMWATER FACILITY
PERFORMANCE EFFICIENCY EV ALUA TION
EXHIBIT A: SCOPE OF SERVICES
Prepared By
Environmental Research & Design, Inc.
Revised January 26, 2009
Proiect Backeround
The Pioneer Key regional stormwater project was constructed as a regional wet detention pond to
provide retrofit water quality treatment and flood attenuation. This facility will provide
treatment for the Pioneer Key I and Pioneer Key II mobile home communities as well as other
developed and undeveloped areas along the Northwest Ditch (I23-acre drainage basin) in the
City of Ocoee prior to discharge into Lake Apopka. Design criteria for the stormwater facility
are summarized below (PEC, 2007):
PARAMETER INFORMATION
Treatment System Tvoe Wet detention pond
Pond Area 3.07 acres at NWL
Drainage Basin Area 123.44 acres
Drainage Basin Land Use Mobile home parks, commercial, highways
Basin Impervious Area --
Treatment Volume 0.47-inch over basin area
Permanent Pool Volume 24.14
Pond Depth
a. Maximum a. 12 ft
b. Mean b. 7.9 ft
Treatment Volume Recoverv 50% in 24-30 hours
Pond Residence Time 16.6 days (mean annual)
Littoral Zone --
Introduction
This document outlines work efforts to be performed by Environmental Research & Design, Inc.
(ERD) for Professional Engineering Consultants (PEC) and the City ofOcoee (City) to conduct a
performance efficiency evaluation of the Pioneer Key Regional Stormwater Facility. This
facility has been recently constructed by the City to reduce pollutant loadings discharging
through the Northwest Ditch into Lake Apopka. Hydrologic and water quality monitoring
equipment will be installed at this site by ERD, and field monitoring will be conducted over a
period of 6 months to evaluate system efficiencies. Collection of field data and water quality
samples will be conducted on a weekly basis. At the end of the 6-month monitoring program, a
complete hydrologic and pollutant budget will be developed for the facility, and the overall
performance efficiency of the system will be calculated for the evaluated parameters. Draft and
Final Reports will be prepared and submitted to the City.
PEC\PIONEER KEY REGIONAL STORMWATER FACILITY. NOV08-PAGE I
Scooe of Services
ERD proposes to perform the specific work efforts outlined below to conduct the performance
efficiency evaluation for the Pioneer Key Regional Storm water Facility. Details of specific work
efforts proposed for this project are summarized below.
I. Proiect Kick-off MeetimuSite Visit: The ERD Project Director will perform a project
kick-off meeting with representatives of PEC and the City to discuss details of the
proposed work efforts to be performed; project schedule; contact personnel for ERD,
PEe, and the City; contract management details; and issues related to site access and
security. A site visit will be conducted to discuss proposed field activities and identify
specific monitoring locations. It is the responsibility of the City to obtain any necessary
permits or authorizations for use of the site for the proposed monitoring activities.
2. Preoare/Submit Proiect OA Plan: Development of a detailed Project QA Plan is a
requirement for all projects receiving Section 319 funding. This plan provides a
description of the proposed field and laboratory activities and outlines specific Quality
Assurance procedures for all anticipated field and laboratory activities. This plan will be
prepared by ERD prior to initiation of the field monitoring activities and submitted to
FDEP for review and approval.
3. SelectlInstalllCalibrate Field Monitorin!!: EQuioment: ERD will evaluate the proposed
monitoring site and appropriate field monitoring equipment will be selected to perform
the performance efficiency evaluation. It is anticipated that flow monitoring and sample
collection activities will occur at four separate sites at the Pioneer Key facility as follows.
Locations of the monitoring sites are indicated on the attached figure.
a. Site I: inflow channel from the Northwest Ditch into the pond
b. Site 2: the 42-inch RCP entering the southeast comer of the pond
c. Site 3: located in the lO-inch HOPE for the pond bleed-down system
d. Site 4: located in the Northwest Ditch downstream from the pond
Sensitive digital water level recorders will also be installed within the pond to assist in
development of a hydrologic budget and to allow quantification of the magnitude of
discharges through the Northwest Canal which bypass the pond system. A digital rainfall
gauge will also be installed at the site along with a pan evaporation station. The
autosamplers and flow monitoring equipment will be housed inside aluminum equipment
shelters for security. After installation, each of the components will be calibrated
according to manufacturer's instructions prior to initiation of the monitoring program.
PEC\PIONEER KEY REGIONAL STORMWATER FACILITY. NOVOS-PAGE 2
4. Perform Routine Monitorin!!: ERD field personnel will visit the site once each week to
retrieve stored hydrologic data and collect composite inflow and outflow samples. The
operation of all on-site equipment will be evaluated during each visit. Activities
performed at the site will be recorded on field notes. The monitoring program will last
for a period of 6 months, with a minimum of 26 weekly monitoring visits conducted
during this study.
Continuous flow-weighted composite samples will be collected at each of the four
monitoring locations. Each of the composite inflow, outflow, and runoff samples will be
returned to the ERD Laboratory and analyzed for the following parameters:
a. pH g. Total Nitrogen
b. Alkalinity h. SRP
c. Conductivity 1. Particulate Phosphorus
d. NH3 J. Total Phosphorus
e. NOx k. Turbidity
f. Particulate Nitrogen 1. TSS
m. Color
For budget purposes, it is assumed that an average of 6 samples per month will be
collected at each of the four sites, for a total of 144 stormwater/baseflow samples
collected during this project (6 samples/month/site x 6 months x 4 sites).
In addition, a bulk precipitation collector will be installed adjacent to the pond, and wet!
dry fallout bulk precipitation will be collected on a continuous basis. For budget
purposes, it is assumed that approximately 3 composite bulk precipitation samples will be
collected each month, for a total of 18 samples during this project (3 samples/month x 6
months).
5. RoutinelFinal Data Comoilation: All data retrieved during the weekly site visits will
be compiled into a common database on a continuing basis. The weekly field data will
be reviewed and evaluated with respect to accuracy and precision of the data. At the end
of the monitoring program, all of the compiled data will be summarized in both tabular
and graphic formats for use in the Final Report.
6. Preoare Draft Final Reoort: A Draft Final Report will be prepared by ERD which
summarizes all field and laboratory activities and provides an analysis of the performance
efficiency of the system. Two copies of the Draft Final Report will be provided to the
City for review and comments.
7. Attend Review Meetin!! with City: The ERD Project Director will attend a review
meeting with the City to discuss comments on the Draft Final Report.
8. Preoare Final Reoort: A Final Report will be prepared for this project which
incorporates the review comments provided by the City. Two hard copies and one digital
copy of the Final Report will be provided to the City.
PEC\PIONEER KEY REGIONAL STORMWATER FACILITY. NOVOS-PAGE 3
Site 1
Inflow Channel
Inflow
Not Monitored
Site 2
42" RCP
Water Level
Recorders
Site 4
Outflow Channel
Site 3
ond Bleed-down
Proposed Monitoring Locations for the Pioneer Key Site
PECIPIONEER KEY REGIONAL STORMWATER FACILITY. NOVOS-PAGE 4
PIONEER KEY REGIONAL STORMWATER FACILITY
PERFORMANCE EFFICIENCY EV ALUA TION
EXHIBIT B: MAN-HOURS / FEE SCHEDULE
Prepared By
Environmental Research & Design, Inc.
Revised January 26, 2009
MAN-HOURS* TASK
TASK DESCRIPTION AMOUNT
PD PE LM FT cH D CL ($)
A. Labor
I Project Kick-off Meeting/Site Visit 4 -- -- -- -- -- -- $ 572.00
2 Prepare/Submit Proiect QA Plan 12 -- 4 -- 16 4 8 3,345.36
3 Select/Install/Calibrate Field Monitoring 24 -- 32 80 -- -- -- 9,106.24
Equip.
4 Perform Routine Monitoring (Weekly) 13 -- -- 260 -- -- -- 14,500.20
5 Routine/Final Data Compilation 13 24 104 -- -- -- -- 9,804.20
6 Prepare Draft Final Report 36 16 12 -- -- 8 16 8,414.44
7 Attend Review Meeting 4 -- -- -- -- -- -- 572.00
8 Prepare Final Report 8 4 8 -- -- 4 6 2,442.58
TOTAL - LABOR: 114 44 160 340 16 16 30 $ 48,757.02
B. Reimbursable Expenses
6,8 Black/White Copies (1000 copies (al $0.1 O/COpy) $ 100.00
6,8 Color Copies (250 copies (al $1 /COpy) 250.00
4 Equipment Rental- Autosamplers, rain gauge, and level recorders ($350/month x 4 samplers x 6 8,400.00
months)
3,4 Mileage (1750 miles x $0.40/mile) 700.00
6,8 Miscellaneous Report Expenses (at cost) 60.00
TOTAL - REIMBURSABLE EXPENSES: $9,510.00
C. Lab Analvses
4 Bulk Precipitation (3 samples/month x 6 months x $1 65/sample ) $ 2,970.00
4 Stormwater/Baseflow (6 samples/month/site x 6 months x 4 sites x $1 65/sample) 23,760.00
TOTAL - LAB ANALYSES: $ 26,730.00
PROJECT TOTAL: $ 84,997.02
*Personnel Billing Rates ($/hour)
PO:
PE:
LM:
FT:
CH:
0:
CL:
Project Director
Project Engineer
Limnologist
Field Technician
Chemist
Draftsman
Clerical
$ 143.00
$ 89.38
$ 55.77
$ 48.62
$ 51.42
$ 57.23
$ 44.33
PEC \ PIONEER KEY REGIONAL STORMWATER FACILITY. NOV 08 -PAGE 5