HomeMy WebLinkAbout01-09-1996 MINUTES OF THE PLANNING AND ZONING COMMISSION
REGULAR MEETING HELD TUESDAY, JANUARY 9, 1996
CALL TO ORDER
The meeting was called to order by Chairman Switzer at 7:35 p.m. followed by a moment of
silent meditation and the pledge of allegiance. A quorum was declared present.
PRESENT: Chairman Switzer, Vice Chairman Bond, Members Jones, Landefeld, Miller, and
Rhodus, and Alternate Members McKey and Williams. Also present were
Planning Director Wagner, Assistant City Attorney Formella, and Deputy City
Clerk Green.
ABSENT: Member Hopkins.
CONSENT AGENDA
The consent agenda consisted of approval of items A and B:
A. Minutes of the Planning and Zoning Commission Regular Meeting held Tuesday,
November 14, 1995.
B. Minutes of the Planning and Zoning Commission Regular Meeting held Tuesday,
December 12, 1995.
tor Member Landefeld noted that line 5, paragraph 3, page 3 of the November 14th Minutes should
be corrected by the insertion of "not" to read ". . . he does not anticipate . . ." and asked Mr.
Wagner if he had checked with the City Engineer about his findings concerning the maintenance
bond for street repairs in Silver Glen. Mr. Wagner said he had not, but would do so shortly.
Member Landefeld seconded by Member Miller, moved to approve the Consent A. enda as
corrected. Motion carried 6 -0.
NEW BUSINESS
PLANTATION GROVE PUD - CROSS CREEK, PHASE II - PROJECT NO. 95 -005
FINAL SUBDIVISION PLANS (INCLUDING MOORE ROAD CONSTRUCTION PLANS)
Planning Director Wagner presented the staff report for Phase II (162 lots) of the Final
Subdivision Plans for the single family portion of Plantation Grove PUD identified as "Cross
Creek." He explained that the Moore Road Construction Plans provided for the paving of the
road from the subdivision west to Maguire Road and that the road would be realigned from its
present location to form what eventually would be a fully signalized intersection with Roberson
Road. He explained staff's suggestion for the waiver of Condition of Approval No. 22 on the
revised PUD Land Use Plan (See Attachment #1) as its requirements would hold up the
subdivision for many months. He said in lieu thereof that staff recommended requiring the
developer to build both the subdivision improvements and Moore Road concurrently and that the
Planning and Zoning Commission Regular Meeting
January 9, 1996
City not give a Certificate of Completion on the subdivision until the road had also been
accepted.
Mr. Wagner also said staff recommended approval subject to changes (largely minor, technical)
as recommended in comments by the attorney and engineers in their memoranda which had been
distributed in the meeting. (See Attachment #2) He added that revised plans have been
submitted reflecting those changes.
He concluded with staff's recommendation for approval subject to the waiver, subject to the
inclusion of additional notes on the plans and subject to the completion and acceptance of the
paving of Moore Road prior to the issuance of the Certificate of Completion.
An area road about which Chairman Switzer expressed concern was determined to be east of the
Plantation Grove property. Attorney Formella assured him, with respect to Moore Road, that
the developer would be required to provide written verification that all of the improvements for
the new Moore Road that they were constructing would be within the area delineated on the plan
and that that matched up with the right of way that had already been conveyed to the City.
Member Landefeld asked how the alignment of Moore and Roberson Roads would be
accomplished.
1 "'' Mr. Wagner said a number of the details were shown in their plan sets but that more right of
way would need to be acquired on Roberson for the intersection.
Mr. Mark Evans, Regional Director of Land Development, Cross Creek Development
Company, Orlando and Mr. Joe Kolb, P.E., Vice President, CCL Consultants, Inc., Maitland
were present to answer questions.
Member Landefeld, seconded by Vice Chairman Bond, moved to recommend approval of the
Final Subdivision Plans for Cross Creek, Phase II, which includes construction plans for Moore
Road as date stam . ed received b the Ci on December 26 1995 and the attached Landsca • e
Plans as date stamped received by the City on December 29, 1995, subject to the comments as
addressed in the attached memoranda ** being incorporated into the Plan Set prior to City
Commission action; and further, that Condition of Approval No. 22* of the Revised Land Use
Plan for Plantation Grove PUD as incorporated in the Third Developer Agreement dated
December 29, 1993, be waived for this portion of the development and that, in lieu thereof, the
Final Subdivision Plans for Cross Creek, Phase II, be a s • roved subject to com • letion and
acceptance of the • avin. of Moore Road as inco • orated therein • rior to issuance of a Certificate
of Com • letion for the subdivision • ortion of the im • rovements . Motion carried 6 -0.
( *Attachment #1 /* *Attachment 2 to Minutes)
2
Planning and Zoning Commission Regular Meeting
.. January 9, 1996
OLD BUSINESS None.
OTHER BUSINESS
ELECTION OF OFFICERS
Member Jones, seconded by Members Rhodus and Landefeld, moved to retain Mr. Switzer
as Chairman and Mrs. Bond as Vice Chairman for the next year. Motion carried 6 -0.
COMMENTS
Planning Director Wagner reported:
1. The mall was expected to open on time as construction was on schedule.
2. Three annexations were pending: an addition to Burnden Park; the 40 acre Pease
property on the southeast corner of Clarke and Silver Star; and a parcel on SR
50 across from Health Central.
3. Senior Planner Horne has almost completed the ORC response to the
Comprehensive Plan Amendment and will be working on the Land Development
Regulations.
Nor" Several members expressed their concerns about problems with termites and siding in the City.
They suggested that the City should do all it could to assist the residents in resolving the
problems through setting policy, providing inspectors, and educating the citizens.
ADJOURNMENT
The meeting was adjourned at 8:12 p.m.
tz , Chairman
- cii(A
1ian Green, Deputy City Clerk
Nt 3
ATTACHMENT 1
_ to
=-Y =�3 NN PLANNING & ZONING COMMISSION
MINUTES OF JANUARY 9, 1996
CONDITIONS OF APPROVAL
'_GAL :NSTRUMCNLS FOR 4ANAGIMLVT Or COMMON AREAS VILE 3C 354E 21. THE DEVELOPER IS 70 CONTR
2MEOwNLRS ASSOCIATION DOCUMENTS w'ZCH WrI.Z, :NCL'U :L 1/3 Or THE COST or THE 9
0ECLARAT20N Of COVENANTS. CDNOITIONS ANO RESTRICTIONS. MOORE ROAD AND MAGUIRE .
PROPERTY ANNEXES INTO THL
PARKING WILL 3r PROVIDED AS REQUIRED :M TIE ORDINANCE. AT CONTRIBUTIONS. THEN TIC 3rvEL.OPER PARTICIPATION SHALL BE
THIS TIME THERE ARE ONLY CONCEPTUAL USES FOR THE PROPOSED REDUCED TO 1/4.
COMMERCIAL PARCEL.
.. :10 surtax= mom= wI4 oZ :SLUED FOR UTILITIES OR HORIZONTAL
ALL LAKES AS S503N ARE MANMAOS. THEY ARE CONCEPTUAL IN SjZE IMPROVEMENTS 2N CONNECTION WIT) ANY OZ\NLLappOT WITHIN
AND LOCATION ANO MAY WARY FROM THOSE. SNOWH. PLANTATION GROVE RIO. AND MO CERTIFICATE OF OCCUPANCY WILL At
A4 LAKE! TO HAVE A S:1 SLOE SLOPE :O A DEPTH OF 2 FEET BLLOy ySSU50 ON ANY SUCK IMPROVEMENTS. 3 NIQ( (i) IS INCONSISTENT
ITn THE =crow= USE of THE 55151I30 30085 ROAD AS A PUBLIC
NORMAL WATER LLEvATTOM WITHOUT FENCES ROADWAY, OR (11) REQUIRES ACCESS TO TIE PROPOSED 35AL:C550
MOORE 20AD. UNTIL SUCH TIME AS:
. LAKES ARE INCLUDED IN PARCEL ACREAGE. a). THE PROCESS FOR VACATING THE EXISTING MOORE ROAD :S
SOi Or TNL GROSS LANG AREA IN EACH MULTI- FAMILY PARCEL SMALL INITIATED: AND
LS). A4 PLANS FOR SAID IMPROVEMENTS HAVE NET ALL RCOUIRDILNTS
95 OPEN SPACE - SAID OPEN SPACE TO INCLUDE 80TH 351 ANO DAT Or TNL HOLDER Or THE UTILITY CASEMENT ALONG THE EXISTING
8515NTSON PON 6S. MOORE ROAD: AND
5). 755 REALIGNED 30085 ROAD HAS BEEN PAVED A DISTANCE OP
. ALL BUILDING SETBACKS room ALL R5;LNT :ON PONO5 SMALL 3C 25 1.281.4 Fir room 7MC EASTERLY =NE OF THE MAGU
FELT room TOP Or 84)18 IN MULT2- FAMILY PARCELS AND 35 FL: FROM 81CKT -Or -WAY. IRE ROAD
TOP Or BANE IN SINGLE FAMILY PARCELS.
FURTHER. NO BUILDING *mars WILL BC ISSUED Son ANY 3 5875543,
ALL COMMERCIAL *UIIaIN65 5HAL•. 8C SET RACE 50 FEES FROM A4 IMPROVEMETS IN CONNECTION wIT14 ANY DEVELOPMENT 'emu
RESIOENTTAL PARCELS AND 40 FELT room MAGUIRE ANO MOORE ROADS PLANTATION GROVE PUD WHICH (1) IS INCONSISTENT 3ITM THE
R261LZ5 -07 -WAY. COMTZM 50 U35 OF TIM EXISTING NOOSE ROAD AS A PUBLIC ROADWAY,
HOMEOWNER'S ASSOCIATIONS IN RESIDENTIAL PHASES AND THE UNTIL SU TIME AtA TO THE PROPOSED REALIGNED MORE ROAD,
•
PROPERTY OWNER IM C71RMEXC:AL AREA! SMALL BC ALSPOm3IEL2 FOR
ALL OPEN SPACE. RETENTION AREA. PRIVATE PARK AND PRIVATE ROAD 4). ALL OF TR5 CONDITIONS IN •1 TIRO C)• ABOVE, RAVE SEEN
MAINTENANCE. MET: ANO
•.) TNR ROAD IMPROV4DIDT3 00734)150 IN of ABOVE MARL BEEN
.U. THE COIOiZ*CZAL PARCEL ACTLNTZON /OLTLNTIDN 1.0m0 WELL 88 IOCATL0 COMPLETED AND ACCLPTZ0 BY THE CITY OF OCCEE,
ON TIM MULTI-7AMZLY TRACT AND WILL MELT 35MI440•5 REQUIRE2MENT
FOR WATL)1 QUALITY (POLLUTION AYTEMETI. *8035050. NOWBVER. THAT NO ACTUAL VERTICAL CONSTRUCTION SHALL
BC ALLOWED mrrnii THE EXISTING MOORE ROAD 80403Ay UNTIL SUCH
.1. THE DIVEZOPER INTENDS THAT ALL :rTQNAL 3118533 ARC TO S8 PART
TIME AS THE 53551516 MOORE AGO IS VACATED. *0* THE mown
or A PRIVATE STRZLT STSTEI. mono' 3N11Ey 55 MAINTAINED BT THE
Or THIS WTI. TIM REAL36N50 N00R1 ROAD IS UNDERSTOOD TO SC A
HOMEOWNER'S ASSOCIATION warn ACCESS GRANTED TO TMC C'1T 0/ TWO CANN NOAD WITH A LLPT -NANO AND RIGHT -NAND TORNLANE ON 70
OCOEE EI
FOR E4GaICT AND MAINTENANCE. PERSONNEL. THIS OS ICY 1{AGDIIE.
i IASE(ErT WILL ALSO BE NOTED OM ANY PLATS. THL APPROPRIATE — --• ACCESS 1010 Imam turnoffs SMALL BE 6R1U1TLD TO THE C^.T OVER 23. RECREATIONAL PARK IMPACT FL53 SHALL SE PAID IN ACCORDANCE WITK
ALL PRIVATE AOAD3833 35774 THE CTY BEIAG RESPONSIBLE FOR ANY THE ORDINANCES Or THE CITY Or OCOEE. AS THEY KAY FROM TIME T9
DAMAGE DONE BY THE CITY IN CONNECTION WITH THE UT:L4 :ON Or TIME BC AMENDED. PAYMENT Of SUQt FEES SMALL SATISFY :H PO4
•
ANY SUCH EASDIDIT2. 7125 REQUIREMENTS or SECTION 13.11(2)(•) OF SECTION 12 Of
CMAPTER :V Or APPENDIX A Or THE OCOEE CITY CODE.
.. THIS REVISED Lu40 USE PLAN SUPERSEDES AND REPEALS ALL
PREVIOUSLY APP8OVED LAND USE PLANS TOR PLANTATION :ROVE =a• TYPICAL !ANGLE FAMILY 6.0'7 SLTBAC7LS AS r9t,LOW3i
P.U.D.
FRONT : 23'
2.L 23 POINTS TO MACUIRE ROAD 51NOLCAT5 LOCATION Or PROPOSED ALAS : 23'
I'B CUTS. SIDE : 7.3'
+. :7tI3 PLOW REFLECTS THE DEDICATION OF THE NORTH 40 rCz. OF • ALL GORIER LOTS SMALL MARL ONE FRONT YARD A )10 ONE SIDE YARD
mOOAZ ROAD RIGHT-0r -WAY. yarn THE SIDE YARD SETBACX AS rOL.LOWS:
5. ALL RLSmolt* TION /DLTDYT :ON PONDS (!AXES) SNO AXE PROIMJ539 (MAN- I3' 27 THE STALL! SIDE or THE A62ACD4T LOT ON THAT SAM STREET
MADE) WITH APPROXIMATE LOCATION AND SIZE. I3 A SIDE YARD: OR
,. X'011 LOCATION Or ALL LZISTIN6 MATURES ON TML PROPERTY Sa THL 25• I7 TLC STREET SIDE or TAIL ADSACEMr LOT ON THAT SASE STRE=
BOUNDARY SURVEY.
IS MERIT YARD, OR
POTABLE WATER SUPPLY 1S • I7 110 AIIJACLNT LOT ON THAT SAME STREET.
WA7ER =MICE SMALL SC PROVIDED ST THE CITY OF 00055 VIA THE
5X127216 WATER MAIN LOCATED ON MAGUIRE ROAD.
FIRE FLOW REQUIREMENTS: (MINIMUM)
SINGLE PARTLY - SOO CPR
MULTI FAMILY - 1000 GPM
COMMERCIAL - 1000 CPR
SANITARY SEWER DISPOSAL:
. !EWER SERVICE SHALL BC PROVIDED BY THE arm Or DOLL 31'
20335750/1 TO TIE EXISTING LIFT STATION LOCATED AT THE
NORTHEAST CORNER or THE SITE.
STOATER MANAGEMENT: 4/. .v lO '+ 'v'
11lM MANAGEMENT:
STORMWATER SYSTEM WILL BE DESIGNED TO MELT CR :T5RSA
• ESTABLISHED BY BOTH THE CITY OF OCOEE AND TIE ST. :011X•5 RIMER HS .o 15
r lSWr
WATER MANAGEMENT 0137830.. POST D!Vt:OPR EN'T DISCHAAGL FROM I 1
�
RC i I - S'. N urW.2 , CNN. 40111' I i
UN.. urtiu. , 1 • .. N 01
SITE 334 8C 2.5142153 TO 40 673 70R INC 25 TCAA /24 HOUR STORM
EVE. *0LZ21TI0) ABATEMENT REQUIREMENTS SMALL 8E NET 3T THE
" •'• • '
(7
USX Or FILTRATION SYSTEMS. I I
I I rr ••
. INS MILSI7A3ILY UNITS SHALL 8E A 3ZX'ZURL Or r•�`�?��
AND THREE BEDROOM 011375. STUDIO. oN [. TNO ,,..4=
- r a- CONE SN 1,31 5. v.. . I7 PROPERTY PROPOSED FOR DEVELOPMENT MERLIN )HAS BEEN INCLUDED I I I
I
1 I I '' A S C S .wl s• N
IN A TRAFFIC STUDY 3IT4IM THE PREVIOUS 12 MYTHS fM
HS ON THE SATE I I 1 O SOl Ceara, YS! C01MS!
Or tans APPLICATION, THEN AN ADDITIONAL :mum STUDY WILL X01 1 I .7". wn0
CO•C1 ?0 �
8Z REQUIRED.
r•r 0lNYrr, • . 5 4 821 O(r «u)
A4 DEDICATED RICM73 -03 4 -WAY SHOWN HLR55 3844 BC 553154TED 8Y I wt. SuNrNAN 117:. ro • M •
• SO
WARRANTY OL5D3 TREE ANO 0258* OP ALL L4II45 yt1KIN 45 3AY5 FROM ( P0 [*mi1
THE DATE Of CI CO)042SS :ON APPROVAL Or THIS PLAN AND 3548 ... C4M� • Gilt , cis TY
DEVELOPERS A6R5E1ET INCORPORATING THE CONDITIONS OF APPROVAL r
SET FORTH ON THIS PLOW.
TYPIC=AL INTE NAL STREET SECTION
ATTACHMENT 2
to
PLANNING & ZONING COMMISSION
MINUTES OF JANUARY 9, 1996
FOLEY & LARONE
" f r o w n e r s wr t.ww
t t
SUITE 1800
111 NORTH ORANGE AVENUE j
W • 01 4rInCLS iN
ORL NO°. Ft.OR10A 32801
JAC}(3ONVtL1,E TELEPHONE t.oTr 4 .23-7858 JAN 0 2 i::S BRUSSELS
TALLAHA
TAMPA FACSIMILE l4077 848•i74 DRESDEN
WEST AL BEACH FRANKFURT
P M
MILWAUKEE MAILING ADORE$$; LONDON
MACISON Pow' am= SOX 2193 CITY CF OCOEE PARIS
C}iiCAGO OAlAN00. Ft. 3a802- 2193
s1NGA PORE
WASHINGTON, O.O. STUTTGART
TAI PEI
MEMORANDUM
TO: Ellen M. King, Development Review Secretary
FROM: Martha E. Formella, Esq., Assistant City Attorney
DATE: December 29, 1995
RE: Crass Creek. Phase II /Final Subdivision Plans
In connection with the above - referenced matter, we have
reviewed the following documents:
Si '"' 1. Cross Creek Phase II Final Subdivision Plans for
Plantation Grove, Parcels B, C, D, G, and I stamped
received by the City of Ocoee December 26, 1995 (the
"Plans ")
2. Response letter from Joseph F. Kolb of CCL Consultants,
Inc. dated December 22, 1995 and stamped received by the
City of Ocoee December 26, 1995 (the "Response ");
3. Owner's Affidavit dated December 19, 1995 and stamped
received by the City of Ocoee December 26, 1995; and
4. Page 2 of Application fcr Subdivision or Site Plan
Review.
This memorandum supplements our prior memoranda dated
November 30, 1995 and December 6, 1995 ( "Prior Memoranda "). Based
upon our review of the above - referenced documents pursuant to the
new Land Development Code, we have the following comments:
1. As noted in our Prior Memoranda, the approved Preliminary
Subdivision Plan ( "PSP ") references utility and drainage
easements in vote 7 on Sheet 1 and on Sheet 2. We have
requested that the Applicant reflect the easements on the
err Plans by locating the easements on the Plans or by
adding notes to the Plans. Note 8 on the Plans is not
sufficient because it does not specifically identify the
easements. The following steps should be taken:
a. Add PSP Note 7, which states the following, to the Plans:
A 15'- utility easement shall exist over all
watermains within the single family portion as well
as an easement over all sanitary lines with a width
of twice the depth of the sewer or I5* miniMUm -
b . It appears that the drainage easements are shown on
Sheet 6. City Staff should confirm that the
location and width of the drainage easements are
acceptable.
c_ Add the following note, which is similar to a note
on PSP Sheet 2, to the Plans:
The land underlying the drainage easements shall be
owned by the individual lot owners. The drainage
easements are for the benefit of and shall be
maintained by the Homeowner•s Association.
2.. For the private easement, the PSP referenced Book "4334"
while the Plans reference Book "3443 ". Please confirm
the correct recording information and revise the Plans if
necessary. The private nature of the easement should be
specified. Please change the labeling to "Private
Roadway Easement ". If documentation of a 10 foot width
and power use is provided, the labeling can be adjusted
accordingly. j
3_ Please be advised that, prior to issuance of a
certificate of completion, - the temporary easements - to ..
accommodate a temporary water line, must be recorded.
If you have any questions regarding these comments,
please do not hesitate to call.
cc: Paul E. Rosenthal, Esq., City Attorney
-2-
FOLEY & LARDNER
A r P O w N c ♦ a A r
7cR. �SUITE' 1800 c a or GLOsALCX
111 NCRTM ORANGE AVENUE , -^ e ; T
oC113 IN
ORLANDO. FLORIOA 32801 ��•'
JA CX SON V ILLS J BERLIN
T,/ LL 4Agg�r TELEPHONE 14071 423 -7858 BRUSSELS
TAMPA FACSIMILE 1407? 648 -1743 Cr aE r DRESDEN
WEST PAL BEACH AGGRESS: CtT/ 1 1 ► C O FRANKFURT PALM MILWAUKEE LONDON
MADISON POST OFFICE SOX 2193 PARIS
C>•11CAGO ORLANDO. FL 32802 -2193 SINGAPORE
WA3MINGTON. O.0 STUTTGART
TAIPEI
MEMORANDUM
TO: Ellen M. Ring, Development Review Secretary
FROM: Martha H. Formella, Esq., Assistant City Attorney
DATE: December 29, 1995
RE: Cross Creek. Phase IT /Moore Road Construction Plans
In connection with the above - referenced matter, we have
reviewed the following documents:
#401 ""' 1. Constr uction Plans for Moore Road [included in the Cross
Creek, Phase II Final Subdivision Plans for Plantation
Grove, Parcels B, C, D, G, and I stamped received by the
City of Ocoee December 26, 1995j ( "Road Plans ");
2- Response letter from Joseph -F. Kolb of CCL Consultants,.
Inc. dated December 22, 1995 and stamped received by the
City of Ocoee December 26, 1995 (the "Response ") ; and
3. Title Opinion through December 9, 1995 prepared by
Maguire, Voorhis & Wells, P.A. and dated December 27,
1995 (the "Title Opinion ") and Certificate of Title
Information through December 9, 1995 prepared by First
American Title Insurance Company and dated December 26,
1995.
This memorandum supplements our prior memoranda dated
November 30, 1995 and December 6, 1995 ( "Prior Memoranda "). Based
upon our review of the above- referenced documents pursuant to the
new Land Development Code, we have the following comments:
1. Please provide a surveyor's certification which states
that the legal description attached to the Certificate of
Tit1 a describes all of the property delineated as Moore 1r??► Road on the Road Plans.
If you have any questions regarding these comments,
please do not hesitate to call.
Skov
cc: Paul E. Rosenthal, Esq., City Attorney
-2-
r' .IBM)
JAN 0 3 1996
Now Cross Creek Phase II
January 2, 1996 CM EIF a tr itig James W. Shirr, P.E., City Engineer/Utilities Direcm
1. I have no problem with, nor anything to add to Martha Formella's comments_ She is
better inforned than I am as to the wording of any notes regarding easements.
2. I still have not seen the easement document for the temporary ware: line easement. If this
project goes to DRC on January 3, 1996, provision of an acceptable easement document
prior to City Commission action should be a condition of DRC approval
3. On the comments submitted by PEC, I have the following:
•
I_ We had not discussed the need for a right turn lane into Cross Creek from
Moore Road, nor was it a requirement of the preliminary plan_ I do not believe
we should require this turn lane;
2. Unless PEC fwis that using the Orange County rainfall distribution will
significantly affect the design, I do not feel that we should required CCL to
revise the drainage calculations in this manner. In a phone conversation with
Kevin Perko (PEC) on January 2, 1996, he indicated to me that no significant
design change would result from using Orange County's distribution.
r
PEC
PROFESSIONAL ENGINEERING CONSULTANTS. INC.
Dec robe: 29, 1995 -747
Ms. Ellen King 1-4 • `� -1.0
Planning Review S 2 15 °6
City of Ocoee
JAN a
150 North Lakeshore Drive •
Ocoee, Florida 32761 CITY OF OCOEE
RE: Revised Moore Road Construction Plans Review
Dear Ms. Sing:
•
Pursuant to the City's request, we have reviewed the revised construction plans dated
December 26, 1995, and various reports associated with Moore Road construction and
realignment from Maguire Creek Subdivision: Road to
approximately 450 feet east of the proposed Cross
en ce These documents were primarily reviewed for conformity
with City standards and design guidelines_ They were not reviewed in detail in order to
determine their conmess, completeness or constructability.
Following are our comments and suggestions:
w
ROADWAY
1. We recommend using a 3.5' flat sod strip (0.04% slope) directly behind the curb
and gutter (type "F") along Moore Road_ This will provide the required clear
zone distal= (4' from fare of curb) and will
provide stability for the curb and
gutter
2. Cross Cry Subdivision entrance bate:secdon has 60' control radii. This will
require that the stop bar be placed 50' away from Moore Road_ Please re-
evaluaa. (See MDT®, Section. 3B-17 for stop bar placement guideines)_
• r- _
• r. v .V... •• .uV �� .V 1 u .W r v i _ •y u�.a • t •
�!�� � ub..W.}ai� +Ul L r WWli va�. • aijlit �i2� .�ti.L .iy�Ji U4t�..uaA. J• .,■■,, � � ty
i .t Liu t. � /1U Y1�1W 3L 1lIL CiuJJ
C �'♦ 0 _ k a _e GCRe- '.Teem
5. flow were the turn lane queue lengths calculated?
law SIGNING AND PAVEMENT MARKING
We note that the following comments are minor labeling comments:
1. Add size (30 "x30 ") to "Right Lane Must Turn Right" signs.
Ms. Elea King OE -247
December 29, 1995
Page
Stow
2. Add bi-direcdonal. amber rpms to 18" yellow striping.
3. Remove rpms from 6" white edge lines. Rpms are not typically used on outside -
edge lines.
4. Revise label for 6" yellow slip to include appropriate skdp description (10' -30'
skip) and delete the "AT 30' 0.C.", it is incorrect
5. Add appropriate two-way left turn arrows at appropriate spacing to center lane
between stations 4 +00 and 8 +00.
6. Label 6" double yellow sniping with bi- directional amber rpms at appropriate
pathn
7. Add 6" double yellow striping with bi-d rec onal amber rpms (at 40 on- center)
beiwee:r stations 10 +45 and I4 +25.
8. Add spacing for rpms on Left turn Ianes at all locations.
9. Add stop sign to Cross Creek Subdivision proposed entrance/exit abutting Moore
*law Road.
10. Note I under pavement marking and signage specification refaces FDOT
"Manual on Uaiforrn Traffic Control. Devices for Streets and. Highways ".. No -
such document exists.. Please revise to appropriate document_ -
DRAINAGE
S attached memorandum.
Pl=se fw situp you have any i l�cns.
Very truly yours,
PROFrSSIONAL aNGINEER.ING CONSULTANTS, INC.
Kenneth R. Eooper J
Project Manage`
KRRE/cr
Attachment
cc: Mr. Russel Wagner, City of Ocoee
Mr. Steven Kr PEC
Mr. Kevin P PEC
PEC
PROFESSIONAL ENGINEERING CONSULTANTS, INC.
PROTECT MEMORANDUM
TO: Ken Kopper 777-77.4747,E .,
E -24
_z1f0
���p 2-La FROM: Kevin Perko K.
,if 21990
DATE: December 29, 1995
CITY OF OCOEE
COPY TO- Fursan Munjed, David Hamstra
RE: Moore Road Plans Review #2 (Revised plans dated December 21, 1995)
City of Ocoee
Upon review of the above referenced plans, the following technical information is required
to sufficiently review the project and demonstrate conformance with the applicable design
vikly
citeria:
1. Sheet 3: Replace inlet detail with one depi inlet without sidewalk as previously
transmitted
2. Structure S-I. Subtract pipe length included in mitered end section payment (see
FDOT Index 272) and length from centerline of inlet to inside wall of inlet bottom.
3. Sheet 5: Provide a Ievei area behind the curb and gutter to provide stability and
iaciitare the consaucdon of the open back inlets.
4. Sheet 5: Consider maintaining a consistent offset to the sidewalk and varying the
backslope to the R'W, with a maximum slope of 2: I.
C117/ .44€4316-.24-it-tauxteirerepbst--
awm02
eery717e915
"CENTER OF LOCO LIVING - PRIDE OF W ORANGE" MAYO�e - commis: mom
Ocoee S. scorn VANDERCZIFr
pai CIT cam►N ISSIONEMS
R USTY JOHNSON
CITY OF COEE SCOTT ANDERSON
D 150 N. LAKESHORE DRIVE SCOTIA. CLASS
�o �v CCOEE. FLORIDA 34761-=.58 JIM CL: ASON
(407) 656 -2322
l F4 , Q� Gads `> art M ANAGER
ELLIS SHAI'IRO
MEMORANDUM
TO: TT.r.FN KING, DI•:vr:LOPM.ENT REVI='W SEC. i r
FROM: JULIAN HARPER, ZONING COORDINATOR
THROUGH: D.W. FLIPPEN, BUILDING AND ZONING IRECTORZ
DATE: DECEMBER 28, 1995
SUBJECT: CROSS CREEK, PHASE II, FILL SUBDIVISION
PLANS, PARCELS B,C,D,G,. AND I
1) Correct and revise Site Data am Lead Sheet to be consistent
with Approved Final Landscape Plan COA #24, and Approved
Waiver #1:
Setbacks:
X Front: 25'
Rear: 25'
Side: 7.5'
* All corner lots shall have one front yard and one side yard
with the side yard setback as follows:
15' - If the street side of the adjacent lot on that same
street is a side yard; or
25' - If the street side of the adjacent lot on that same
street is front yard; or
15' - If no adjacent lot on that same street;
25' - Moore Road
JRE /sas /714
4r1ir