HomeMy WebLinkAboutItem #06 Approval of Change Order #2 with Hazen Const. for North Side Reclaimed Water Mainlk4SO%/� 0 CnP( florlda AGENDA ITEM COVER SHEET Meeting Date: December 3, 2013 Item # Reviewed By: Contact Name: David A. Wheeler, P.E. Department Director: Contact Number: 407 - 905 -3100, Ext. 1504 City Manager: lif Subject: Change Order No. 2 with Hazen Construction LLC for the North Side Reclaimed Water Main Extension Project — District 1 (Commissioner John Grogan) Background Summary: The North Side Reclaimed Water Main Extension project provides for the installation of a 16 inch reclaimed water main along McCormick Road from the entrance to the McCormick Woods subdivision west to Ocoee - Apopka Road and then south on Ocoee - Apopka Road to the entrance to the Fountains West commercial development. The North Side Reclaimed Water Main Extension project was awarded to Hazen Construction LLC (Hazen) at the April 16, 2013, City Commission meeting. The path of the pipeline followed the right -of -way for McCormick and Ocoee - Apopka Roads. The original design proposed to have the City's new 16 inch reuse pipeline located approximately half way between the edge of pavement and the SR 429 bridge end wall as the pipeline passed under SR 429. During the design of the project, CPH, Inc. attempted to obtain information from all existing utilities in this area to avoid conflicts. Had CPH, Inc. been provided with the existing utilities information, their design would have been to place the pipeline out in the west bound travel lane. Both shoulders of McCormick Road are very crowded with existing water, sewer, and gas pipelines, and telephone, electrical power, and cable TV conduits. To maintain minimum spacing from all of these pipelines, conduits, and the bridge end wall, the new reuse pipeline needed to be located under the pavement. Because the new pipeline is proposed to be installed under the west bound travel lane the work will include a more complex maintenance of traffic because the work will require one lane to be closed during the day, temporary road rebuild every night, and mill and resurface and restriping the entire width of McCormick Road in the affected area. The additional pavement requirements were from Orange County Public Works as McCormick Road is an Orange County jurisdictional road. Hazen was able to return the steel casing pipe originally required by the Expressway Authority permit but was unable to return the casing spacers and receive a credit. The projected cost for this work will result in an increase in the project of $41,777.00 and an addition of 15 days to the contract time. The second item on the change order is to change the method of pipe installation in crossing McCormick Road at the intersection with Ocoee - Apopka Road from open cut to directional drill. When the project was being designed CPH, Inc., City staff, and Orange County Public Works looked at both the open cut and directional drill installations in the intersection. The project was designed and bid utilizing the open cut method, because it was not anticipated that there were many conflicts in this area. Once accurate locates of the existing utilities and the convenience stores septic system were provided, it was determined that installing the new 16 inch pipeline across the intersection would be easier and safer by the directional drill method. The pipeline could be installed deeper than the open cut method and therefore be below all the existing utilities. The directional drill method will also eliminate the potential for extra costs associated with having to work around other utilities. As a general rule, costs are comparable when comparing an open cut versus a directional drill installation. This would have been the case, had the pipeline supplier been willing to take back the 300 feet of PVC pipe and charge a nominal restocking fee. The City will not be seeing the additional reduction of deducting the PVC pipe installation that would have reduced this change order item by an 14,700. The projected cost for this work will result in an increase in the project of $17,614.00 and an addition of 30 days to the contract time. However, in this case where the material supplier is not so inclined to avail the contractor and the City and accept the material back at the nominal fee, the City is going to have Hazen install the 300 feet of PVC pipe on McCormick Road east towards the Kensington Manor subdivision, a portion of phase 2 of the North Side Reclaimed Water Extension Project to be bid next year. The total cost for Change Order #2 is $59,391.00 with an adjustment in contract time of 45 days. The attached document is Change Order No. 2 with Hazen Construction LLC. Issue: Should the City of Ocoee approve Change Order No. 2 with Hazen Construction LLC to move the reclaimed water main out into McCormick Road under SR 429 and allow the crossing of McCormick Road at Ocoee - Apopka Road to be by directional drill method? Recommendations: The Engineering and Utilities Departments recommends that the City Commission approve Change Order No. 2 with Hazen Construction LLC in the amount of $59,391.00 and extend the project completion date by 45 calendar days and authorize the Mayor and City Clerk to execute the change order. Attachments: Change Order No. 2 between the City of Ocoee and Hazen Construction LLC Financial Impact: This change order will result in an increase of the project's construction contract by $59,391.00. Funds are available for this change order in the overall project budget in the Utility Fund. Type of Item (please mark with an °x') Public Hearing Ordinance First Reading Ordinance Second Reading �r Resolution y Commission Approval Discussion & Direction Original Document/Contract Attached for Execution by City Clerk Original Document/Contract Held by Department for Execution Reviewed by City Attorney Reviewed by Finance Dept. Reviewed by () For lerk's De Use: Consent Agenda Public Hearing Regular Agenda N/A N/A N/A 4 t/ OC()( >(> florida 150 North Lakeshore Drive Ocoee, Florida 34761 NORTH SIDE RECLAIMED WATER MAIN EXTENSION PROJECT CHANGE ORDER NO.2 DATE: November 25, 2013 The following changes are hereby made to the CONTRACT DOCUMENTS. Original CONTRACT PRICE Current CONTRACT PRICE ADJUSTED by previous CHANGE ORDERS Net Increase (Decrease) Resulting from this CHANGE ORDER The current CONTRACT PRICE including this CHANGE ORDER Original CONTRACT COMPLETION DATE: Current CONTRACT COMPLETION DATE adjusted by previous CHANGE ORDERS Net Increase Resulting from this CHANGE ORDER Current CONTRACT COMPLETION DATE including this CHANGE ORDER $978,838.10 $993,114.85 $59,391.00 $1,052,505.85 February 12, 2014 March 14, 2014 45 days April 28, 2014 CHANGES ORDERED: I. GENERAL This change order is necessary to cover changes in the work to be performed under this Contract. The GENERAL CONDITION, SUPPLEMENTARY CONDITIONS, SPECIFICATIONS and all parts of the Project Manual listed in Article 1, Definitions, of the GENERAL CONDITIONS apply to and govern all work under this change order. 11. REQUIRED CHANGES A. In the area of the project where McCormick Road passes under SR 429, the pipeline has to be moved out into the middle of the west bound travel lane. B. At the intersection of McCormick and Ocoee - Apopka Roads, the contractor has requested that the pipe be installed by directional drill methods as opposed to the open cut method on the design plans. III. JUSTIFICATION A. At the time the project was bid, CPH, Inc. obtained limited information on the location of existing utilities. When Hazen Construction LLC contacted SSOCOF, Inc. about the location of existing utilities, all the utilities proceeded to mark their facilities. Both shoulders of McCormick Road are very crowded with existing water, sewer, and gas pipelines, and telephone, electrical power, and cable TV conduits. To maintain minimum spacing from all of these pipelines, conduits, and the bridge end wall, the new reuse pipeline needed to be located under the pavement. B. When the project was being designed CPH, Inc., City staff, and Orange County Public Works looked at both the open cut and a directional drill installation in the intersection. Once accurate locates of the existing utilities and the convenience stores septic system were provided, it was determined that installing the new 16 inch pipeline across the intersection would be easier and safer by the directional drill method. The pipeline could be installed deeper than the open cut method and therefore be below all the existing utilities. The directional drill method will also eliminate the potential for extra costs associated with having to work around other utilities. IV. NARRATIVE OF NEGOTIATIONS Many of the pay items in each construction change were either added or deleted based upon the unit prices in the bid schedule. For tasks not covered by a particular bid item, the price was negotiated between both parties. See attached cost estimates from Hazen Construction. V. PAYMENT Change Description Net Increase Net Increase Order Item (Decrease) Unit Total Price (Decrease) No. Quantity Price Item A Relocation of pipe under SR 429 $41,777.00 $41,777.00 Item B Directional Drill Installation at 17,614.00 17,614.00 Ocoee - Apopka and McCormick Road Intersection. Total Net Increase for Change Order No. #2 $59,391.00 V. APPROVAL AND CHANGE AUTHORIZATION This proposed change to the Contract requires approval by the City Commission and execution by the Mayor. It is expressly understood and agreed that the approval of the Change Order shall have no effect on the original contract other than matters expressly provided herein. CONTRACTOR acknowledges, by its execution and acceptance of this Change Order, that the adjustments in Contract Price and Time shown hereon constitute full and complete compensation and satisfaction for all costs and modifications of performance time incurred by the CONTRACTOR as a result of this Change Order. No other claim for increased costs of performance or modifications of time will be granted by the OWNER for the Work covered by this Change Order. The CONTRACTOR hereby waives and releases any further claims for cost or time against the OWNER arising from or relating to the matters or Work set forth or contemplated by this Change Order. RECOMMENDED BY: CITY OF OCOEE, FLORIDA By: Signature Date: Title: APPROVED BY: CITY OF OCOEE, FLORIDA By: S. Scott Vandergrift, Mayor Attest: Beth Eikenberry, City Clerk FOR USE AND RELIANCE ONLY BY THE CITY OF OCOEE, APPROVED AS TO FORM AND LEGALITY THIS DAY OF , 20_ SHUFFIELD, LOWMAN & WILSON, P.A. I: ACCEPTED BY: HAZEN CONSTRUCTION, LLC By: Date: Title: Signature Date APPROVED BY THE CITY OF OCOEE COMMISSION IN A MEETING HELD ON AGENDA ITEM NO 20 UNDER City Attorney HAZEN CONSTRUCTION, LLC UNDERGROUND UTILITIES November 18, 2013 VIA EMAIL: dwheeler(q�)ci.ocoee.fl.us City of Ocoee 150 N. Lakeshore Drive Ocoee, Florida 34761 Attn: David A. Wheeler, P.E. RE: North Side Reclaim Main — Ocoee, Florida EWO 003 Dear David, Hazen Construction is pleased to submit this proposal for changes in our scope of work on the above - mentioned project. Our unit price cost of $13,216 and lump sum cost of $4,200 for a total cost of $17,614 is based on directional drilling under McCormick Road in lieu of open cut due to conflicts with existing utilities. I have outlined our pricing below based on the contract unit prices and adding items as required • $( 5,340) — Delete 89 sy of open cut repair at $60 / sy • $( 7,760) — Delete 194 sy of 1.5 mill and overlay at $40 /sy • $( 750) — Delete 30' of curb repair at $25 / if • $( 1,536) — Delete 48 sy of concrete driveway repair at $32 / sy • $( 7,800) — Delete 300 sy of sidewalk repair at $26 / sy • $ 36,600 — Add 300' of 16" directional drill at $122 / if • 4,200 — Add additional mobilization of drill rig and equipment S 17,614 — Total cost of change based on items above In addition, we are requesting an additional 30 days to complete this work in order to procure the directional drill material. We are willing to meet with you to discuss this proposal in more detail at your earliest convenience. The reason the 300' of 16" open cut is not included in the deduct amount above is the City has requested Hazen to install the extra pipe at a different location. Assuming the conditions are similar to the North Side installation, we will install at the contract unit prices. If you have any questions or require additional information, please give me a call. Sincerely, Hazen Construction, eith M n Proj anager 1599 Tionia Road Phone: 386 322 -8700 New Smyrna Beach, Florida 32168 Fax: 386 756 -0000 HAZEN CONSTRUCTION, LLC UNDERGROUND UTILITIES November 18, 2013 City of Ocoee 150 N. Lakeshore Drive Ocoee, Florida 34761 Attn: David A. Wheeler, P.E. RE: North Side Reclaim Main — Ocoee, Florida EWO 002 Dear David, VIA EMAIL: dwheeler @ci.ocoee.fl.us Hazen Construction is pleased to submit this proposal for changes in our scope of work on the above - mentioned project. Our lump sum price of $41,777 is based on the revised plan sheet 18 dated 11 -06 -13 from Orange County. I have outlined our pricing below for your review along with the original pricing in the contract that will not be billed: New items Required: • $ 38,445 — Open cut 466' of 16" DIP • $ 4,240 — Temporary asphalt in open cut • $ 14,400 — Open cut repair 240 sy using contract unit prices of $60 / sy • $ 62,000 — Mill and resurface 1,550 sy using contract unit prices of $40 / sy • $ 2,250 — MOT, VMS and additional flaggers • $ 1,850 — Saw cut roadway 860' thru 12" of asphalt and soil cement • $ 5,844 — Material cost for casing spacers and end seals — City of Ocoee to keep. • 8,938 — Pavement markings, thermo and RMP's $ 137,967 Total cost of new items required Items Deleted from Contract: • $ 81,600 — Open cut 300' of 16" DIP with 30" casing at $272 / if • $ 6,456— Asphalt shoulder 269 sy at $24 / sy • 8,134 — Open cut 166' of 16" PVC at $49 / if $ 96,190 Total cost of items delete from contract In addition, we are requesting an additional 15 days to complete this work above the original scope of work. We are willing to meet with you to discuss this proposal in more detail at your earliest convenience. If you have any questions or require additional infonnation, please give me a call. Sincerely, Hazen Construction r7 Keith an Pro' anager 1599 Tionia Road Phone: 386 322 -8700 New Smyrna Beach, Florida 32168 Fax: 386 756 -0000