AGENDA ITEM COVER SHEET
Meeting Date: September 16, 2014
Item # (0
Reviewed By:
Contact Name: Stephen C. Krug Department Director:
Contact Number: 6002 City Manager:
Subject: Floral Street Improvements. Commissioner Johnson, District 3.
Background Summary:
Public Works had identified Floral Street for curb line reconstruction to improve the flow of storm water
draining to the existing curb inlets and also for installation of a sidewalk to improve the pedestrian
access throughout the city center. The Public Works Team determined combining these two
improvements into a single project reduces the total construction time and associated costs while
accomplishing the improvements.
Public Works solicited pricing from the contractors on the City's Small Construction Projects Term
Contract. Four (4) contractors responded with the low bid below the Engineer's estimate. Public Works
recommends awarding the project to the low bidder, Schuller Contractors, Inc., in the amount of
$25,560.00. The project has a forty five (45) calendar day duration and is funded under the Stormwater
Division's Miscellaneous Small Projects and Streets Divisions Capital Sidewalk Improvements.
Issue:
Request the City Commission approve award of Floral Street Improvements Project to Schulte
Contractors, Inc.
Recommendations:
Recommend approval to award the Floral Street Improvements Project to Schuller Contractors, Inc. for
$25,560.00 based on pricing solicited through the City's Small Construction Projects Term Contract
RFP11 -004, and authorize City Manager to execute any change orders up to the limits in the approved
purchasing code.
Attachments:
Floral Street Improvements Price Quotes.
Floral Street Improvements Plan Sheet.
Financial Impact:
The project is adequately funded through the Public Works' Stormwater Division's Miscellaneous Small
Projects ($15,560.00) and Streets Division's Capital Sidewalk Improvements ($10,000.00).
Type of Item: (please mark with an 'Y)
Public Hearing
For Clerk's Dept Use:
Ordinance First Reading
Consent Agenda
Ordinance Second Reading
Public Hearing
Resolution
Regular Agenda
X Commission Approval
Discussion & Direction
Original Document/Contract Attached for Execution by City Clerk
X Original Document/Contract Held by Department for Execution
Reviewed by City Attorney
N/A
Reviewed by Finance Dept.
N/A
Reviewed by ( )
N/A
2
9%upor�
To:
From:
Date:
Re:
Sch
C • # fi
City of Ocoee
Schuller Contractors Inc.
8/28/2014
Floral Street Sidewalk Improvements
Richard,
The break down on cost for the above referenced project is as follows:
• $ lo,000 for the proposed sidewalk installation
• $ 15,56o for road and drainage repairs
• Total Job: $25,560.00
Thanks
Jonathan Jaiseiwcz
Project Manager
407- 509 -0803
Campanale, Richard
From: Campanale, Richard
Sent: Monday, May OS, 2014 10:22 AM
To: 'majid @apec.us'; Elizabeth Diaz (Elizabeth @apec.us); Chris Sousa (chris.sousa@atlantic-
civil.com); James Thompson (barracudabc @embargmail.com); Travis Greer
(travis @brittconstructioninc.com); 'schullercontract @aol.com'
(schullercontract @aol.com); 'David Stalowy'; info @mvbec.com;
'estimating @pcginc.org'; jeff suberman @rubybuilders.com; jeff @sbsfl.com
Subject: Floral Sidewalk Improvements
Morning Contractors:
City has reviewed the bids prepared and submitted for the above referenced project. The apparent low bidder is
Schuller Contractors. The following is a summary of the bids evaluated;
Schuller Contractors - $25,560.00
Atlantic Civil - $31,532.00
Barracuda Building - $32,948.00
CFE - $38,231.00
Thank you all for bidding, The City will be in contact with Schuller Contractors to discuss the project schedule...
Regards
Richard Campanale, P.E.
Street and Stormwater
Operations Manager
(407) 905 -3170 ph
(321) 281 -7025 cell
mill
vu
LIJ
S
4
r-
C
r,
.�
Q
43 ; 44 45
46
.
_
I
w
5Q 50 I
50 12 118
- - - m
I -y
-_- FLORAL_ -- TILT
- i
-- s -
-
RESTORE'EXISTING BRICK _
CONSTRU aCONCRETE SIDWALK CONSTRUCT DRIVES 6" THICK,
CN
CONSTRUCT FDOTTYPE'D' ALONG CURBING AND DRIVES 11
6" RISER CURB
5' WIDE, TYPICAL
t
•
V t1 `
1
��"' -' "� RELOCATE LANDSCAPING BRICK
6' OFF ROADWAY FOR NEW SIDEWALK
i
» RELO I-AE S REEi LIGHT ANO RISER
6` OFF ROADWAY FOR NEW SIDEWALK
-
.. e
..
a .e • • - • a -' -
•
339'
a2 81 -
55.72. ?' >• 14�.L 47 w
CONNECT SIDEWALK, >
$'ORE DISTURBED AREAS 1
_
MATCH EXISTING GRADE
64
49
Li m
_
-
QQ
,°
63 L
55.72
82