AGENDA ITEM COVER SHEET
Contact Name:
Contact Number:
Bob Zaitooni
6002
Subject: Change Order #1 to Britt Construction for Public Works Building
Background Summary:
This Change Order #1 in the amount of $27,296.77, is for the addition of items not included in the original
bid which include (1) additional electrical circuits for the hydraulic lifts, (2) additional circuits for the
emergency generator, (3) additional NC unit for the sign shop, and (4) change from standard galvanized roof
to factory color panels. This time extension will also require an additional 52 days which will move the final
completion date to August 21,2006.
Issue:
City Commission to approve Change Order #1 to Britt Construction Inc. for Public Works Building
Recommendations
Staffrespectfully requests that City Commission approve Change Order #1 for $27,296.77 and 52 days additional time
to Britt Construction, Inc., and authorize the Mayor and City Clerk to execute the Change Order.
Attachments:
Change Order # 1
Financial Impact:
Funds have been programmed and are available from the project budget.
Type of Item:
o Public Hearing
o Ordinance First Reading
o Ordinance First Reading
o Resolution
o Commission Approval
o Discussion & Direction
Original Document/Contract Attached for Execution by City Clerk
Original DocumenUContract Held by DepartmenUor Execution
For Clerk's OeDt Use:
[8J Consent Agenda
o Public Hearing
o Regular Agenda
o
o
o N/A
o N/A
o N/A
Reviewed by City Attorney
Reviewed by Finance Dept.
Reviewed by ( )
Commissioners
Gary Hood. District 1
Scott Anderson. District 2
Rusty ,Johnson. District :3
,Joel F. Keller. District 4
Mayor
S. Scott Vandenrrift
City Manag-er
Robert Frank
STAFF REPORT
TO:
The Honorable Mayor and City Commissioners
FROM:
Robert Zaitooni, Director of Public Works
DATE:
May 8, 2006
RE:
Change Order #1 to Britt Construction, Inc. for Public Works Building
ISSUE
Should the City Commission approve Change Order #1 to Britt Construction, Inc., for $27,296.77 and 52 days
time extension for additional work for the Public Works building?
BACKGROUNDIDISCUSSION
This Change Order #1 for $27,296.77, is for the addition of items not included in the original bid which include
(10 additional electrical circuits for the hydraulic lifts, (2) additional circuits for the emergency generator, (2)
additional individual A/C unit for the sign shop, and (4) change from standard galvanized roof to factory color
panels. This change order requires an additional 52 days time extension which will move the final completion
date to August 21, 2006.
Funds have been programmed and are available from the project funds.
RECOMMENDATION
Staff respectfully requests that City Commission to approve the Change Order #1 to Britt Construction, Inc., for
$27,296.77 and 52 days time extension, and authorize the Mayor and the City Clerk to execute the Change
Order.
CITY OF OCOEE
Department of Public Works
301 Maguire Road
Ocoee, Florida 34761.2258
CHANGE ORDER NO. #1
CITY OF OCOEE
Public Works Pre-Eng:ineered Building:
BID # B05-09R
CONTRACTOR: Britt Construction, Inc.
AGREEMENT DATE: November 1,2005
The following changes are hereby made to the CONTRACT DOCUMENTS.
Original contract amount
$ 876,142.00
Current contract adjusted by previous change order
$ 876,142.00
Net Increase Resulting from this change order
$ 27,296.77
The current contract amount including this change order
$ 903,438.77
ORIGINAL CONTRACT TIME:
180 calendar days from notice-to-proceed date of January 2, 2006
Original completion date June 30, 2006
CONTRACT TIME EXTENTION:
Net 52 calendar days increase for Change Order #1
New completion date: August 21, 2006
SCOPE OF WORK FOR CHANGE ORDER #1
This Change Order #1 is for the purpose of the additional electrical circuits not included in original bid for (1)
electrical circuits for the hydraulic lifts in Fleet Maintenance area, (2) additional circuits for the emergency power
system, (3) additional individual A/C unit for the sign shop, and (4) change from standard galvanized roof panels to
factory color panels.
APPROVAL AND CHANGE AUTHORIZATION
This proposed change to the Contract is to be approved by the Ocoee City Commission.
Acknowledgements:
The aforementioned change, and work affected thereby, is subject to all provisions of the original contract not
specifically changed by this Change Order; and,
It is expressly understood and agreed that the approval of the Change Order shall have no effect on the original
contract other than matters expressly provided herein.
CONTRACTOR acknowledges, by its execution and acceptance of this Change Order, that the adjustments in
contract amount and time shown hereon constitute full and complete compensation and satisfaction for all costs and
modifications of performance time incurred by the CONTRACTOR as a result of this Change Order. No other
claim for increased costs of performance or modifications of time will be granted by the OWNER for the Work
covered by this Change Order. The CONTRACTOR hereby waives and releases any further claims for cost or time
against the OWNER arising from or relating to the matters or Work set forth or contemplated by this Change Order.
APPROVED BY:
CITY OF OCOEE, FLORIDA
ACCEPTED BY:
BRITT CONSTRUCTION, INC.
By:
By:
S. Scott Vandergrift, Mayor
Signature
Date:
Name:
Title:
Date:
ATTEST:
Beth Eickenberry, City Clerk
(SEAL)
FOR USE AND RELIANCE ONLY BY THE
CITY OF OCOEE, APPROVED AS TO FORM
AND LEGALITY THIS DAY OF
,2006.
APPROVED BY THE OCOEE CITY
COMMISSION IN A MEETING HELD ON
, 2006 UNDER
AGENDA ITEM NO.
FOLEY & LARDNER LLP
By:
City Attorney
britt construction inc.
cbc034413
post office box 651 - oakland, f10rida 34760-0651
phone 407-877-0000
fax 407-877-0014
10 March, 2006
City of Ocoee
150 North Lakeshore Drive
Ocoee, Florida 34761
n~"~.~_~~. 1':..... _& n__~_ ,"on!:: nno
n.OIOlOII\"O. ...,n.y VI "''''VGG - ...~v.wr-v;;;..""
The following are changes to the above-mentioned contract. (see below)
(COP #02)
Gentlemen:
We are pleased to offer a proposal for Equitable Adjustment in accordance with section 01035
of the contract documents. The following is a recapitulation of the costs associated with this
work. Applicable detail and/or subcontractor proposal is attached (when applicable).
Electrical Changes
$16,944.00
G.C. Overhead & Profit 7%
1,186.08
Total Change
$18,130.08
We request an additional amount of time (5) days.
Should you have any questions, please do not hesitate to call me.
Respectfully Yours,
8.20 STRUCTION, INC.
Steve Brown
Vice President
Attachment(s):
Fax Copy:
Disk File:
Detail Sheets
N/A
\ \proiects\OcoeeROC\COPs\cop02.doc
britt construction inc.
cbc034413
post office box 651 - oakland, f10rida 34760-0651
phone 407-877-0000
fax 407-877-0014
10 March, 2006
City of Ocoee
150 North Lakeshore Drive
Ocoee, Florida 34761
o_~_...____. ,,:~.. _~ ^____ .u.on~ ^^rt
n.o ,,;:; 1 OlivO. \JILY VI V'"'VG"G" - rrgvi,IP-V;;'r..
The following are changes to the above-mentioned contract. (see below)
(COP #03)
Gentlemen:
We are pleased to offer a proposal for Equitable Adjustment in accordance with section 01035
of the contract documents. The following is a recapitulation of the costs associated with this
work. Applicable detail and/or subcontractor proposal is attached (when applicable).
52 Additional Days
Zero
G.C. Overhead & Profit 7%
Zero
Total Change
Zero
We request an additional amount of time (see above) days.
Should you have any questions, please do not hesitate to call me.
Respectfully Yours,
BRITT CONSTRUCTION, INC.
~&~
Steve Brown
Vice President
Attachment( s):
Fax Copy:
Disk File:
Detail Sheets
N/A
\ \proiects\OcoeeROC\COPs\cop03.doc
britt construction inc.
cbc034413
post office box 651 - oakland, f10rida 34760-0651
phone 407-877-0000
fax 407-877-0014
26 January, 2006
City of Ocoee
150 North Lakeshore Drive
Ocoee, Florida 34761
Cofo..o...."o. I"i+.. ^(; n,,^^^ _ #Cnl::_nOD
I ''JI"lvll\.lV. ",."y "III ",",,'VV'fiirOV - rr..........."'-"V'.,
The following are changes to the above-mentioned contract. (see below)
(COP #01)
Gentlemen:
We are pleased to offer a proposal for Equitable Adjustment in accordance with section 01035
of the contract documents. The following is a recapitulation of the costs associated with this
work. Applicable detail and/or subcontractor proposal is attached (when applicable).
G.C. Overhead & Profit 7%
$3,843.00
2,891.00
400.00
$7134.00
(3,567.00)
$3,567.00
249.69
Painted Roof
20 framed openings 3' x 4' w/trim
Add 1 - 3070 walk door
$7134.00 divided by 2 = $3,567.00
/~ ""-,
/~
Total Change
( $3,816.69
\
We request an additional amount of time (7) days.
Should you have any questions, please do not hesitate to call me.
Respectfully Yours,
BRITT CONSTRUCTION, INC.
A
Steve Brown
Vice President
Attachment(s):
Fax Copy:
Disk File:
Detail Sheets
N/A
\\proiects\OcoeeROC\COPs\cop01.doc
britt construction incs
cbc034413
post office box 651 - oakland, florida 34760-0651
phone 407-877-0000
fax 407-877-0014
25 April, 2006
City of Ocoee
150 North Lakeshore Drive
Oeoee, Florida 34761
Reference: City of Ocoee - #B05-09R
The following are changes ta the 8bcvs-mG~t:on6d contract (see be!ovv)
....1 COP #04)
,
Gentlemen:
We are pleased to offer a proposal for Equitable Adjustment in accordance with section 01035
of the contract documents. The following is a recapitulation of the costs associated with this
work. Applicable detail and/or subcontractor proposal is attached (when applicable).
AlC Sign Shop
5,000.00
G.C. Overhead & Profit 7%
350.00
Total Change
5,350.00 ..... 1 s-~ . I;:)~
~
We request an additional amount of time (5-five) days.
Should you have any questions, please do not hesitate to call me.
Respectfully Yours,
4fJt;,joac
BRiT?~.., NST.RUCTION, INC.
4~~
Steve Brown
Vice President