AGENDA ITEM COVER SHEET
Meeting Date: July 7, 2015
Item # 3
Reviewed By:
Contact Name: Charles K. Smith, P.E. Department Director: Chart-; ,
Contact Number: 407-905-3159 City Manager: Robert Fra ,;,�/���/`�-I
Subject: Ocoee West Transmission System Lift Station #10 and #12 Modifications
Background Summary:
As part of the Ocoee West Transmission System Project, and in conjunction with the State Road 50 widening
project, sewer flows from the South and North Maguire Road areas and along State Road 50 West of Bluford
Avenue shall be temporarily directed to the gravity collection system on the north side of State Road 50 until the
Ocoee West Transmission Project is completed. To ensure the redirected flows can be accommodated by the
gravity system, three (3) lift stations' ( #10, #12 and #62) flows need to be throttled in concert with each other.
To accomplish this work, each station needs to be equipped with Variable Frequency Drives (VFDs) and Radio
Terminal Units (RTUs) capable of communicating with each other through the Alarm Monitoring Control Center.
Lift Station #62, for which construction shall begin with the next 45 days, is planned to be outfitted accordingly.
Rehabilitation of Lift Station #10 shall be completed in July 2015, and it will need to be retrofitted with VFDs and
have its RTU (SciText SCADA programmable logic controller) reprogrammed. Lift Station #12 is a triplex
station (three pumps) which requires three (3) VFD retrofits and the conversion of its RTU to a SciText system.
The City's standard for lift stations is the SciText SCADA programmable logic controller system.
Issue:
Should Commission approve the modifications to Lift Station #10 and Lift Station #12 to accommodate flows to
the existing gravity system along State Road 50 west of Bluford Avenue until the Ocoee West Transmission
Project is completed?
Recommendations
Staff recommends that Commission authorize the City Manager to contract with Sanders Company, Inc. in the
amount of$29,025.00 to supply the equipment and labor to convert Lift Station #10 and Lift Station #12 to VFD
stations running on the Department's Alarm Monitoring Control Center.
And Attachments:
Proposal from Sanders Company, Inc. for Scope of the Project.
Financial Impact:
Cost associated with the proposed work to Lift Station #10 and #12 totals $29,025.00. The Department's
Approved Fiscal Year 2015 budget includes $459,270.00 for the Ocoee West Transmission System
Construction (G/L account 401-531-00-6302), of which $329,684.23 remains unencumbered. Therefore, after
this approval, $300,659.23 will remain available for additional work on the transmission project.
Type-of Item: (please mark with an "x")
Public Hearing For Cle►k's Dept Use:
Ordinance First Reading X Consent Agenda
Ordinance Second Reading Public Hearing
Resolution Regular Agenda
X Commission Approval
Discussion&Direction
Original Document/Contract Attached for Execution by City Clerk
Original Document/Contract Held by Department for Execution
Reviewed by City Attorney _ / N/A
Reviewed by Finance Dept. _ �Jjd/V- N/A
Reviewed by 0 v' N/A
2
411 SANDERS
COMPANY. INC.
2816 Southeast Monroe Street
Stuart, Florida 34997
772.220.2900
Cost Proposal
Date: June 25, 2015
Project: Lift Station modifications
City of Ocoee Tom King:
In accordance with the attached Terms and Conditions, Sanders Company is
pleased to offer the following materials/services for the above referenced project.
PRICE, DELIVERY AND TERMS OF OFFERING
Prices submitted are for equipment/services specifically listed within this Scope of
Supply which constitute our complete offering.
Scope of the Project
Sanders Company is providing an cost proposal for the following scope of work.
When looking at lift stations 10, 12, and consumers we can only flow 1500gpm
total from all three stations. We reviewed utilizing scada to lock out station based
upon level needing to pump and found several issues.
In conjuction with the futer lift station 32 (Consumers Court), Our idea is to add
VFDs to lift station 10 and 12, adjust speed to limit flow from all stations to an
acceptable level.
Below is the cost:
2 - 10-hp N4X VFD $2,475 each
3 - 20-hp N4X VFD $3,725 each
5 - Labor to install VFD $1,150 each
5 - Material to install $225 each
1- VFD Scitext 1062 $3,825 each
1- Add IO to existing 1062 $450 each
1-Program exist.1062 to VFD $1,000 each
1 - Level Transducer $750 each
TOTAL $29,025.00
Sanders Company will provide a complete turnkey project to the City including
Engineering, Design, Fabrication, Installation, Setup, Training, and Superior
Support.
SCI's price includes:
Field Installation
Programming
Start-up and Training
PAGE 1 OF 3
SANDERS
COMPANY, INC.
2816 Southeast Monroe Street
Stuart, Florida 34997
772.220.2900
Engineering
Submittals, Operation & Maintenance Manuals
1-Year Warranty
Factory Check Out
SCI's price does not include: Taxes
Cost Proposal: See Above PLUS TAX if applicable. FOB factory with freight
allowed to jobsite, shipped via standard commercial carrier.
DELIVERY: 8-10 weeks after complete and acceptable approval is received in the
Stuart offices of Sanders Company, Inc.
SUBMITTAL FOR APPROVAL: 5 - 7 weeks after acceptable purchase Agreement
is received in the Stuart offices of Sanders Company, Inc.
TERMS OF PAYMENT
Based on initial and continuing credit approval by Sanders Company, Inc., the
following payment terms apply: Net 30
SCI form 575 Terms and Conditions, which is attached, is an integral part
of this offering.
Thank you for the opportunity to offer this Scope of Supply.
Please contact me with any questions and/or comments regarding this offering.
Rom RoOi,ette
Sales
Cell 321-229-7643 Stuart office 800-247-0880
Ron @Mrsewage.com
PAGE2OF3
SANDERS
COMPANY, INC.
2816 Southeast Monroe Street
Stuart, Florida 34997
772.220.2900
TERMS AND CONDITIONS
Sanders Company, Inc.
2816 SE Monroe St
Stuart, Fl 34997
AN ORDER WILL CONSTITUTE A CONTRACT BETWEEN THE COMPANY AND THE
BUYER WHEN ACCEPTED IN WRITING BY THE COMPANY AT ITS HOME OFFICE
IN STUART FLORIDA. A CONTRACT RESULTING FROM THE ACCEPTANCE OF AN
ORDER MAY BE CANCELED OR ALTERED BY THE BUYER ONLY IF AGREED TO
IN WRITING BY THE COMPANY AT ITS HOME OFFICE SUBJECT TO PAYMENT OF
REAONABLE CHARGES NECESSARY TO PROTECT THE COMPANY FROM LOSS.
UNTIL ACCEPTED, AS PROVIDED HEREIN,AN ORDER SHALL CONSTITUTE AN
OFFER TO PURCHASE. NEITHER THE ACCEPTANCE OF ANY DEPOSIT MADE
WITH AN ORDER NOR THE CASHING OF ANY CHECK OR OTHER INSTRUMENT
THEREFOR, NOR THE HOLDING OF SUCH DEPOSIT BY THECOMPANY SHALL BE
DEEMED AN ACCEPTANCE OF AN ORDER, BUT IF THE ORDER IS NOT
ACCEPTED, THE COMPANY WILL PROMPTLY REFUND SUCH DEPOSIT. THE
COMPANY SHALL NOT BE LIABLE FOR ANY FAILURE TO MAKE DELIVERY OR
OTHER DEFAULT BY REASON OF ANY OCCURRENCE OR CONTINGENCY
BEYOND THE REASONABLE CONTROL OF THE COMPANY OR OF ANY OF ITS
SOURCES OF SUPPLY. IN THE EVENT OF ANY SUCH OCCURRENCE OR
CONTINGENCY THE COMPANY MAY EXTEND DELIVERY SCHEDULES OR MAY,
AT ITS OPTION, CANCEL THE ORDER IN WHOLE OR IN PART WITHOUT LIABILITY
OTHER THAN TO RETURN ANY DEPOSIT OR PREPAYMENT. SHOULD THE
WHOLE ORDER BE CANCELED, THE BUYER WILL REIMBURSE THE COMPANY
FOR ALL TAXES, EXPENSES AND SIMILAR CHARGES BASED UPON OR
MEASURED BY THE PRODUCTION, STORAGE, SALE, TRANSPORTATION OR USE
OF THE PRODUCTS DESCRIBED HEREIN.THE COMPANY SHALL NOT BE BOUND
BY ANY TERMS, CONDITIONS, OR REPRESENTATIONS WHICH ARE NOT STATED
HEREIN. THE COMPANY SHALL NOT BE OBLIGATED TO PERFORM HEREUNDER
IF AT ANY TIME: BUYER'S CREDIT RATING BECOMES IMPAIRED. THE COMPANY
SHALL RETAIN A SECURITY INTEREST IN THE PRODUCTS/SERVICES SUPPLIED
HEREUNDER TO SECURE PERFORMACE OF BUYER'S OBLIGATIONS AND BUYER
SHALL EXECUTE ALL FINANCING STATEMENTS AND OTHER INSTRUMENTS
THAT THE COMPANY DEEMS NECESSARY TO PERFECT ITS SECURITY
INTEREST. IF THE BUYER DEFAULTS IN ANY OF ITS OBLIGATIONS HEREUNDER
OR IS UNABLE TO PAY ITS DEBTS AS THEY MATURE,THE COMPANY SHALL
HAVE THE RIGHT TO REPOSSESS THE PRODUCTS WITH OR WITHOUT RESORT
TO LEGAL PROCESS. ACCEPTANCE OF THIS SUBMISSION ACKNOWLEDGES
THAT EQUIPMENT LISTED IS IN COMPLIANCE WITH THE PLANS AND
SPECIFICATIONS OR IS ACCEPTED AS AN EQUAL TO THE PLANS AND
SPECIFICATIONS. THE FOREGOING TERMS AND CONDITIONS WILL PREVAIL
NOTWITHSTANDING ANY VARIANCE WITH THE TERMS AND CONDITIONS OF
BUYER'S ORDER FOR THE PRODUCTS.