HomeMy WebLinkAboutItem # 05 Change Order No. 4 - Public Works Bldg.
AGENDA ITEM COVER SHEET
Meeting Date: November 7, 2006
Item # 5
Contact Name:
Contact Number:
Steve Krug
6002
Reviewed By:
Department Director:
City Manager:
Subject: Change Order #4 to. Britt Construction for Public Works Building
Background Summary:
This Change Order #4 in the amount of $11,871.44, is for the addition of items not included in the original bid which
includes (1) completion of wet tap, underground work and back flow preventor for the fire protection service
connection per State Fire Codes and (2) additional electrical and plumbing required to revise the ice machine location.
These two changes include 32 additional calendar days to the contract for completion. In addition the contractor
requested in a letter that the City grant them an open number of days for completion of the facility. Staff is
recommending that we grant them 21 extra days and ask them to submit for more days at a later date if it becomes
necessary. Total number of calendar days added to the project with Change Order #4 is 53 days. With the funds
remaining for the Public Works Facility budget of $2,795.12 it is necessary to seek additional funding in the amount of
$9,076.32. Staff is proposing that the $10,000 budgeted for the gate system revision at Public Works be utilized for this
purpose as the gate item will be included in a future security access plan at the Public Works Complex being reviewed
by the Police Department for a standard City wide implementation. This project is budgeted in the Public Works
Departments Maintenance Operations Division in line item 001-519-00-6302.
Issue:
Should the City Commission approve Change Order #4 to Britt Construction, Inc. in the amount of $11,871.44 for the
Public Works Building and authorize the funding be taken from the Public Works gate project in line item 001-519-00-
6302.
Recommendations
Staff recommends City Commission approve Change Order #4 to Britt Construction, Inc. for $11,871.44, allow the
additions of 53 calendar day time extension, approve there-appropriation ofthe funding in line item 001-519-00-6302,
and authorize the Mayor and City Clerk to execute the Change Order.
Attachments:
Change Order Form, Britt Construction Change Order Info
Financial Impact:
Funds are available from the budgeted project funds for the Public Works Facility with additional funds in the amount
of$9,076.32 from the Gate System at Public Works Facility in line item 001-519-00-6302.
Type of Item:
o
o
o
o
[8]
o
Public Hearing
Ordinance First Reading
Ordinance First Reading
Resolution
Commission Approval
Discussion & Direction
For Clerk's Deof Use:
[8] Consent Agenda
o Public Hearing
o Regular Agenda
[8J Original Document/Contract Attached for Execution by City Clerk
o Original Document/Contract Held by Department for Execution
Reviewed by City Attorney
Reviewed by Finance Dept. ~ ~ ff
Reviewed by ( )
D N/A
rg) N/A
D N/A
CITY OF OCOEE
Department of Public Works
301 Maguire Road
Ocoee, Florida 34761-2258
CHANGE ORDER NO. #4
CITY OF OCOEE
Public Works Pre-Engineered Building
BID # B05-09R
CONTRACTOR:
Britt Construction, Inc.
AGREEMENT DATE:
November 1, 2005
The following changes are hereby made to the CONTRACT DOCUMENTS.
Original contract amount $ 876,142.00
Current contract adjusted by previous change order $ 903,438.77
Net Increase Resulting from this change order $ 11,871.44
The current contract amount including this change order $915,310.21
ORIGINAL CONTRACT TIME:
180 calendar days from notice-to-proceed date of January 2, 2006
Original completion date June 30, 2006
CONTRACT TIME EXTENTION:
Net 52 calendar days increase for Change Order #1
New completion date: August 21, 2006
Net 21 calendar days increase for Change Order #2
New completion date: September 11, 2006
Net 5 calendar days increase for Change Order #3
New completion date: September 16, 2006
Net 53 calendar days increase for Change Order #4
New completion date: November 7, 2006
SCOPE OF WORK FOR CHANGE ORDER #4
This Change Order #4 in the amount of $11,871.44, is for the addition of items not included in the original bid
which includes (1) completion of wet tap and underground work for sanitary sewer connections and (2) additional
electrical to change from supply line in Men’s restroom to ice machine location. These two changes include 32
additional calendar days to the contract for completion. In addition the contractor requested in a letter that the City
grant them an open number of days for completion of the facility. Staff is recommending that we grant them 21 extra
days and ask them to submit for more days at a later date if it becomes necessary. Total number of calendar days
added to the project with Change Order #4 is 53 days.
APPROVAL AND CHANGE AUTHORIZATION
This proposed change to the Contract is to be approved by the Ocoee City Commission.
Acknowledgements
:
The aforementioned change, and work affected thereby, is subject to all provisions of the original contract not
specifically changed by this Change Order; and,
It is expressly understood and agreed that the approval of the Change Order shall have no effect on the original
contract other than matters expressly provided herein.
CONTRACTOR acknowledges, by its execution and acceptance of this Change Order, that the adjustments in
contract amount and time shown hereon constitute full and complete compensation and satisfaction for all costs and
modifications of performance time incurred by the CONTRACTOR as a result of this Change Order. No other
claim for increased costs of performance or modifications of time will be granted by the OWNER for the Work
covered by this Change Order. The CONTRACTOR hereby waives and releases any further claims for cost or time
against the OWNER arising from or relating to the matters or Work set forth or contemplated by this Change Order.
APPROVED BY: ACCEPTED BY:
CITY OF OCOEE, FLORIDA BRITT CONSTRUCTION, INC.
By: By:
S. Scott Vandergrift, Mayor Signature
Date: Name:
Title:
Date:
ATTEST:
Beth Eickenberry, City Clerk
(SEAL)
FOR USE AND RELIANCE ONLY BY THE APPROVED BY THE OCOEE CITY
CITY OF OCOEE, APPROVED AS TO FORM COMMISSION IN A MEETING HELD ON
AND LEGALITY THIS DAY OF , 2006 UNDER
, 2006. AGENDA ITEM NO. .
FOLEY & LARDNER LLP
By:
City Attorney
britt construction inc.
cbc034413
post office box 651 - oakland, f10rida 34760-0651
phone 407-877-0000
fax 407-877-0014
16 October 2006
City of Dcoee
150 North Lakeshore Drive
Dcoee, Florida 34.761
Reference: City of Ocoee - #B05-09R
The following are completion of Wet Tap - Underground Work (see below) (COP #13)
Gentlemen:
We are pleased to offer a proposal for Equitable Adjustment in accordance with section 01035
of the contract documents. The following is a recapitulation of the costs associated with this
work. Applicable detail and/or subcontractor proposal is.attached (when applicable).
Underground Work-Davy Fire
10,700.00
749.00
G.C. Overhead & Profit 7%
Total Change
11,449.00
We request an additional amount of time (~c) days.
Should you have any questions, please do not hesitate to call me.
Respectfully Yours,
BRIT~NSTRUCTION, INC.
4,L-~
Steve Brown
Vice President
Attachment( s):
Fax Copy:
Disk File:
Detail Sheets
N/A
\ \proiects\OcoeeROC\CDPs\cop13.doc
FRO'1 : DAVY F J RE PROTECT J ON J NC
FAX NO. : 407 679 1733
Oct. 27 2006 10:10AM P2
D. V, FIRE PROTECTION,INC.
~
.
,
P.O. 80X 880490 ORLANDO. FLORIDA 32_
(401) $1N332 FAX (407) 678-1733
Proposal
October 27, 2006
Page 1 Of 1.
Proposal Submitted -1'0
City ofOcoec
301 Maguire Road
Ocoee, Florida 34761
Work. To Be Performed A.t
Ocoee Public Worb Building
Attn: Terry Reed
Phone: 407.905-3170
Fax: 401-905.)116
We hereby propose tofumish the tabor and materials necessary for the completion of: Wet tap
existing 8" PVC underground water main that is approximately 35 LF from buUdin.g. 'nstall a
new 4" Double detector check with tamper switches also one rough brass 4"x21l2"x2112" fire
Department connection mounted on discharge side of backflow prevcotor. Tic into existing 4"
stub out from building. Shop drawings to be submitted to the city ofOc:oee for approval.
Our price for this work will be: TEN THOUSAND SEVEN HUNDRED DOLLARS
($10,7..00) .
.EJduiOns from 01lr work wiD be: ReJDoval or replacement of existing sidewalk.
Accepted 8y:.~.__..
Respectfully Submitted ~
~Rt4~ .~.
Tom Wingntl:~
Name:
'Title :
britt construction inc.
cbc034413
post office box 651 - oakland, f10rida 34760-0651
phone 407-877-0000
fax 407-877-0014
25 October 2006
City of Ocoee
150 North Lakeshore Drive
Deoee, Florida 34761
Reference: City of Ocoee - #BOS-09R
The following is a change for supplying ~ine from Men's bathroom to new location for ice
machine (See below) (COP #15)
Gentlemen:
We are pleased to ofter a proposal for Equitable Adjustment in accordance with section 01035
of th,e contract documents. The following is a recapitulation of the costs associated with this
work. Applicable detail and/or subcontractor proposal is attached (when applicable).
Supplying new line (Ross)
394.80
G. C. Overhead & Profit 7%.
27.64
Total Change
422.44
We request an additional amount of time ( '2....) days.
Should you have any questions, please do not hesitate to call me.
Respectfully Yours,
Steve Brown
Vice President
Attachment( s):
Fax Copy:
Disk File:
Detail Sheets
N/A
- \ \proiects\OcoeeROC\COPs\cop 15.doc
brittconstruction inc.
cbc034413
post office box 651 . oakland, florida 34760-0651
phone 407.877.0000
fax 407.877.0014
October 16, 2006
City of Ocoee
150 North Lakeshore Drive
Ocoee, Fl. 34761
Re: Additional Days - B05-09R
To the City of Ocoee:
Please be advised that as of October 11, 2006 we are delayed by the City of Ocoee.
Weare requesting additional days to be granted to our contract and the reasons are
as follows:
· Lift Station
· Back-Flo Preventer
· Electrical Conduit not inspected under the asphalt
Please let us know in writing that these additional days will be granted. Also keep in
mind that this request has no monetary amount, just days.
Sincerely,
Britt Construction, Inc.
Steve Brown
Vice President