Background Summary:
In order to continue with our efforts to provide customers cost effective water utility services and conserve
valuable potable water, the City of Ocoee has been maturing the North Service Area by construction of a
perimeter loop of the area. Currently the loop is constructed on the north and west sides and portions along the
south and east sides have been completed. Refer to the attached Figure 1 to see the looping and proposed
links to be completed. Having a mature reclaimed system will allow the City to adequately provide reclaimed
water to the current neighborhoods in the North Part of the City and the neighborhoods currently under
construction such as Crown Pointe Cove, The Preserve at Crown Point, Westyn Bay Commercial, Forest Lake
Estates, Arden Park, Oak Trail Reserve, and McCormick Reserve.
City Staff working with the developer of the McCormick Reserve Subdivision, Ocoee II, LLC, have conditionally
agreed to have Ocoee II, LLC construct a portion of the loop (east side) in the Clarke Rd right-of-way (Segment
3 in Figure 1). The City has agreed to reimburse the developer for constructing the reclaimed water extension.
The portion of the main to be constructed by McCormick Reserve will be 940 linear feet of eight (8) inch
reclaimed water pipe and will connect the existing main from the west entrance to Kensington Manor (Whitefriar
Dr.) to a future main to be constructed by the Arden Park North Development.
Attached is the IBI Group's Proposal (dated September 19, 2016) for the eight (8) inch reclaimed line on Clarke
Rd which includes a construction break down by ",The Briar Team" Site Developer - Contract Cost (signed
September 16, 2016) in the amount of $47,293.75. The cost appears to be in line with other costs recently
experienced by the City on projects similar in nature. Also attached is the Wholesale Reclaimed Water Service
Area Map.
This extension of the City's Reclaimed Water System will move the City one step closer to having a mature
reclaim system. A mature reclaimed water system will help reduce the demand for potable water, decrease
diversion of freshwater from sensitive ecosystems, reduce the need for chemical fertilizers on yards, and will
maintain groundwater recharge of our natural aquifer.
Issue:
Should the City accept the IBI Group's proposal for extending reclaimed water service on Clarke Road in the
amount of $47,293.75 to be reimbursed by the City?
Recommendations
The Utilities Department recommends the acceptance of the Proposal submitted by the IBI Group for the
reclaimed water main extension on Clarke Road and that the funds be released to reimburse the IBI Group
accordingly ($47,293.75).
Financial Impact:
Funds to be used by this project will be expended from
funds available due to the favorable bid of the Lake
where $1,046,125 was programmed for the project.
Type of Item: (please mark with an 'V)
Public Hearing
Ordinance First Reading
_ Ordinance Second Reading
_ Resolution
X Commission Approval
Discussion & Direction
(408-535-10-6302) in the amount of $47,293.75 using
Olympia Neighborhood in the amount of $576,429.50,
Original Document/Contract Attached for Execution by City Clerk
Original Document/Contract Held by Department for Execution
Reviewed by City Attorney
Reviewed by Finance Dept.
Reviewed by ()
2
For Clerk's Dept Use:
X consent Agenda
Public Hearing
Regular Agenda
N/A
N/A
N/A
Lake /jpapJta Beach Ave
..
Nal Dr
Orange Co' ty Utilities Northwest
Water Declamation Facility
N
Section or,
u
Lea.
W E
c c
E
`
m rn O u 0 mc
r Paradlse E t° a
OCU Point of
0 1,000 2,000
Y `
1
^ ConnectionOWE
e
b'Hotghtsy 1s„
Valley Or
ts^
krtwoiw
S,.,,.
12"
1raoI LOW
LEGEND
Future Storage and
Phase II Future RW Facility
Repump Facility - Site A
4sRe suaa
Reclaimed Pipe
Segment I Pipe (Existing)
Segment 2 Pipe (In Construction
WHOLESALE SERVICE AREA
— Segment 3 Future Pipe
`o
— Segment 4 Future Pipe
012"
— Segment 5 Future Pipe
0
Future Storage and
12"
_
— Existing Pipe
—Existing Golf Course Pipe
-/
Repump Facility- Site B
:
■ ■ ■ Sub -Service Areas
,,,■,
___ � _�
16" 16.112
■■ ■•*Ir`
Reclaimed Service Area
Lnmi C.
u
12
12"
Geo
Fuliiii,._
c ---
v
CENTR/PL SERVIC,4 �A ,
■
'"
Hak % * n ■ ■ • • ■ ■ ■ ■7"1"R1ktxnl
.
, epee_
" •T 2 nd Ave
H o
u n
nw
City of Ocoee
Wholesale Reclaimed Water Service Area (WRWSA)
Figure 1:1
Existing Infrastructure
G:\Ogis\G:\Ogis\6763-Ocoee North Reclaimed Water Expansion\PDF\WRWSA Reclaimed Plan Update - Figure 2.mxd
IBI Group (Florida) Inc.
IBI 2300 Maitland Center Parkway—Suite 101
Maitland FL 32751 USA
GROUP tel 407 660 2120
fax 407 875 8308
September 19, 2016
Milen Womack
City of Ocoee
150 N Lakeshore Drive
Ocoee, Florida 34761
Re: McCormick Reserve
Dear Milen:
Please find enclosed the revised proposal for the 8 inch reuse line on Clark Road. The following
is a breakdown on the cost of the project:
Item
Cost
Construction Cost
$41,125.00
Engineering
10% $ 4,112.50
Management
5% $ 2,056.25
Tota 1
$ 47,293.75
We will modify the plans as an as -built when the work is complete. Will you please process a
purchase order for the work? Please let me know the City's Staff position to approval the above.
We need to start the work in the next 2-3 weeks, probably prior to the approval of the PO.
Please Jet me know if that will.be a problem from the, City's position. It would also be great to
have the date that the Commission will be able to process and approve the PO.
Thanking you in advance.
Should you have any questions, please feel free to contact me at 407.660.2120.
Best Regards,
(:�ichardCCWohIfarth, P.E.
MCCORMICK RESERVE
(please sign and return)
September 16, 2016
REQUEST FOR CHANGE NUMBER FOURTEEN 1 141 REVISED
TOTAL THIS CHANGE .... 1 $41,125A0
ADD TEN (10) DAYS TO COMPLETION DATE
The items and contingencies of your original contract
will remain in effect and govern this change
APPROVED BY OWNER APPROVED BY CONT OR
T-3 Ocoee, LLC The Briar Team, LLC -
By:
Date: Date: the// e,
4570 Orange Boulevard • Sanford, FL 32771 • 407-321-2773
State Certified Underground Utility Contractor #CUC057145
THIS CHANGE ... , .
$41,125.00
The work covered by this order shall be performed under the same Terms
and Conditions as that included in the
Original Subcontract Revise the scope of Subcontract dated 4127115 to Include all labor, materials,
tools,
equipment and supervision to complete the following:
CHANGES PER OWNER'S DIRECTION
I. REUSE
a) add connect to existing
1 EA
2.65900 •- - •••---•••---
$2,659.00
b) add 8" PVC (DR -18)
940 LF
21.30 •---=---------•••_
$20,022.00
c) add 2" reuse poly stub out
1 EA
810.70 -••-----------------
$810.70
d) add 8" gate valve and accessories
2 EA
1,164.40 ...•-.••--•- ---
$2,328.80
e) add 8" x 8" tee with accessories
1 EA
44880 —----- -.--..........
$448.80
f) add 8" MJ 45" bend with accessories
10 EA
347.40 ........
$3,474.00
g) add 8" MJ 22.5' bend with accessories
2 EA
328.40 -------------------- -
$656.80
h) add 8" MJ 11.25" bend with accessories
2 EA
328.40 •-•..- -- •••••
$656.80
i) add air release valve
2 EA
3,080.00 - ------ ----- ......
$6,160.00
j) add blow off assembly
1 EA
1,078.00 •.------- -----------
$1,078.00
k) add mist. fittings, tracer wire and tape
1 LS
1.76010 ........
$1,760.10
1) add testing
1 LS
1.07000 --•••------•-------
$1,070.00
TOTAL THIS CHANGE .... 1 $41,125A0
ADD TEN (10) DAYS TO COMPLETION DATE
The items and contingencies of your original contract
will remain in effect and govern this change
APPROVED BY OWNER APPROVED BY CONT OR
T-3 Ocoee, LLC The Briar Team, LLC -
By:
Date: Date: the// e,