HomeMy WebLinkAboutItem #03 Approval of Ocoee Crown Point PUD Change Order No. 6 AGENDA ITEM COVER SHEET Meeting Date: December 5, 2006 3 pc 4/A ~~ Item # Contact Name: Contact Number: David A. Wheeler, P.E. 407 -905-3100, ext. 1504 Reviewed By: Department Director: City Manager: Subject: Approval of the Ocoee Crown Point PUD Project Change Order NO.6 Background Summary: The phase 1 infrastructure for the Ocoee Crown Point PUD project included mast armed "School Zone" signage for the Ocoee High School on Ocoee Crown Point Parkway. This signage was to be in addition to the signage and striping that is already present on Ocoee Crown Point Parkway. The existing warnings include the pole mounted flashing lights and the appropriate striping in the roadway and signage along the road. All of this signage and striping is in accordance with the FDOT and Manual of Uniform Traffic Control Devices (MUTCD) standards. VHB, Inc. over interpreted the standards and included the mast armed "School Zone" signage in the design of the project. FDOT Secretary Denver Stutler, Jr., P.E., issued a policy memorandum on May 3, 2006 titled "Establishing School Zones and School Crossings" for FDOT controlled roads. The policy statement explicitly provides that school speed zones may be established only for "public and private elementary, middle schools (Jr. High), or federally funded Headstart facilities providing a full-time education program" (p. 2, Section 1.1). It is similarly explicit in stating that high schools are not eligible for school speed zones, but are more appropriate for alternative measures, such as pedestrian crossing signs or warning signs for a driveway entrance (p. 2, Section 1.2). Even with these reduced traffic control measures, the policy statement cautions against their indiscriminant use: "Traffic control devices are not normally needed at a high school, but when special circumstances occur, they should be addressed on a case-by-case basis, only used when needed, and justified by an engineering study". This policy memorandum has been applied as a regional practice standard for other roadways and can be viewed as the policy guidance established under Section 316.1895, F.S. The deletion of the mast armed "School Zone" signage will result in decrease of $81,479.00 to the project cost. The final cost for the Phase 1 and 1 b infrastructure Projects will $3,836,443.50. This change order will final the Ocoee Crown point PUD Phase 1 Infrastructure Project. Issue: Should the Mayor and City Commissioners approve the Ocoee Crown Point PUD project change order no. 6. Recommendations The Engineering Department recommends that the City Commission approve the deletion of the mast armed "School Zone" signage and authorize the Mayor and City Clerk to execute Change Order no. 6 with Master Site Development, Inc. Attachments: 1) Change Order NO.6 between the City 0 f Ocoee and Master Site Development, Inc. Financial Impact: This change order will result in project cost reduction. Type of Item: (please marl< with an "x'J Public Hearing _ Ordinance First Reading Resolution _ Commission Approval Discussion & Direction For Clerl<'s DeDt Use: _ Consent Agenda _ Public Hearing _ Regular Agenda ~ Original DocumenUContract Attached for Execution by City Clerk _ Original DocumenUContract Held by Department for Execution Reviewed by City Attorney Reviewed by Finance Dept. Reviewed by ( ) N/A N/A N/A CITY OF OCOEE Engineering/Utilities 150 North Lakeshore Drive Ocoee, Florida 34761-2258 CHANGE ORDER NO. #6 CITY OF OCOEE Ocoee Crown Point pun - Phase 1 Infrastructure DATE: November 21,2006 CONTRACTOR: Master Site Development, Inc. AGREEMENT DATE: March 2, 2004 The following changes are hereby made to the CONTRACT DOCUMENTS. Original CONTRACT PRICE Current CONTRACT PRICE ADJUSTED by previous CHANGE ORDER Net Increase Resulting from this CHANGE ORDER The current CONTRACT PRICE including this CHANGE ORDER ORIGINAL CONTRACT TIME: 420 Consecutive Calendar Days from Notice to Proceed Current CONTRACT TIME adjusted by previous CHANGE ORDERS Net Increase Resulting from this CHANGE ORDER Current CONTRACT TIME Including this CHANGE ORDER 00842-1 CHANGES ORDERED: I. GENERAL This change order is necessary to cover changes in the work to be performed under this contract. The GENERAL CONDITION, SUPPLEMENTARY CONDITIONS, SPECIFICATIONS and all parts of the Project Manual listed in Article 1, Defmitions, of the GENERAL CONDITIONS apply to and govern all work under this change order. II. REQUIRED CHANGES Item No.6-A: Deletion of Mast Arm Signage for the High School This change order consists of deletion of the Mast Arm Signage which is not be installed. III. JUSTIFICATION Item No.6-A: Deletion of Mast Arm Signage for the High School The Deletion of the Mast Arm Signage for the High School was based on a review ofFDOT and MUTCD requirements which failed to support such a school speed zone and therefore the need for the Mast Arm Signage. IV. NARRATIVE OF NEGOTIATIONS Deleted based on unit prices. V. PAYMENT Change Order Description Net Increase Unit Unit Price Net Increase Item No. (Decrease) Ouantitv (Decrease) Price Item No. 6-A Deletion of Mast Arm Signage for the High LS ($ 81,479.00) School Total Net Increase Change Order No. #6 ($ 81,479.00) VI. APPROVAL AND CHANGE AUTHORIZATION This proposed change to the Contract is to be approved by the Ocoee City Commission. 00842-2 Acknowledgements: The aforementioned change, and work affected thereby, is subject to all provisions of the original contract not specifically changed by this Change Order; and, it is expressly understood and agreed that the approval of the Change Order shall have no effect on the original contract other than matters expressly provided herein. CONTRACTOR acknowledges, by its execution and acceptance of this Change Order, that the adjustments in Contract Price and Time shown hereon constitute full and complete compensation and satisfaction for all costs and modifications of performance time incurred by the CONTRACTOR as a result of this Change Order and/or relating to or arising out of the reasons and justifications for this Change Order. No other claim for increased costs of performance or modifications of time will be granted by the OWNER for the Work covered by this Change Order. Nothing contained in this action by the City shall be deemed to constitute a waiver or an estoppel to assert its rights or remedies under the Contract Documents nor shall it be deemed to set a precedent for an equitable adjustment for any other materials required by the Work. The CONTRACTOR hereby waives and releases any further claims for cost or time against the OWNER arising from or relating to the matters or Work set forth or contemplated by this Change Order and/or relating to or arising out of the reasons and justifications for this Change Order. RECOMMENDED BY: CITY OF OCOEE. FLORIDA ACCEPTED BY: MASTER SITE DEVELOPMENT. INC. By: By: Signature Signature Date: Date: Title: Title: APPROVED BY: CITY OF OCOEE. FLORIDA By: S. Scott Vandergrift, Mayor Date Attest: Beth Eikenberry, City Clerk FOR USE AND RELIANCE ONLY BY THE CITY OF OCOEE, APPROVED AS TO FORM AND LEGALITY THIS DAY OF ,2006. APPROVED BY THE OCOEE CITY COMMISSION IN A MEETING HELD ON , 2006 UNDER AGENDA ITEM NO. FOLEY & LARDNER By: City Attorney 00842-3