HomeMy WebLinkAboutItem III (B) Approval and Authorization to Execute Change Order No 6, 7 and 8 for Contract with Butler Construction Company for South Water Plant. AGENDA 6-16-92
• • Item III B
t.
4rF4 of Goo‘,• JAMES W.SHIRA,P.E.
CITY ENGINEER/UTILITIES DIRECTOR
150 N.LAKESHORE DRIVE•OCOEE,FLORIDA 34761
(407)656-2322
MEMORANDUM
DATE: June 8, 1992
TO: The Honorable Mayor and Board of City Commissioners
FROM: James W. Shira, P.E.
City Engineer/Utilitie irector
SUBJECT: South Water Plant
Change Order # 6, 7 and 8
Construction of the South Water Plant is now complete.
The attached change orders are for a variety of small items that arose during the final days of
construction.
Change Order Number 6 is a credit in the amount of $7,150.00. This credit is the result of
changing the type of seed used as ground cover, and the deletion of grout in the casing under
the turnpike.
Change Order Number 7 is a cost of$1,824.17 for the installation of insect screens on the large
ventilation louvers in the operations building, modification to a chain-link fence, and several
minor electrical wiring modifications.
Change Order Number 8 is a cost of$1,518.17 for additional 16" D.I.P. 45° elbows that were
required to match field conditions.
Together, these three change orders have a net credit value of$3,807.66. This amount brings
the total change order amount(excluding the$274,000.00 16" water main addition) to$9,795.80
which represents 0.92% of the original contract amount of $1,067,635.00.
rottSe"'
THE PRIDE OF WEST ORANGE
The Honorable Mayor and Board of City Commissioners
June 8, 1992
Page Two
I recommend that the City Commission approve these change order proposals and authorize the
City Engineer to execute Change Order # 6, 7, and 8 in an amount not to exceed ($7,150.00),
$1,824.17 and $1,518.17, respectively.
JWS/jbw
O
* Adjustment as of
Change Order No. 05
I
(Short title of Change Order)
CHANGE ORDER FORM
CITY OF OCOEE
OPROJECT: SOUTH WATER PLANT
I
CHANGE ORDER NO. 06
tDATE: CONTRACTOR: Butler Construction Ca.
tOWNER: CITY OF OCOEE, FLORIDA AGREEMENT DATE:
IThe following changes are hereby made to the CONTRACT DOCUMENTS :
Original CONTRACT PRICE $ 1 ,067,615_00
ICurrent CONTRACT PRICE ADJUSTED by previous CHANGE ORDER* $ 1 ,355,534.38
Net (Increase) (Decrease) Resulting from this CHANGE ORDER $ 7,150.00
rThe current CONTRACT PRICE including this CHANGE ORDER $ 1 ,348,384. 38
ORIGINAL CONTRACT TIME: 240 days Date March 28, 1992
Current CONTRACT TIME adjusted by previous CHANGE ORDERS* Date 4/21/92
Net (Increase) (Decrease) Resulting from this CHANGE ORDER Days
OCurrent CONTRACT TIME Including this CHANGE ORDER Date 4/21/92
CHANGES ORDERED:
I
00842-1 0E-137/WP
I. GENERAL IL
This change order is necessary to cover changes in the work to be
performed under this Contract. The GENERAL CONDITIONS , SUPPLEMENTARY II
CONDITIONS, SPECIFICATIONS and all parts of the Project Manual listed in
Article 1, Definitions, of the GENERAL CONDITIONS apply to and govern
all work under this change order.
Change Order No. 06
II. REQUIRED CHANGES
See Change Proposal Summary I
11
III. JUSTIFICATION
I
I
IV. PAYMENT
•
M
I
V. NARRATIVE OF NEGOTIATIONS
11
I
VI. APPROVAL AND CHANGE AUTHORIZATION
Par City Commission Action.
;acknowledgements:
The aforementioned change, and work affected thereby, is subject to all I
provisions of the original contract not specifically changed by this
Change Order; and,
I
00842-2 OE-137/WP
I
INI '
111
It is expressly understood and agreed that the a
Chane
Order shall have no effect on the original contractt other than oval of ematters
:IIIi expressly provided herein.
CONTRACTOR acknowledges, by its execution and acceptance of this Change
Order, that the adjustments in Contract Price and Time shown hereon
constitute full and complete compensation and satisfaction for all costs
and modifications of performance time incurred by the CONTRACTOR as a
result of this Change Order. No other claim for increased costs of
PI performance or modifications of time will be granted by the OWNER for
the Work covered by this Change Order. The CONTRACTOR hereby waives and
releases any further claims for cost or time against the OWNER arising
from or relating to the matters or Work set forth or contemplated by
this Change Order.
Change Order Request by: City of Ocoee, Florida
Change(s) Ordered by: James W. Shira, P.E.
:::
RECOMMENDED BY: ACCEPTED BY:
Butler Constructio Co
111 Contractor
By: By
IIISignature - Engineer of Record S 'g . It
Date: . Date: Lt(z Jq z
10! Title: Title: V?
APPROVED BY:
IIICity of Ocoee, Florida
Owner
II By:
Signature Lester Dabbs, Jr. , Mayor Date
/1 Attest: Change Order No.
Jean Grafton, City Clerk
END OF SECTION
11
FOR USE AND RELIANCE ONLY
•
SY THE CITY:,'F OCOFE,
APPROVED/1 10 FORM AND LEGALITY
WI day of 19_�
FOLEY&LARDNER
OF
City Atturney
I
00842-3 0E-137/WP
1
► /PROFESSIONAL ENGINEERING (��
PEC b1AJOF1 PARK PLAZi. SUITE •Su0 E pOBIN$ON � Ue !:� I!� CHANGE PROPOSAL
enq,nee,: `` Ira 0�
► planners uld.uc Firm PEC.W K D _z, *- „{� SUMMARY
sunvema
MAR 19 ►992J NO.
► P R O J ECT DATA •
NAME: Souk W ArraL Pin AWMBER: O-�_ ( 3
II �"1
LOCATION: �GOA r1.L GATE: (tV N�AA
/J
2i
OWNER: C
m Of OCO,E
DRAWING NO.:
OTHER:
SPEC SECTION:
REFERENCE: ::::..::.',.i.. .:-:. .:.. .......1.:.:.
..,..::. 7::,..;.
..,..`..:.--'..-•-•
► RFP No. Work Directive No.
► Field Order No. Other
DESCRIPTION: 1 t3 U I I4`�(� 'O S1G Z r0 I. e G' TO 12 1 ./ .t.
Ga-o0-1 C� Tu" fir•N �E 'J(J4Ct IL`��ikTl 1�
S..CJ
PRICING INFORMATION
► 1. DIRECT LABOR
Skill/Trade Manhours Rate
Cost
► 1.A Production Labor: ( I i ►
I ►
► 1
0 Foreman I ►
8 Supervision: 0 S ns>»»>.x:n»».»>:•»:»: ►
1.0 Field► ld
Engineering:in
c
eri
9:
1
:iii>s•::: ,...;
.. ..
►
1
.D
Expenses:s „»>
es-
► 2. MATERIALS AND EQUIPMENT SUBTOTAL (1) ► ► j
I1
Description Quantity Unit Price Cost
2.A Incorporated in Work:
► 2.8 Consuned in Performance:
I � ►
2.0 Equipment: I
2.0 Direct Costs: I I
2.E Bonds, Insurance: /
l3ato� i3coas Krsit itr— ►
»»» » »» >%»»> ;>:;.....:»> »»>»>»,» »»:»> SUBTOTAL ( )
,.... �:::::::i'::� <ii;<:': :'•::: ;.:::'::'ii:: :::::::::>;>::::: >:s:s>?ss»;s>s»»»>s»»»s>sssa»>s»s>.
WNER. p CONTRACTOR: , PROJECT NO. ►
0 ENGINEER: I
0 FIELD: ►
I DATE:
r1 ARCHITECT: 0 OTHER: I I
1
00865
BUTLER CONSTRUCTION COMPANY
GENERAL CONTRACTORS
P.O.Box 2038 1 P.O.Box 560398
4807 GEORGIA AVENUE / 210 HARDEE LANE
WEST PALM BEACH,FLORIDA 33402 �' ROCKLEDGE,FLORIDA 32956-0398
PLEASE REPLY TO: PHONE(407)632-6234
ROCKLEDGE OFFICE FAX#(407)632-6331
March 16, 1992
City of Ocoee
150 N. Lakeshore Drive
Ocoee, Florida 34761
Attn: James W . Shira, P.E.
City Engineer/Utilities Director
Credits for berm seed change and deletion of grout in casing
Re: South Water Plant
Dear Jim:
The following is a breakdown of the credit we can offer you for the
deletion and/or changes to the scope of work for the above
referenced project :
1) Seed and Mulch Change: 40 ,000 sf @ $ . 07/sf = $2800 .00
2) Grout Turnpike Casing: $4350 .00
Total Credit = $7150 .00
Per the direction of Ted Moore we are proceeding with seeding
operations with the different type of seed and will remove the
small pipe left in place for the grouting of the casing.
If you have any questions please give me a call .
Sincerely,
BUTLER 1S R C l ON COMPANY, INC.
D
E@EOWIE0
effrey` L . Gibson
Vice-President MAR 1 8 i992
* Adjustment as of
Change Order No. 06
I
(Short title of Change Order)
CHANGE ORDER FORM
CITY OF OCOEE
PROJECT: SOUTH WATER PLANT
I
CHANGE ORDER NO. 07
11
DATE: April 28, 1992 CONTRACTOR: Butler Construction Co.
11 OWNER: CITY OF OCOEE, FLORIDA AGREEMENT DATE:
11 The following changes are hereby made to the CONTRACT DOCUMENTS:
Original CONTRACT PRICE $ 1 .067,635.00
11 Current CONTRACT PRICE ADJUSTED by previous CHANGE ORDER* $ 1.348.384.38
Net (Increase) (Decrease) Resulting from this CHANGE ORDER $ 1.824.17
11 The current CONTRACT PRICE including this CHANGE ORDER $ 1 ,350,708.55
ORIGINAL CONTRACT TIME: 240 days Date March 28, 1992
11 Current CONTRACT TIME adjusted by previous CHANGE ORDERS* Date 4/21/92
Net (Increase) (Decrease) Resulting from this CHANGE ORDER Days
11 Current CONTRACT TIME Including this CHANGE ORDER Date 41/92
CHANGES ORDERED:
11
11
I
00842-1 0E-137/WP
11
I
I. GENERAL
41
This change order is necessary to cover changes in the work to be
performed under this Contract. The GENERAL CONDITIONS, SUPPLEMENTARY
CONDITIONS, SPECIFICATIONS and all parts of the Project Manual listed in
Article l, ' Definitions, of the GENERAL CONDITIONS apply to and govern
all work under this change order.
Change Order No. 07
II. REQUIRED CHANGES
See Change Proposal Summary
111 III. JUSTIFICATION
I
IV. PAYMENT
r1
a
V. NARRATIVE OF NEGOTIATIONS
lit
•
a
VI. APPROVAL AND CHANGE AUTHORIZATION
Per City Commission action.
Acknowledgements:
The aforementioned change, and work affected thereby, is subject to all 111
provisions of the original contract not specifically changed by this
Change Order; and,
•
a
00842-2 0E-137/WP III
1
*I
III
It is expressly understood and agreed
Order shall have no effect on thorig nal ontractroval other thanofemaChane
ttersexpressly provided herein.
•
CONTRACTOR
acknowledges, by its execution and acceptance of this Change
Order, that the adjustments in Contract Price and Time shown hereon
constitute full and complete compensation and satisfaction for all
costs
and modifications of performance time incurred by the CONTRACTOR as a
result of this Change Order. No other claim for increased costs of
performance or modifications of time will be
granted bthe OER for
the Work covered by this Change Order. ' The CONTRACTOR hereby waives and
releases any further claims for cost or time against the OWNER arising
!I from or relating to the matters or Work set forth or contemplated
this .Change Order. by
Change Order Request by: City of Ocoee, Florida
Change(s) Ordered by: James W. Shir
RECOMMENDED BY:
ACCEPTED BY:
I
...1 . .
Ili ' .
Contractor
By:
6 III
Signature - Engineer of Record B �-�14 . Aillr
e
Date:
Date: 5 Z •
le Title:
Title: _ r
' APPROVED BY:
ICity of Ocoee Florida
Owner
11 BY:
Signature Lester Dabbs, Jr. , Mayor Date
gAttest: Change Order No.
Jean Grafton, City Clerk
END OF SECTION
II
FOR USE AND RELIANCE MLY
dY THE CITY OF OCOEE,
APPROVED AS TO FORM AND tECGAL/TY
INS day W 10
FOLEY&LARDNER
~
City Attorney ,
I
00842-3 0E-137/WP
1
PEC/PROFESSIONAL ENGINEERING CONSULTANTS. INC. CHANGE PROPOSAL
MAJOR PARK PLAZA SUITE ,5u0 :co C ROBINSON ST ORLANDO. FLORIDA 32001 M,��
evmeerS Alldl.11e Firm P SUMMARY
Banners EC.W K Daugherty Consulting Engmecl;
surveyors
NO. 8
PROJECT DATA
OCOEE SOUTHWATER PLANT
NAME: 0E-137
NUMBER:
LOCATION: OCOEE, FLORIDA
DATE: APRIL 20 a 1 992
OWNER: CITY OF OCOEE
DRAWING NO.:
OTHER:
SPEC. SECTION:REFERENCE:
RFP No. work Directive No. Field Order No. Other
MISC. CLAIMS FOR EXTRA WORK REQUESTED BY OWNER AND
DESCRIPTION:
ELECTRICAL ITEMS NOT SHOWN ON DRAWINGS
PRICING INFORMATION
1. DIRECT LABOR
Skill/Trade Manhours Rate Cost
1.A Production Labor: CARPENTER(SCREENS ) 2 I 1 2 . 00 24 . 00
' I
1.8 Supervision: ❑ Foreman i}i}.. �:.}:}}}ii:i: : ;:>>}ay}:.}:':"
❑ Sup1
1.
e
ld( Engineering:
ri
e n
9:
ori}a}i jj: i
1.D
SSj}iji}�ia:i
Expenses:
I ia.
SUBTOTAL (1)
2. MATERIALS AND EQUIPMENT
Description Quantity Unit Price Cost
2.A Incorporated in Work: ! LOUVER SCREENS 4 — 132 . 29
2.6 Consumed in Performance: � I
I I
2.0 Equipment:
2.0 Direct Costs:
•
2.E Bonds, Insurance: BLDR' S RISK;
27. 78
BONDS SUBTOTAL (2) 160 . 07
;;s}}s•:......:.s :..,,>sii::::.•,;;i}iu}••••••••ris:s>:is:s:is>sssr:;a:;iasssasi;}} s••ss>assss•a>s»•»>a>ssr>ss>s>a+s s>s»ssiaisiasv•s
......................:
.:,}:.,a..,.,•.:aaaa•.:v::iitii:iiii:v:ii»:.:Ciiii:.:i4�:::.::...:. :i:...::::. ..: .::.:.........: .. ....... ..... : .....
.a.v.ia.S}a.aa
a>ivvni
WNER:
.a. ....n.,,,...n},.:v..:...a.........a...,.....aaa}.a n.:...a...v.:,.... .,............a........ I
. ..... .::......::•::::::::::::.:::.::ii:....:::'.i"i:'::i.;..:::::.:i:::�"'i::i'•:is i`i�".`.`:'�':j
1
El CONTRACTOR: 4.15\
� f4- tl(�M� � PROJECT NO.
ENGINEER: El FIELD:
ii\c 2 2992
Fjji DATE:
APR
n ARCHITECT: El OTHER: I
00865 i
1
•
•
03. C3.'9O 95:46 DON MILLER'S PATRIOT FENCE. INC. P:01
Don Miller's
PATRIOT FENCE
125(3rillln Road Nonh (407) 833.4427 8o, 1250
Cecolk Florida 32928 FAX 639-8377 Cocoa,Florida 32923
OWNER REF ! DMPF QUOTE 1B91-
~ Ph#
Qc.tTi. r COivDate
ST 3 ) 2.3100
Addresnt NARnTc 4.A.) Job Name: C , T.y QCorG' C1JwrP
ROCk• 1—F0,51. FI-P Job Loc at ion: a GOFr F44
*0* PROPOSAL, **a
RF)tovt + iqv JA-Is ALL ro 2. t' T11w& Feud •
Re Ntr 1 S JNG-L E G A Ti Akio ADD I ros. 21. ' Rol-L. GATT
4 ! 1Js a
el5. 0oa
l..
CSS CQ l r 't) u Z J /i1 ` G,A'r L
aQ � � 5 eo
TL P1 O u r �
C MA Cry.
CONDITIONS OP PROPOSAL
Yes No , '
N Addendums Acknowledged � Grounding X
Bonding X. Core-Drilling Requiteri
Certified Payrolls X Special Ground Conditions?
Clearing/r3rading X Special Insurance Req.
Underground Utilities )( "Suy American" y A ,
Fence removal X Davis Bacon required
Temporary Fence required Permit Included? X
We propose hereby to furnish meter lel and I ahc'r -- complete and in accord-
ance with the above spec i f !cat ions for the sum of
Dol l are ($ 8tau dG
All material is guaranteed to be an specified, unless otherwise noted.
All work to be completed in a workmanlike manner according to standard
practices. Any alterations or deviation from the above spec 1 >#igatic.ns
involving extra coats will be executed only upon written orders; and
will become an extra charge over and above this estimate. All agree-
ments are contingent upon strikes, accidents or delays beyond our
control . Owner to carry fire, tornado and other necessary insurance.
Our workers are fully covered by Worker ' s Compensation Insurance.
�r - a CA
92. 0 3/ 1 8 2 0 : 4 8 P 0 1 * F 1
• FAX Memo --- -: -..zi:-=--------z-------- , .
A.:* 1• Date,1.4.1 )12_—Time:Ailagf , 1 5
• :
a ,,Locotion:,_ Rc.4.4.12....._ ,L03(t.......-cb....,y•
•
• FAX #: Lo ..- ("31 1 I
O From: •
• •
•
Location: (.. 'r*-AirS 1,3-.)1/4/41.-...) •
• •
i FAX #: Lit) 2-CA 231 •
•
• •
Phone #: C9":" (1, - 2149-1 3
•
1 •
c.fr,ek•94667 t
I 1
i ,.....- 1.4 i.,
' ,...k...-- LL
6/1 3
t.A.ft tzi,sr 5
c:\ .
"..
--.
:us-romER.s ORDER NO. iDEPT. DAT • .
639 — 6.9 39 ; ,---
y--il
itiA:41,ex.
cI_ 's.,(„Cacr_ f7L(._
i.IT1 ECRTii-—--------------
D I 0 1-tetecie,e_ _kg .WIr
.t. '
_ . .
SOLO •Y CASH C.O.O. CtIANGlat 014 Af..:Y. PAOSCASTO. VAIO OUT .-
(MAN DESCHIP HON PRICEAMOUN I
33 1 i)* 4 X 66 g !tido 9e) .0.
/— 3 — *44,-- _IX —2/fiii - . - ----._ ;I ° LouvEas
4 --
7 • 4-ci
6 • q 0
6 711;.4 B1)?(_______ (1).i.1.1. A.11.1oN •
.... I 3
8
--T --Pk-
O:C- la ------------ -
----- — - -- .___... ___
... ........ ...... ,
10 DeR. J 00 °° ..........___
•
11 7-1C--- -----
• ..... _____-
- -.-
13
14
-... - • . . - - -•
•
15
- - .- - - . ----
-'•
18 li a a
. .
RECD BY
MURDAUGH CONST. CO. INC.
Electrical Contractors
$lite 124
780 Mullet Rd.
TO: BUTLER CONSTRUCTION Cape Canaveral, FL 32920-4504
210 HARDEE LANE (407)784-2179
ROCKLEDGE, FL 32955
RE: OCOEE WATER PLANT CHANGE ORDER NO. : 9113-5
DATE; 16 MAR 92
SUBJECT: SHIELDED WIRE TO FLOW SWITCHES
Our cost for subject change is $ 180 . 22 . Following is a cost
breakdown :
#14 SHIELDED
MATERIAL: 560 FT @ . 24 $ 134. 40
Sales Tax: 8 .06
TOTAL MATERIAL ; $ 142 . 46
EQUIPMENT RENTAL : S
TOTAL RENTAL: $ 0 .00
LADQR;
ELEC: HRS @ $ 0 . 00
Q.C. : HRS @ $ 0 . 00
FORE: HRS @ $ 0 . 00
SUPT; HRS e S 0 . 00
S/T $ 0 . 00
P/R TAX & INS: 0 . 28 $ 0 . 00
TOTAL LABOR: S 0 . 00
TOTAL COST: $ 142 . 46
OVERHEAD: 21 . 37
FEE: 16. 38
Very truly y�ur.s ,
l TOTAL : S 180 . 22
MURDA/GH STRUCTION CO. , INC.
Time required to accomplish
this change is :
Jjnles C. Sp ve ,
Project Ma -.ger
MURDAUGH CONST. CO. INC.
Electrical Contractors
Suite 124
TO: BUTLER CONSTRUCTION 780 Mullet Rd.
210 HARDEE LANE Cape Canaveral, FL 32920-4504
ROCKLEDGE, FL 32955 (40717844179
RE: OCOEE WATER PLANT CHANGE ORDER NO. : 9113-4
SUBJECT: TRANSFER SW SIGNAL TO CONTROL PANEL DATE: 16 MAR 92
Our cost for subject change is $ 110 . 79 . Following is a cost
breakdown:
MATERIAL: (see attached) $ 12 . 13
Sales Tax: 0 . 73
TOTAL MATERIAL: $ 12 . 86
EQUIPMENT RENTAL: $
TOTAL RENTAL: $ 0 . 00
LABOR:
ELEC: 3 HRS @ 19. 46 $ 58 . 38
Q.C. : HRS @ $ 0 . 00
FORE: HRS Q $ 0 .Q0
SUPT: HES @ $ 0 . 00
S/T $ 58 . 38
P/R TAX & INS: 0 . 28 $ 16 . .3.5
TOTAL LABOR: S 74. 73
TOTAL COST : $ $7 . 58
OVERHEAD: 13 . 14
Very truly swat FEE: 10 . 07
)
TOTAL: $ 110 . 79
!TURD GH S7REACT I ON CO. , INC.
\ Time required to accomplish
this change is :
J;ti"
es C. Spject Manager
FROM MURDAUGH CONST. '92 03/16 17: 10 P.07
Ii Ni it C)
_ u It '.L`
iIZ II Ii 2
II
II II 0
11 2 I I M
II O li ••
II ' II
i'' II II
O VD CO "J CM to .A• co NJ I--' It it
II 6
at N 1-+ — 1-r II 11 '0 ►-j O
F-'\---\\ II 11 ►-- "pl ('j
.C- NJ NJNNJ II Ii N.* )0 0
11 i1 Cate m
co II u 1 U! 01
1-3 Ill VI t23 11 „'3„" X X4 Z II II II M '
zf--344 4 u u 0No
P 0 0 It II elt C 2 II II S
CO Pa z u II
*0C" II Ii - r
En I1 II yt
I I II Z Z
II II > y
I I II t-.
fi u
u u .-
II II 0
I I 11
I I I I (a)
ii n 6
II II x
II II y
11 II 5!
II II Q X
It io it r Cl
II C II >f
II •)I I I b C7
li Z II 04 0P
y
II II C
I' n I-1 II tN 0
w rvlly it r x
0 L WN0 11 PC II
II II
H � �
b H II a II b p0
2
II II Wbo
►3 II I1 r•. 4
O II I I c) xi
ha ii pt n w C
'0 Ii II Z ()
L--. 00000 II C: iI G7 y
.. . . . . ii x 03 I I f+
NN1r II M.0 NI II thC5
4. d) N .. Lh n II mx
WOOOW II °p fl PI
0000 .1 u r u tai O
00000n a y0
Ii u Ii .
II H
II II
0 II IP 2
I,
II X 0 e5
u X Ii
11 lI H '$ II
ii II pi 0-3 11
II II Z till II
t-+ 11 I i (n i>y i t
NJ II O0 CG 00 .1000 W II "...I 0.4 Ii
I I Il 0 �s ii
I-- a aeaaa -4N4hJ. a n 2 ril II
W 11 000004. W Ch CC0 .1 II II
11 II II
II II
II Il
II II
•
MVAPAVGN CWNST, C4, INC.
Electrical Contractors
Suite 124
780 Mullet Rd.
TO: BUTLER CONSTRUCTION Cape Canaveral, FL 32920-4504
210 HARDEE LANE (407)784-2179
ROCKLEDGE, FL 32955
RE: OCOEE WATER PLANT CHANGE ORDER NO. : 9113-2
DATE: 16 MAR 92
SUBJECT: CL2 RECORDER NOT SHOWN
Our cost for subject change is $ 99 . 88 . Following is a cost
breakdown:
MATERIAL: (see attached) $ 3 . 99
Sales Tax: 0 . 24
TOTAL MATERIAL: $ 4 . 23
EQUIPMENT RENTAL : $
TOTAL RENTAL : $ 0 . 00
LABOR;
ELEC: 3 HRS @ 19 . 46 $ 58 . 38
Q.C. : HRS q $ 0 . 00
FORE: HRS @ $ 0 . 00
SUPT: HRS @ $ 0 .00
S/T $ 58 . 38
FIR TAX & IN$: Q12$ $ 16 . 35
TOTAL LABOR : $ 74.73
TOTAL COST: $ 78 . 96
OVERHEAD: 11 . 84
PEE: 9 . 08
V7rul y ours ,
TOTAL: S ' 99. 88
1URD GH r %NS'RUCTION CO. , INC.
i` Time required to accomplish
this change is :
('a s C.4. +vey
Pfoject Mal.ge
FROM MURDAUGH CONST. '92 03/16 17:08 P.03
u H 11 O
u y it M
11 rg it ¢+
11 NE II 2
II II 4)
II 2 II ru
II 0 u ••
A . II
I-- n II
0 kD W v cn to .la (.4 N I-' n II
II II
4*# I•-+ I-, I I II uD C( O
h-' I-'\\ 1I I I F-, C" C]
Nj+ NN II II 1--' NO
I I I I W (s3
HH n u I xiM
xO) QQ 11 n NJ VII
= 23 XI II ti 0 Z
Z C) SI SI n II ID Di
5+1 tTJ MH u 5J P-3
t O 2 4 n II t 7 M
t' 1.1Jhj u II m7D
tg PM /4 II 11 ›i
rui rul u II 'd
rru n 2r
0 0 II u o �11
II u y 2
0 n II '-3
O II 11 O
SC ii ii x
2 II 11 0
II II Z
II II
I I II
II II
II II
II II
II u
Ii 1► M
11 0 II a
II C It P3
M DI n 0
A 't4 n Po
II y II tP
II h-1 II C
I-1 u P3 I I rx.
n) 11i co ,A ►1 Fti u
I I Il 0
ma ma '_] t>h a A n 0
H HHDs II a *0Z
A u
'"3 11 11 r+ r.-]
0 u II
H II pc u yr0•e C
r CD
oaQCD Mo II Cy ii CI Pi
•• • • II Z tal II H
O NI-• n? II N.+ pi If to
,oatoO ii 5d iI bd
N 000 II t'+ II ts3 f7
u+ 000 u II H0
II it li •
II II
II II
►1 11 I-1
►1 II II 2
11 11 VII I I CD
II 11 'c M II
11 II 14 Ogi II
ii 11 t=i H 11
11 I I 2 to I I
11 0J
II 1 P3 n
W u 0000000Oh-t0 n PA ri 11
II . . . . . . II 01,0 II
Ib II 000000 . u5 Jt. 65 II tet:. ii
.o II 0000pa1-0cmCO 45. It ii
II II II
it II
II II
II it
MURDAUGH CONST, CO. INC.
Electrical Contractors
Suite 124
780 Mullet Rd.
TO: BUTLER CONSTRUCTION Cape Canaveral, FL 32920-4504
210 HARDEE LANE (407)784„2179
RQCKLELQE, FL 329$5
RE: OCOEE WATER PLANT CHANGE ORDER NO. : 9113-3
DATE: 16 MAR 92
SUBJECT: SIGNAL CIRCUIT CL2 ANALYZER TO CONTL PNL
Our cost for subject change is $ 135 . 95 . Following is a cost
breakdown;
MATERIAL: (see attached) $ 7 , 39
Sales Tax: 0 . 44
TOTAL MATERIAL : $ 7 . 83
EQUIPMENT RENTAL: $
TOTAL RENTAL: $ 0 .00
LABOR:
ELEC: 4 HRS @ 19 . 46 $ 77 . 84
Q.C, ; HE5
FORE: HRS @ $ 0 , 00
SUPT: HRS @ $ 0 . 00
S/T $ 77 . 84
P/R TAX & INS: 0 . 28 $ 21 . 80
TOTAL LABOR: $ 99. 64
TOTAL COST : $ 107 . 47
OVERHEAD: 16. 12
FEE: 12 . 36
Very truly/{ou}s ,
TOTAL: $ 135 . 95
MGRDUG NSTRUCTION CO. , INC.
/ Time required to accomplish
this change is :
�n� �
47;pires C. Sp. vey,
roject Ma ger'
I
FROM MURDAUGH CONST. '92 03!16 1':O9 P. 05
11 1.4 11 C)
II H II 1i�i
" M
5,1
II
11 I I O
II 1g II
11 0 II 11
• n
W II it
O kD CO J Cn (J+ .A (.4 N F-• I I I I
II II
stl. rrwl.-a II M tpCAO
()
.pNNNN M II W O U
It II W rn
En I I ,I I ;w Ci]
,•3 rl r4 (rnC4 II 11 wr �1
w M .M. M 11 II .y
0 t-1 a 11 II
ti II I-1 a
ti cm c) II II .hdt�7
E=J •� 00
t'J ;Ij C: II II d
h:1 L-4 II II yr
N II n y
II II C7 Z
II u r
II H iV
II 1
D
II ii x
I, II
II II r
II II 1<
II it N
I II (s7
II DJ
1 II X
110 II 03 C_,
I C II Q
1 DW n
I t4 u 0
I y II O C
re 10 't,' (;J
O N P s• �Q
CS W N 6 I
Ii iI 4 A
'00 DI 7 VO r00 II II r I1 Q
.jyDal yy 11 II w '?.'
n n NJ 53 to
y II II DPI r3
O tI I I ?, n ;x1
y II X II trJ I--1 C
r' 00000 11 CH 1.4
•• • • . II M rritt .,
O ONNI I ,I H `,>y II (!) Q
IA On N Iia LT 11 r3 F-1II `.r. 2
co O00 co II , 5 II [s7
Q Q Q Q Q IIII H O
II ii It •
11 II
II Ii
II II II "�
11 It t II (2
11 11 X
II 11 I-3 II
,'p1
II II 1 y H
II II sz rm II
II II V) .'ID 11
-4 II 00000 W 000 co U 1--, r-1 II
It II (D Do U
Co le 4884) 45au NJ u :4r
tp II O00QQ40. 00NCOII II
11 It II
II II
II II
* Adjustment as of
Change Order No. 07
(Short title of Change Order)
11 CHANGE ORDER FORM
CITY OF OCOEE
11 PROJECT: SOUTH WATER PLANT
11
CHANGE ORDER NO. 08
DATE: April 28, 1992 CONTRACTOR: Butler Construction Co.
OWNER: CITY OF OCOEE, FLORIDA AGREEMENT DATE:
11 The following changes are hereby made to the CONTRACT DOCUMENTS:
11 Original CONTRACT PRICE $ 1.067.635.00
t] Current CONTRACT PRICE ADJUSTED by previous CHANGE ORDER* $ 1 ,1511,7fR_ SS
Net (Increase) (Decrease) Resulting from this CHANGE ORDER $ 1,518.17
11 The current CONTRACT PRICE including this CHANGE ORDER $ 1.351.726.79
ORIGINAL CONTRACT TIME: 240 days Date March 28, 1992
11 Current CONTRACT TIME adjusted by previous CHANGE ORDERS* Date 4/21/92
Net (Increase) (Decrease) Resulting from this CHANGE ORDER Days -0-
11 Current CONTRACT TIME Including this CHANGE ORDER Date 4/21/92
CHANGES ORDERED:
11
I
I
00842-1 OE-137/WP
11
I
I. GENERALNM
It
This change order is necessary to cover changes in the work to be
performed under this Contract. The GENERAL CONDITIONS, SUPPLEMENTARY It
CONDITIONS, SPECIFICATIONS and all parts of the Project Manual listed in
Article l,' Definitions, of the GENERAL CONDITIONS apply to and govern
all work under this change order.
Change Order No. 08
II. REQUIRED CHANGES
See Change Proposal Summary
III. JUSTIFICATION
OIL
111
IV. PAYMENT
I
I
V. NARRATIVE OF NEGOTIATIONS
I
.
VI. APPROVAL AND CHANGE AUTHORIZATION
Per City Commission action.
Acknowledgements:
The aforementioned change, and work affected thereby, is subject to all III
provisions of the original contract not specifically changed by this
Change Order; and,
I
00842-2 OE-137/WP III
iPir
ill
rig It is expressly understood and areed that the
Order shall have no effect on the original contractroval other thanofe maChane
ttersI expressly provided herein.
!II •
CONTRACTOR ack
nowledges, by its execution and acceptance of this Change
Order, that the adjustments in Contract Price and Time shown hereon
constitute full and complete compensation and satisfaction for all costs
and modifications of performance time incurred by the CONTRACTOR as a
result of this Change Order. No other claim for increased costs of
performance or modifications of time will be
granted bthe OER for
the Work covered by this Change Order. The CONTRACTOR hereby waives and
releases any further claims for cost or time against the OWNER arising
from or relating to the matters or Work set forth or contemplated by
this Change Order.
Change Order Request by: City of Ocoee, Florida
Change(s) Ordered by: James W. Shira, P.E.
RECOMMENDED BY:
ACCEPTED BY:
1
1 Butler Construc_ ion Co.
Contract• t
By: B *if ../
111 Signature - Engineer o Record �'�
Date:
Date: S'SIq2 •
pi Title:
Title: v.?.
APPROVED BY:
11 city of Ocoee Florida
Owner
II By:
Signature Lester Dabbs, Jr. , Mayor
Date
gAttest:
Jean Grafton, City Clerk Change Order No.
END OF SECTION
II
PON L$E WID MINCE ONLY
IN Ng CIN Of OCOEE.
AIMOMEo As TO"UM NIMH""
I -
car Am mey
I
00842-3 0E-137/WP
1
/PROFESSIONAL ENGINEERING CONSULTANTS. INC. CHANGE PROPOSAL
I PEC MAJOR PARK PI.AZA SUITE 150 :CO E. ROBINSON ST ORLANDO.FLORIDA 32001
planners dlldi..Ie Firm PEC.W K Daugnerly Consulting Engineers SUMMARY
enpmesurrerots
NO. `?
PROJECT DATA
NAME: SOUTH WATER PLANT OE-137
NUMBER:
OCOEE, FLORIDA
LOCATION: DATE: APRIL 24 , 1 992
OWNER: CITY OF OCOEE
DRAWING NO.:
SOUTH CONNECTOR CHANGE ORDER
OTHER
SPC SECTION:
REFERENCE: ... ... .: . ...:.. - •....• .:....,:.... ..:... ._ ....
RFP No. Work Directive No. Field Order No. Other
PROVIDE TWO ADDITIONLA 45° BENDS ABOVE & BEYOND THOSE SHOWN
DESCRIPTION:
ON THE BID DOCUMENTS
. I
PRICING INFORMATION
1. DIRECT LABOR
Skill/Trade Manhours Rate Cost
1.A Production labor: ( I I I I
I I i I I
❑ Foreman » .>,.:::•::,>»• ::,»>:>»»,:,,.,»»:>:
1.8 Supervision: ❑ Supf AKWagT"'•;' »>;
1.0 Field Engineering: 1:4?�s>
1
1.D Expenses: >{ >> •1
I I
SUBTOTAL (1) I —(1'-
2. MATERIALS AND EQUIPMENT I
Description Quantity Unit Price Cost
r I t
2.A Incorporated in Work: I
I f �
2.8 Consumed in Performance:
II2.0 Equipment: I I
2.0 Direct Costs:
•
2.E Bonds, Insurance: BLDR' S RISK,BOND 20. 15
SUBTOTAL (2) ' 20 . 1 5
;;»fsa>:;» >s>»r••••s,,,,,:......»:»»>>»»>>»»»»»s>»»»:»>»»sa»s»ss»>»»»>a;• •,, ,s»a »»s>:»»»>s»a sss•ss>a»>»»> .. .. .. ...
:s:aa:ii?itttttfaf : .::;;:::•;;.:.::::.•;.;:::........
na.'...... s s i .::.:..::.:...>:y :f>fsw•a:T:a:.:�s.,.......�;.:.,;...;_......: >,>.
::iii..ii:iiv:::iiiiiv:iii4:�i:i<iiv:iiiiii: .<i.i..i<•..n:.:::,.i. :::>��.;�•:
.,..v.:,.n..n,.>..nnv.i>K,...:.>tv....in .. .a.vw:::,�> ::t;yt;:i<':::it::•:ii::::>;�n::::::
. .. .• .' '•••....;"""'iiiiii<iii4:iiv:ii:isiiia:iv:iii:;ti{<<iiv:i�iii:�::::5 i�:iiiii:iii
I WNER: PROJECT NO.
0CONTRACTOR:
0 ENGINEER: 0 FIELD: I
DATE:
n ARCHITECT: 0 OTHER: li
00865 • 1
3. SUBCONTRACTORS
Name Description of Work Cost
3.A Direct: C.A. MEYER 2 ADDITIONAL 16" 1 1_t300 .00
45° BENDS
3.3 Lower Tier:
SUBTOTAL (3) 1 , 3 0 0 . 0 0
4. CONSULTANTS
Name Description of Work Cost
I .
SUBTOTAL (4) -0-
5. FEE STRUCTUR
A. Contractor Cost Percent Fee
I. Direct Labor: -0-
2. Material and quipment: I
20 . 15 1 5 _11
•
8. Subcontractors: 1 , 300 .00 15 195 . 00
I Ii
SUBTOTAL (5) 198 .02
TOTAL COST OF THIS CHANGE PROPOSAL (all deductions shown in parentheses): TOTAL
EXTENSION OF CONTRACT ME
As part of this Change Proposal, the Contractor requests an extension of Contract Time -
Justification: PLANS ISSURED FOR CONSTRUCTION ADDED TWO
THAT WERE NOT ON PLANS WHEN USED FOR PREPARING OUR
. . .
RECORD DOCUMENTS
As part of this Change Proposal, th C ntract r h provide applicable record drawing information affected by
this change.
Sign9A
Title
RESIDENT
Contractor BUTLER CONSTRUCTION COMPANY, TNC_
Date APRIL 24 , 1992