Subject: Marshall Farms Road Resurfacing, Change Order 1, B18-02 Asphalt Paving Projects
FY 2018 with Hubbard Construction Company. Commissioner Firstner, District 3.
Background Summary:
At the May 15, 2018 Commission meeting, the FY 2018 asphalt paving projects bid was awarded to
Hubbard Construction Company (HCC). The City had allocated funding for the resurfacing of Marshall
Farms Road in previous fiscal years, yet deferred moving forward with the work until such time as the
parallel State Road 50 widening project was completed. The State completed their project about the
same time the City awarded the resurfacing projects. Public Works approached HCC to extend the
awarded bid pricing to incorporate the work on Marshall Farms Road as this heavily traveled access
road for commercial traffic is long overdue for resurfacing. The $288,465.39 cost to mill and resurface
approximately 3,000 linear feet of roadway is adequately funded with the carry-forward funds allocated
for this project in previous fiscal years. Public Works recommends approval of the change order to
incorporate Marshall Farms Road resurfacing in the FY 2018 asphalt paving program.
Issue:
Request the City Commission approval of Change Order #1 with Hubbard Construction Company to
incorporate Marshall Farms Road resurfacing into the FY 2018 asphalt paving program.
Recommendations:
Recommend the City Commission approve Change Order #1 in the amount of $288,465.39 with
Hubbard Construction Company, Winter Park, Florida, to incorporate the Marshall Farms Road
resurfacing into the awarded Asphalt Paving Projects for FY 2018.
Attachments:
Change Order No 1, B18-02 Asphalt Paving Projects FY 2018.
Financial Impact:
The $288,465.39 cost for the change order is adequately funded in the FY 2018 paving program with
the carry-forward funds allocated for this project in previous fiscal years.
Type of Item: (please mark with an "x")
Public Hearing For Clerk's Dept Use:
Ordinance First Reading x Consent Agenda
Ordinance Second Reading Public Hearing
Resolution Regular Agenda
X Commission Approval
Discussion&Direction
Original Document/Contract Attached for Execution by City Clerk
Original Document/Contract Held by Department for Execution
Reviewed by City Attorney N/A
Reviewed by Finance Dept. \ 'v N/A
Review ed by ( ) N/A
2
ocoee
florida
CITY OF OCOEE
150 North Lakeshore Drive
Ocoee,Florida 34761
B18-02 ASPHALT PAVING PROJECTS FY 2018
CHANGE ORDER FORM
DATE: 8/21/2018 PURCHASE ORDER: 1425622
The following changes are hereby made to the CONTRACT DOCUMENTS.
Original CONTRACT PRICE $835,757.00
Current CONTRACT PRICE ADJUSTED by previous CHANGE ORDERS $835,757.00
Net Increase(Decrease)Resulting from this CHANGE ORDER $288,465.39
The current CONTRACT PRICE including this CHANGE ORDER $1,124,222.39
Original CONTRACT COMPLETION DA lb: 11/2/2018
Current CONTRACT COMPLETION DATE adjusted by previous
CHANGE ORDERS 11/2/2018
Net Increase Resulting from this CHANGE ORDER 0 days
Current CONTRACT COMPLETION DATE including this
CHANGE ORDER 11/2/2018
B 18-02 Asphalt Paving Projects
CHANGES ORDERED:
I.
REQUIRED CHANGES: Public Works requests contract changes to include the milling and
resurfacing of Marshall Farms Road at the unit costs presented by Hubbard Construction.
Capital Improvements for this asphalt project was approved in prior fiscal year; however Public
Works postponed the project due to the FDOT reconstruction of SR 50. In evaluating the unit
costs submitted by Hubbard Construction,Public Works believes it is cost effective to include the
asphalt repairs at this time.
II. JUSTIFICATION: Marshall Farms Road milling and resurfacing is justified due to current
pavement condition. Pursuant to the Pavement Survey and Evaluation Report prepared by
Universal Engineering Sciences,Inc.,the pavement is in poor condition with severe rutting,
raveling,shoving and cracking.
III. NARRATIVE OF NEGOTIATIONS:Current unit are cost effective. Refer to attached Bid Form
IV. PAYMENT: Total Change Order is$288,465.39
V. APPROVAL AND CHANGE AUTHORIZATION
This proposed change to the Contract requires approval by the Ocoee City Commission or the City Manager,
dependent upon project approval authority, in order to supplement the project budget to fund the changes.It is
expressly understood and agreed that the approval of the Change Order shall have no effect on the original
contract other than matters expressly provided herein.
CONTRACTOR acknowledges,by its execution and acceptance of this Change Order,that the adjustments in
Contract Price and Time shown hereon constitute full and complete compensation and satisfaction for all costs
and modifications of performance time incurred by the CONTRACTOR as a result of this Change Order. No
other claim for increased costs of performance or modifications of time will be granted by the OWNER for the
Work covered by this Change Order. The CON TRACTOR hereby waives and releases any further claims for
cost or time against the OWNER arising from or relating to the matters or Work set forth or contemplated by
this Change Order.
B 18-02 Asphalt Paving Projects
RECOMMENDED BY: ACCEPTED BY:
CITY OF OCOEE,FLO• IDA Hubbard Construction Company
By: `i. / / 4.0"11110624—c-1 By:
Signature Signature
Date: ff/ZZb!O Date: df/?-/l//F
/�
P. Frederick O'Dea,Jr.
Title: e IA/4/AJ ie Title: Vice President&Secretary
APPROVED BY:
CITY OF OCOEE F ORIDA
By: . Date: 'o —Z-2---2---2 6 i g
Stev- Arg, ublic Wo Director
ByaltkOc-i . .t tS Date: g` 077 1 it)
Rebecca Roberts,Director of Finance
I
g(
By:
Date: 2 I
Robert D. rank, City Manager
By: Date:
Rusty Johnson, Mayor
Attest:
Melanie Sibbitt, City Clerk
FOR USE AND RELIANCE ONLY BY THE APPROVED BY THE CITY OF OCOEE
CITY OF OCOEE,APPROVED AS TO FORM COMMISSION IN A MEETING HELD ON
AND LEGALITY THIS DAY OF , 20 UNDER
,20 AGENDA ITEM NO.
By:
City Attorney
B18-02 Asphalt Paving Projects
O R LA n D O PAV I n G ORLANDO PAVING COMPANY
A division of Hubbard Construction Company
co m PA n y 1936 Lee Road,Suite 300-Winter Park,FL 32789
P.O.Box 547186-Orlando,FL 32854-7186
T/407-578-9779-F/407-578-5251
www.hubbard.com
To: City of Ocoee Attn: Richard Campanale, PE
Address: 150 N. Lakeshore Drive Email: richard.campanale@ci.ocoee.fl.us
Ocoee, FL 34761-2258 Phone: (407)905-3100
Mobile: (321)281-7025
Estimate: 018-150719
Project: City of Ocoee(Marshall Farm Road)
Bid Date: 07/17/2018 #of Addenda:
Completion: End of 3-QTR-2018
100.00 MOBILIZATION&CONSTRUCTION REQUIREMENTS 1.000 LS $7,615.57 $7,615.57
MARSHALL FARMS ROAD
101.01 MILL EXIST ASPH PAVT,3.00"AVG DEPTH 5,750.000 SY $ 3.99 $22,942.50
101.02 MILL EXIST ASPH PAVT,5.50"AVG DEPTH 2,400.000 SY $ 9.62 $23,088.00
101.03 1.50"SP-12.5 RESURFACING 5,750.000 SY $ 11.75 $67,562.50
101.04 4.00"SP-12.5 RESURFACING 2,400.000 SY $ 27.63 $66,312.00
101.05 1.50" FC-12.5,PG76-22 OVERLAY 8,150.000 SY $ 9.96 $81,174.00
101.06 TEMP PAINT&FINAL THERMOPLASTIC PAVEMENT MARKINGS 1.000 LS $19,770.82 $19,770.82
GRAND TOTAL: $288,465.39
**ALL PRICING IS CONFIDENTIAL**
Qualifications:
- Night work is excluded.
- Priced as Change Order to existing contract"B18-02 Asphalt Paving Projects for 2018."
Respectfully submitted,
Dustin Baker-Estimator
July 19,2018 2:41 PM Page 1 of 1