CITY OF OCOEE
AGENDA ITEM COVER SHEET
Date: August 9,2004 Meeting Date: August 17, 2004
Subject: McKey Street Project, Change Order# 1 to Gibbs&Register, Inc.
Issue: Approval of Change Order# 1 ($16,025.00)for modifications to water main and
distribution system.
Recommendation:
Staff recommends approval of Change Order# 1 to Contract B04-07 to Gibbs&Register, Inc.,
for the amount of$16,025.00
Background Summary:
The design of the existing water main and distribution system was relatively unknown due to the
age of the system. Modification to the design of the main and distribution system became
necessary as described in the attached Change Order form.
Fiscal Impacts:
The additional $16,025 is available from the Water R&R Funds. The balance of the Water R&
R.Funds is estimated at$515,000 after this expenditure.
Commission Action:
Reviewed by City Manager
Reviewed by City Attorney X N/A
Reviewed by Finance _)/ _ N/A
Reviewed by N/A
Mayorve centet of Good Ll,ktb. Commissioners
S. Scott Vandergrift :,f..+r`�-. Danny Howell,District 1
Scott Anderson, District 2
City Manager Rusty Johnson,District 3
Robert Frank Nancy J. Parker,District 4
STAFF REPORT
TO: The Honorable Mayor and City Commissioners
FROM: Bob Zaitooni, Deputy Director Public Works
DATE: August 17, 2004
RE: McKey Street Project Change Order# 1
ISSUE
Approval of Change Order# 1 for the amount of$16,025 for Gibbs&Register, Inc., for
modifications to the water main and distribution system.
BACKGROUND/DISCUSSION
Contract B04-07 was awarded to Gibbs&Register on June 15, 2004,which included the
replacement of the existing 6" water main on McKey Street. The details of the existing water
main and distribution system were relatively unknown at the time of the design due to the age of
the system. As the south side of the McKey Street was excavated, it became apparent that
modification to the design of the main and distribution system as necessary. A Change Order
Form and detail breakdown of the items are attached to this report.
The additional $16,025 is available from the Water R&R Funds. The balance of the R&R
Funds is estimated at$515,000 after this expenditure.
RECOMMENDATION
Staff respectfully recommends City Commission approve Change Order# 1 for the amount of
$16,025 from the Water R&R Funds; and authorize the Mayor and Clerk to execute the Change
Order.
She Ceritet of Good if
_,. ►,,,,,� CITY OF OCOEE
Engineering/Utilities
150 North Lakeshore Drive
Ocoee, Florida 34761-2258
CHANGE ORDER NO. #1
CITY OF OCOEE
McKev Street Streetscaoe Project
PROJECT NO.B04-07
DATE: August 9,2004 CONTRACTOR Gibbs&Register,Inc.
AGREEMENT DATE:June 15,2004
The following changes are hereby made to the CONTRACT DOCUMENTS.
Original CONTRACT PRICE $890,900.00
Current CONTRACT PRICE ADJUSTED by previous CHANGE ORDER $890,900.00
Net Increase Resulting from this CHANGE ORDER $ 16,025.00
The current CONTRACT PRICE including this CHANGE ORDER $906,925.00
ORIGINAL CONTRACT TIME:
180 Consecutive Calendar Days from Notice to Proceed Date: January 2,2004
Current CONTRACT TIME adjusted by previous CHANGE ORDERS Date: January 2,2004
Net Increase Resulting from this CHANGE ORDER Days: 0 Days
Current CONTRACT TIME including this CHANGE ORDER Date: January 2,2004
CHANGES ORDERED:
I. GENERAL
This change order is necessary to cover changes in the work to be performed under this Contract. The
GENERAL CONDITION,SUPPLEMENTARY CONDITIONS, SPECIFICATIONS and all parts of the
Project Manual listed in Article 1,Definitions,of the GENERAL CONDITIONS apply to and govern all
work under this change order.
II. REQUIRED CHANGES
Modify the water main design and the connections to the existing water main at Bluford Avenue,provide service
connections to customers along McKey Street,provide 4"extension for future use on McKey Street,and extend and
terminate distribution line on Cumberland Avenue,north of McKey Street.
III. JUSTIFICATION
The original design included the replacement of the existing 6"water main on McKey Street. The details of the
existing water main and distnbution system were relatively unknown at the time of the design due to the age of the
system. As the south side of the McKey Street was excavated,it became apparent that modification to the design of
the main and distribution system was necessary.Also,to serve the future needs,
IV. NARRATIVE OF NEGOTIATIONS
Prices were negotiated.
V. PAYMENT
ITEM NO. DESCRIPTION QTY UNIT UNIT PRICE TOTAL
ADDITIONAL WATER ITEMS
1 8'DIP 200 LF $ 25.00 $ 5,000.00
2 4"DIP 60 LF $ 17.50 $ 1,050.00
3 8'Cross 1 EA $ 300.00 $ 300.00
4 8'x4'Tee 1 EA $ 200.00 $ 200.00
6 Water Services 7 EA $ 850.00 $ 4,660.00
6 8'Gate Valve 1 EA 5 750.00 $ 760.00
7 4'Gate Valve 1 EA $ 450.00 $ 460.00
8 Blow Ott 3 EA S 350.00 $ 1,060.00
9 Patch Paving 950 SF S 3.00 $ 2,850.00
10 Connect b Existing 1 EA $ 500.00 f 600.00
11 8'Bend 3 EA $ 175.00 $ 626.00
SUB TOTAL $ 17,226.00
DELETE WATER ITEMS
12 Service Piping by City 6 EA S (200.00) $ (1,200.00)
TOTAL $ 16,026.00
VI. APPROVAL AND CHANGE AUTHORIZATION
This proposed change to the Contract is to be approved by the Ocoee City Commission.
Acknowledgements:
The aforementioned change,and work affected thereby,is subject to all provisions of the original contract not
specifically changed by this Change Order;and,
It is expressly understood and agreed that the approval of the Change Order shall have no effect on the original
contract other than matters expressly provided herein.
CONTRACTOR acknowledges,by its execution and acceptance of this Change Order,that the adjustments in
Contract Price and Time shown hereon constitute full and complete compensation and satisfaction for all costs and
modifications of performance time incurred by the CONTRACTOR as a result of this Change Order. No other
claim for increased costs of performance or modifications of time will be granted by the OWNER for the Work
covered by this Change Order. The CONTRACTOR hereby waives and releases any further claims for cost or time
against the OWNER arising from or relating to the matters or Work set forth or contemplated by this Change Order.
RECOMMENDED BY: ACCEPTED BY:
CITY OF OCOEE,FLORIDA GIBBS®ISTER INC.
By: By:
Signature Signature
Date: Date:
Title: Title:
APPROVED BY:
CITY OF OCOEE,FLORIDA
By:
S. Scott Vandergrift,Mayor Date
Attest:
Brenda Brasher,Acting City Clerk
FOR USE AND RELIANCE ONLY BY THE APPROVED BY THE OCOEE CITY
CITY OF OCOEE,APPROVED AS TO FORM COMMISSION IN A MEETING HELD ON
AND LEGALITY THIS DAY OF ,2004 UNDER
,2004. AGENDA ITEM NO.
FOLEY&LARDNER
By:
City Attorney