HomeMy WebLinkAboutItem E(8) Consideration of Change Order No 3 to Gibbs and Register Inc for $8,685 for Modification tot he Irrigation System and Water Distribution System for the McKey Street Project center of Good Lives
AGENDA ITEM COVER SHEET
Meeting Date: November 16, 2004
Item# 8
Reviewed By:
Contact Name: Bob Zaitooni Department Director:
Contact Number: 6002 City Manager: 6/2#/ -
Subject: Approval of Change Order No. 3 for McKey Street Project
Background Summary:
This change order is for the (1) modification to the irrigation system and (2) additional items for the new
water distribution system. Modifications to the irrigation system include extending the sleeve for the supply
line, addition of extra'/"irrigation pipe, and addition of concrete access boxes for landscape pots. The
additional items for the water distribution system include the items that were not anticipated in the original
design and are required to insure connectivity and integrity of the system.
Issue:
Approve Change Order# 3 to Gibbs & Register, Inc., for$8,685.00 and an additional 2 days time extension
for additional items for the irrigation system and water distribution system.
Recommendations
Recommend City Commission to approve Change Order#3 and authorize Mayor and City Clerk to execute
the Change Order form.
Attachments:
Change Order#3
Financial Impact:
The additional $2,995.00 budget for the irrigation system will be funded from McKey Street project funds.
The additional $5,690.00 budget for water distribution changes will be funded from the Water Utilities
Contingency funds.
Type of Item:
❑ Public Hearing For Clerk's Dept Use:
❑ Ordinance First Reading ® Consent Agenda
❑ Ordinance First Reading 0 Public Hearing
❑ Resolution 0 Regular Agenda
❑ Commission Approval
❑ Discussion&Direction
® Original Document/Contract Attached for Execution by City Clerk
O Original DocumentContract Heid by Department for Execution
Reviewed by City Attorney ® N/A
Reviewed by Finance Dept. - 8- 0 y- 0 N/A
Reviewed by ( ) l N/A
Mayor cents pfd Ll Commissioners
S. Scott Vandergrift ..,•1 -.. Danny Howell,District 1
Scott Anderson, District 2
City Manager ' Rusty Johnson, District 3
Robert Frank — Nancy J. Parker, District 4
STAFF REPORT
TO: The Honorable Mayor and City Commissioners
FROM: Bob Zaitooni,Director of Public Works
DATE: November 8,2004
RE: Change Order#3—McKey Street Project
ISSUE
Should the Honorable Mayor and City Commission approve Change Order#3 to Gibbs&Register, Inc., for
$8,685.00 for modification to the irrigation system and water distribution system for the McKey Street project?
BACKGROUND/DISCUSSION
This change order is for the(1)modification to the irrigation system and (2) additional items for the new water
distribution system including a 2-day time extension as a result of the changes.
Modifications to the irrigation system are for$2,995.00 as detailed on the attached change order form and
include extending the sleeve 300 feet for the supply line, addition of extra 200 feet of 3/4" irrigation pipe, and
addition of 22 concrete access boxes for landscape pots. The funds for this part of the change order will be
funded from the McKey Street project budget.
Changes for the water distribution system are for the amount of$5,690.00 and include the items listed on the
attached change order form. The items included in this change order were not anticipated in the original design
and are required to insure connectivity and integrity of the system. Funds for these items are available from
Water Utilities Contingency Funds.
The water distribution modifications will also require a 2-day time extension to the Contract. The new total
contract amount is$915,610.00 and the new final completion date is January 17, 2005.
Center of Good LI
,,,,,c►, CITY OF OCOEE
406,
Engineering/Utilities
- 150 North Lakeshore Drive
Ocoee, Florida 34761-2258
CHANGE ORDER NO. #3
CITY OF OCOEE
McKev Street Streetscai a Project
PROJECT NO.B04-07
DATE: November 9,2004 CONTRACTOR: Gibbs&Register,Inc.
AGREEMENT DATE: June 15,2004
The following changes are hereby made to the CONTRACT DOCUMENTS.
Original CONTRACT PRICE $890,900.00
Current CONTRACT PRICE ADJUSTED by previous CHANGE ORDER $906,925.00
Net Increase Resulting from this CHANGE ORDER $8,685.00
The current CONTRACT PRICE including this CHANGE ORDER $915,610.00
ORIGINAL CONTRACT TIME:
180 Consecutive Calendar Days from Notice to Proceed Date: January 2,2004
Current CONTRACT TIME adjusted by previous CHANGE ORDERS Date: January 15,2005
Net Increase Resulting from this CHANGE ORDER Days: 2 Days
Current CONTRACT TIME including this CHANGE ORDER Date: January 17,2005
CHANGES ORDERED:
I. GENERAL
This change order is necessary to cover changes in the work to be performed under this Contract. The
GENERAL CONDITION,SUPPLEMENTARY CONDITIONS, SPECIFICATIONS and all parts of the
Project Manual listed in Article 1,Definitions,of the GENERAL CONDITIONS apply to and govern all
work under this change order.
II. REQUIRED CHANGES
This change order is for the(1)modification to the irrigation system and(2)include additional items for the new
potable water distribution system.Modifications to the irrigation system include extending the sleeve for the
irrigation supply line,addition of extra of%"irrigation pipe,and addition of concrete access boxes for future
maintenance.The additional items for the water distribution system include the items that were not anticipated in the
original design and are requested to insure connectivity and integrity of the system.
III. JUSTIFICATION
The original design of McKey Street included a new irrigation system for the proposed landscaping. The original
design did not however include sleeves into several critical areas for the protection of the irrigation pipe did not
provide access boxes for the 22 proposed landscape pots within the project limits. An additional 200'of pipe was
also added to provide for adequate irrigation.
The changes for the water distribution system include additional items for the connectivity of the new water main
with the adjacent systems and to insure integrity of the design.
IV. NARRATIVE OF NEGOTIATIONS
Prices were negotiated.
V. PAYMENT
ITEM DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Irrigation Items
1 Concrete meter/access boxes 22 EA $ 110.00 $ 2,420.00
2 11/4" Sch 40 sleeving 300 LF $ 1.25 $ 375.00
3 3/4" PVC pipe 200 LF $ 1.00 $ 200.00
Sub-total ,$ 2,995.00
Water Distribution Items
1 6" DIP 20 LF $ 22.00 $ 440.00
2 4" Sleeve 1 EA $ 150.00 $ 150.00
3 8"x 6"Tee 1 EA $ 300.00 $ 300.00
4 8" Sleeve 1 EA $ 175.00 $ 175.00
5 8"45 Bend 4 EA $ 175.00 $ 700.00
6 8"x 6" Increaser 1 EA $ 200.00 $ 200.00
7 6" Gate Valve 1 EA $ 650.00 $ 650.00
8 6" 90 Bend 1 EA $ 175.00 $ 175.00
9 6" 45 Bend 4 EA $ 175.00 $ 700.00
10 Connect to Existing 2 EA $ 500.00 $ 1,000.00
11 Patch Paving 400 SF $ 3.00 $ 1,200.00
Sub-total $ 5,690.00
Grand Total $ 8,685,00
VI. APPROVAL AND CHANGE AUTHORIZATION
This proposed change to the Contract is to be approved by the Ocoee City Commission.
Acknowledgements:
The aforementioned change,and work affected thereby, is subject to all provisions of the original contract not
specifically changed by this Change Order;and,
It is expressly understood and agreed that the approval of the Change Order shall have no effect on the original
contract other than matters expressly provided herein.
CONTRACTOR acknowledges,by its execution and acceptance of this Change Order,that the adjustments in
Contract Price and Time shown hereon constitute full and complete compensation and satisfaction for all costs and
modifications of performance time incurred by the CONTRACTOR as a result of this Change Order. No other
claim for increased costs of performance or modifications of time will be granted by the OWNER for the Work
covered by this Change Order. The CONTRACTOR hereby waives and releases any further claims for cost or time
against the OWNER arising from or relating to the matters or Work set forth or contemplated by this Change Order.
RECOMMENDED BY: ACCEPTED BY:
CITY OF OCOEE,FLORIDA GIBBS®IS I'ER,INC.
By: By:
Signature Signature
Date: Date:
Title: Title:
APPROVED BY:
CITY OF OCOEE,FLORIDA
By:
S. Scott Vandergritt,Mayor Date
Attest:
Beth Eickenberry, City Clerk
FOR USE AND RELIANCE ONLY BY THE APPROVED BY THE OCOEE CITY
CITY OF OCOEE,APPROVED AS TO FORM COMMISSION IN A MEETING HELD ON
AND LEGALITY THIS DAY OF ,2004 UNDER
,2004. AGENDA ITEM NO.
FOLEY&LARDNER
By:
City Attorney
OCT-28-2004 1340 P.02
GIBBS & REGISTER, INC.
I v_ 1 '-N.I\ 530 South Main Street
Winter Garden,Florida 34787
Telephone:(407)654.6133
Facsimiles(407)6546134
October 28, 2004
Bob Zaitooni
City of Ocoee Public Works
150 North Lakeshore Drive
Ocoee, Florida 34761
Re: McKey Street Improvements
Subject: Request for Change Order#2 Revised
Changes to Water Distribution Plans
Dear Mr. Zaitooni:
Per your request,please find below G&R revised price to make the changes to the
water distribution plans so the 6"main on McKey Street east is connect and southbound
Bulford Avenue is also connect to the new main so the system will be looped.These
changes are an extra and were not part of the original bid or change order#1. Please find
below a cost breakdown for the changes for the above-mentioned work:
ITEM No. DESCRWflO11 OTT (ROT UNIT PRICE TOTAL
ADDITIONAL WATER ITEMS
_ 1 8'DIP 20 LF $ 22.00`$ 410.0o
2 4'Sleeve 1 EA S 150.00 i 160.00
S 6x6'Tao 1 EA $ 300.00 $ 300.00_
4 8-Sleeve 1 EA $ 175.00 $ 178.00
5 0.45 Bend 4 EA 5 175.00 $ 700.00
6 8116'Increaser 1 EA S 200.00 $ 200.00
7 V Oats Vie I EA 6 $50.00 $ 650.00
s 6*00 Band I EA $ /75.00 $ 175.00
6 4r 45 Band 4 EA S 175.00 $ 700.00'
10 Connect to Existing 2 EA 5 500.00 $ 1,000.00
11 Patch Paving 400 SF $ 3.00 $ 1200.00
��. TOTAL $ 5,50.00
Additional Contract Days—2 days
Please review the above proposal and if satisfactory issue a Change Order for$5,690.00
for the installation of the above work. And as always feel free to call should you have any
questions.
Sincerely:
Gibbs&Register,Inc.
dert44-4A. •
J. Kalish
Sr.Project Manager
TOTAL P.02
OCT-25-2004 1027 P.03
GIBBS & REGISTER, INC.
530 South Main Street
Winter Garden,Florida 34787
Telephone:(407)654-6133
Facsimile:(407)6546134
October 25,2004
Bob Zaitooni
City of Ocoee Public Works
150 North Lakeshore Drive
Ocoee, Florida 34761
Re: McKey Street Improvements
Subject: Request for Change Order#3
Changes to Irrigation Plans
Dear Mr.Zaitooni:
Per your request,please find below G&R price to make the changes to the
irrigation system so that the piping to the cast stone planters would have sleeving and a
meter box under it so future repairs could be made. These changes are an extra and were
not part of the original bid. Please find below a cost breakdown for the changes for the
above-mentioned work:
ITEM NO. DESCRIPTION OTT UNIT- MAT PRICE TOTAL
ADDITIONAL.IRRIGATION ITEMS
1 Concrete miter boxy 22 EA 5 110.00 ! 2420.00
2 11/4'Soh 40 sMwino 300 LF 5 1.25 $ 37400
3 3br PVG 200 LF 5 1.00 $ 200.00
TOTAL $ 2,91400
Please review the above proposal and if satisfactory issue a Change Order for 52,995.00
for the installation of the above work. And as always feel free to call should you have any
questions.
Sincerely:
Gibbs&Register,Inc.
p' 2,j7'
Robert J.Kalish'
Sr. Project Manager
TOTAL P.03