MEMORANDUM
DATE: September 26, 1994
TO: The Honorable Mayor and Board of City Commissioners
FROM: James W. Shira, P.E.
City Engineer/Utiliti Director
SUBJECT: Storm Drain Repairs - Flewelling and Ocoee Hills
= ago==
On August 16, 1994 the City Commission awarded an emergency contract to C.A. Meyer for
repair to a storm sewer at this intersection. The award was for the amount of $21,910.00. This
amount was based on their bid, which anticipated removal and replacement of 200 square
yards of pavement. Due to the high water table, the whole intersection and the majority of the
Flewelling Avenue pavement was destroyed in order to get a hole opened up large enough to
work in without danger of cave-ins. This caused the pavement removal and replacement
quantity to more than double the estimated amount. The work is complete, and the final field
measured quantity of pavement removal and replacement is 483 square yards, which added
$5,518.50 to the bid amount. The final amount of the work is $27,428.50. The other two
original bids were $42,500 and $81,500.
There are sufficient funds in the Stormwater Contingency account to cover this extra cost. I
recommend that the City Commission authorize the expenditure of an additional $5,518.50
from Stormwater Contingency for repairs to the storm sewer at the intersection of Flewelling
and Ocoee Hills.