Loading...
Item #10 Award of RFQ #1401 Engineering Services for Ocoee West Sanitary Transmission ProjectI laka � X -4. df� 0C0(?P Florida AGENDA ITEM COVER SHEET Meeting Date: January 6, 2015 Item # i 0 Reviewed By: Contact Name: Joyce Tolbert Department Director: Contact Number: 1516 City Manager: Subject: Award of RFQ #1401 Engineering Services for Ocoee West Sanitary Transmission Proiect Background Summary: In compliance with the Consultants' Competitive Negotiations Act (CCNA), Florida Statutes Section 287.055 and Chapter 21 of the City's Code of Ordinances, the City solicited statements of qualifications from qualified professional engineering, engineering /surveying firms /teams that are interested in providing design, coordination, permitting and bidding services for the City's Ocoee West Sanitary Transmission Project. The project consists of 21,400 feet of 12" to 20" diameter sanitary sewer forcemain and a regional master lift station. The selected Consultant will assist the City by supplying sanitary sewer transmission design, coordination, permitting, and bidding services needed to support the project. The RFQ was advertised on August 3, 2014 and was publicly opened on September 9, 2014. There was a pre - submittal conference held on August 19, 2014. There were six (6) responses submitted. The Finance and Utilities Departments reviewed the proposals and all were considered responsive, see the attached Checklist. Attached are the six ranked responses; original copies of all responses are available in the Finance Department for your review. The six (6) responses were evaluated by the RFQ Evaluation Committee appointed by the City Manager, which was comprised of four (4) members: Richard Campanale, Public Works Operations Manager; Michael Rumer, City Planner; Charles Smith, Utilities Director; and David Wheeler, City Engineer. The public RFQ Evaluation Committee meeting was held on September 30, 2014 with the Evaluation Committee evaluating and short- listing the firms on specific evaluation criteria. Please see the attached shortlist /evaluation form. The evaluation committee short- listed the following firms in ranked order, and recommends contracting with the top ranked firm, BFA Environmental, per the attached award recommendation from the Utilities Director. The Table below is the Evaluation Committee's rankings: Rank /Respondent 1. d /b Barnes, Ferland and Associates Inc. /a BFA Environmental 2. Pegasus Engineering LLC 3. Inwood Consulting Engineers Inc. 4. (Tie) Atkins North America Inc. 4. (Tie) Dewberry/Bowyer-Singleton 5. Neel- Schaffer Inc. Issue: Should the City Commission award the continuing contract for Engineering Services for Ocoee West Sanitary Transmission Project to the top- ranked firm, BFA Environmental, as recommended by the Evaluation Committee? Recommendations: Staff recommends that the City Commission award RFQ #1401 Engineering Services for Ocoee West Sanitary Transmission Project to Barnes, Ferland and Associates Inc., d /b /a BFA Environmental, and authorize Staff to proceed with contract negotiations with the selected firm, and authorize the Mayor, City Clerk, and staff to execute all necessary contract documents with this firm once the required insurance is received. Per the State of Florida CCNA Act Statute 287.055, if contract negotiations are unsuccessful with the top- ranked firm, staff shall terminate negotiations and initiate negotiations with the next ranked firm, and so on, until an agreement is reached. Attachments: 1. RFQ #1401 2. Addendum #1 3. BFA Response 4. Pegasus Response 5. Inwood Response6. 6. Evaluation Form /Shortlist 7. RFQ Checklist 8. Award Recommendation from Utilities Director Financial Impact: The Engineer's Planning Level Opinion of Probable Cost (2014) for the Western Transmission Main project is $7,228,108.00 with $625,000.00 pre- staged with the Bluford Storm Water and the Dollar General Projects. Also included with this work is the initial phase of the Downtown Sewer Project with a planned $500,000 expenditure. Based on the remaining work for the transmission project and downtown work. The project's complexity has been reduced to the hydraulic design work and liftstation design work being completed by others. Engineering fees should range around $450,000. Type of Item: (please mark with an 'k') Public Hearing For Clerk's Dept Use: Ordinance First Reading Consent Agenda Ordinance Second Reading Public Hearing Resolution Regular Agenda X Commission Approval Discussion & Direction Original Document/Contract Attached for Execution by City Clerk X Original Document/Contract Held by Department for Execution Reviewed by City Attorney Reviewed by Finance Dept. Reviewed by ( ) N/A N/A N/A 2 Mayor S. Scott Vandergrift City Manager Robert Frank TO: Honorable Mayor and City Commission I ko � �1� _ 0 11-> florida MEMORANDUM THRU: Robert Frank City Manager FROM: Charles K. Smith, P.E. Utilities Director r f DATE: November 4, 2014 Commissioners John Grogan, District 1 Rosemary Wilsen, District 2 Rusty Johnson, District 3 Joel F. Keller, District 4 RE: Recommendation for Award of RFQ #1401 Engineering Services for Ocoee West Sanitary Transmission Project Based on the review of the submittal Engineering Firm's qualifications, including but not limited to experiences, project approach, and team members, and firms reference checks the RFQ Evaluation Committee recommends the awarding of the engineering design service for the Ocoee West Sanitary Transmission Project and Downtown sewer project to Barnes, Ferland and Associates Inc. (d /b /a BFA Environmental). City of Ocoee Utilities • 1800 A.D. Mims Road • Ocoee, Florida 34761 Phone: (407) 905 -3159 • Fax: (407) 877 -5899 • www.ocoee.org RFQ #1401 ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT EVALUATION FORMISHORTLIST Barnes, Ferland and Associates, Respondent Atkins North America, Inc. d/b /a BFA Environmental Evaluator 1 Evaluator 2 Evaluator 3 Evaluator 4 Vi Neel- Schaffer, Inc. TOTAL RANKING Note. Lowest Total is Highest Ranking Dewberry Engineers, Inc. d1b /a Dewberry/Bowyer- Singleton Inwood Consulting Engineers, Inc. Neel- Schaffer, Inc. Pegasus Engineering, LLC y l 1 "7 1 RFQ #1401 ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT INDIVIDUAL EVALUATION FORM 0� Evaluator Name Charles K. tI Evaluator Signaturo_ �� Barnes, Ferland and Associates, Inc. Dewberry Engineers, Inc. Inwood Consulting Engineers, Inc. Neel- Schaffer, Inc. Pegasus Engineering, LLC Evaluation Criteria Atkins North America, Inc. dlb /a BFA Environmental d /bla Dewberry/Bowyer- Singleton Experience of the firm & project team: Past Performance & Experience of the Firm; Past Performance d Experience of the Team Members; Past Performance & Experience with or in the City; Overall Experience; References 25 26 24 29 (0-40 Points) 30 32 Ability to Meet Time and Budget Requirements: Projected Workloads of the Finn; Affect of Legal Action Against the Firm 15 15 1 y 10 (0 -20 Points) 15 15 Project Approach: Briefly describe your Firm's understanding of the services requested and how the firm would accomplish the work. 20 22 22 23 (0 - 30 Points) 25 27 Office Location: Location of the Office and Proximity to the City of Ocoee 4 4 q 4 (0 -5 Points) A 4 Certified Minority Business Enterprise: Include copy of MBE cerlificalion 3 3 0 5 (0.5 Polnis) 0 5 TOTAL POINTS 67 70 85 71 (0 -100 Points) 74 83 2 1 5 4 6 3 MEMBER RANKING Evaluator Name Charles K. tI Evaluator Signaturo_ �� RFQ #1401 ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT / INDIVIDUAL EVALUATION FORM 1 7 Evaluation Criteria Atkins North America, Inc. Barnes, Feriand and Associates, Inc. d /b /a BFA Environmental Dewberry Engineers, Inc. d /b /a DewberrylBOwyer- Singlelon Inwood Consulting Engineers, Inc. Neel- Schaffer, Inc. Pegasus Engineering, LLC Experience of the firm 8 project team: Past Performance & Experience of the Firm; Past Performance & Experience of the Team Members; of 35 3 V 3 0 3 5 [ 3 J Past Performance & Experience with or in the City; Overall Experience; References (0 -40 Points) Ability to Meet Time and Budget Requirements: Projected Work'oads of the Firm; Affect of Legal Action Against the Firm (0 -20 Points) Project Approach: Briefly describe your Firm's understanding of the services requested and 2.5 [ Z s Z 5 �, 7. z . 5 how the firm would ,S accomplish the work. (0 -30 Points) Office Location: Location of the Office and Proximity to the City of Ocoee 4 4 4 4 4 (0 -5 Points) 4 Certified Minority Business Enlerprise: t7 T S `� t S u f Vt� n Include copy of MBE Codification 5 3 3 0 5 (as Points) 0 TOTAL POINTS 4 9 7 4 y (0.100 Points) V 4 r �. 2— ply . MEMBER RANKING f Evatualor flame _ - - Evaluator Signature y • -- - -- - - -- RFQ #1401 ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT INDIVIDUAL EVALUATION FORM 0 Evaluator Name M • - a Evaluator Stgnelure _ _ _ Barnes, Ferland and Associates, Inc. Dewberry Engineers, Inc. Inwood Consulting Engineers, Inc. Neel- Schaffer, Inc. Pegasus Engineering, LLC Evaluation Criteria Atkins North America, Inc. dlbla BFA Environmental dlbla DewberrylRowyer- Singleton Experience of the firm & project team: Past Performance & Experience of the Firm, Past P e rfo r m ance & Experience of the Team Members; of the T d � O Past Performance & Experience with or In the City; Overall Experience; References (0-40 Points) Ability to Meet Time and Budget R equirements ; / I ' d Workloads o Projected Workloads of ( the Firm; Affect of Legal Action Against the Ft; m (0 -20 Points) Project Approach: Briefly describe your Firm's understanding of the services requested and how the firm would accomplish the work. (0 - 30 Points) a� C/• CC / Office Location: Location of the Office and Proximity to the City of Ocoee 4 4 4 4 4 (0 -5 Points) 4 Certified Minority Business Enterprise: Include copy of MBE Certification 5 3 3 0 5 (0 -5 Points) 0 - TOTAL POINTS Points) (0-100 MEMBER RANKING Evaluator Name M • - a Evaluator Stgnelure _ _ _ RFQ #1401 ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT INDIVIDUAL EVALUATION FORM Evaluator Name Evaluator Signature 00 7 190 , 5 1 P. 0221 V. 01—A Barnes, Ferland and Associates, Inc. Dewberry Engineers, Inc. Inwood Consulting Engineers, Evaluation Criteria Akins North America, Inc. dlbla BFA Environmental d /bla Dewberry/Bowyer - Singleton Inc. Neel- Schaffer, Inc. Pegasus Engineering, LLC Experience of the firm & - project team: Past Performance & Experience of the Firm; Past Performance & Experience Of the Team Members, Past Performance & Experience with or in the City; Overall Experience;Reforences 39 39 (0.40 Points) 38 39 38 38 Ability to Meet Tlme and Budget Requirements: Projected Workloads of "* the Firm; Affect of Legal F Action Against the Firm 18 18 (0 -20 Points) 15 18 17 17 Project Approach: Briefly describe your Firm's underslanding of the T services requested and how the firm would > accomplish the work. 28 28 (0 - 30 Points) 25 29 21 28 Office Location: Location 'f of the Office and Proximity to the City of Ocoee _ 4 (0-6 Points) 4 4 4 4 4 Certified Minority Business Enterprise: Include copy of MBE - artlffcatron 4 0 -6 Points) 5 3 3 0 $y TTO § t yy TOTAL POINTS g (0.100 Points) 3 82 1 95 83 90 89 94 MEMBER RANKING 1 6 1 5 3 4 1 2 Evaluator Name Evaluator Signature 00 7 190 , 5 1 P. 0221 V. 01—A RFQ #1401 ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT CHECKLIST 9/09/14 2:00 PM RESPONDENT Submission Requirements - Qualifications, References, Litigation Acknowledge Addendum #1 Company /License Verification MBE CERT. Company Info/ Signature Sheet Office Location No. Atkins North America, Inc. ✓ ✓ Active none ✓ Orlando, FL 1 2 I Barnes, Ferland and Associates, Inc. d/b/a BFA Environmental ✓ ✓ Active Respondent ✓ Orlando, FL 3 Dewberry Engineers, Inc. d /b /a Dewberry/Bowyer- Singleton ✓ ✓ Active Subconsultant ✓ Orlando, FL 4 Inwood Consulting Engineers, Inc. ✓ ✓ Active Subconsultant ✓ Oviedo, FL 5 Neel- Schaffer, Inc. ✓ ✓ Active none ✓ Maitland, FL 6 Pegasus Engineering, LLC ✓ ✓ Active Respondent ✓ Winter Springs, FL CITY OF OCOEE REQUEST FOR QUALIFICATIONS (RFQ) #1401 ENGINEERING SERVICES FOR Ocoee West Sanitary Transmission Project 4 2: A v n. MrOTHM Request for Qualifications, Legal Advertisement The City of Ocoee, Florida, (City) is soliciting for sealed statements of qualifications for RFQ 41401 Engineering Services for Ocoee West Sanitary Transmission Project. Qualification Packages will be received at the office of Joyce Tolbert, CPPB Purchasing Agent, Finance Department/Purchasing, Second Floor, 150 North Lakeshore Drive, Ocoee, Florida 34761 until 2:00 pm, local time, on September 9, 2014. Qualification Packages received after that time will not be accepted under any circumstances. Sealed qualification packages that have been timely received will be publicly opened and the name of the responding firms read aloud at that time. A non - mandatory Pre - Submittal Conference is scheduled for August 19, 2014, at 10:00 am, local time, at Ocoee City Hall, 150 N. Lakeshore Dr., Ocoee, FL 34761. Prospective respondents may secure a copy of the documents required for submitting a response through Onvia /Demandstar by accessing the City's website at httl,):/ /www.ococe.or� under Finance /Purchasing. Partial sets of the documents required for submitting a response will not be issued. By using Onvia /Demandstar, prospective respondents will be provided with all information regarding this RFQ and addendums and changes to the project requirements. Membership with Onvia /Demandstar is not required to submit a response; fees may apply for non - members. Persons other than prospective respondents may inspect the documents required for submitting a response at the Ocoee City Hall City Clerk's Office, 150 N. Lakeshore Drive, Ocoee, FL 34761. Persons inspecting the documents at the City Clerk's office that request copies will be required to pay a fee, as prescribed by statute. Beth Eikenberry, City Clerk, August 3, 2014. RFQ 9 1401 - ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT 2 CITY OF OCOEE REQUEST FOR QUALIFICATIONS "RFQ" 41401 ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT A. INTRODUCTION AND GENERAL INSTRUCTIONS The City of Ocoee, Florida, in conformance with the Consultants' Competitive Negotiations Act (CCNA), Florida Statutes Section 287.055, and the policies and procedures of the City of Ocoee (City) is soliciting statements of qualifications from qualified professional engineering, engineering /surveying firms /teams that are interested in providing design, coordination, permitting and bidding services for the City's " OCOEE WEST SANITARY TRANSMISSION PROJECT ". The project consists of 21,400 feet of 12" to 20" diameter sanitary sewer forcemain and a regional master lift station. The City may elect to breakup and /or phase the project. The project will include coordination with liftstation and hydraulic design efforts (by others). For more details of the project, the "Ocoee West Wastewater Utility Plan Study ", dated August 2008 and "Western Force Main Route Study ", dated June 2011, prepared by Reiss Engineering Inc. is available at: Responding firms (Respondent) must be experienced in providing engineering services for projects of a scope and nature comparable to those described. Use of qualified subconsultants for specialty work is acceptable. To be considered, the firm shall be qualified by a licensed professional in accordance with Florida State law and be familiar with all applicable State of Florida, St. Johns River Water Management District, Orange County, and City land development codes, regulations, and laws, and with City and Orange County construction standards. The selected Consultant will assist the City by supplying sanitary sewer transmission design, coordination, permitting, and bidding services needed to support the PROJECT. It is anticipated that both geotechnical and professional land survey services will be needed in support of the design of the PROJECT. Consultant will be tasked with preparing a detailed scope and necessary support services, where the City will procure those services utilizing ongoing professional contracts. 2. The City intends to award a contract to one (1) qualified engineering firm, but may elect to divide the work between multiple qualified engineering firms, to perform the required services. In determining whether a firm is qualified, the City shall consider such factors as: the firm's locale and similar project experience, firm's experience providing similar services, firm's past project performance in terms of scheduling and budget compliance, abilities of the professional firm's project personnel; and whether a firm is a certified minority business enterprise. 3. Prospective respondents may secure a copy of the documents required for submitting a response through Onvia /Demandstar by accessing the City's website at http: / /�vww.ocoee,M under Finance /Purchasing. Partial sets of the documents required for submitting a statement of qualifications will not be issued. By using Onvia /Demandstar, prospective respondents will be provided with all information RFQ #1401 — ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT 3 regarding this RFQ, all addendums and changes to the project requirements; Fees may apply for non - members. Membership with Onvia /Demandstar is not required to submit a response. 4. Each qualification package must consist minimally of a cover letter, statement of qualifications, and company information form (attached at the end of these instructions). Please also include a copy of all applicable licenses held by firms or key subconsultants proposing to perform the work. Statements of qualifications must be limited to a total of forty (40) 8.5 "x 11" pages (including any resumes and 2 -page cover letter but excluding front and back covers, dividers, table of contents, and company information form), single- sided, portrait orientation, 12 -point font. Additional requirements of submissions are supplied below in Section D. Any qualifications package failing to conform to these specifications is subject to rejection. The person signing the signature sheet on behalf of the respondent must have the legal authority to bind the respondent to the submitted qualification package and shall be understood to do so. All expenses for providing qualification packages to the City shall be borne by the respondent. 5. Firms, companies and /or individuals interested in providing these services shall submit one (1) original paper, one (1) paper copy, and four (4) electronic copies of their qualifications package. The electronic copies shall be submitted in a fully electronic form on a labeled CD -ROM or USB FLASH DRIVE as an Adobe PDF file, version 5 or later. Qualification Packages shall be submitted to the City of Ocoee in one sealed package, clearly marked on the outside with the appropriate RFQ number and closing date and time, addressed to: Joyce Tolbert, Purchasing Agent City of Ocoee 150 N. Lakeshore Drive Ocoee, Florida 34761 Phone: (407) 905 -3100 x 1516 FAX number: (407) 905 -3194 jtolbert @ci.ocoee.fl.us No fax or e- mailed submissions will be accepted 6. Qualification packages must be received no later than 2:00 p.m. (local time) on September 9, 2014. Any qualification packages received after the above -noted time will not be accepted under any circumstances. Any uncertainty regarding the time a qualification package is received will be resolved against the Respondent. It shall be the sole responsibility of the Respondent to have the qualifications package delivered to the Ocoee City Hall by U.S. mail, hand delivery, or any other method available to them. Delay in delivery shall not be the responsibility of the City. A qualifications package received after the deadline shall not be considered and shall be returned unopened. Any request to withdraw a qualifications package must be addressed in writing. Such requests must be received by the City prior to the deadline of the submission. RFQ #1401 - ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT 4 7. Pre - Submittal Conference: A non - mandatory pre - submittal conference is scheduled for August 19, 2014 at 10:00 A.M., local time, in the City Hall Commission Chambers, 150 N. Lakeshore Dr., Ocoee, FL 34761. All Respondents will be held liable for information presented at the pre - submittal conference, as any clarifying addendums issued as a result of questions asked and answered at the pre- submittal conference may not be all - inclusive. The City will receive questions regarding the RFQ only through written inquiries directed to the Purchasing Agent. Deadline for receipt of written inquiries will be August 28, 2014 at 2:00 p.m., local time. 8. Potential Respondents should not contact City staff, with the exception of the Purchasing Agent, or other City consultants or City Commission for information regarding this RFQ before the project award date. Any contact with any other member of the City Staff, City Commission, or its consultants during the RFQ, award, and protest period may be grounds for Respondent disqualification. 9. Action on qualification packages is expected to be taken by the City Commission within ninety (90) days of the submission opening date; however, no guarantee or representation is made herein as to the time between receipt of the qualification package and subsequent City Commission action. A more detailed schedule is given below. 10. All applicable laws and regulations of the United States, the State of Florida, and the City of Ocoee will apply to any resulting Agreement. The provisions of the Consultant's Competitive Negotiations Act (Section 287.055, Florida State Statutes) shall apply, where applicable. 11. The successful Respondent shall be required to execute an Agreement, in form and content acceptable to the City, indemnifying and holding harmless the City, its officials, officers, employees, and agents from all clairns. 12. CONVICTED VENDOR LIST (PUBLIC ENTITY CRIME): A person or affiliate who has been placed on the convicted vendor list following a conviction for a public entity crime may not submit a proposal on an award to provide any goods or services to a public entity, may not submit a proposal on an award with a public entity for the construction or repair of a public building or public work, may not submit proposals on leases of real property to a public entity, may not be awarded or perform work as a Contractor, Supplier, Subcontractor, or Consultant under a award with any public entity, and may not transact business with any public entity in excess of the threshold amount provided in section 287.017 for Category Two for a period of 36 months from the date of being placed on the convicted vendor list. [See Florida State Statute 287.133 (2) (a). 13. FLORIDA PUBLIC RECORDS LAW: In accordance with Chapter 119 of the Florida Statutes, and, except as may be provided by Chapter 119 of the Florida Statutes and other applicable State and Federal Laws, all Respondents should be aware that the proposal and the responses thereto are in the public domain and are available for public inspection. Respondents are requested, however, to identify RFQ #1401 -ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT 5 specifically any information contained in their proposal which they consider confidential and /or proprietary and which they believe to be exempt from disclosure, citing specifically the applicable exempting law. All proposals received in response to this request of proposal become the property of the City of Ocoee and will not be returned. In the event of an award, all documentation produced as part of the contract will become the exclusive property of the City. 14. PATENT INDEMNITY: Except as otherwise provided, the successful respondent agrees to indemnify the City and its officers, agents, and employees against liability, including costs and expenses for infringement upon any letters patent of the United States arising out of the performance of this Contract or out of the use or disposal by or for the account of the City or supplies furnished or construction work performed hereunder. Further, the Respondent shall fully indemnify, defend, and hold harmless the City and its officers, agents, and employees from any suits, actions, damages, and costs of every name and description, including attorneys' fees, arising from or relating to violation or infringement of a trademark, copyright, patent, trade secret, unpatented invention, or intellectual property right. If the bidder uses any design, device, or materials covered by letters, patent, or copyright, it is mutually agreed and understood without exception that the bid price shall include all royalties or cost arising from the use of such design, device, or materials. 15. The City reserves the right to accept or reject any or all proposals, to waive formalities, technicalities or irregularities, to request clarification of information submitted in any proposal, or to re- advertise for new proposals. The City may accept any item or group of items of any proposal, unless the Respondent qualifies its proposal by specific limitations. The City may accept one or more proposals if, in the City's discretion, the City determines that it is in the City's best interest to do so. The City reserves the right to award the contract to the Respondent which, in the City's sole discretion, is the most responsive and responsible Respondent The City reserves the right, as an aid in determining which proposal is responsible, to require a Respondent to submit such additional evidence of Respondent's qualifications as the City may deem necessary, and may consider any evidence available to the City of the financial, technical, and other qualifications and abilities of a Respondent, including past performance (experience) with the City and others. The City Commission shall be the final authority in the selection of any and all proposals. B. INSURANCE TERMS AND CONDITIONS The successful respondent shall be required to provide evidence of both General (Public & Property) Liability and Professional (Design Errors and Omissions) Liability Insurance in the form of a certificate of insurance issued on behalf of the City of Ocoee and naming the City as an additional insured, by companies acceptable to the City at the minimum limits and coverages listed below with deductible amounts acceptable to the City. The selected consultant shall not commence any work in connection with an Agreement until all of the following types of insurance have been obtained and such insurance has been approved by the City, nor shall the consultant allow any subconsultant to commence work on a RFQ #1401 - ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT subcontract until all similar insurance required of the subconsultant has been so obtained and approved. Policies other than Workers' Compensation shall be issued only by companies authorized by subsisting certificates of authority issued to the companies by the Department of Insurance of Florida which maintain a Best's Rating of "A" or better and a Financial Size Category of "VII" or better according to the A.M. Best Company. Policies for Workers' Compensation may be issued by companies authorized as a group self - insurer by F.S. 440.57, Florida Statutes. 1. Loss Deductible Clause: The City shall be exempt from, and in no way liable for, any sums of money which may represent a deductible in any insurance policy. The payment of such deductible shall be the sole responsibility of the General Consultant and /or subconsultant providing such insurance. 2. Workers' Compensation Insurance The Consultant shall obtain during the life of this Agreement, Worker's Compensation Insurance with Employer's Liability Limits of $500,000 /$500,000 /$500,000 for all the Consultant's employees connected with the work of this project and, in the event any work is sublet, the Consultant shall require the subconsultant similarly to provide Workers' Compensation Insurance for all of the latter's employees unless such employees are covered by the protection afforded by the Consultant. Such insurance shall comply fully with the Florida Workers' Compensation Law. In case any class of employees engaged in hazardous work under this contract for the City is not protected under the Workers' Compensation statute, the Consultant shall provide, and cause each subconsultant to provide adequate insurance, satisfactory to the City, for the protection of the Consultant's employees not otherwise protected. Include Waiver of Subrogation in favor of the City of Ocoee. 3. Consultant's Public Liability and Property Damage Insurance The Consultant shall obtain during the life of this Agreement COMMERCIAL AUTOMOBILE COVERAGE, this policy should name the City of Ocoee as an additional insured, and shall protect the Consultant and the City from claims for damage for personal injury, including accidental death, as well as claims for property damages which may arise from operations under this Agreement whether such operations be by the Consultant or by anyone directly or indirectly employed by the Consultant, and the amounts of such insurance shall be the minimum limits as follows: 4. Automobile Bodily Injury Liability & Property Damage Liability • $1,000,000 Combined single limit per occurrence (each person, each accident) • All covered automobile will be covered via symbol I • Liability coverage will include hired & non -owned automobile liability • Include Waiver of Subrogation in favor of The City of Ocoee 5. Comprehensive General Liability (Occurrence Form) - This policy should name the City of Ocoee as an additional insured and should indicate that the insurance of the Consultant is primary and non - contributory. • $2,000,000 GENERAL AGGREGATE • $2,000,000 PRODUCTS- COMPLETED OPERATIONS AGGREGATE • $1,000,000 PER OCCURRENCE • $1,000,000 PERSONAL & ADVERTISING INJURY RFQ #1401 - ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT 7 • Include Waiver of Subrogation in favor of the City of Ocoee Subconsultant's Comprehensive General Liability Automobile Liability and Worker's Compensation Insurance The Consultant shall require each subconsultant to procure and maintain during the life of this subcontract, insurance of the type specified above or insure the activities of these subconsultants in the Consultant's policy, as specified above. Owner's Protective Liability Insurance (Not applicable for Engineering Services). As applicable for construction projects, providing coverage for the named insured's liability that arises out of operations performed for the named insured by independent consultants and are directly imposed because of the named insured's general supervision of the independent consultant. The Consultant shall procure and furnish an Owner's Protective Liability Insurance Policy with the following limits: $1,000,000, and per occurrence, $2,000,000. Aggregate and naming the City of Ocoee as the Named Insured. Contractual Liability If the project is not bonded, the consultant's insurance shall also include contractual liability coverage to insure the fulfillment of the contract. NOTE: PUBLIC LIABILITY INSURANCE AND AUTOMOBILE LIABILITY INSURANCE, THE CITY SHALL BE NAMED AS ADDITIONAL INSURED. • $1,000,000 PER OCCURRENCE • $2,000,000 AGGREGATE Commercial Umbrella: • $1,000,000 PER OCCURRENCE • $2,000,000 Aggregate • Including Employer's Liability and Contractual Liability Builders Risk: (Not Applicable for Engineering Services). • $100,000 Any (1) Location • $1,000,000 Any (1) Occurrence (remainder of page left blank intentionally) RFQ #1401 - ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT -- of Ins ¢ATE,M " "¢gnYYYt ACORD_ CERTIFICATE OF LIABILITY INSURANCE FRAZS -1 I i1t04104 raq¢u¢EE THIS CERTIFI�15 ED T A MATTER O R F INFOMATION ONLY CERTTC IGHTS UPON THE CERTIFIINFOCATE HOLDER. THITE DOES NOT AMEND, EXTEND OR ALTER THE C FORDED HY THE PO LICIES HELOly INSURERS A COVERAGE ,,. NAIC a Contractor's Name �"SuRER t. ..... Address r-.. -.— _.. �ra]uREa4 OVERAGES _ - -- 41NG Cn EHIKiCw�1E T Nl.v i OR QT POCC4WEMw � YEC i W«�N 9C aE �aSt.gQ OP «] ANY REgUR1EMfxt, L�EP�M OR CONfRT10N OF AM'C�ONTaSC uEY RERTA +N. THE iMSURANCE AifOROEO ev TUE pQLiCiEa OESCRiRED«EREW SSUCJE:T 14 AU CNE TERMS, EXLLUSb «SA «, CgN0�ii0 ROE�OES AGGPECATELWITS SHOWNW Ha'rE 6EEN RE4/Y.ED av oRl0 tV.5U _.____. —.-- .—... �. .--.. .__. .. . _.____ Nsfp TYRE OE WS4RAN RgLCY NUMBFA '. I4N ¢aTI ISIES't� ',E� «OGCURAENLE Sl, OOO, OOO_ EnAt.Lwrtm � I a SO 000_ T Y eoEaaRC.+L aENEPAL "octuR� Me4 ExR,+EY 1 � 000 -- )cuu•ns u.5x L� J eERSO+us +«!SPY 51 000 X 000 _ i. GE «ERAia oPr TE s1, 000__ _.._ __ POLICY 2; i �'. LCG �i � ]Rrest OW 51,000.000 AUTONSOaRE LYeaIIY I IEr mi.'axl j[ ANY P4T0 ¢oaLY Wx/RY y 1 aU[CS � 9OD x! NWFO AUTOS ESRi Y 1 iPr xT—) 5 y'.�rR)NLWNEO '', PROPERTY M.wGL y 1 ¢APACE tSAaR.m T— vEUtO ATRER uTO MT AQp S .-- E.rtn 4ccuRRlncE S 1.000, 000 excfsw'wResu S.MmLm i QcReq�TE _ s Z 000, 000 _ X X + occur cUR.a A 1 CEllUGTtaIE - _--- 5_.— —.- -- YeOR %ERS CO ✓ExaAT�ON K10 F t. fAC« 'C+QE�T -- S SOO r OOO__. i pMPL.¢vERTLWhiTY .____�— .-- ... � E.E DISEASE. EA fiuPLOVEE 5 OOO 5011, __... I Am PROPSUETOR+PAP'NERh I/ECUSrrE p[[iQlWLNrMaER E)cCWDf¢t __,__ e wsEw -POUCV .an 1 500 , 000 _ OTNER Any 1 Loc 10() ,000 ld Risk An T c)" 1,000,000..__ Hui era i DESCRiPTgN C# OP EMTMk19 +LOCATf)MS /Y!)flCLU+E%CLU]10 «a 1,6¢EO 6Y E s hat /S �R c ificate shall name the certificate The insurance evidenced by this cart holders as an additional insured on thloGersraLiabilitytG Gemara l l Liability Liability. Workers' Compensation, Rmp Y shall contain a Waiver of Subrogation is favor of the certificate holder. The Certificate holder is added as a Emed irourud fTr PUL.1�.E' 14 Riik- E HOLDER OCOZ801 p10'-aDiL"Y°FT'rf ASOVS!¢ExR/sE4 roLE�l9 sE CANCaLfQ afPORf THE fSPraATW* DATE THEREQP. na as Wq +MSUefR wR.L EN¢EAYOR Tq MNI lO Wva WRITTEN NOME TO TRf CfiST,FlCATE HGLOlP —W TO THE LEPT, OUT FEAURE TO W SO s L 4e0Ef NO 05U MR GR LMNIJTY O/ ANY KiNb UPON THE +N4UREF, RS AGENTS QR City of Ocoee . 150 N. Lakeshore Drive Ocoee FL 34761 - 2258 AUTRONtlEDRURESEN*.TNE n Rowrosl 9. Certificates of Insurance Certificate of Insurance Form (see sample, above), naming the City of Ocoee as an additional insured will be furnished by the Consultant upon notice of award. These shall be completed by the authorized Resident Agent and returned to the Office of the Purchasing Agent. This certificate shall be dated and show: • The name of the Insured consultant, the specific job by name and job number, the name of the insurer, the number of the policy, its effective date, and its termination date. • Statement that the Insurer shall mail notice to the Owner at least thirty (30) days prior to any material changes in provisions or cancellation of the policy, RFQ #1401 — ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT 9 except ten (10) days written notice of cancellation for non - payment of premium. C. SCOPE OF SERVICES The City of Ocoee, Florida, in conformance with the Consultants' Competitive Negotiations Act (CCNA), Florida Statutes Section 287.055, and the policies and procedures of the City of Ocoee (City) is soliciting statements of qualifications from qualified professional engineering, engineering /surveying firms /teams that are interested in providing design, coordination, permitting and bidding services for the City's "OCOEE WEST SANITARY TRANSMISSION PROJECT " . The project consists of 21,400 feet of 12" to 20" diameter sanitary sewer forceinain and a regional master lift station. The City may elect to breakup and /or phase the project. The project will include coordination with liftstation and hydraulic design efforts (by others). For more details of the project, the "Ocoee West Wastewater Utility Plan Study ", dated August 2008 and "Western Force Main Route Study ", dated June 2011, prepared by Reiss Engineering Inc. is available at: http: / /www.ocoee.org /Departments /PU/ . Responding firms (Respondent) must be experienced in providing engineering services for projects of a scope and nature comparable to those described. Use of qualified subconsultants for specialty work is acceptable. To be considered, the firm shall be qualified by a licensed professional in accordance with Florida State law and be familiar with all applicable State of Florida, St. Johns River Water Management District, Orange County, and City land development codes, regulations, and laws, and with City and Orange County construction standards. The selected Consultant(s) will assist the City by supplying sanitary sewer transmission design, coordination, permitting, and bidding services needed to support the PROJECT. It is anticipated that both geotechnical and professional land survey services will be needed in support of the design of the PROJECT. Consultant will be tasked with preparing a detailed scope and necessary support services, where the City will procure those services utilizing ongoing professional contracts. D. SUBMITTALS Qualifications packages shall be designed to portray to the City how the respondent's services can best match the knowledge, skills, and abilities suggested by the anticipated Scope of Services given above. In order for the City to evaluate the qualification package, each Respondent shall provide information relative to their ability to provide services that will best meet the needs of the City. The required submission materials include the following: I. Firm's Qualifications • List of all firm's employees, their qualifications, and their role in providing the desired City services. • Firm's and employee's certifications and registration with regulatory agencies, professional organizations, etc. RFQ 41401 - ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT 10 • List firm's sub - consultants, their qualifications, and their role in this project. • List of firm's other current or recently completed similar services within the past two 2 years with other public or private agencies. • List and quantity of firm's (and firm's sub - consultants' if applicable) equipment including survey instruments, computers, plotters, vehicles, etc. • List of at least three (3) client references to include organization name, contact person, telephone number (s), and e -mail address. • Project Manager education, experience and any special consideration • Key Project Members education, experience and any special consideration • Firm's Project organization and coordination structure II. Firm's Office Location & Other Forms (not included in page limit) • List the location of all offices (firm and sub - consultants) involved with this project and approximate distance (in miles) and time (in hours) to City Hall. • Company Information /Signature Sheet p. 14. • Receipt of any addenda issued. • MBE Certification • Summary of Litigation, if none please so state. Provide a summary of any litigation, claim(s), bid or contract dispute(s) filed by or against the Firm in the past five (5) years which is related to the services that the Firm provides in the regular course of business. The summary shall state the nature of the litigation, claim, or contact dispute, a brief description of the case, the outcome or projected outcome, and the monetary amounts involved. E. TIME SCHEDULE The anticipated schedule of events related to this solicitation is: Date of RFQ Request for qualifications published 25 days later Last day for questions 37 days later Statements of qualification are due 39 days later Qualification statements distributed to evaluation committee 53 days later Evaluation committee meeting held Next meeting Short -list of ranked firms recommended to City Commission Dates are estimated and subject to change at the City's discretion. F. SELECTION PROCESS The criteria for selection shall be based on the criteria listed above, including the firm's qualifications, location, past performance, and reference check. The City reserves the right, before awarding the contract, to require a Respondent to submit such evidence of its qualifications, as the City may deem necessary and may require oral presentations of firms. The City shall be the sole judge of the competency of Respondents. RFQ 41401 - ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT 1 I 2. A City evaluation committee will evaluate each respondent's qualifications and will short -list and recommend to the City Commission up to three firms in ranked order of qualifications based upon the selection committee's evaluation of the proposals and any client references. All Respondents shall be notified via Onvia /Demandstar or other means of staff's recommended ranking of firms to the City Commission. The City Commission's decision to endorse or modify the ranking by staff shall be final. 3. The City will apply the negotiation requirements of Section 287.0055, Fla. Stat., (a.k.a., CCNA). The City will attempt to negotiate an agreement with the top- ranked Respondent. If no agreement is reached with the top- ranked Respondent, negotiations will be terminated and initiated with the second - ranked Respondent, and so on, until an agreement is reached. 4. The successful Respondent shall be required to execute an agreement which provides, among other things, that all plans, drawings, reports, and specifications that result from Respondent's services shall become the property of the City. Upon the successful negotiation of an agreement, a formal contract will be prepared and subsequent executed by both parties. Evaluation Criterion Maximum Points 1. Experience /References of the firm and project team • Past Performance and Experience of the Firm • Past Performance and Experience of the Team Members • Past Performance and Experience with or in the City 40 • Overall Experience • References 2. Ability to Meet Time and Budget Requirements • Projected Workloads of the Firm 20 • Affect of Legal Action Against the Firm 3. Project Approach • Briefly describe your Firm's understanding of the services requested 30 and how the firm would accomplish the work. 4. Office Location • Location of the Office and Proximity to the City of Ocoee 5 5. Certified Minority Business Enterprise • Include Copy of MBE Certification 5 100 G. WORK ASSIGNMENT PROCEDURES RFQ 9 1401 - ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT 12 The firm selected by the City will provide professional engineering services for design, coordination, permitting and bidding services for the City's Ocoee West Sanitary Transmission Project. No work shall commence until the verification of the issuance of the purchase order or other authorization document. Invoicing for completed work or progress billing shall be submitted to the requesting Utilities Department for processing and submission for payment by the Finance Department with a copy to: Accounts Payable Finance Department City of Ocoee 150 N. Lakeshore Drive Ocoee, Florida 34761 H. BID PROTESTS All Bid Protests shall be submitted to the Purchasing Agent in the following manner: A Bidder shall file a written bid protest under this Article or be barred any relief; oral protests shall not be acknowledged. A bid protest shall be limited to the following grounds: (a) issues arising from the procurement provisions of the Project Manual, its addenda, and other bidding documents; and /or (b) applicable federal, state, or local law. No bid protest may be based upon questions concerning the design documents (drawings and specifications). The Bidder shall clarify all questions concerning the design documents of the project prior to submitting its bid. The content of the bid protest shall fully state the factual and legal grounds for the protest and the legal basis for the relief requested. The bid protest shall be filed with the Purchasing Agent not later than three (3) calendar days after the posting of the notice of intent to award or recommendation of award by staff, whichever is earlier. The Purchasing Agent, on behalf of the City, shall make a determination of the merits of the protest not later than five (5) business days after receipt of the protest. If the City denies the protest, the City may proceed with award of the contract unless enjoined by order of a court of competent jurisdiction. END OF INSTRUCTIONS RFQ 41401 - ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT 13 COMPANY INFORMATION /SI GNATURE SHEET RFQ 41401 FAILURE TO COMPLY WITH THESE RFQ INSTRUCTIONS WILL RESULT IN DISQUALIFICATION OF YOUR QUALIFICATION PACKAGE. PLEASE SIGN BELOW ATTESTING THAT YOU HAVE READ AND UNDERSTAND ALL RFQ INSTRUCTIONS AND THAT YOU UNDERSTAND THAT THE SUCCESSFUL RESPONDENT WILL BE REQUIRED TO ENTER INTO A LEGALLY BINDING CONTRACT WITH THE CITY OF OCOEE. COMPANY NAME TELEPHONE (INCLUDE AREA CODE) FAX (INCLUDE AREA CODE) E- MAIL, ADDRESS AUTHORIZED SIGNATURE (manual) NAME /TITLE (PLEASE PRINT) STREET ADDRESS IF REMITTANCE ADDRESS IS DIFFERENT FROM PURCHASE ORDER ADDRESS, PLEASE INDICATE BELOW: CITY STATE ZIP FEDERAL ID 4 Individual Corporation Partnership _Other (Specify)_ Sworn to and subscribed before me this day of _ 1 20 Personally Known _ _ or Produced Identification Notary Public - State of (Type of Identification) County of Signature of Notary Public Printed, typed or stamped Commissioned name of Notary Public RFQ 41401 — ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT 14 M S. Scott Vandergrift City Man ager Robert Frank September 3, 2014 � r fIorida Commissioners John Grogan, District 1 Rosemary Wilsen, District 2 Rusty Johnson, District 3 Joel F. Keller, District 4 ADDENDUM NO: ONE (1) CITY OF OCOEE RFQ #1401 ENGINEERING SERVICES FOR OCOEE WEST SANI'T'ARY TRANSMISSION PROJECT This addendum consists of two 2 pages, and shall modify and become a part of the original RFQ documents for Engineering Services for Ocoee West Sanitary Transmission Project. Respondents shall acknowledge receipt of this Addendum in the space provided on this Addendum. Failure to do so may subject the Respondent to disqualification. The RFQ due date remains the same. The following Documents have been posted to Demendstar: I. Pre - Submittal Conference Sign -in Shect 8/19/14 2. Presentation at Pre - Submittal Conference 8/19/14 3, Bluford Avenue Stormwater and Utility Improvements Project Drawings Amendments and /or Clarifications to the RFQ documents are as follows: Clarification #1 Firm shall be considered "FIRM /TEAM" when referenced within Request for Qualifications (RFQ) 9 140 1. "FIRM /"TEAM" shall include all sub - consultants to support prime Consultants work. Clarification #2 Incidental to and in support with, the City has cause two portions of the project (pre - staged work) to be design and permit and shall, if in the best interest of the City and other mutual parties, cause the construction of those portion of the project before /or during the Consultant design efforts. Consultant shall be required to coordinate with City and others all pre - staged work. Clarification #3 As indicated in Table "Evaluation Criterion" Page 12 responders to the RFQ should include a "Project Approach ". Failure to provide a project approach will result in no points awarded for that category. Amend #1: "C, Scope of Services" Original: The selected Consultant will assist the City by supplying sanitary sewer transmission design, coordination, permitting, and bidding services needed to support the PROJECT. It is anticipated that both geoteehnical and professional land survey services will be needed in support of the design of the PIZOIECT. Consultant will be tasked with preparing a detailed scope and necessary support services, where the City will procure those services utilizing ongoing professional contracts. Shall be replaced with: The selected Consultant will assist the City by supplying sanitary sewer transmission design, coordination, permitting, and bidding services needed to support the PROJECT which shall incl ude all _needed sub consulta ser to support the efforts of the Consultan City of Ococe • 150 N Lakeshore Drive • Ocoee, Florida 34761 phone: (407) 905 -3100 • fax: (407) 905 -3 194 • www.ocoee.org Amend #2: 'T Firm's Qualifications" Original: • List of all firm's employees, their qualifications, and their role in providing the desired City services. • Firms and employee's certifications and registration with regulatory agencies, professional organizations, etc. • List firm's sub - consultants, their qualifications, and their role in this project. • List of firm's other current or recently completed similar services within the past two 2 years with other public or private agencies. • List and quantity of firm's (and firm's sub - consultants' if applicable) equipment including survey instruments, computers, plotters, vehicles, etc. • List of at least three (3) client references to include organization name, contact person, telephone number (s), and e -mail address. • Project Manager education, experience and any special consideration • Key Project Members education, experience and any special consideration • Firm's Project organization and coordination structure Shall be replaced with: • List of all firm's employees, their qualifications, and their role in providing the desired City services. • Firm's and employee's certifications and registration with regulatory agencies, professional organizations, etc. • List firm's sub - consultants, their qualifications, and their role in this project. • List of firm's other Current or recently completed similar set-vices within the past t_iv_e L5)years with other public or private agencies. • List and quantity of firm's (and firm's sub - consultants' if applicable) equipment including survey instruments, computers, plotters, vehicles, etc. • List of at least three (3) client references to include organization name, contact person, telephone number (s), and e -mail address. • Project Manager education, experience and any special consideration • Key Project Members education, experience and any special consideration • Firm's Project organization and coordination structure a �� e l �� Jo Tolbert, CPPB Purchasing Agent cc: Evaluation Committee All respondents shall acknowledge this addendum in your qualification package by completing the section below and including in Section II- Firm's Office Location & Other Forms. Respondent: Signatru•e: _ - -- Name: Title RFQ 1401 — Addendum # 1 2 COPY Engineering Services for Ocoee West Sanitary Transmission Project Presented to: City of Ocoee 150 North Lakeshore Drive. Ocoee, Florida 34761 Presented by: . �t�.�. Environme C Barnes, F°arland aril Associates, Inc_ 1230 Hillcrest Street Orlando, Florida 32803 September 9, 2014 14MRW CONTENTS Cover Letter Section 1 Firm's Qualifications 1.1 Proposed Prime Team Members ...................................... ............................... 1 -1 1.2 Professional Registrations and Certifications ................... ............................... 1 -4 1.3 Proposed Subconsultant Team Members ........................ ............................... 1 -6 1.4 Current or Recently Completed Similar Projects .............. ............................... 1 -9 1.5 Team Software and Equipment ...................................... ............................... 1 -12 1.6 Client References ............................................................ ............................... 1 -14 1.7 Resumes .............................................................................. ...........................1 -15 1.8 Organizational Chart ....................................................... ............................... 1 -30 1.9 Project Approach ............................................................ ............................... 1 -31 1.10 Current and Projected Workloads .................................. ............................... 1 -39 Section 2 Firm's Office Location and Other Forms 2.1 Office Location (firm approximate distance in miles and time to City Hall) 2.2 Company Information / Signature Sheet 2.3 Acknowledgement of Addenda 2.4 Minority Certification 2.5 Summary of Litigation i ` -HLRA . Environmental Consultants Barnes, Ferland and Associates, Inc. September 9, 2014 Ms. Joyce Tolber, Purchasing Agent City of Ocoee 150 N. Lakeshore Drive Ocoee, Florida 34761 SUBJECT: Request for Qualifications (RFQ) #1401 Engineering Services for Ocoee West Sanitary Transmission Project Dear Ms. Tolbert, Barnes, Ferland and Associates, Inc. (BFA) is pleased to submit this Letter of Interest to the City of Ocoee for providing engineering services for the Ocoee West Sanitary Transmission Project. We are excited about the opportunity to be of service to the City of Ocoee. BFA is a civil engineering, environmental engineering, hydrogeological consulting and survey firm established in 1994 to meet the growing need for utilities and environmental consultants. We are a certified minority business enterprise with the State of Florida and numerous other local government agencies. Our firm's Orlando office has the capabilities and experience to provide the City with the range of engineering and surveying services required for this project. Our Orlando office is staffed by- professionals who have dedicated their careers specifically to the development of innovative and effective solutions for planning, design and construction of municipal sanitary, potable water and reclairned water pipeline projects. Our home office is located about 25 minutes from the City Hall. Our approach is focused on providing value and timely services from a knowledgeable and capable staff of professionals. We believe we can provide the City significant advantages for this project including: • A Project Team who have worked in Central Florida for 30 years; • An abundance of previous wastewater, water and reclaimed water pipeline design and construction experience; • An experienced team of professional engineers who have focused their careers on public utilities. The contents of this submittal are true and accurate and express our strong desire to work with the City of Ocoee. We appreciate your consideration and look forward to the opportunity to work with the City of Ocoee. Sincerely r Barne$,/ er an arid/ ss bates, Inc. Daniel L: en, P.E. Senior Vice President 1230 Hillcrest Street . Orlando, FL Office (407) 896 -8608 • Fax (407) 896 -1822 SECTION 1' FIRM'S QUALIFICATIONS 1.1 Proposed Prime Team Members Barnes, Ferland and Associates, Inc. (BFA) is a civil /environmental engineering, hydrogeological consulting, and surveying/mapping firm that specializes in the design and construction management of water, wastewater, and reclaimed water infrastructure improvements. BFA, incorporated in 1994, is a certified minority business with the State of Florida and numerous local government agencies including Orange County and the City of Orlando. We are committed to providing reliable, responsive, cost - effective, and high - quality design services to our municipal /utility clients. BFA is a Florida firm with its main headquarters in Orlando, Florida. BFA's Orlando -based water /wastewater group is staffed by five (5) professional engineers who have dedicated their careers specifically to the development of innovative and effective solutions for the planning, design, and construction of municipal water and wastewater projects. Our staff also includes two project engineers, two professional geologists, a professional hydrologist, a professional surveyor, a SUE utility coordinator, two (2) environmental scientists, and eleven (11) technical and administrative support staff. Since BFA's inception, our focus has been on building trust, and providing exceptional service and attention to our clients. We have assembled a project team comprised of individuals and subconsultants who are fully experienced in the design, permitting and bidding activities necessary to successfully deliver a large diameter transmission main project. Our company has been providing similar services to those requested in the RFQ for the past 20 years, since its incorporation in 1994. Our proposed engineering team has provided similar services over the past 30 years throughout Central Florida including many large diameter transmission main projects. Daniel L. Allen, PE, will serve as Principal -in- Charge and 0,A/QC Officer. Mr. Allen, Senior Vice President, has over 31 years experience in the design, permitting and construction of potable water, wastewater and reclaimed water pipelines. Daniel's specific pipeline experience includes over 41 miles of 12 -inch to 36 -inch transmission mains. He served as project manager for Orange Count's Eastern Regional Water Transmission System Improvements which included 37,000 feet of 20 -inch and 24 -inch water mains and 37,000 feet of 12-inch, 16-inch and 24 -inch force mains. Recently, Daniel served as project manager on the design and construction of 4,000 feet of 30 -inch wastewater force main along Sand Lake Road, the replacement of the two (2) 54 -inch influent mains at the South WRF and 6,840 feet of 12-inch, 16-inch and 24 -inch water transmission mains along Apopka Boulevard. He will provide our commitment to the City that all necessary resources and technical expertise are available to consistently provide superior products and meet established schedules. He will ensure the Team continually exceeds the expectations of the City in all phases of the project. Geoff Hennessy, PE will serve as our Team's Project Manager. Geoff has over 29 years of engineering experience, including planning, design, permitting, bidding and construction of potable water, wastewater and reclaimed water transmission pipelines. He has managed and /or designed more than 130 miles of water, wastewater and reclaimed water system pipelines for municipal clients with a construction value of over $55 million. Over 14% miles were designed specifically for City of Ocoee. Geoffs recent pipeline design projects include Orlando /OUC's Marks Street Sewer and Water Main Improvements including 5,140 feet of 8 -inch to 15 -inch sewer and 4,630 feet of 8 -inch to 20 -inch water main and Orange County's West SR 50 utilities Improvements including 10,500 feet of 6 -inch and 8 -inch force main; 2,000 feet of 42 -inch water main; 5,300 feet of 16 -inch water main and 1,200 feet of 12 -inch sanitary sewer. Geoff will be directly involved in and responsible for, the day -to -day decision - making and coordination with the City's personnel. Cynthia Malone, PE will serve as our Team's Project Engineer. Cynthia has over 16 years of experience related to the planning, design, permitting, bidding and construction of potable water and reclaimed water transmission pipelines for municipal clients. She has participated in the design of over 10 miles of pipeline projects for the City of Ocoee. She will be directly involved in the day -to -day project coordination with the City's personnel and design implementation. Geoff and Cynthia have continuously worked together as a Project Manager and Project Engineer team for over 15 years. During this time, they have completed the design, permitting and construction administration of many large diameter wastewater, water and reclaimed water pipeline projects in municipal corridors similar to that contemplated by this RFQ including but not limited to: • City of Ocoee -Old Winter Garden Road /Professional Parkway Utility Relocations & Improvements: Design, permitting and construction phase services for relocation of 6,000 feet of 6 -inch through 12 -inch water main, 1,400 feet of 6 -inch force main, and installation of 5,900 feet of 4-inch through 16 -inch reclaimed water main. The utility relocation and improvements were designed and constructed in conjunction with the City's Professional Parkway road widening and storm drainage improvements. • City of Ocoee - Reclaimed Water Mains, Phase I & II: Completed the design of 9,300 feet of 16 -inch reclaimed water main and 2,100 feet of 12 -inch reclaimed water main as part of the City's Reclaimed Distribution Program. The project included eleven directional drills ranging in size from 8 -inch to 16 -inch. • City of Ocoee -Water Transmission Mains, Phase I, II & II: Completed the design and permitting of a Citywide water distribution improvement project. The project included 23,500 feet of 12 -inch water main and 4,400 feet of 16 -inch water main. • Orange County's Sand Lake Road Force Main Improvements for construction of 6,500 feet of 16 -inch, 20 -inch and 24-inch force mains, including a 200 ft. long 20 -inch diameter HDPE directional drill under the Sand Lake cross culverts. • City of Orlando's Baldwin Park Reclaimed Water Transmission Main for the construction of 10,100 feet of 24 -inch reclaimed water main, including a 190 ft. long 24 -inch diameter HDPE directional drill across Curry Ford Road, and a 340 ft. long 24 -inch diameter HDPE directional drill across East Colonial Drive. • City of Tiitusville's SR 405 Utility Improvements for construction of 11,500 feet of 20 -inch and 9,600 feet of 16 -inch reclaimed water main, 11,500 feet of 12 -inch force main, and 6,700 feet of 12 -inch water main. The project included 14 separate triple bore & jack crossings across SR 407, US-1, CSX railway and numerous side streets, one subaqueous creek crossing with triple pipes, and two separate 16 -inch diameter HDPE reclaimed water directional drills. • Seminole County Utilities' SR46 Reclaimed Water Transmission Main for the construction of 13,000 feet of 20 -inch reclaimed water main including two bore & jacks and three 20 -inch diameter HDPE horizontal directional drills. 1 -2 • Orange County/s Curry Ford Road Extension and Alafaya Trail Water Transmission Mains for 20,100 feet of 36 -inch water main, 7,000 feet of 24 -inch water main, 4,700 feet of 24 -inch water main, 2,800 feet of 20 -inch water main, and 4,500 feet of 12 -inch force main including a 550 ft. long 36 -inch diameter HDPE directional drill under the Little Econ River. • Orange Count's Dr. Phillips Blvd. Utility Improvements for construction of 12,400 feet of 18 -inch gravity sanitary sewer, 8,000 feet of 16 -inch reclaimed water main and 5,300 feet of 12 -inch water main from Conroy Road to Sand Lake Road. Willie Thomas, PE, will provide engineering and design support. Willie has 20 years' experience in the design, permitting and construction of potable water, wastewater and reclaimed water pipelines. Recent similar pipeline transmission projects include: Apopka Boulevard Water Transmission Mains; Kirby Smith Road Reclaimed Water Main and Golfway Blvd. Force Main Improvements. Other pipeline transmission projects he has engineered include GOAA's Heintzelman Blvd. Utilities Project; the City of Belleviev✓s Spruce Creek Reclaimed Water Main; Orange County's Holden Heights Infrastructure Improvements Phases II and III; and most recently, Toho Water Authority's Pleasant Hill Road Water Main Extension. Erin Giblin, PE, will provide engineering and design support. Erin has 12 years' experience in utilities systems planning, design, permitting and construction. She has served as project engineer on a number of recent pipeline projects including the Holden Heights Infrastructure Improvements Phases II and III and the Wekiva Manor /Clearview Heights Water System Improvements. Erin was also the project engineer for the design and construction of 4,000 feet of 30 -inch wastewater force main along Sand Lake Road. Frank Gidus, LEP, will provide ecological support if required. Frank has over 20 years' experience as an environmental scientist. He is highly experienced and skilled at executing multi - parameter ecological and environmental assessments, wetland impact permitting, wetland jurisdictional determinations and endangered /threaten species evaluations and permitting including gopher tortoise capture and off -site relocation. Frank recently performed the environmental and ecological services in Orange County for the Southern Water Transmission Mains project including environmental evaluation /assessment of 3 -1/2 miles of the pipeline corridor. William Miller, PSM, will supervise the survey and mapping effort. With over 45 years of survey experience, all within the State of Florida and 32 years in Orange County, Bill has a very broad range of skills that span almost every aspect of land surveying for pipeline design. He will be responsible for the survey and mapping aspects of the project including directing our subsurface utility exploration (SUE) crews. Bill has worked on several City of Ocoee projects and is very familiar with the City's survey standards. He currently leads our team in providing continuing survey services to the City. He recently completed the 5 miles long design survey for the Lee Vista Blvd. to Innovation Way Transmission Mains and performed both design survey and SUE for the Marks Street Sewer and Water Main Project. Our in -house SUE capabilities, led by Mr. Dave Ragland, will locate existing utilities along the project corridors. Dave has 20 years' experience in utility location and field coordination in Central Florida, and is proficient in the use of BFA's state -of- the -art electronic and GPR sub - surface locating and vacuum excavation equipment. 1 -3 1.2 Professional Registrations and Certifications Barnes, Ferland and Associates, Inc. is a Corporation formed in the State of Florida. BFA Environmental is a Fictitious Name filed under the Corporation. Copies of our Certification from the Florida Secretary of State are provided below. Also provided are copies of our Professional Licenses. State of Florida Department of 'Strrte I certify Gun, the record, of 0u. I ice that UAK\ES. F I,RL.AND AND ASSCx'IATES, INC. in a c. +tl4 +rs ion organlaed nnrler It. 13 10he Slam of HIH,U, filed Dn Aptil 3, 1994. 'Itte documoN numtxr of 0 i, ccq —1i"i rs P94000076169, 1 fluthar c tilj du,t nud-1 —ticu Ina I.,id all fee, du .e e Ihia efli Ihnmgh I,— nl r 31, 204, that it, mess r an+urd rq-t m+if ml b,.i —, report filed WI imnlmy 14. '_011 and Ile w:an" is active I hudicr.•enilj B,:u and c.rpcamion Ims raw ilk,1 Anidc, of D11 -44ion ro-or .x✓.rAO' anx✓.x✓ u. c..rr.t.ar Jtlrc.Sab �T7mib m T.J4il.wrr, rir fwplwR Ad a. £...r.rxa ✓. J�,xxa�. :ar.r r f Awa., Secrelaq of State �+U nr4 I :Cf At I `TO wUxrt4 N Yk, b N ruUO 5+f d+r,rc[e1 U+4 I ID,.n4U fMl tl k i 044.K h A,.eN mbC e Ir,N . State of Florida Board of Professional Engineers' Attc.ls a,a, Barnes, Ferland And Associates, Inc, h omhorhed under the pro.ldon. of S n {71,023, Florida Seamen, co offer englncedng cc i— rothe pubtk though o r{orwional Fngin «r, duly lic—cd under Chopin, 471, rlorldu Stommi. FxpUa,kn: ?!'g/20I5 CA Uc No: Audit No: 22'82111502708 Cl..Ilk— of A.th.,i,.ti 6899 1 -4 State of Florida Departinent of State I certify from the records of this office that BFA f{NVIRONMGN'fAL is a Fictitious Name registered with the Department of State on April 2, 2007. '1 lie Registration Number of this Pictitimu Narne is 607092700160. 1 further certify that said Fictitiou. Nine Registration is active. 1 father ccilifi' that said Fictitious Name Registration filed a renewal on DccemN , r 10, 2012, and cspires on Deec nKr 31, 2017, ch'. ..d—q haAJ uxJSFremt J £lo,ld.,. ,T U/ huasrr, M, C. ;W, this M, h y /D.r Seeretaq of State w Sail lW4 t SIIII {aT092'OaibA U rC,p H I n 1.. Maps r,efik aan0.org,ce I oth+<r.hl,xi LBm4 Proftsalonal 8urvspor and Msrrer ¢us)neta ideeass tw„ {tea .TALA.Vn A.Ya.l,Htf'IAl4T I •W ;,Lie Ai[i SfRE5r �. i alcK scow. DDreaNOR KEN UY/SON. SECRE tARv STATE OF FLORIDA DEPARTME OF PROFESSONAL GEOLOGISTSEGUUTtOtI , state of Flor l cesu TNeaEOLOGY BaSINEBS 6 Board of Professional Engineers amed bebv IS CERTIFIED � 492 FS AttKts(hot Erry�tun, let Jul 31C2010r Daniel Lord Allen, P.E. BARNEB. FERLANDANDASSOCIATES, INC N' d it. �i 1230HILLCRESTST ORLANDO FL 32803 $ is licensed as o Professional Engineer under Chapter 471, Florida SCO[UCeb O. el I E.piroi— 2282015 P.L Lk, No Audi, No: 2282015(5233 32891 u, v 01-014 OISP1AYASREOUIREOBYLAW SEOe ,I.o!an/al to State of Florida Board of Professional Engineers Attet IT that Geoffrey J. Hennessy, P.E. i Is licensed as a Professional Engineer under Chapter 471, Florida Stotutes Erpi,atioo: 2282015 P.E. Lk. No Audit No: 228201506599 58637 State of Florida Board of Professional Engineers Aae,iu tho, Willie Ervin Thomas, P.E. Is licensed as a Professional Engineer under Chapter 471, Florida Statutes &pimti- 22812015 PY Lit. No: Audit No: 228201522702 57612 Pn2tv'x4lutz15crnyol and !lap P!r tlaaxo Ii I+vt I. 1111.11. r. Ik 1 -5 State of Florida Board of Professional Engineers Aaem that Cynthia Knox Malone, P.E. A' Is licensed as a Professional Engineer under Chapter 471, Florida Statutes E.pitotion'. 2/28!2015 P.E. Lit. No: Audit No: 228201527663 58685 State of Florida Board of Professional Engineers Av— [I., Erin Joanne Giblin, P.E. Adk Is licensed as a Professional Engineer under Chapter 471, Florida Statutes E.pi.mron: WM015 PY lit. No Audit No: 228201528974 6FA65 rVY�I 1.3 Proposed Subconsultant Team Members We have complimented the abilities of our own staff with those of our Subconsultant, Antillian Engineering Associates, Inc., to provide geotechnical engineering services. Antillian Engineering Associates, Inc. was selected because of their previous experience and outstanding performance on previous projects with BFA. Antillian Engineering Associates, Inc. is considered an expert in their field and adds significant value to the BFA Project Team. They provide comprehensive technical support in the fields of geotechnical engineering. Their clients include civil engineers and other design professionals engaged in the design, construction, operation and maintenance of public works, commercial and industrial facilities and mining. Their project experience includes a broad spectrum of utility pipelines, structural foundations, bridges, highways, stormwater management facilities, commercial developments, airports and storage tanks. In the 14 years since their office opened in Orlando, they have successfully served the City of Orlando and other clients on more than 700 projects throughout the state of Florida and the Caribbean basin. Antillian Engineering Associates, Inc. is certified as a Minority Business Enterprise (MBE) by Orange County, the City of Orlando, The State of Florida Commission on Minority Economic and Business Advancement and is recognized as a Disadvantaged Business Enterprise (DBE) by the Florida Department of Transportation. Antillian Engineering Associates, Inc. will assist our Team by providing geotechnical engineering services. Mr. Peter Suah, PE will serve as Antillian's Project Manager. Peter has 30 years of experience as a geotechnical engineer and has worked with BFA on over twenty previous pipeline projects. Provided below are Professional Licenses and MBE Certification for Antillian, followed by Peter Suah's resume. State of Flor ida Board of Professional Engineers Aura. i6« Peter Gregory Suah, P.E. I licensed as a Professional Engineer under Chapter 471, Florido Statutes 1'q mo212E1C15 P.E Iic.Na Auda Na 22HTG152 Cr059 49:0 State of Florida Boord of Professionol Engineers .All —, It Antillian Enqineerinq Associates, Inc. S �. muhnrimd undo Ih<pm.9douc of Seeriuud4lA13, fiaridu Swuxes, In offer enslrmohg, se.ol «s w the public 0, Sh o P-ftc .iouol F W.— duly bcrns<d nude. 4`hupm� 671, 11orldo timmas L'P7r t 1'28'2 Audu h 1 2N2011' SU to 71 C— ,f,,— of Aut1— iwllon k5 1 -6 v+i State of Fl orida Btomncss Certification or sip' Antillian Engineering Associates, Inc. is certified under the provisions of 287 and 29118 Florida Statutes for a period from! n W20;2013 to 0 512 0 /201 5 'r/ Prr� I o—da S211ire5 1 1 1 111 r Mile:, Seue[ar, Q fee of Supplier 0i,ercty • ANTILLIAN ENGINEERING ASSOCIATES, INC. Geotechnical Engineering • Construction Quality Assurance PETER G. SUAH, P.E. (Geotechnical) Position Principal Engineer, President Registration Professional Engineer, Florida (Registration No. 46910) Years of Experience Thirty -two years, including 21 years with present firm Expertise Geotechnical engineering, foundation analysis and design, applied geophysics, ground improvement, trenchless construction, heavy construction management Education M.S. (Geotechnical Engineering), University of Maryland 1989 B.Sc. (Civil Engineering), University of the West Indies 1982 Affiliations American Society of Civil Engineers Representative Projects Pine Hills Road Force Main, Orange County, Florida Geotechnical investigation for 670 feet of 12 -inch and 10,700 feet of 16 -inch wastewater force main. Due to limited available right - of -way and conflicts with existing utilities, 3,600 feet along Pine Hills Road is proposed to be constructed by horizontal directional drill. Mr. Suah directed the geotechnical investigation alongstreets and easements, developed recommendations for underground utility construction by both conventional and trenchless methods and prepared the geotechnical engineering report. Apopka Boulevard Water Main Project Geotechnical investigation for 1,790 feet of 20 -inch water main, 3,120 feet of 16 -inch water main, 1,580 feet of 12 -inch water main along Apopka Boulevard (Lake Pleasant Rd to Platinum Rd and Vulcan Rd to Palm Ave) and segments along Overland Road and Palm Avenue to US 441. Mr. Suah directed the geotechnical investigation along streets and easements, developed recommendations for underground utility construction by both conventional and trenchless methods and prepared the geotechnical engineering report. Heathrow - Markham Raw Water Main, Seminole County, Florida Three miles of new raw water main from well site to treatment plant in suburban area with difficult soils and challenging geology. Mr. Suah directed the geotechnical investigation along streets and undeveloped properties, developed recommendations for underground utility construction by both conventional and trenchless methods and prepared the geotechnical engineering report. Country Club Water Mains, Seminole County, Florida Approximately 2,800 feet of new 16 -inch water main to connect an existing water main to the Country Club Water Plant. Mr. Suah directed the geotechnical investigations, developed recommendations for utility installation using both conventional and trenchless methods and prepared the geotechnical report. 1 -7 Riverside Acres Water Main Replacement, Orange County, Florida Replacement of about one mile of potable water distribution lines in suburban area with difficult soils and high groundwater. Mr. Suah directed the geotechnical investigations, developed recommendations for pipe replacement and prepared the geotechnical engineering report. Georgia Avenue Water Main CSX Railroad Crossing, Longwood, Florida Geotechnical engineering services to support design of installation of new water main requiring a jack- and -bore crossing beneath the CSX railroad tracks in order to connect two existing water mains. Crossing was expected to be approximately 15 feet beneath the existing ground surface. Continuing Utilities Engineering Services, Orange County, Florida Responsible geotechnical engineering professional for design of many minor water distribution, wastewater collection and treatment facility projects. Mr. Suah directed the field investigations, the evaluation of subsurface conditions, development of design recommendations and preparation of the geotechnical engineering reports. Holden Heights Infrastructure Improvements, Orange County, Florida Sixteen miles of new sanitary sewer lines, three lift stations, three miles of force main and seven stormwater ponds in a densely populated urban district with difficult soils. Mr. Suah directed the geotechnical investigations, which required coordination of several underground utility companies, surveyors and two drilling contractors. The field investigation required more than 150 test borings and an extensive laboratory testing campaign. Mr. Suah developed recommendations for underground utility construction and prepared the geotechnical engineering reports. Eastern Water Reclamation Facilities Expansion, Orlando, Florida Expansion of existing wastewater treatment and reclamation plant, including two new 150 ft diameter storage tanks, associated control buildings, deep lift stations and eight miles of force main along urban arterial roadways and in difficult terrain. Mr. Suah directed the geotechnical investigations, developed recommendations for underground utility construction and supervised preparation of geotechnical reports. Continuing Utilities Engineering Services, Altamonte Springs, Florida Geotechnical engineering services supporting miscellaneous design of sanitary sewer facilities. Mr. Suah directed field operations, laboratory testing, subsurface evaluation and report preparation for two projects. Harbor East Subdivision Wastewater Improvements, Orange County, Florida New sanitary wastewater lift station and replacement of several thousand feet of force main in an existing urban subdivision with high groundwater conditions. Mr. Suah directed the geotechnical investigations, developed recommendations for underground utility construction and prepared the project geotechnical report. Other Qualifications Adjunct Professor, Geotechnical Engineering 2004 to 2009 Department of Civil and Environmental Engineering University of Central Florida am 1.4 Current or Recently Completed Projects Below is list of projects that are currently active or were completed within the past 5 years. The list is ordered by the most recently completed projects followed by the projects at the greatest completion level. All of these projects included preliminary design, final design, permitting, bidding and award, and construction administration services that were performed by our Project Team. Over the past 5 years, currently active or completed pipeline projects by our Project Team included: • 32,085 feet of 4 -inch to 36 -inch wastewater force mains • 12,440 feet of 8 -inch to 15 -inch sanitary sewer • 111, 860 feet of 4 -inch to 42 -inch water mains • 17,500 feet of 8 -inch to 24 -inch reclaimed water mains Orange County - Avalon Park Blvd. Reclaimed Water Main Project included 1,040 feet of 16 -inch reclaimed water main. (Design and construction completed in 2014) Orange County - Ramir Water Main Replacement Project included 8,500 feet of 6 -inch and 8 -inch PVC water main. (Design and construction completed in 2014) Orange County - SR 482 (Sand Lake Road) Wastewater Mains Relocation Project Project included 3,800 feet of 30 -inch force main, 415 feet of 12 -inch and 300 feet of 4 -inch and 6 -inch wastewater force main; 48" Casing Jack and Bore crossing of the CSX railroad; and the rehabilitation of 2,030 feet of 10" and 15" VCP gravity sewer pipe. (Design and construction completed in 2013) Orange County - Sand Lake Road Shingle Creek Force Main Crossing Project included 860 feet of 36 -inch wastewater force main. 760 feet of 36 -inch force main was installed by horizontal directional drill beneath Shingle Creek and the adjacent wetlands. (Design and construction completed in 2013) Orange County - Apopka Boulevard Water Main Project Project included 1,790 feet of 20 -inch water main; 3,120 feet of 16 -inch water main and 1,580 feet of 12 -inch water main. 120 feet of 16 -inch and 230 feet of 12 -inch installed by horizontal directional drill. (Design and construction completed in 2013) Toho Water Authority - Pleasant Hill Road Water Main Extension Project included 2,320 feet of 16 -inch water main, 413 feet of 8 -inch water main, 541 feet directional drill of 20 -inch HDPE water main, 387 feet directional drill of 10 -inch HDPE water main, 187 feet directional drill of 8 -inch HDPE water main, and 415 feet directional drill of 4- inch HDPE water main. (Design and construction completed in 2012) .W_A 1 -9 Orange County - Meadow Woods WSF to South Regional WSF 16 -inch Water Supply Main Project included 5,500 feet of 16 -inch water main from two water supply wells at the existing Meadow Woods WSF to the new South Regional WSF. Project included horizontal directional drill of Orange Avenue and bore and jack of the CSX railroad. (Design and construction completed in 2012) Orange County - Narcoossee Road (SR 15) Utilities Improvements Project included 8,200 feet of 8 -inch reclaimed water main and 6,600 feet of 12 -inch, 16 -inch and 24 -inch water mains. (Design and construction completed in 2012) Longwood - Georgia Avenue, Columbus Harbour, Oak Street Water Main Loops Project included 910 feet of 6 -inch water main and 138 feet of 12 -inch water main. The project also included 24 -inch Jack and Bore at the FDOT /CSX railroad crossing. (Design and construction completed in 2012) City of Belleview - US 441 Water Main Improvements Project included 16,750 feet of 12 -inch water main. (Design and construction completed in 2011) Orange County - West SR 50 Utility Improvements /Relocations Project included 10,800 feet of 6 -inch and 8 -inch force main, 2,000 feet of 42 -inch and 5,300 feet of 16 -inch water main; 1,200 feet of 6 -inch to 12 -inch water main; 1,100 feet of sanitary sewer, CIPP lining of 1,200 feet of 12 -inch sanitary sewer and lift station site improvements. (Design and construction completed in 2010) Orange County - Wekiva Manor Subdivision Water System Improvements Project included 8,500 feet of 6 -inch and 8 -inch PVC water main. (Design and construction completed in 2010) Orange County - Fiquette Road Force Main Replacement Project includes 3,600 feet of 16 -inch wastewater force main. (Design completed in 2014, construction at 5% completion level) Longwood - Skylark Subdivision, Phase 1 Water Main Replacement Project includes 8,170 feet of 6 -inch and 8 -inch water mains. (Design completed in 2014, construction at 95% completion level) Longwood - Skylark Subdivision, Phase 2 Water Main Replacement Project includes 6,860 feet of 6 -inch and 8 -inch water mains. (Design completed in 2014, construction anticipated to start in early 2015) Orlando /OUC - Marks Street Sewer and Water Main Improvements Project includes 1,930 feet of 8 -inch, 800 feet of 12 -inch and 1,900 feet of 20 -inch water mains; and 435 feet of 8 -inch, 2,600 feet of 10 -inch and 2,105 feet of 15 -inch sanitary sewer. (Design completed 2014, construction expected to start early 2015.) 1 -10 Orange County - Eastern Service Area SRF Water and Reclaimed Water Transmission Mains Project includes 4,580 feet of 36 -inch water main and 4,570 feet of 24 -inch reclaimed water main. (Design completed in 2014, construction at 10% completion level) Longwood - SR 434 Water Main Improvements Project includes 2,370 feet of 12 -inch water main. (Design completed in 2013, construction at 90% completion level) Orlando - Dahlia Drive Sewer System Improvements Project includes 110 feet of 8 -inch and 3,170 feet of 15 -inch sanitary sewer. (Design completed 2013, construction at 20% completion level.) Orange County - Pine Hills Road Force Main Project includes 670 feet of 12 -inch and 10,700 feet of 16 -inch force main. 3,600 feet of 16- inch force main will be constructed by Horizontal Directional Drill along Pine Hills Road. (Design is at 95% completion level, construction expected to start in 2015) Orange County - SR528 /Innovation Way Reclaimed Water Main Project includes 4,730 feet of 24 -inch reclaimed water transmission main and Jack & Bore of the Beachline Expressway. (Design is at 95% completion level, construction expected to start in 2015) Orange County - Sweetwater S/D Water Main Replacement Project includes 5,600 feet of 6 -inch, 8 -inch and 12 -inch water mains. (Design is at 60% completion level, construction expected to start in 2015) Orange County - Colonial Village MHP Water Main, Pump Station and Sewer Improvements Project includes 6,640 feet of 4 -inch, 6 -inch and 8 -inch water main and pump station upgrade. (Design completed in 2014, construction at 95% completion level) Orange County - Bali Hai MHP Water Main, Pump Station, Force Main and Sewer Imp. Project includes 6,860 feet of 6 -inch water main, 940 feet of 4 -inch force main and pump station replacement. (Design completed in 2014, construction at 10% completion level) Longwood - Palmetto Ave Sewer Project includes 1,720 feet of 8 -inch sanitary sewer. (Design completed in 2014, construction at 50% completion level) 1.5 Team Software and Equipment Barnes, Ferland and Associates, Inc. (BFA) has extensive technical resources including equipment and state -of- the -art software located in our Orlando office necessary for the successful completion of any project assignments. Computer Equipment 13 Desktops Savin C4540 Color Copier / Printer 17 Laptop Computers Ricoh MP5001 HP Designjet 1050C Plus 1 Server Oce TDS 600 Printer / Scanner / Plotter 1 FTP Server Design Software Aquifer Test AutoCAD Civil 3D (2009, 2010, 2011) Groundwater Vistas 4 Pumplink MODFLOW FirstSearch Jacob - Hantush Analytical Model SURFER Contouring GWIS (FDEP Water Quality Database) Mound HT H (Sewer, Water) Solutrans (3D Solute Transport Model) Surfer 8 Softdesk 8 Grapher 3 AutoCAD Infrastructure Design 2015 Support Software MS Word (Versions 2013) MS Excel (Versions 2013) MS Powerpoint (Version 2013) MS Project (2010) MS Publisher (2013) MS Access (2010) GIS Capabilities Arc View 10.1 Arc Explorer Vehicles 2007 Ford Escape 2004 Chevrolet Truck (1) 2006 Toyota Truck (4) 2014 4 WD Toyota Tundra Land Survevinq Equipment Nikon DTM -310 Total Station (1) Nikkon AS -2 Automatic Level (1) Carlson Explorer w /software Topcon GR -3 GPS Receivers (2) Topcon FC -2500 Data Collector (1) Schoenstedt Metal Locators (2) Wooden tripods (3) Philladelphia Level Rod (1) ES -105 Topcon TTL Station w /data cable SUE Equipment Trailer (2) Sullair 183 Compressor (2) Utilivac System (2) Sullair Jackhammer (2) Sullair Pogo Tamper (2) Topcon GPS Unit (GR -3) w/ accessories Carlson Software Packages (2) Standalone License AutoCAD MAP Metrotech 810 & RD 400 Pipe / Cable Locators Metrotech vLocPro2 — Locator LMX100 Ground Penetrating Radar 1 -12 .. Other In -Situ Mini Troll Water Level Data Loggers Electronic Water Level Indicators 35 MM Camera (4) Parestaltic Sampling Pump WAA5 GPS Meters (Garmin) DO, CO2, Manganese Ferrus Iron, Alkalinity, Hydrogen Sulphide, Chlorinity, Total Sulfide (Hach Analyticals) Multiparameter Water Quality Instrument (VSI) 12' Jon Boat Water Level Data Logger and Transducers Hand Augers Heath Tech Detecto Pack III — Organic Vapor Analyzer (OVA) Electronic Interface Probe Centrifugal Water Pumps (both gas and electric) Multiparameter Meter (Insitu Low Flow Sampling System, HydroLab) Petroleum in Soil Detection Kit (Hanby) Acoustic Doppler Current Profiler Antillian Geotechnical Equipment A. Equipment Type B. Brand Name C. Quantity Drilling and Sampling Miscellaneous hand augers and field tools NA Mechanical Analysis Geotest E -194 Soil Hydrometer and Jar 2 Humboldt Sieve Shaker 1 Gilson Testing Screen TS -1 1 Cress Electronic Furnace 1 Quincy Forced Air Electric Drying Oven 2 Humboldt Soil Mixer 1 Electronic Scales Acculab 9 OHaus 2 AND 1 Plasticity Indices Soil Test Casagrande Liquid Limit Apparatus CL 208 1 CL 204A 1 Soil Chemistry Cole Parmer pH Meter 1 Spectronic 20 -D Spectrophotometer 1 Nilsson Soil Resistance Meter and soil box 1 Hach Chloride Test Kit 1 Redox Potential Meter 1 Soil Density Rainhart Mechanical Compaction Machine 1 Lab Strength Tests SoilTest LBR Load Frame 1 LBR Molds w. Spacers and Surcharge Weights 16 Soil Permeability Permeability Cells and Board 2 1 -13 1.6 Client References City of Orlando Contact Name: Chuck Shultz, PE, Asst. Director Wastewater Division Telephone number: 407 - 246 -2658 Email address: Charles .Shultz @CityofOrlando. net City of Longwood Contact Name: Richard Kornbluh, Utilities Manager Telephone number: 407 - 263 -2388 Email address: rkornbluh @longwoodfl.org Orange County Utilities Department Contact Name: Jose Hernandez, PE, Chief Engineer Telephone number: 407 - 254 -9718 Email Address: Jose. Hernandez2 @ocfLnet 1 -14 1.7 Resumes DANIEL L. ALLEN, P.E. (Project Director — QA/QC) SENIOR VICE PRESIDENT AREAS OF SPECIALIZATION Mr. Allen is an experienced environmental engineer with 31 years experience in utility management, master planning, water resources engineering and the design and construction of water and wastewater treatment, effluent reuse and disposal, water distribution, wastewater collection /transmission and well pumping systems. As Senior Vice President at BFA, Mr. Allen is responsible for coordinating engineering activities associated with water resources, civil and environmental engineering. Mr. Allen's specific pipeline experience includes the design, permitting and construction management of over 260 miles of pipelines ranging from 2 -inch diameter low pressure sewer pipelines to 42 -inch potable water transmission mains. He has also designed larger mains to 54- inch diameter at water and wastewater treatment facilities. EXPERIENCE Barnes, Ferland and Associates, Inc. 2007 - Present Orange County Utilities 1999 -2007 DRMP 1989 -1999 Orange County Utilities 1982 -1989 Fishbeck, Thompson, Carr and Huber, Inc., Grand Rapids, Michigan 1981 -1982 EDUCATION B.S., Civil Engineering, 1981 Michigan State University PROFESSIONAL REGISTRATION Registered Professional Engineer, No. 37891 (Florida) REPRESENTATIVE PROJECT EXPERIENCE Orange County Utilities —Pine Hills Road Force Main Project Manager — Provided preliminary design, final design and permitting for 670 feet of 12 -inch and 10,700 feet of 16 -inch wastewater force main. This project redirects the wastewater flows northward towards Master Pump Station #3006 in a direct path to the Northwest WRF and relieves capacity at both the Huggins Street Pump Station and the Hiawassee Road force main. Due to limited available right -of -way and conflicts with existing utilities, 3,600 feet along Pine Hills Road is proposed to be constructed by horizontal directional drill. Orange County Utilities - SR 482 (Sand Lake Road) Wastewater Utility Improvements Project Project Manager — Provided preliminary design, final design, permitting, bidding and award, and construction administration services for the relocation and removal of existing wastewater force mains located within the right of way along SR 482 (Sand Lake Road), between Presidents Drive and South Orange Blossom Trail. Corridor analysis of the existing and proposed roadway was performed for determination of existing dry and wet utility locations along with potential conflicts with proposed 1 -15 �A utilities. Project included the relocation of 322 feet of 4 -inch and 6 -inch force main, 415 feet of 12 -inch force main, and 3,800 feet of 30 -inch force main; 48 -inch Casing Jack and Bore at the CSX railroad crossing; and the rehabilitation of 2,030 feet of existing 10" and 15" VCP gravity sewer pipe and manholes. Orange County Utilities — Apopka Boulevard Water Main Project Project Manager — Provided preliminary design, final design, permitting, bidding and award, and construction administration services for the installation of 1,790 feet of 20 -inch water main, 3,120 feet of 16 -inch water main, 120 feet of 16 -inch horizontal directional drill, 1,580 feet of 12 -inch water main and 230 feet of 12 -inch horizontal directional drill along Apopka Boulevard (Lake Pleasant Rd to Platinum Rd and Vulcan Rd to Palm Ave) and segments along Overland Road and Palm Avenue to US 441. Services included subsurface utility engineering (SUE), preliminary environmental assessment, and groundwater sampling and analysis. Permitting services included City of Apopka ROW Permit, FDOT Utility Permit, and two (2) FDEP General Permits to construct water distribution system extensions. The purpose of this project is to connect existing water main segments along Apopka Boulevard, Overland Road, Palm Avenue and US 441 to improve system pressure, fire protection and system reliability. Toho Water Authority - Pleasant Hill Road Water Main Extension Project Director, QA /QC — Provided preliminary design, final design, permitting, and bidding assistance services for the installation of approximately 2,320 -ft of 16 -inch water main, 413 -ft of 8 -inch water main, 541 -ft directional drill of 20 -inch HDPE water main, 387 -ft directional drill of 10 -inch HDPE water main, 187 -ft directional drill of 8 -inch HDPE water main, and 415 -ft of directional drill of 4 -inch HDPE water main. Corridor analysis of the existing roadway was performed for determination of existing utility locations for selection of the best water main alignments. Orange County Utilities - Meadow Woods WSF to South Regional WSF 16 -inch Water Main Project Project Manager — Provided preliminary design, final design, permitting, bidding and award, and construction administration services. This project involved the extension of 5,500 feet of 16 -inch water main from two water supply wells at the existing Meadow Woods WSF to the new South Regional WSF. The pipe alignment presented many coordination and technical design challenges as it was located within a dual easement occupied by OUC high voltage electrical transmission mains, crossed numerous wetland areas, crossed a CSX Railroad, crossed a major transportation shipping facility driveway and the highly congested Orange Avenue right -of -way. Orange County Utilities — Clearview Heights /Westmont Manor Water System Improvements Project Manager - This project included improvements to the water distribution systems serving the Clearview Heights and Westmont Manor Subdivisions. The number of residential single - family homes served by these improvements is 325. The existing water mains within these subdivisions are 2 -inch, 4- inch & 6 -inch asbestos - cement (AC); 4 -inch, 6 -inch and 8 -inch PVC; and 2 -inch and 4 -inch galvanized steel pipe (GS). Improvements included upgrades to all existing AC and undersized water mains with PVC water mains and addition of fire hydrants to provide increased fire protection. City of Longwood - Shadow Hills Subdivision Water Distribution System Improvements Project Manager - The City of Longwood has an ongoing program to improve their existing water distribution system through the scheduled replacement and upgrade of the older A 1 -16 � and undersized distribution mains. This project included the replacement of the 2 -inch and 4 -inch GS and 6 -inch AC water mains. Preliminary design included a hydraulic analysis for the addition of fire hydrants and sizing of a potential interconnect through the subdivision. Pipe bursting and directional drill construction methods were evaluated as alternative to standard open trench excavation. The project included 7,800 feet of 6 -inch; 2,700 feet of 8 -inch and 1,140 feet of 12 -inch water main. The 12 -inch water main will provide for the future looping of the City's transmission system based on the hydraulic analysis performed in the preliminary design. City of Belleview - US 441 Water Main Improvements Project Manager - Completed the preliminary engineering, final design, permitting and construction administration services for 16,750 feet of 12 -inch water main. The water main is to provide water service and fire flow to the existing commercial businesses along the water main corridor. During preliminary design, BFA performed a hydraulic analysis to size the water main for existing and future users for build -out conditions. We also performed an alignment study to determine the best routing options. As portions of the pipeline corridor were located within Marion County rights -of -way and FDOT rights -of -way, it was also necessary to obtain Right -of -Way Utilizations permits from Marion County and the FDOT, in addition to the FDEP Water System Construction Permit. Orange County Utilities - Eastern Regional Transmission System Improvements Project Manager- Project included master planning and transmission system improvements in the County's Eastern Regional Water Service Area. The hydraulic modeling prepared during the master plan was used to develop the County's 20 year plan for this service area. The transmission improvements included 37,350 feet of 24 -inch DIP water transmission main in eastern Orange County. In addition, 37,350 of 12 -inch to 24 -inch wastewater force main were designed and constructed as part of the projects based on County's Wastewater Master Plan. This project included crossing of the Econlockhatchee River, an Outstanding Florida Water, by open cut method while meeting all state and local environmental requirements. 1 -17 GEOFF HENNESSY, P. E. ( Project Manager) SENIOR PROJECT MANAGER AREAS OF SPECIALIZATION Mr. Hennessy is a Senior Project Manager. He directs the planning, design and permitting of municipal water, wastewater and reclaimed water transmission and distribution systems, as well as wastewater collection systems (including pumping stations). He has participated in the design of more than 140 miles of municipal pipeline projects in Florida. His formal education is enhanced by more than eight years of hands -on experience constructing major pipeline and irrigation systems. Mr. Hennessy's career began as a mechanical engineering tradesman in Australia, where he was responsible for the design, installation and maintenance of mechanical systems, and hydraulic and pneumatic piping and control systems to accommodate various industrial applications in a large steel mill. After moving to the United States, he utilized his piping knowledge as a supervisor of large -scale commercial irrigation installations in California and Florida. As Senior Project Manager, Mr. Hennessy oversees and coordinates the efforts of staff members and subconsultants involved in his discipline's projects and ensures that project budgets, objectives and schedules are met. EXPERIENCE Barnes, Ferland and Associates, Inc. 2009 - Present Jacobs 2006-2009 Prior Firms 1979-2006 EDUCATION Bachelor of Science, Environmental Engineering, 1993, University of Central Florida PROFESSIONAL REGISTRATION Professional Engineer, 2002, FL, #58637 REPRESENTATIVE PROJECT EXPERIENCE Orange County Utilities - Fiquette Road Force Main Replacement Project Manager - Completed the design, permitting, and bidding phase services for 3,600 feet of 16- inch wastewater force main between the Stillwater Pump Station and the end of the proposed roadway improvements. The project included preparation of maintenance of traffic plans and jack and bore of the existing roadway. City of Orlando /Orlando Utilities Commissions - Marks Street Improvements Project Manager - Completed the design and permitting phase services for 1,930 feet of 8 -inch, 800 feet of 12 -inch and 1,900 feet of 20 -inch water mains; and 435 feet of 8 -inch, 2,600 feet of 10 -inch and 2,105 feet of 15 -inch sanitary sewer. The project is located in a very developed urban area and required extensive coordination with the adjacent Lake Highland Prep School and neighborhoods. Orange County Utilities - Narcoossee Road (SR 15) Utilities Improvements Project Manager. Design, permitting and construction phase services for relocation /improvement of existing water and reclaimed water utilities along Narcoossee Road, from Lee Vista to McCoy Road. The improvements included 8,200' of 8 -inch reclaimed water main, two reclaimed water JW. 1 -18 metering stations and relocation of 6,600' of 12 -, 16- and 24 -inch water mains. The utility improvements were constructed through a Joint Project Agreement (JPA) between Orange County and the City of Orlando, in conjunction with the City's Narcoossee Road roadway and drainage improvements project. Orange County Utilities - West SR 50 Utility Improvements /Relocations Project Manager - As part of the UWHC Agreement between Orange County and FDOT, provided engineering design, permitting and construction phase services for relocation /improvement of existing water /wastewater utilities along 3.7 miles of West SR 50, from Good Homes Road to Pine Hills Road, as well as 2,500' section of Good Homes. This project included 2,000' of 42 -inch water main; 5,300' of 16- inch water main; 1,200' of 6- to 12 -inch water main; 10,800' of 6- and 8 -inch force main and 1,100' of gravity sanitary sewer. Also included CIPP lining 1,200' of existing 12 -inch gravity sanitary sewer and lift station site improvements. The improvements were constructed by FDOT's highway contractor as part of their West SR 50 road widening project. City of Orlando - Romano Ave. Reclaimed Water Transmission Main Project Manager - Planning, design, permitting, and construction phase services for the installation of 14,700 feet of 24 -inch reclaimed water transmission main through a residential neighborhood to extend the City's reclaimed water system from SR 436 to the Baldwin Park Community. Design included two separate 24 -inch HDPE directional drill crossings of FDOT roadways, Curry Ford Road and SR 50. City of Orlando — S.R. 436 Reclaimed Water Transmission System Project Manager — Design, permitting and construction phase services for the installation of 19,800 feet of 24 -inch reclaimed water main and 1,800 feet of 4 -inch through 12 -inch reclaimed water main in the S.R. 436 median from T.G. Lee Boulevard to Curry Ford Road. The project was designed and constructed as a Joint Project Agreement with FDOT's S.R. 436 road widening project. Orange County Utilities - Apopka - Vineland Road Water /Force /Reclaimed Water Main Improvements Project Manager - Completed the design, permitting, and construction phase services for 1,900 feet of 36 -inch water main, 2,800 feet of 20 -inch water main, 300 feet of 8 -inch water main, 2,700 feet of 16- inch force main, 1,800 feet of 12 -inch force main, 1,850 feet of 16 -inch reclaimed water main, and 2,500 feet of 12 -inch reclaimed water main. In addition, the project included three bore and jacks under the Florida Turnpike. City of Ocoee — Reclaimed Water Transmission Mains, Phase I, II, and III Project Manager - Design, permitting, and construction phase services for 9,300 feet of 16 -inch reclaimed water main and 2,100 feet of 12 -inch reclaimed water main as part of the City's Reclaimed Water Distribution Program. The project included 11 directional drills ranging in size from 8 -inch to 16- inches. City of Ocoee — Water Transmission Mains, Phase I, II, and III Project Manager - Design, permitting, and construction phase services for a City wide water transmission and distribution system improvement Project. The project included 23,500 feet of 12 -inch water main and 4,400 feet of 16 -inch water main installed in narrow urban and rural County and City owned rights -of -way with congested existing utilities. 1 -19 City of Ocoee - Maguire Road Segment I & II Utility Relocations Project Manager. Completed the design and permitting of 7,600 feet of reclaimed water main, 8,750 feet of water main, 3,800 feet of force main, and 1,400 feet of gravity sanitary sewer. The project involved relocating City utilities to allow for the widening and improvements of Maguire Road. The project also involved a reclaimed water main bridge crossing across the Florida Turnpike. City of Ocoee- Maguire Road /Story Road Intersection Improvements feet of 12-inch water main Project Manager. Completed design, permitting, and construction ntersection reco 0 0 r ruction p oject The project along Maguire Road as part of the City's roadway a also involved the removal and disposal of 2,000 feet of 10 -inch asbestos cement water main. City of Ocoee -Old Winter Garden Road /Professional Parkway Utility Relocations & Improvements Project Manager. Design, permitting and construction phase services for relocation of 6,000 feet of 6- inch through 12 -inch water main, 1,400 feet of 6 -inch force main, and installation of 5,900 feet of 4- inch through 16 -inch reclaimed water main The utility wpden ng an storm dwere and constructed in conjunction with the city's Professi onal improvement project. IRLPA 1 -20 CYNTHIA MALONE, P.E. ( Project Engineer) Sr. PROJECT ENGINEER / PROJECT MANAGER AREAS OF SPECIALIZATION Ms. Malone is a senior project engineer. She specializes in the planning, design and permitting of municipal and private water, wastewater and reclaimed water systems construction plans and specifications with a primary emphasis on pipeline projects throughout Florida. Her assignments include completing field visits to existing facilities and sites; retrieving existing facility and demographic documentation; data analysis and computer modeling of systems and preparation of detailed engineering reports and system designs. Ms. Malone also is experienced with facility and community - wide utility system master plans, regulatory agency permit applications, and facility operations and maintenance manuals and is responsible for coordinating with clients and monitoring project budgets, schedules and deliverables. EXPERIENCE Barnes, Ferland and Associates, Inc. 2009 - Present Jacobs 2006 —2009 Prior Firms 1994-2006 EDUCATION Bachelor of Science, Environmental Engineering, 1997, University of Central Florida Bachelor of Arts, Public Administration, 1991, University of Central Florida PROFESSIONAL REGISTRATION PROFESSIONAL ORGANIZATION Professional Engineer, 2002, FL, #58685 Florida Engineering Society (FES) National Society of Professional Engineers (NSPE) REPRESENTATIVE PROJECTS Orange County Utilities —Pine Hills Road Force Main Project Engineer — Provided preliminary design, final design and permitting for 670 feet of 12 -inch and 10,700 feet of 16 -inch wastewater force main. This project redirects the wastewater flows northward towards Master Pump Station #3006 in a direct path to the Northwest WRF and relieves capacity at both the Huggins Street Pump Station and the Hiawassee Road force main. Due to limited available right -of -way and conflicts with existing utilities, 3,600 feet along Pine Hills Road is proposed to be constructed by horizontal directional drill. Orange County Utilities - Narcoossee Road (SR 15) Reclaimed Water Main Improvements Project Manager - Project Engineer. Design, permitting and construction phase services for relocation /improvement of existing water and reclaimed water utilities along Narcoossee Road, from Lee Vista to McCoy Road. The improvements included 8,200' of 8 -inch reclaimed water main, two reclaimed water metering stations and relocation of 6,600' of 12 -, 16- and 24 -inch water mains. The utility improvements were constructed through a Joint Project Agreement (JPA) between Orange County and the City of Orlando, in conjunction with the City's Narcoossee Road roadway and drainage improvements project. 1- 21"x'.. Orange County Utilities -West SR 50 Utility Improvements /Relocations Project Manager - Part of a UWHC Agreement between Orange County and FDOT, provided engineering design services and currently providing construction administration services for relocation /improvement of existing water /wastewater utilities along 3.7 miles of West SR 50, from Good Homes Road to Pine Hills Road, as well as 2,500' section of Good Homes centered at West SR 50. Improvements included 2 of 42 -inch water main; 5,300' of 16 -inch water main; 1,200' of 6- to 12- inch water main; 10,800' of 6- and 8 -inch force main and 1,100' of gravity sanitary sewer. Also included slip - lining 1,200' of existing 12 -inch gravity sanitary sewer and lift station site improvements. The improvements are being constructed by FDOT's highway contractor as part of their West SR 50 road widening project. City of Belleview - US 441 Water Main Improvements Project Manager - Completed the preliminary engineering, final design, permitting and construction administration services for 16,750 feet of 12 -inch water main. The water main is to provide water service and fire flow to the existing commercial businesses along the water main corridor. During preliminary design, BFA performed a hydraulic analysis to size the water main for existing and future users for build -out conditions. We also performed an alignment study to determine the best routing options. As portions of the pipeline corridor were located within Marion County rights -of -way and FDOT rights -of -way, it was also necessary to obtain Right -of -Way Utilizations permits from Marion County and the FDOT, in addition to the FDEP Water System Construction Permit. Orange County Utilities- Apopka - Vineland Road Water /Force /Reclaimed Water Main Improvements Project Engineer - Completed the design, permitting, and construction phase services for the installation of 1,900 feet of 36 -inch water main, 2,800 feet of 20 -inch water main, 300 feet of 8 -inch water main, 2,700 feet of 16 -inch force main, 1,800 feet of 12 -inch force main, 1,850 feet of 16 -inch reclaimed water main, and 2,500 feet of 12 -inch reclaimed water main. In addition, the project included three bore and jacks under the Florida Turnpike. The utility improvements were designed and constructed in conjunction with the County's Apopka - Vineland Road widening and storm drainage improvement project. Orange County Utilities - Curry Ford Road /Alafaya Trail Water /Wastewater Transmission Mains Project Engineer - Completed the design and permitting for over six miles of water transmission mains along Curry Ford Road from the Eastern Beltway to Alafaya Trail; and along Alafaya Trail, from Lake Underhill Road to Golfway Boulevard. The project included 20,100 feet of 36 -inch water main, 7,000 feet of 30 -inch water main, 4,700 feet of 24 -inch water main, 2,800 feet of 20 -inch water main, and 4,500 feet of 12 -inch force main. Also included a 600 -foot, 36 -inch directional bore under the Little Econlockhatchee River. The utility improvements were designed and constructed in conjunction with the County's Curry Ford Road widening and storm drainage improvement project. City of Ocoee - Reclaimed Water Mains, Phase I & II Project Engineer - Completed the design of 9,300 feet of 16 -inch reclaimed water main and 2,100 feet of 12 -inch reclaimed water main as part of the City's Reclaimed Distribution Program. The project included eleven directional drills ranging in size from 8 -inch to 16 -inch. 1 -22 City of Ocoee -Water Transmission Mains, Phase I, II & III Project Engineer, - Completed the design and permitting of a Citywide water distribution improvement project. The project included 23,500 feet of 12 -inch water main and 4,400 feet of 16 -inch water main Performing company name: Professional Engineering Consultants (PEC). City of Orlando- Romano Ave. Reclaimed Water Transmission Main Project Manager - Completed the planning, design, permitting, and construction services of 14,700 feet of 24 -inch ductile iron reclaimed water main within FDOT right -of -way, through obtained utility easements, the Romano Avenue residential neighborhood, and Greater Orlando Aviation Authority (GOAA) property at the Orlando Executive Airport. The project also included two separate 24 -inch HDPE directional drills across Curry Ford Road and State Road 50, FDOT roads. City of Orlando -SR 436 Reclaimed Water Transmission System Project Engineer - Completed the design and construction phase services for the installation of 19,800 feet of 24 -inch reclaimed water main and 1,800 feet of 4 -inch through 12 -inch reclaimed water main in the SR 436 median from T.G. Lee Boulevard to Curry Ford Road. The project was designed and constructed as a Joint Project Agreement (JPA) with FDOT's SR 436 road widening project. 1 -23 WILLIE E. THOMAS, P. E. ( Project Engineer) SENIOR PROJECT MANAGER / VICE PRESIDENT AREAS OF SPECIALIZATION Mr. Thomas is a Senior Engineer with over 18 years of experience in utility and municipal engineering, master planning, water resources engineering, design and construction of water and wastewater treatment facilities, effluent reuse and disposal, water distribution /transmission and pumping systems, wastewater collection /transmission and pumping systems, and well field development and well pumping systems. As Senior Project Manager and Vice President at BFA, Mr. Thomas supervises and coordinates various engineering and project management activities related to BFA staff members and subconsultants ensuring project objectives, schedules and client expectations are met. Specific experience includes the planning, design, permitting and construction management of over 50 miles of pipelines ranging from 2 -inch diameter distribution mains to 54 -inch potable water and wastewater transmission mains, and over 30 pump station designs for potable water, raw water, wastewater, reuse, and stormwater conveyance systems. Mr. Thomas also has experience evaluating and designing wastewater, potable water, and reuse water conveyance systems using various hydraulic modeling platforms and integration with GIS Mapping. EXPERIENCE Barnes, Ferland and Associates, Inc. 2000- Present Brown and Caldwell, Inc. 1994-2000 EDUCATION University of Central Florida, B.S., Civil Engineering, 1996 PROFESSIONAL REGISTRATION ASSOCIATIONS Professional Engineer FL 57612 (2000) Florida Water and Environment Association (FWEA) REPRESENTATIVE EXPERIENCE Orange County Utilities — Apopka Boulevard Water Main Project Senior Project Engineer — Provided preliminary design, final design, permitting, bidding and award, and construction administration services for the installation of 1,790 feet of 20 -inch, 3,120 feet of 16 -inch, and 1,580 feet of 12 -inch water main along Apopka Boulevard (Lake Pleasant Rd to Platinum Rd and Vulcan Rd to Palm Ave) and segments along Overland Rd and Palm Ave to US 441. Two segments were installed by horizontal directional drill, 120 feet of 16 -inch and 230 feet of 12 -inch water main. Corridor analysis of the existing and conceptual roadway improvements was performed for determination of existing utility locations along with potential conflicts with existing utilities. Services included subsurface utility engineering (SUE), preliminary environmental assessment, and groundwater sampling and analysis. Permitting services included City of Apopka ROW Permit, FDOT Utility Permit, and two (2) FDEP General Permits to construct water distribution system extensions. Orange County Utilities - SR 482 (Sand Lake Road) Utility Relocation Project Senior Project Engineer — Provided preliminary design, final design, permitting, bidding and award, and construction administration services for the relocation and removal of existing wastewater force mains located within the right of way along SR 482 (Sand Lake Road), between Presidents Drive and South Orange Blossom Trail. Corridor analysis of the existing and proposed roadway was 1 -24 performed for determination of existing dry and wet utility locations along with potential conflicts with proposed utilities. Project included the relocation of 322 LF of 4" and 6" FM, 415 LF of 12" FM, and 3,800 LF of 30" FM; 48" Casing Jack and Bore installation at the CSX railroad crossing; and the rehabilitation of approximately 2,030 LF of existing 10" and 15" VCP gravity sewer pipe and manholes. Toho Water Authority - Pleasant Hill Road Water Main Extension Project Manager /Senior Project Engineer — Provided preliminary design, final design, permitting, and bidding assistance services for the installation of 2 -ft of 16 -inch water main, 413 -ft of 8 -inch water main, 541 -ft directional drill of 20 -inch HDPE water main, 387 -ft directional drill of 10 -inch HDPE water main, 187 -ft directional drill of 8 -inch HDPE water main, and 415 -ft of directional drill of 4 -inch HDPE water main. Corridor analysis of the existing roadway was performed for determination of existing dry and wet utility locations for selection of the best water main alignments. Orange County Utilities - Meadow Woods WSF to South Regional WSF 16 -inch Water Main Senior Project Engineer — Provided preliminary design, final design, permitting, bidding and award, and construction administration services. This project involved the extension of 5,500 feet of 16 -inch raw water main from two water supply wells at the existing Meadow Woods WSF to the new South Regional WSF. The pipe alignment presented many coordination and technical design challenges as it was located within a dual easement occupied by OUC high voltage electrical transmission mains, crossed numerous wetland areas, crossed a CSX Railroad, crossed a major transportation shipping facility driveway and the highly congested Orange Avenue right -of -way. Orange County Utilities - Harbor East Pump Station and Force Main Improvements Project Manager — Design, permitting and construction management services for the replacement of an existing duplex pump station with a new triplex master pump station within an existing residential neighborhood. Infrastructure improvements included the installation 13,350 -LF of 12 -inch force main (4,000 -LF along University Blvd and the 9,350 -LF within an existing subdivision) and abandonment of 3,040 -LF of 6 -inch force main. Project included two (2) horizontal directional drills, under the Little Econ River at University Blvd and also crossing University Blvd. Orange County Utilities - Golfway Boulevard Wastewater Force Main Replacement Project Manager /Project Engineer — Design, permitting and construction management services for the replacement of existing 8 -inch and 10 -inch wastewater force main within the public right of way of Golfway Boulevard with 5,100 feet of 12 -inch PVC wastewater force main installed by horizontal directional drill. The force main was being replaced due to several failures of the existing force main. Preliminary design services included conducting an alternative analysis to evaluate pipeline installation utilizing directional drilling or traditional open cut methods. Greater Orlando Aviation Authority - Heintzelman Boulevard at Orlando International Airport Project Engineer - Project included utility relocations and improvements necessitated by the roadway improvements along Heintzelman Boulevard at the Orlando International Airport. As the utility engineering subconsultant, provided preliminary design, final design, permitting and construction administration services for removal of 3,000 feet of 14 -inch reclaimed water main and the installation of 25,000 feet of 16 -inch and 20 -inch water main for the Orlando Utilities Commission; and 14,500 feet of 12 -inch wastewater force main and 12,600 feet of 12 -inch reclaimed water main for the City of Orlando. Other work included the relocation of reclaimed water meters and a 16 -inch reclaimed water main under a canal. 1 -25 ERIN J. GIBLIN, P. E. ( Project Engineer) PROJECT ENGINEER AREAS OF SPECIALIZATION Ms. Giblin is an environmental engineer with eleven years of experience of providing planning; design, permitting assistance and engineering services for wastewater, potable water, water resources, and reclaimed water projects. She has been involved in various phases of master plan development for several projects. Ms. Giblin also has experience evaluating and designing wastewater, potable water, and reuse water conveyance systems using various hydraulic modeling platforms and graphical information systems such as H Cybernet /Watercad and ArcGIS. EXPERIENCE Barnes, Ferland and Associates, Inc. Orange County Utilities 2003 - Present 2002 -2003 EDUCATION University of Central Florida, B.S., Environmental Engineering, 2002 PROFESSIONAL REGISTRATION Professional Engineer, FI (66465) — 2007 Professional Engineer, LA (33896) — 2008 Professional Engineer, MS (18631) — 2009 Professional Engineer, TX (104323) — 2009 ASSOCIATIONS Florida Water and Environment Association (FWEA) American Water works Association (AWMA) REPRESENTATIVE EXPERIENCE Orange County Utilities - SR 482 (Sand Lake Road) Wastewater Utility Relocation Project Project Engineer — Provided preliminary design, final design, permitting, bidding and award, and construction administration services for the relocation and removal of existing wastewater force mains located within the right of way along SR 482 (Sand Lake Road), between Presidents Drive and South Orange Blossom Trail. Corridor analysis of the existing and proposed roadway was performed for determination of existing dry and wet utility locations along with potential conflicts with proposed utilities. Project included the relocation of 322 LF of 4" and 6" FM, 415 LF of 12" FM, and 3,800 LF of 30" FM; 48" Casing Jack and Bore installation at the CSX railroad crossing; and the rehabilitation of approximately 2,030 LF of existing 10" and 15" VCP gravity sewer pipe and manholes. Orange County Utilities — Wekiva Manor Subdivision Water System Improvements Project Engineer — Design, permitting and construction management services for the replacement of existing 2" through 8" asbestos - cement and galvanized steel water mains with new water mains. Project included the installation of over 8,500 LF of 6" and 8" PVC water main. The majority of work for this project was performed in an existing subdivision of approximately 450 residential lots. Preliminary design services included conducting an alternative analysis to evaluate pipeline installation methods. The analysis, preliminary layout, cost estimate and recommendations were presented at a review meeting. Prepared and distributed project notification fliers. Coordinated and _EWA 1 -26+,� conducted community meeting for all residents and business owners within the project vicinity to disuss the project purpose and anticipated disruption to the community during construction. Orange County Utilities — Cypress Springs Pump Station and Force Main Improvements Project Engineer - Provided engineering preliminary and final design, permitting, and construction management services for the rehabilitation of a wastewater pump station and the replacement of the discharge force main. The project includes the removal of existing submersible pumps and control panel, discharge piping, fittings and valves; and installation of duplex submersible pumps, discharge piping and valves, aboveground by -pass piping, wetwell and valve vault repair, replacement of 2,462 feet of 12" PVC wastewater force main within public roadways in an established neighborhood. Orange County Utilities — Clearview Heights /Westmont Manor Subdivisions Water System Project Manager - This project included improvements to the water distribution systems serving the Clearview Heights and Westmont Manor Subdivisions. The number of residential single - family homes served by these improvements is 325. The existing water mains within these subdivisions are 2 -inch, 4- inch & 6 -inch asbestos - cement (AC); 4 -inch, 6 -inch and 8 -inch PVC; and 2 -inch and 4 -inch galvanized steel pipe (GS). Improvements included upgrades to all existing AC and undersized water mains with PVC water mains and addition of fire hydrants to provide increased fire protection. Orange County Utilities — Harbor East Pump Station and Force Main Improvements Project Engineer - Assisted in the engineering design for the replacement of a wastewater pump station and forcemain components. The project includes a triplex submersible wastewater pump station, 13,350 LF of 12" PVC wastewater forcemain, 1,000 LF of 8" & 15" PVC gravity sanitary sewer and manholes, abandonment of an existing duplex submersible wastewater pump station, force main and gravity sewer connections to existing wastewater system, abandonment of 760 LF of existing 8" gravity sewer and manholes and 3,040 LF of 6" PVC Force main. Provided bidding evaluations and recommendation of award. Prepared and distributed project notification fliers and coordinated community meeting for all residents and business owners within the project vicinity. Orange County Utilities — Holden Heights Community Improvements Project Engineer - Provided assistance for construction management services for Phase 2, which includes the construction of approximately 12 -miles of sanitary sewer, 1900 LF of forcemain, 6 -miles of potable water lines, and one (1) wastewater lift stations. Tasks performed include monthly progress meetings, contractor RAls coordination; shop drawing review, periodic site visits, review change order requests, public information fliers, and license agreement database. City of Belleview — Spruce Creek Reclaimed Water Transmission Main Project Engineer — Provided preliminary design, final design, permitting and construction administration services for 15,000 feet of 12 -inch reclaimed water main within the public right of way of the City of Belleview and Marion County. Conducted corridor analysis of the project area and hydraulic modeling of the City's reclaimed water system to determine optimal location, sizing and operation of the reclaimed water main to supply reclaimed water to the Spruce Creek Golf Course from the City's wastewater treatment facility. Assisted the City in obtaining and administering a grant from the SJRWMD and a loan from the Florida SRF program. Prepared applications for a FDEP General Permit for Addition of a Major User of Reclaimed Water and a Marion County right -of -way utilization permit. 1 -27 WILLIAM MILLER, PLS SENIOR SURVEYOR AREAS OF SPECIALIZATION Over 45 years of surveying experience that has included a wide range surveying issues and tasks beginning with 15 years on a field crew including 10 years as a party chief before moving into the office to become a survey technician and eventually a project manager for 18 years. Managed large acquisition projects of up to 10,000 acres, large construction with high levels of precision and numerous design surveys for both in -house and external clients. Duties include complete project management from inception through fee estimation and scope negotiations, proposals, supervision of field and office staff, client contact and delivery of record surveys. Mr. Miller's exceptional skill at project budget management and on time delivery of completed work provides a client with reliable and accurate information. William has been surveyor of record for large Boundary Surveys, Topographic Surveys for design projects, photogrammetry support, construction staking and As -Built Surveys, Horizontal and Vertical Control Surveys, Legal Descriptions and Specific Purpose Surveys. EXPERIENCE Barnes, Ferland and Associates, Inc. 2009- Present Street Smarts, Inc. 2005 —2009 Weidener Surveying & Mapping 2002 —2005 Regional Engineers Planners & Surveyors / MACTEC 1994 —2002 Professional Engineering Consultants 1983 —1994 Various throughout Florida 1969 —1983 EDUCATION Bureau of Land Management Retracement Camp Numerous Continuing Education Seminars PROFESSIONAL REGISTRATION Florida Professional Surveyor and Mapper: LS 5010 Registered 1991 PROFESSIONAL AFFILIATIONS Florida Survey and Mapping Society Central Florida Chapter FSMS Valencia Community College: Civil and Survey Advisory Committee REPRESENTATIVE EXPERIENCE Orange County Utilities: Anderson Street Water Main and Force Main Replacement Project Surveyor/ SUE Manager — Topographic Surveys of Anderson Street for the replacement of aging water pipe lines and wastewater force main. Designation and excavation of pertinent conflicting underground utilities within right of ways. Horizontal and vertical control for construction established and a Control Survey prepared for the inclusion into construction plans 1 -28 Orange County Utilities: Lee Vista Blvd to Innovation Way Project Surveyor — Topographic Survey of a 7 mile corridor to for the design of a 30" water line and 24" force main. Control Survey for horizontal and vertical controls prepared for inclusion in plans. Orange County Utilities: Sweetwater Country and Ramir Subdivisions Project Surveyor/ SUE Manager — Topographic Surveys of the Ramir Subdivision and portions of Sweetwater Subdivision for the replacement of aging water pipe lines. Designation and excavation of pertinent conflicting underground utilities within right of ways. Horizontal and vertical control for construction established and a Control Survey prepared for the inclusion into construction plans Orange County Utilities: Park Manor Water and Sewer Project Surveyor/ SUE Coordinator — Topographic Survey of over 7 miles in various areas of the Park Manor development area for the design of replacement of concrete asbestos water lines and failing sanitary sewer systems. Horizontal and vertical control for construction established and a Control Survey prepared for the inclusion into construction plans City of Orlando: Marks Street Project Surveyor/ SUE Coordination — Topographic Survey and Control Survey prepared for the design of construction plans to replace sanitary gravity sewer system and existing force main in vicinity. Underground utilities were marked for inclusion in survey and excavation of force main and electrical duct banks performed to determine the exact location, type, material and condition of utility. Horizontal and vertical control established for construction and Control Survey prepared for plans. City of Orlando: Dahlia Drive Project Surveyor/ SUE Coordination — Topographic Survey and Control Survey prepared for the design of construction plans to replace sanitary gravity sewer system. Underground utilities were marked for inclusion in survey.. Horizontal and vertical control established for construction and Control Survey prepared for plans. City of Longwood: Skylark Subdivision Survey/ SUE Coordination — Prepared Topographic Survey for in -house design to replace water line system for approximately 3 miles within Skylark Subdivision. Control established resulting in Control Survey for inclusion in the construction plans. City of Orlando: Water Consery II to City of Apopka SUE Coordinator — Designated underground utilities for location survey by others of over 5 miles of large re -use water pipe line to provide reclaim water to the City of Apopka. Provided color coded sketches of utilities marked for use by the survey crew. Excavation of conflicting point along pipe line route. ZMA 1 -29 1.8 Organizational Chart 1 \`�1I Geoff Hennessy, PE (BFA) " Daniel L. Allen, PE (BFA) Cynthia Malone, PE (BFA) Legend BFA Barnes, Ferland and Associates* ANT Antillian Engineering Associates* M /WBE Firms 1 -30 1.9 Project Approach PROJECT UNDERSTANDING: BFA has thoroughly reviewed the City of Ocoee's RFQ for Engineering Services for the Ocoee West Sanitary Transmission project, RFQ #1401; discussed the project with our Team members; performed a photographic aerial review of the project corridor, reviewed the rights -of -way of the proposed project corridors on the Orange County Property Appraisers web site; attended the pre - proposal conference; and conducted a field investigation of the project corridors We have also reviewed the documentation made available by the City of Ocoee, which included the Ocoee West Wastewater Utility Plan; the Western Force Main Route Evaluation; the Reclaimed Feasibility and Capacity Plan; the Final Conceptual Downtown Ocoee Sewer Plan; and the Bluford Avenue Stormwater and Utility Improvements Plans. We understand this Project is being implemented by the City of Ocoee because one of the major shortcomings of the City's existing sanitary sewer system is that it moves all wastewater flow in a circle around the city, which imposes a large demand on the facilities serving State Road 50. These facilities are currently operating at near capacity and impact the ability for the State Road 50 corridor to grow significantly. The West Sanitary Transmission Project will redirect a major portion of the wastewater flow from the western part of the City in a different direction and free capacity for future Community Reinvestment Act (CRA) redevelopment. PROJECT SCOPE AND APPROACH: The BFA Team is experienced and qualified to provide the professional engineering services required for the successful completion of this Project. Our Team is made up of licensed professionals who are familiar with all applicable regulations and construction standards of the City of Ocoee, State of Florida, St. Johns River Water Management District, Orange County, and the Pinsly Railroad. BFA understands this project involves the design, coordination, permitting and bidding services (no construction phase services) for the construction of 20,500 feet of 12 -inch, 16 -inch and 20- inch force main segments from the project's southern point of beginning at the corner of Kissimmee Avenue to the project's point of completion at A.D. Mims Road in front of the City's Wastewater Treatment Facility. The City has made it clear that any necessary support services required for this project should be included on the successful consultant's Team. BFA anticipates that we can provide the majority of services in -house including engineering design; topographic, utility and boundary surveying and mapping; subsurface utility exploration (soft digs); ecological services (if required); and civil engineering for Stormwater Pollution Prevention Plans. BFA anticipates the need for and has included Antillian Engineering to provide geotechnical investigations and engineering services. 1 -31 ,�', The overall project corridor can be best described in a series of project segments as follows: 12 -inch Force Main from H.M. Bowness Road to Bluford Avenue: This 12 -inch segment of force main is 2,250 feet long, primarily located along Lee Street and Franklin Street between H.M. Bowness Road and Bluford Avenue. Design considerations for this pipe segment: • The point of connection to the existing force main is in the right -of -way of H.M. Bowness Road, which is S.R. 4371S.R. 438, and will need to be permitted through FDOT. • The Lee Street right -of -way (ROW) is 40 feet wide and the Kissimmee Avenue ROW is 30 feet wide and parallel to the railroad. The proposed force main may need to be installed in pavement in these sections. • This segment includes a crossing of the Florida Central Railroad (owned by Pinsly Railroad), and will need to be permitted through the railroad owner. A bore and jack of this crossing is anticipated. • The 40 foot long jacking pit for the railroad crossing could be best set up on the east side of the railroad along the north side of Franklin Street. However, the force main would best be installed on the south side of Franklin Street for the remainder of the segment to reduce restoration costs. 16 -inch Force Main from Kissimmee Avenue to Franklin Street: This 16 -inch segment of force main is 4,790 feet long, located along Columbus Street between Kissimmee Avenue and Bluford Avenue; and along Bluford Avenue from Columbus Street to Franklin Street. Design considerations for this pipe segment: • A 1,580 foot long portion of this segment of force main has already been designed by the City of Ocoee and is included in the City's Bluford Avenue Stormwater and Utility Improvements Project. This portion of City- designed force main is along Bluford Avenue from Columbus Street to north of Delaware Street. The successful consultant will be required to coordinate and match designs with the City for this Downtown force main element of the project. • The ROW width through this segment appears to vary in width in several areas from only 55' wide to 80' feet wide. ROW availability will need to be confirmed during survey and design will need to address these variances. • This segment of force main is directly adjacent to the City's Fire Station No. 25, and is also a primary thoroughfare for vehicular and pedestrian traffic to Ocoee Middle School and Ocoee Elementary School. Careful consideration needs to be given to traffic control and the potential need for full roadway detours during the construction. • Bluford Avenue in the vicinity of McKey Street and the signalized McKey Street intersection have been recently hardscaped and consideration with regard to restoration is necessary when considering passing through this area. 1 -32 20 -inch Force Main along Bluford Avenue, Rewis Street and Lakewood Avenue from Franklin Street to the Lakewood Master Lift Station Site: This portion of the 20 -inch force main is 2,840 feet long, located along Bluford Avenue, Rewis Street and Lakewood Avenue from Franklin Street to the proposed Lakewood Master Lift Station Site on the corner of Lakewood Avenue and Security Circle. Design considerations for this pipe segment: • This segment includes crossing Silver Star Road, which is a State Road (S.R. 438), and will need to be permitted through FDOT. A horizontal directional drill may be the best crossing method for this intersection. Relatively deep SPT borings will be an important requirement of the geotechnical investigation in this area. • On Bluford Avenue, in the vicinity of Silver Star Road, there is a storm sewer system to consider in design in addition to the signalized intersection • This segment includes crossing the Florida Central RailRoad at the intersection of Bluford Avenue and Rewis Street, and will need to be permitted through the railroad owner. A bore and jack is anticipated. Jacking and receiving pits will have to be carefully placed so as not to impede the entrance to the "buffalo farm ". • We understand the City of Ocoee will design the Lakewood Master Lift Station and the successful consultant will coordinate with the City to incorporate the City's construction documents for the master lift station with the consultant's force main construction documents. • The ROW width through this segment appears to vary in width in several areas from only 55 feet wide to 70 feet wide. ROW availability will need to be confirmed during survey and design will need to address these variances. 20 -inch Force Main along Lakewood Avenue, Wurst Road and A.D. Mims Road from the Lakewood Master Lift Station Site to the WWTF: This portion of the 20 -inch force main is 10,360 feet long, located along Lakewood Avenue, Wurst Road and A.D. Mims Road from the Lakewood Master Lift Station Site to the City's Wastewater Treatment Facility. Design considerations for this pipe segment: • Portions of this segment along Lakewood Avenue and Wurst Road are located within Orange County rights -of -way. Coordination and permitting with Orange County Public Works will be necessary. • The ROW width through this segment appears to vary in width in several areas from only 50 feet wide to as wide as 100 feet. ROW availability will need to be confirmed during survey and design will need to address these variances. • This segment also includes crossing the Florida Central Railroad at the intersection of Wurst Road and A.D. Mims Road A bore and jack is anticipated. Jacking and receiving pits will have to be carefully placed due to the curve in the roadway at this location. Preliminary Engineering: The goal of the preliminary engineering phase of the project is to evaluate, develop and present project completion recommendations to the City of Ocoee in a 1 -33 manner that will allow the determination of the best and most cost effective fit for the proposed force main within the project corridors. To achieve this goal, our Team, led by Project Manager, Geoff Hennessy, PE, will first meet with City Staff to initiate the project and collect and review all available information pertaining to the proposed project corridors, including records, reports, aerials, maps, right -of -way and easements, property ownership, proposed roadway construction plans, record drawings and utility as- builts. Based on our understanding of this project, we know that early, thorough, ongoing and consistent coordination during preliminary engineering and design will be essential to the success of the project. We understand that we will be responsible for extensive coordination with multiple stakeholders. Our primary coordination will be with the City of Ocoee Project Manager. However, it will be imperative to coordinate with the FDOT, Orange County Public Works Department, FDEP, SJRWMD, Pinsly Railroad, and existing utility owners who are located within the project corridors. At the first stage of the project, our Team will initiate contact and pre- design meetings with these stakeholders to obtain guidelines and information related to the design, permitting and construction of the project. It will be incumbent upon us, as the project designers, to evaluate the most feasible pipe alignments and most efficient installation methods within the project corridors. We will perform extensive field reviews of the project corridors to ascertain field conditions with respect to utility alignment and design considerations. Surveying: Upon receiving the Notice to Proceed, our Surveyor, Mr. Bill Miller, PLS, will review and research the topographic, right -of -way and easement boundaries. We will then identify the survey requirements along the project corridors and identify areas where subsurface utility excavation (SUE) may be required. Our Survey Team will establish the Construction Base Lines specifically relative to the force main corridor and perform the survey identified as necessary. Utilizing our own equipment, including ground penetrating radar, utility locating equipment and vacuum excavation equipment, our BFA SUE crews will perform any soft digs identified as necessary. We anticipate designating, survey and vacuum excavation of existing utilities at regular intervals along the project corridor. Geotechnical Investigation: Our Geotechnical Subconsultant, Mr. Peter Suah, PE, will mobilize to perform auger borings, as required for the utilities construction, at suitable intervals within the force main project corridors; and standard penetration tests (SPTs) at bore and jack and directional drill locations such as the Silver Star Road crossing and the railroad crossings. We will also obtain pavement test cores in all areas where we anticipate needing to install the force main within existing paved roads for design of our roadway restorations. Our geotechnical team will perform laboratory tests and analyses of the soil borings. A Soils Report will be prepared for the project that will address soil classifications, existing and estimated seasonal groundwater levels, pipe trench preparation, backfill recommendations and other geotechnical recommendations or restrictions. The report will be submitted to City Staff for review and ultimately, copies of the report will be included with the construction documents as information available to bidders. 1 -34 Preparation of Construction Documents: With oversight from our Project Manager, Geoff Hennessy, PE, and direction from our Project Engineer, Cynthia Malone, PE, our Team will design the proposed force main improvements in plan and profile utilizing AutoCAD. We will create General Notes and Standard Detail Sheets in accordance with the City's Engineering Standards Manual. In addition, we will prepare any special cross section sheets that are required to design railway and road crossings by directional drills and /or bore and jacks. We also will prepare the Project Manual including specific Technical Specifications, General Requirements, Bid Form, and a Measurement and Payment section that will relate directly to each pay item in the Bid Form. Should the City request as part of the scope of work, Maintenance of Traffic (MOT) plans and Stormwater Pollution Prevention (SW3P) plans will be developed by our Team. We will develop the construction contract documents through a series of 60 %, 90% and 100% submittal packages. Each submittal package will include the documents required by the City of Ocoee including construction drawings, technical specifications, bid form, and engineer's construction cost estimate. Prior to each submittal, our QA /QC Officer, Daniel Allen, PE, will conduct and provide written certification of an internal QA /QC review of the submittal package. Following each submittal, we will meet with the City of Ocoee to obtain review comments and discuss the documents and then prepare a written list, in spreadsheet form, of the City's comments and actions taken and submit that list to City for verification prior to revising the construction documents in accordance with the comments. Permitting: BFA anticipates the need to prepare and submit the following permit applications: FDEP Application for Constructing a Domestic Wastewater Collection/ Transmission System; Pinsly Railroad Applications for Utility Installations; FDOT Utility Permits; and FDEP's Generic Permit for Stormwater Discharge from Large and Small Construction Activities (NPDES). The project does impact Orange County ROW on portions of Lakewood Avenue and Wurst Road. Therefore, our Team will coordinate with Orange County Public Works for review and pre_ approval of the construction documents prior to bidding. However, we anticipate the selected contractor will prepare, submit and pay the Orange County Underground Utility and ROW Permit Applications. During the preparation of construction documents, we will begin to prepare the necessary permits for the project. Once the City has approved final construction documents, we will finalize and submit the required permit applications with supporting documentation and applicable fees. We understand that the City relies on their consultant to prepare thorough permit application packages that allow efficient review and approval by the jurisdictional agency involved. Our goal in the permitting phase of a project is to prepare high quality submittals that limit the need for requests for additional information (RAI) from the permitting agencies. In the event RAI's are submitted, we will coordinate our responses with City Staff accordingly. At this level of completion of the project, it is crucial to obtain the necessary permits as quickly as possible to allow the project to proceed to the bidding phase. 1 -35 Public Involvement: The project corridor along Bluford Avenue, Rewis Street, Lakewood Avenue, Wurst Road and A.D. Mims Road are developed and the roads carry significant traffic. Should the City wish to include a public involvement component in the scope of work for the project, with oversight from our Project Manager we will prepare for and conduct at least one (1) pre- construction community meeting to discuss the proposed construction with adjacent residential property owners, business owners and potentially affected commuters. Bidding Assistance: Our Team will prepare bidding documents and coordinate closely with the City's Purchasing Department, respond to bidders' questions and prepare written addenda, attend the pre -bid conference, prepare meeting minutes, evaluate bids and make a recommendation of award. We have the prescribed forms in place to tabulate and certify the bids. All bids will be compiled into an Excel spreadsheet, checked for math errors and compared against the Engineer's Estimate. In addition, we have a standard reference checklist that we use to verify contractor's references and evaluate the specifics of a contractor's previous project performance. We then will include the certified bid tabulation and the results of the contractor's reference checks in the Recommendation of Award Letter for the City's use. SPECIAL CONSIDERATIONS: Major Road and Railroad Crossings: The project corridor includes making a force main connection within H.M. Bowness Road, (S.R. 437/ S.R. 438), crossing under Silver Star Road (S.R. 438), and crossing the Pinsly Railroad at three locations. We anticipate crossing the railroad by bore and jack, and crossing S.R. 438 by either directional drill or by bore and jack. For S.R. 438, we will evaluate the crossing and recommend the most viable and cost effective of the two potential trenchless crossing methods. Obtaining approval for the roadway crossing, the railroad crossings, and occupying portions of Orange County rights -of way will require early dialog with the Florida Department of Transportation, the Pinsly Railroad and Orange County Public Works. Pre - design meetings will be conducted early in the project to discuss the design concepts, soils conditions, future planned improvements and construction issues, and to ascertain submittal requirements and review schedules. Public Involvement: Coordination and discussion with the homeowner's, businesses and public schools in the project area are critical to the acceptance of the project by the residents, businesses and commuters in the area. Should the City request assistance within the scope of work of the project, BFA has successfully developed and conducted public participation programs on many similar projects in urban settings throughout Orange County and the City of Orlando. POSSIBLE DIFFICULTIES AND ALTERNATIVE APPROACH: It is apparent that the urban roadways in the project corridor are well traveled and important thoroughfares for the City of Ocoee and Orange County residents. We have reviewed daily traffic counts reported by Orange County and have found the following: • Bluford Avenue, south of McKey Street; 12,500 cars per day. • Bluford Avenue from McKey Street to Rewis Street; 8,200 cars per day. • Silver Star Road in the vicinity of Bluford Avenue; 13,800 cars per day. 1 -36 • Lakewood Avenue from Rewis Street to Wurst Road; 6,700 cars per day. • Wurst Road from Lakewood Avenue to A.D. Mims Road; 5,500 cars per day. • A.D. Mims Road from Wurst Road to Clarke Road; 6,900 cars per day. The high traffic and the numerous important connecting roads, in addition to the critical locations of Ocoee Fire Station No. 25, Ocoee Middle School, and Ocoee Elementary School will present difficulties and could potentially create hazardous conditions to the public and construction crews. We believe it would be prudent to include a vehicular and pedestrian Maintenance of Traffic Plan with project construction plans and specifications. This way, we, as the design engineer, can present for the contractor's consideration well thought out controls and safeguards necessary to protect the public and workers from traffic hazards during construction, and protect the general public using these corridors on their daily commutes. SPECIALIZED SKILLS: We consider our extensive experience with municipal pipeline projects through urban corridors to be our most important specialized skill for this Project. Our key Team members have specific in -depth knowledge of City of Ocoee design and construction standards and procedures and extensive design and construction experience though many of the same or similar City of Ocoee high traffic urban corridors. Our key Team Members are considered experts in their field and add significant value to the overall Team. Three (3) areas of expertise where we believe our Team provides the City of Ocoee unique specialized skills directly correlated to this project are 1) our Team's large pipeline design experience within major urban public roadways, 2) our extensive knowledge of trenchless technology construction methods and 3) our past involvement in projects requiring critical public involvement. 1) Our Project Manager, Geoff Hennessy and Project Engineer, Cynthia Malone, who have worked together for over 15 years, are highly experienced with Central Florida utility pipeline design and construction projects within major urban public roadways. Geoff has designed over 130 miles of Central Florida pipeline projects, 60 miles of which has been large diameter water and wastewater and reclaimed water transmission mains ranging in size from 16 -inch to 42- inches. Cynthia has participated in the design of more than 100 miles of Central Florida pipeline projects. More importantly, since 1993, while employed by a previous company, Geoff has designed over 14 miles of utility piping throughout the City of Ocoee, including many of the same corridors as this project. He has designed 46,900 feet of water mains, 25,000 feet of reclaimed water mains, 5,200 feet of force mains and 1,400 feet of sanitary sewer. Working with Geoff, Cynthia has participated in many of the same designs for a total of over 10 miles of utility piping within the City. 2) Our Team has extensive trenchless technology knowledge and experience that has spanned over 20 years in Central Florida. We were able to highlight some of Geoff's and Cynthia's recent projects in earlier sections of this proposal, but that is only a small portion of our Team's trenchless technology experience. Specifically for horizontal direction drilling 1 -37 projects, we have developed spreadsheets to verify the length and limits of construction and required pipe wall thickness using industry standards Our Team's projects have included trenchless crossings of causeways on the coast; rivers, canals and streams in Central Florida; major arterial roadways and expressways; and all the railroad companies in Central Florida. 3) Our Project Manager, Geoff Hennessy and Project Engineer, Cynthia Malone, routinely conduct successful Community Meetings in support of utility pipeline projects in urban corridors. For example, they recently prepared and conducted a public participation meeting for the City of Orlando's Dahlia Drive Sanitary Sewer Improvements project located in unincorporated Orange County. The project will significantly impact the commute of the Orange County residents and businesses in the project corridor. In another example, Geoff and Cynthia (as a subconsultant to the prime engineering consultant) prepared and conducted a community meeting for Orange County Utilities Southern Service Area Transmission Main Project. This project involves the construction of approximately 4,100 feet of 42 -inch diameter pipe and 4,200 feet of 36 -inch diameter pipe, much of which is to be installed along the urban and heavily landscaped Town Center Boulevard in the Hunter's Creek Home Owner's Association area. Most recently, Geoff and Cynthia prepared and conducted two public participation meetings for the City of Orlando's Marks Street Utility Improvements Project. This project involves the replacement of 4,700 feet of the City's gravity sanitary sewer system and OUC's 12 -inch and 20 -inch water main in an urban mixed residential and commercial corridor that is also fronted by Lake Highland Preparatory School. The project will require a series of seven (7) construction phases and associated MOT phases including full roadway detours to complete construction. As a company, BFA developed and implemented a successful community outreach program to the Holden Heights community that resulted in widespread community acceptance of the Holden Heights Community Improvements Project. We have a thorough understanding of the requirements for successful public outreach. 1 -38 _' 1.10 Current and Projected Workloads Over the past four years, BFA has been very fortunate to retain our staffing capacity during these economic times. The table below presents the availability of the key project staff. This availability is expected to increase because several projects are winding down over the next 2 to 4 months. This availability will peak as the notice to proceed is issued for the services required for the Ocoee West Sanitary Transmission Main Project. This will enable us to meet anticipated project requirements for schedule, budgets and quality service. We firmly believe that with the proposed Project Team, we can staff and manage the project through completion and meet all critical project milestones. Name Current Clients Current Workload Availability for Contract Daniel L. Allen, PE Project Director, QA /QC City of Ocoee 40 City of Longwood 5 City of Orlando 10 ToHo Water Authority 5 Orange County 40 Geoff Hennessy, P.E. Project Manager City of Ocoee 65 City of Longwood 5 City of Orlando 15 Orange County 15 Cynthia Malone, P.E. Senior Project Engineer City of Ocoee 55 City of Orlando 10 Orange County 35 Willie E. Thomas, PE Senior Project Engineer City of Ocoee 30 City of Longwood 5 City of Orlando 10 Orange County 25 ToHo Water Authority 15 Miami -Dade County 15 Erin J. Giblin, PE Project Engineer City of Ocoee 40 City of Longwood 20 City of Orlando 5 Orange County 35 William Miller, P.L.S. Senior Surveyor and Mapper City of Ocoee 35 City of Orlando 5 City of Ocoee 5 Orange County 15 GOAA 25 FDOT District 5 5 Other Clients 10 1 -39 �A SECTION 2 FIRM 's OFFICE LOCATION AND OTHER FORMS "'�.� .•/` 2.1 Office Location Prime Consultant — Barnes Ferland and Associates,_ Inc. Total Distance — 12.38 miles Estimated Travel Time — 23 minutes 2.2. Company Information /Signature Sheet Company Information / Signature Sheet is provided on the following page. 2 -1 COMPANY INFORMATION /SIGNATURE SHEET RFQ #1401 FAILURE TO COMPLY WITH THESE RFQ INSTRUCTIONS WILL RESULT IN DISQUALIFICATION OF YOUR QUALIFICATION PACKAGE. PLEASE SIGN BELOW ATTESTING THAT YOU HAVE READ AND UNDERSTAND ALL RFQ INSTRUCTIONS AND THAT YOU UNDERSTAND THAT THE SUCCESSFUL RESPONDENT WILL BE REQUIRED TO ENTER INTO A LEGALLY BINDING CONTRACT WITH THE CITY OF OCOEE. Barnes, Ferland and Associates, Inc. dba: BFA Environmental COMPANY NAME AUTHORIZED SIGNATURE (manual) (407) 896 - 8608 TELEPHONE (INCLUDE AREA CODE) (407) 896 - 1822 FAX (INCLUDE AREA CODE) daflen@bfaenvironmental.com E- MAIL, ADDRESS IF REMITTANCE ADDRESS IS DIFFERENT FROM PURCHASE ORDER ADDRESS, PLEASE INDICATE BELOW: D aniel L, Allen, P.E.. Sr. Vice Pres ident NAME /TITLE (PLEASE PRINT) Same 1230 Hillcrest Street STREET ADDRESS Orlando, FL 32803 CITY STATE ZIP FEDERAL ID # 59- 3237612 Individual Corporation _x_ Partnership Other (Specify) Sworn to and subscribed before me this 9th _day of September 1 2014_. Personally Known x or Produced Identification N/A (Type of Identification) E ruse Notary Public State of Florida Pamela Gibbs Stevens My Commission EE104904 r f� Expiros 09 /1912015 Notary Public - State of Florid County of Orange ,� �7 Signature of No ary Public Pamela Gibbs Stevens Printed, typed or stamped Commissioned name of Notary Public RFQ # 1401 — ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT 14 2 -2 13 J4 2.3 Acknowledgement of Addenda Acknowledgement of Addendum is provided on the following page. or Cacnm ?aeione S. Scott Vaadergrift John Grogan, D istrict I Roeentary wilsnn, Digtrict2 City Mgnngor Ru;ty Johnaon, District ,3 Robert Frank Joel F. Keller, District 4 (_)( -(W flout cia September 3, 2014 ADDENDUM NO: ONE (1) CITY OFOCOEE RFQ #1401 ENGINEERING SERVICES FOR OCOEE WESTSANITARY TRANSMISSION PROJECT This addendurn consists of two 2 pages, and shall modify and become it pmt of the or RFQ documents for Engineering Services for Ocoee West Sanitary ' fransmission Project. Respondents shall acknowledge receipt of this Addendum in the space provided on this Addendum. Failure to do so may subject the Respondent to disqualification. The RFQ due date remains the same. The following Documents have been posted to Demandstar: I, Pre - Submittal Conference Sign -in Shect 8119/14 2. Presentation at Pre - Submittal Conference 8119114 3. filuford Avenue Stormwater and Utility improvements Project Drawings Amendments and /or Clarificatiotrs to the RFQ documents are as follows: Clarification #1 Firm shall he considered "I'IRM/TEAM" when referenced within Request for Qualifications (RFQ) #1401. "FIRM/TEAM" shall include all sub- consultants to support prime Consultants work. Clarification H2 Incidental to and in support with, the City has cause two portions of the project (pre - staged work) to be design and permit and shall, if in the best interest of the City and other mutual parties, cause the construction of those potion of the project beforc/or during the Consultant design efforts. Consultant shall be required to coordinate with City and others all pre- staged work. Clarification 43 As indicated in Table "Evaluation Criterion" Page 12 responders to the RFQ should include it "Project Approach ". Failure to provide a project approach will result in no paints awarded for that category. Amend #I: "C. Scope of Services" Original: The selected Consultant will assist the City by supplying sanilmy sewer transmission design, coordination, permitting, and bidding services needed to support the PROJECT, It is anticipated that both geotechnical and professional land survey services will be needed 'm support of the design of the PROJECT. Consultant will be tasked with preparing a detailed scope and necessary support scrvices, where the City will procure those services utilizing ongoing prufessiuual contracts. Shall be replaced with: "file selected Consultant will assist Ire City by supplying sanitary sewer transmission design, coordination, permitting, and bidding services needed to support the PROJECT w_iuchshttll..uk.!ud_s..411_ne ed Su, b- coftsuldarlt ery lOe o s u port Lh5 C(FOrts 4�1.4_Con,� larZ. City of Ococc • 150 N Lakeshore Drive • Ocoee, Florida 14761 phoce: (407) 905 -3 t00 • rim. (407) 905 -3194 • ,vww occee.mg 2 -3 Amend #2: "1. Firm's Qualifications" Original: • List of all firm's employees, their qualifications, and their rote in providing the desired City services. • Firms and employee's certifications and registration with regulatory agencies, professional organizations, etc. • List firm's sub - consultants, their qualifications, and their role in this project. • List of firm's other current or recently completed similar services within the past two 2 years with other public or private agencies. List and quantity of firm's (and firm's sub - consultants' if applicable) equipment including survey instruments, computers, plotters, vehicles, etc. • List of at least three (3) client references to include organization name, contact person, telephone number (s), and e-mail address. • Project Manager education, experience and any special consideration • Key Project Members education, experience and any special consideration • Firm's Project organization and coordination snveture Shall be replaced with: • List of all firm's employees, their qualifications, and their role in providing the desired City services. • Firm's and employee's certifications and registration with regulatory agencies, professional organizations, etc. • List firm's sub - consultants, their qualifications, and their role in this project. • List of firm's other current or recently completed similar services within the past five (S) years with other public or private agencies. • List and quantity of firm's (and firm's sub - consultants' if applicable) equipment including survey instruments, computers, plotters, vehicles, etc. • List of at least three (3) client references to include organization name, contact person, telephone number (s), and e-mail address. • Project Manager education, experience and any special consideration • Key Project Members education, experience and any special consideration • Firm's Project organization and coordination structure c Tolbert, / CPPB Purchasing Agent cc: Evaluation Committee Title All respondents shall acknowledge)this addendum In your qualification package by completing the section below and including in Section II- Firm's Office Locatitill & Qthej Respondent: Barnes add' ssocia Inc. (dba: BFA Environme Signature: r NIaroe. Daniel L. Allen, P.E. Senior Vice President RFQ 1401— Addendum #I 2 -4 2.4 Minority Certification ,J R j� $.B /Jp _ 9 j Minority, Women & Florida Veteran Business Certification Barnes, Ferland and Associates, Inc. I cartifted under the provisions of 287 and 293.187. Floriia Statutes for a period from: so 06117/2013 06/17/2015 T u A 4 4 �'SO SERVICE 2.4 Summary of Litigation In 2009 and 2010, BFA provided field services, as a subconsultant to Parsons Brinckeroff, during the drilling of the water supply wells at Orange County's Southern Regional Water Supply. The driller for the project was A.C. Schultes of Florida. Near the end of the drilling contract, Orange County awarded the treatment plant construction project to Wharton Smith. Wharton Smith's site subcontractor, Emerald Utilities & Site Development, filed a claim three years later that the water discharged from the well testing performed by A.C. Schultes impacted their project schedule. Four other companies were also named in the claim. Our insurance carrier has filed a motion to dismiss the claim. 2 -S 2.5 Certificate of Insurance A � CERTIFICATE OF LIABILITY INSURANCE BARNFER -01 CDIXON DATE tMmwfyyy) B/19f2014 THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER. IMPORTANT: If the certificate holder Is an ADDITIONAL INSURED, the policy(ies) must be endorsed. if SUBROGATION IS WANED, subject to the terms and conditions of the policy, certain policies may require an endorsement. A statement on this certificate does not confer rights to the certificate holder in lieu of such endorsemen s). PROD410ER Ames & Gou9h CONT _ NAME: ... IAA, N ° }1 ( PHONE 703 -227 F� 703 827 -2 E " ! !` ( ) 8 8300 Greensboro Drive �' • N° - - -- -.. Suite 980 ADDR McLean, VA 22102 INSUREFybI AFFORDING COVERAGE NAIC r INSURERA:Travelers Indemnl Com any 25656 INSURED INSU RERS: Phoenix Insurance Company A +, XV 256 _ INSURER C Travelers Casu and .Surety Company 19038 Barnes Ferland & Associates, Inc. 1230 Hillcrest Street INSURER D: — - - - - -- _ - — Orlando, FL 32803 INSURER E DAMAGE REFTTEn pREN115ES (EN aaxrer,caj IN SU 1111. COVERAGES OFRTIFICATF NUMBER: REVISION NUMBER: THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWTHSTAND(NG ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WNICFI THIS CERTIFICATE MAY BE ISSUED OR MAY PERTAIN. THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHO WN MAY HAVE BEEN REDUCED BY PAID CLAIMS. - -._ aR _ POLICY EPP POLICY EMP �._. _. __...__.._. __..._......._._._.... LT TYPE OF INSURANCE POLICY NUMBER MMIDDrYYYY MM/D NYYY ) LIMN A X COMMERCIAL GENERAL LIABILITY AUTHORIZED REPRESENTATIVE EACH OCCURRENrE 1 � CLAIMS-MAUL t ^__I Gccwf '880.10153222 08!0112014 0810112015 DAMAGE REFTTEn pREN115ES (EN aaxrer,caj . 1,000,00 1 1 , S ,0 00,00 a _ ..... 10, _1 MF FXP IAPY rx w �eraonl .. $ 1,000,00 PERSONAL L ADV INJURY GENERAL AGGREGATE GErrL AGGREGATE LIMIT APPLIES PER $ 2,000,00 X POLK:Yn JF i F LOC /' PRODUCTS - COMPIO S 2,000,00 OTHER AUTOMOBILE LIABILITY CCMNIW EDSXJGLE LAII N wr WwN S 1,000,00 lu>DILY WJLMY w B X ANY AUTO BA 143158666 08101/2014 08ID112015 t BOOILYINJLMYIPer°ec + lerN) AI.I. OWNED S AUTOS _... AUTOS n ITROT'tiN1Y DAMAGE t I 'SCH - OlUtED HIRED AU TOS AUTOS U106 leers r E X IuNaR ELLAU" X OCCUR EACH (K:GURREN(.E 5 _ 4,000 A EXCESS DAB C_IAIM$ - MADE CUP 9E12699A 0810112014 08ID1/2015 AGCaercArc i_ 4,000,00 _ DFD X I RETENTIM _ S 10,000 WORKERS COMPENSATION Or ('ER H STATUTE ER ' ANDEMPLOYERS' LIABILITY N EL. EACH ACCOENT _.. _. s ANY PROPRIEIORWARTNER /EXECU TIVE ( FI. DISEASE FAEMPIOYFFS __. _ ......._._ _ . CFFICERaMEMeER EXCLUDED? t ] (Mandatory In NH) N) A a ye� a DFSCRIPTK)N Or OPERATION$ bw— EL. DISEASE POLICY LIMIT S C fessional 105778556 0810112014 08/01/201 Per Claim 1,000,0 C Fbility 105778556 0610112014 08101/2015 Aggregate 2,000,0 DESCRIPTION OF OPERATIONS/ LOCATIONS /VEHICLES IACORD IOI, Adc UwW R—Ox Sch°OWe, may"SUChO N m°r° spay is raquirMl (0 1966 -2014 ACUKU CUKPUKA I ION. All rlgnts reservau. ACORD 26 (2014101) The ACORD name and logo are registered marks of ACORD 2 -6 /a3 a AM - Y WI SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN BFA Environmental Consultants ACCORDANCE WITH THE POLICY PROVISIONS. 1230 Hllicrest Street Orlando, FL 32803 AUTHORIZED REPRESENTATIVE (0 1966 -2014 ACUKU CUKPUKA I ION. All rlgnts reservau. ACORD 26 (2014101) The ACORD name and logo are registered marks of ACORD 2 -6 /a3 a AM - Y WI A C"RV • DATE (MMMDNYYY( CERTIFICATE OF LIABILITY INSURANCE 08/05114 THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER. IMPORTANT: If the certificate holder Is an ADDITIONAL INSURED, the pollcy(tes) must be endorsed. If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may require an endorsement. A statement on this certificate does not confer rights to the certificate holder In Ileu of such endorsement(s)- PRODUCER NAME: Aw Rlsk Smvices, Inc of Florida AM Risk Smvlcrx, Iro d Fbrida 1001 BricW Bay Drive, Sultw #1100 A/C No Est : 800 - T43 - 8130 AIC N oY. 800 - 522 - 751 4 MI-aml, FL 331314931 EM I ADDRESS: ADP.COI.Conter@Aon.com INSURERISI AFFORDING COVERAGE NAIC 0 INSURER A: Rkwk Wtirnal U.wmnco Co 23817 INSURED INSURER B ADP T"Scurrs MI XXX, I- 1.200 S-1.4 Drove INSURER C Miami, FI. 33173 INSURER D ALTENNATE EMPLOYER Dernes, Fedmd, aM Assxlwtes Inc INSURER E 1130 UPI SA—I INSURER F OrI.M., FL 32803 COVERAGES CERTIFICATE NUMBER: 025739 REVISION NUMBER: IN SURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD i CERTIFICATE HOLDER CANCELLATION SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE Bsrnu, Fedand, and Asaa'Jamw Inc THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN 1230 HW.M Svc 1 ACCORDANCE WITH THE POLICY PROVISIONS. OrPondu, FL 32803 AUTHORIZED REPRESENTATIVE p4oa &i-Sk$e'C&'&es, Qaco oflotida (0 1988 -2010 ACORD CORPORATION. All rights reserved. ACORD 25 (2010105) The ACORD name and logo are registered marks of ACORD 2-7 THIS IS TO CERTIFY THAT THE POLICIES OF INDICATED. NOTWITHSTANDING ANY RFOUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO All THE TERMS, EXCLUSIONS AND CONDI'YKN -!5 OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS. LIMITS SHOWN AREAS REQUESTED. NSA ADDL SUER POLICY NUMBER POLICY EFF POLICY EXP LIMITS LTR TYPE OF INSURANCE INSft WVD MMIDDlYYYY MMlODIYY —... — WA. RENCE. $ GENERAL UABIUTY ENTED COMMERCIAL GENERAL LIABILITY aartenoe 3 CLAIMS-MACE n OCCUR mw rson S ADV INJURY S GREGATE S .- C61dPIOPAGG 3 GEN'L AGGREGATE I IMIT APPLIES PER '. S POLICY nf'ROJECT LOC En ucud,rnl S ._-. AUTOMOBILE LIABILITY BODILY INJURY f`ar arem S ANY AUTO ALL OWNED AUNSCHEDULED OoO1LY INJURY Y Per auldent $ AUTOS - DAMAGE HFRED AUTOS AUT FD OS J fle+wuklwnt 3 3 EACN OCCURRENCE 3 UMBRELLA LIAR OCCUR AGGREGATE 3 EXCE68 LIAe CLAIMS -MADE CFO RETENTIONS -- V."C 9TATLL OTH� WORJfER3 COMPENSATION X IOItY LFMiT3 ER , A AND EMPLOYERS UABILnY YIN WC 694179802 FL 07101114 07701115 ANY pROPRiET[NTrPARTNER/F %FCUTIVF F. 1.. EACH ACC:IUENI S 2,000,000 OFFICER/MEMRF.R FXCI UDE07 ❑ NIA _ _, _2.D00.000 E.L. 67SEAE -EA EMPLOYE S (Mandatory 6 NHl 2,OOD,OW r 1 •.. unuw. ruw E.L. u4SEA`:I; - POLICY LI1.RT DESCRIPTION OF OPERATIONS / LOCATIONS) VEHICLES (Attach ACORD tOt, Addltl � S DESCRIPTION OF OPERATIONS W— E.L. Remarks Bc A�.d ttmore space Is required) 0te atwro stated rc aEOVa rvarrwd ciora B an apci na:u Puy y Al waksie mlpbycrs wurkh,y Wr the above named dim( cvnpwny, pakf under ADP TOTAt.30URCE. INC's ma, are arrwrr«I under .The emphrywr under Ines pnery. , yip t AN N 4 i ia• } �. . :a Pegasus September 9, 2014 City of Ocoee Finance Department/ Purchasing Attn: Ms. Joyce Tolbert 150 North Lakeshore Drive Ocoee, Florida 34761 Re: Cover Letter - Engineering Services for Ocoee West Sanitary Transmission Project RFQ #1401 Dear Ms. Tolbert: Our Pegasus -CPH Engineering Team appreciates this opportunity to submit our Team's qualifications to provide the City of Ocoee with engineering services for this project. Pegasus will serve as Prime Consultant on this contract and will be responsible for overall contract and project management, and will lead our Design Team "1 ". CPH will serve as our primary subconsultant and lead our Design Team "2 ". CPH will also provide High Definition Laser Right -of -Way Scanning where necessary to assist with pipeline alignment decisions. Pegasus Engineering, LLC is a public infrastructure engineering firm with extensive successful experience by our firm's personnel in all phases of planning, design, permitting, bidding, and construction administration of utility pipeline, roadway, drainage, and projects for Florida cities, and counties. Pegasus is an MBE - certified firm by Orange County and the State of Florida. Pegasus is thoroughly experienced in addressing all types of utility design and coordination issues along both urban and rural roadways. Pegasus notes with pride that our 11 Florida- registered Professional Engineers have a total combined experience of over 235 years. Pegasus senior engineering staff have a proven record of providing successful engineering services to numerous governmental entities including the Cities of Altamonte Springs, Clearwater, DeBary, Daytona Beach, Deltona, Delray Beach, Edgewater, Lakeland, Lake City, Longwood, Mount Dora, New Smyrna Beach, Ocoee, Orange City, Orlando, Ormond Beach, Plant City, Pierson, St. Petersburg, Titusville, Winter Garden, Winter Haven, Winter Springs, Windermere, and Winter Park and the Counties of Citrus, Polk, Pasco, Brevard, Flagler, Indian River, Lake, Marion, Orange, Osceola, Santa Rosa, Seminole, and Volusia. Our Principal -in- Charge / Project Manager, Fursan Munjed, P.E., has directed over 100 successful public infrastructure projects, including roadway, drainage, and public utility pipeline projects. Mr. Munjed has extensive experience in Ocoee, including having recently served as Project Manager on Ocoee's Southwest Development Utilities Project. His other experience in Ocoee includes: the Maguire Road Widening (Segments 1 and 2) including the bridge over the Florida Turnpike, Professional Parkway / Old Winter Garden Rd. Widening, Maine St. Alignment Study, White Rd. Improvements, 7 th Ave. Improvements, Maguire Rd. / S.R. 50 Intersection Improvements, Maguire Rd. / Moore Rd. / Roberson Rd. Intersection Improvements, and the Bluford Ave. / Orlando Ave. Intersection Improvement project. RFQ #1401 - Engineering Services for Ocoee West Sanitary Transmission Project September 9, 2014 Pegasus and CPH have successfully teamed together on previous governmental contracts, including on -going projects under a current continuing contract with the City of Orlando where CPH is the prime consultant and Pegasus is a subconsultant. CPH also has extensive experience in Ocoee, having recently designed the City's utility improvements associated with the on -going S.R. 50 Widening Project. CPH has designed and permitted over 300 miles of pipeline projects with pipes ranging in size up to 54 inches diameter. CPH has extensive experience in pipeline construction techniques, including directional drilling and Jack and Bore. CPH has successfully permitted hundreds of pipeline projects throughout the State of Florida. Pegasus' Beth Whikehart, P.E. will serve as Leader of our Design Team 1. Beth recently served on the same capacity on the above referenced Ocoee Southwest Development Utilities Project. David Mahler, P.E. of CPH has significant experience in Ocoee and will serve as Leader of our Design Team 2. Resumes for Ms. Whikehart and Mr. Mahler and our other key Team members are included in Section 5 Team Resumes. Pegasus' record in consulting engineering in achieving long -term "collegial" relationships with governmental staff, subconsultants, and permitting agencies and our unsurpassed "error and omissions claims performance attests to our success in achieving the objectives of our governmental clients. Our emphasis on the ability to efficiently design projects, coordinate subconsultants, estimate costs, provide effective QA /QC reviews, and obtain required permits from multiple regulatory agencies, has ensured that Pegasus' projects have consistently met budgets and schedules. This can be attributed to our highly experienced engineering staff our emphasis on partnering with subconsultant Team members, well established QA /QC procedures, and our emphasis on an on -going responsive relationship with client staff members. Our Pegasus -CPH Team appreciates this opportunity to submit our interest and qualifications to serve the City on this project, and we guarantee the City will be pleased with our Team's provision of timely, cost - effective, and highly ethical services. Sincerely, THE PEGASUS -CPH TEAM Fursan Munjed, P.E. Principal -in- Charge / Project Manager WWI x c�c o TABLE OF CONTENTS Tabs Cover Letter Table of Contents 1 - The Pegasus -CPH Team 2 - Understanding and Approach 3 - Projected Workloads 4 - Licenses, etc. 5 - Team Resumes 6 - Similar Projects 7 - Equipment List 8 - References 9 - Office Locations & Forms Table of Contents PegaSUS RFQ #1401 — ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT RFQ #1401 Engineering Services for Ocoee West Sanitary Transmission Project The Pegasus-CPH Team vWx 1. THE PEGASUS -CPH TEAM A. Introduction to Pegasus -CPH Team Pegasus Engineering, LLC is an MBE - certified public infrastructure engineering firm with extensive successful experience by our firm's personnel in all phases of planning, design, permitting, bidding, and construction administration of utility pipeline, drainage, and roadway projects for Florida cities and counties. Pegasus senior personnel have extensive experience in completing infrastructure design services for the City of Ocoee, including the recent Southwest Development Utilities Project. For this contract, Pegasus has teamed with highly respected CPH, Inc. based on the unique qualifications of our two firms, our mutual project experience for the City, and our well - established record of our two firms working closely together as a team on public infrastructure projects for local government. Pegasus will serve as Prime Consultant on this contract and will be responsible for overall contract and project management, and will lead our Design Team "1 ". CPH will serve as our primary subconsultant and lead our Design Team "2 ". CPH will also provide High Definition Laser Right -of -Way Scanning where necessary to assist with pipeline alignment decisions. B. TEAM MEMBERS Listed below are our Team members who will provide project management, engineering, design, surveying, SUE, geotechnical and contamination services, and related services for our Team's design of the Ocoee West Sanitary Transmission Project: 1. Assignment /Title Name Years Experience Pegasus Engineering, LLC Principal -in- Charge /Sr. Project Manager Fursan Munjed, P.E. 22 years Design Team "1" Leader Beth Whikehart, P.E. 12 years Construction Plans Keith Johnson, P.E. 12 years Sean Beck, Sr. Designer 13 years Maintenance of Traffic (MOT) Plans Juan Fong, P.E. 21 years 2. Primary Subconsultant CPH, Inc. Design Team "2" Leader David Mahler, P.E. 24 years Construction Plans Jay Morris, P.E. 14 years Construction Plans Mason Gardberg, E.I. 2 years High Definition Laser Right -of -Way Scanning Thomas Galloway, PSM 24 years Tab 1 1 Pagel Pegasus RFQ 41401 — ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT (W(WO 1. THE PEGASUS -CPH TEAM 3. Other Subconsultants Southeastern Surveying and Mapping Corp. Surveying Gary Krick, PSM 41 years Utility Location Services (SUE) Darryll DeMarsh, GPRT 21 years PSI, Inc. Geotechnical Robert Trompke, P.E. 19 years Contamination Lydia Wing, BS 20 years C. ORGANIZATION CHART An Organization Chart for our Pegasus -CPH Team is included in this section. Resumes for our key Team members are included in Section 5. Our Team's project understanding and approach are addressed in Section 2, with our Team member availability addressed in Section 3, resumes are included in Section 5, recent similar projects are included in Section 6, and the requested references are included for Pegasus and CPH in Section 8. Pe Tab 1 1 Page 2 ga5u5 RFQ #1401 - ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT Organization Chart Permitting Entities FDEP, Orange County, FDOT, Florida Central Railroad QA / QC Constructability Reviews (Individuals to be assigned) Beth Whikehart, RE Keith Johnson, P.E. Sean Beck, Sr. Designer Surveying & Utility Location Services Southeastern Surveying and Mapping Corp. Gary Krick, PSM Darryll DeMarsh, GPRT (SUE) Juan Fong, RE Permitting Coordination David Mahler, P.E. Permitting Coordination Jay Morris, P.E. Mason Gardberg, E.I. RFQ #1401 ��� M Engineering Services for Ocoee West Sanitary Transmission Project 40 W/ ()(()F'(? 2. UNDERSTANDING AND APPROACH 2. UNDERSTANDING AND APPROACH Our Team's project understanding and approach have been developed based on our review of the following: • City of Ocoee's Request for Qualifications (RFQ) #1401; • Information provided by City staff at the City's pre - submittal conference on August 19, 2014, including the handout materials; • Ocoee West Wastewater Utility Plan by Reiss Engineering, dated August 2008; • Draft Technical Memorandum of Western Force Main Route Extension (Revision #2) by Reiss Engineering, dated June 2011; • Final conceptual Downtown Ocoee Sewer Plan — Analytical Results (Technical Memorandum) by Reiss Engineering, dated March 2014; • City of Ocoee CIP — 5 -Year Plan, Fiscal Years 2015 -2019; • Bluford Avenue Stormwater and Utility Improvements Project Construction Plans, dated July 2013; • Bluford Avenue Stormwater and Utility Improvements Project Permit Submittal, dated March 2013; • Bluford Avenue Pollutant Removal Structure 100% Plans by PEC, dated January 2006; and • Preliminary route site visit. We understand that the City's proposed project includes the design, coordination, permitting, and bidding services for construction of the Ocoee West Sanitary Transmission Project. This project is primarily intended to provide additional capacity and redundancy to the existing eastern backbone force main system while relieving the currently overloaded systems in the City's southerly sanitary sewer service area and along S.R. 50. Wastewater flows in that area are currently routed easterly along S.R. 50 and then northerly along Clarke Road to the City's Wastewater Treatment Facility (WWTF). The City's proposed force main alignment along Bluford Avenue will also provide convenient force main connection availability for the proposed Downtown Ocoee sewer collection system. That proposed collection system is intended to create opportunities for additional commercial development in Ocoee's downtown area, while reducing nutrient loadings in groundwater from existing septic tank / drainfields in the FDEP designated Wekiva Basin. We understand that the City's proposed force main alignment includes approximately 4 miles of 12 -inch, 16 -inch and 20 -inch diameter force main. Figure 1 provides a schematic alignment for this proposed force main system. We also understand that a Master lift station will be designed for the City by others at a site near the northeast corner of the Lakewood Avenue / Security Circle intersection. While our Team has not had an opportunity to review the hydraulic modeling performed by the City's wastewater transmission system consultant (Reiss), we assume the proposed Master lift station is intended to serve primarily as a "re- pump" facility due to future system hydraulic considerations. Our Team will coordinate closely with City staff and the City's lift station design consultant to establish the interface piping and valve configuration between the Lakewood Avenue force main and the proposed Master lift station. This coordination will also address selection of the desired PVC pipe class, and positioning of air release valves at appropriate locations. Tab 2 1 Page 1 Pegasus RFQ #1401 - ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT 0 m, �f./ 2. UNDERSTANDING AND APPROACH A segment of the proposed 12 -inch force main along Maguire Road and across S.R. 50 was recently designed by CPH and is being constructed as part of FDOT's on -going S.R. 50 widening improvements. Our Team is prepared to design the necessary remaining short sections of 12 -inch pipe that will provide for connection to the existing force main piping north and south of S.R. 50. This will provide for the desired routing of wastewater flow in a northerly direction along Maguire Road, as the flow direction in the existing Maguire Road force main will be reversed when the Ocoee West Transmission System is completed and placed in operation. The proposed alignment for the 16 -inch section of the proposed force main system commences at the intersection of Maguire Road and West Columbus Street, and is proposed to extend east along Columbus Street. The City's construction plans for the above referenced Bluford Avenue Stormwater and Utility Improvements extend from Columbus to just north of Delaware Street. The City's plans indicate that the 16 -inch force main is proposed to be constructed along the south side of Columbus, and the force main along Bluford is proposed to be located on the east side of the road through the downtown area north to Franklin Street. A 2,250 foot long section of east -west 12 -inch force main is proposed to be installed along Lee Street and Franklin Street, with a connection to the proposed Bluford Avenue force main at the Bluford / Franklin intersection. A railroad crossing will be required prior to construction of this east -west 12 -inch force main section. A pipe crossing contract must be coordinated with the Florida Central Railroad Company (a part of the Pinsly Railroad Company) which is initiated with an application submittal. Pegasus recently coordinated a railroad crossing with the Florida Central Railroad during Pegasus' design of the Plant Street Widening Improvements for the City of Winter Garden. At the Bluford / Franklin intersection, the force main will be increased to a 20 -inch diameter. A culvert crossing will be required just north of Franklin. The 20 -inch force main will extend north along Bluford across Silver Star Road where an FDOT Right -of -Way Utility Permit will be required. At the Bluford / Rewis junction, the 20 -inch force main will require a railroad crossing, with a pipe crossing contract to be coordinated with the Florida Central Railroad. The force main is then aligned along Rewis to Lakewood, and thence north along Lakewood to the proposed Master lift station site located at the City's designated site north of Security Circle. The 20 -inch force main will then extend north along Lakewood through approximately 2,500 feet of Orange County right -of -way to the Wurst Road intersection. Other design considerations include a petroleum groundwater plume that has been identified at the Lakewood (Clarcona -Ocoee Road) / Wurst Road intersection where the former Circle K #7046 facility was located. This issue will be addressed during our preliminary and final design phases. The 20 -inch force main will then continue east along Wurst Road in 1,325 feet of unincorporated Orange County right -of -way to Peters Avenue, thence continuing within the City limits to the junction with A.D. Mims Road, and thence east along A.D. Mims Road to a connection with the influent system to the City's WWTF. A railroad pipe crossing contract will be required with the Florida Central Railroad at the Wurst Road / A.D. Mims Road junction. We understand the City has already commenced the process with the railroad to obtain this pipe crossing contract. Tab 2 1 Page 2 Pegasus RFQ #1401 - ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT 'J 2. UNDERSTANDING AND APPROACH Force Main Design Approach Our Pegasus -CPH Team proposes that this force main design project be accomplished by utilizing two design teams, as shown in our Organization Chart in Section 1. The Lakewood Master lift station is a logical location for dividing the design work between our two design teams. Our Team is flexible and is prepared to adapt to any segment assignment and /or accelerated design schedule preferred by the City. The Team we have assembled has individually provided engineering services to the City and both firms are familiar with City standards and specifications. Our familiarity and successful working relationship with the City is an added benefit our Team brings to the City. Our Team understands the sensitive location of the force main along main City streets. Our well established design approach will also focus on developing an alignment that will cause the least disturbance for the City and its residents. As part of the final alignment along each roadway segment, our Team will strive for the least amount of disturbance to driveways, historic trees, and general impacts during construction. Both Pegasus and CPH have multiple project experience in historic areas, along with the expertise to limit construction impacts by designing specialty trenchless pipeline installations where appropriate. Our Team will develop the optimum final alignment for this pipeline system. We also have successful expertise with public relations, as both firms have held town hall type meetings for review of potential impacts by concerned citizens. Both of our Pegasus and CPH Team have successfully provided similar force main design services as those required for this project. Following is a listing of design project activities that our Team proposes to utilize in developing a detailed scope of services for initial review with City staff. While the format below is based on a 30 %, 60 %, and 100% final plans submittal sequence, project schedules can be significantly accelerated to meet the City's required completion dates. Scope Preparation & Existing Conditions Review • Meet with City Staff to develop detailed understanding of City's objectives including City's other planned projects that are to be coordinated with this force main design and construction, Schedule Requirements, Brainstorming, & any other Pertinent Information • Identify all Critical Project Issues, including driving the route with City staff to insure any special concerns are noted to be addressed during design • Utilize Sunshine State One -Call for all Existing Utilities in Project Area • Determine Survey, Geotechnical & Environmental Analysis Investigation Limits • Obtain all Available ISIS and available As -built Information • Develop Preliminary Project Schedule for review with City Staff • Complete Scope & Fee Negotiations • Receive City's Notice -to- Proceed Preliminary Engineering & 30% Plans Phase • Design Survey • Confirm Existing Right -of -Way Limits • Complete Geotechnical Investigation • Existing Utility Locations • Prepare a Design Memorandum with Preliminary Alignment Plan for City's Review and Approval • Develop 30% Plans for City Review Tab 2 1 Page 3 Pe989UB RFQ #1401 - ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT 2. UNDERSTA A ND AP PROACH 60% Construction Plans • Complete Plan Profile Sheets • Maintenance of Traffic Plans • Preliminary Quantities Estimate • Preliminary Cost Estimate • Assemble Project Manual Including City's Front End Documents and Technical Specifications • City Review of 60% Plans Submittal • Prepare & Submit Permit Applications 100% Construction Plans • Prepare Final Construction Plans & Quantities • Finalize Technical Specifications • Complete Internal QA /QC Process & Constructability Review • Value Engineering Review for Potential Cost Savings Permitting • Schedule Early Meetings with all permitting agencies, as well as with Florida Central Railroad for specific pipe crossing contract design criteria requirements and required application information • Prepare & Submit Permit Applications Utility Coordination • Identify & Coordinate with All Utilities Along Corridor • Utilize SUE Information with Horizontal / Vertical Locates • Submit Construction Plans to affected utility companies • Address Potential Conflicts • Finalize Utility Coordination Plans Cost Estimate • Develop Final Cost Estimate for Submittal with 100% Plans based on Latest Unit Price Data Bidding Phase Assistance • Prepare Bid Forms • Attend City's Pre -bid Meeting if Authorized • Assist with Analysis of Bids if Authorized • Conform Contract Documents After receipt of the City's Notice -to- Proceed, a "Kick -off Meeting" will be held with our designated Team members to set task responsibilities, establish schedules, and milestones, and review reporting assignments. All telephone conversations and meetings that include or affect a project decision will be documented. Minutes of meetings will be prepared and distributed to attendees promptly for confirmation of decisions made, with the meeting minutes then filed after appropriate correction. Tab 2 1 Page 4 Pe9a5u5 RFQ #1401 - ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT 1 2. U NDERSTANDING AND APPROACH 0(_0P(? QA /QC Technical Reviews Pegasus and CPH have agreed that each firm will review the other firm's work products, including construction drawings, quantity estimates, and draft bid forms prior to submittal to the City. The reviewing individual will sign and date the documents and prepare a record of review. Review comments will be resolved by the originator of the work product and checked again until corrected. Our Project Manager will insure that an inventory of all comments received during the course of the project is maintained. Our Team's subconsultants for surveying, SUE, geotechnical, and contamination services will be required to provide documentation that their work products have similarly been QA /QC reviewed prior to submittal. Combining Projects It may prove timely and cost effective for the City to incorporate additional improvements into this force main project. Additional utility improvements could include design of Downtown gravity sanitary sewers (along Bluford Avenue, etc.), system connection points for future Downtown development, and any desired water main replacements due to deteriorated pipe conditions or asbestos - cement pipe material. In addition to additional utility improvements, it is noted that roadway and /or stormwater improvements could be combined with this force main project at the City's direction to provide future project cost avoidance. Our Pegasus -CPH Team also has an extensive knowledge of the City's roadway design criteria and stormwater basin characteristics through our previous engineering efforts within the City. Furthermore, Pegasus' recent completion of the Ocoee Southwest Development Utility Improvements Project is a good example of our completion of a utility project in a timely manner and working closely with City staff for successful project design phase completion. Special Construction Considerations Construction of large utility pipelines through highly urban areas can often present unique challenges. Our Pegasus -CPH Team has a great deal of experience in addressing and designing pipelines in challenging urban settings. We have experience with various trenchless technologies, such as Directional Drilling and Jack & Boring, that could prove useful in different areas of the project. For example, Jack and Bore installation at a railroad crossing is typically preferred since the casing would provide easy access for future maintenance purposes. Environmentally sensitive areas or roadway crossings in congested areas may require utilization of directional drilling. Pipe Bursting may be appropriate if any existing asbestos - cement water mains were to be encountered along the route of the proposed force main. Methods and Controls to be Utilized to Balance and Maintain Quality, Schedule, and Budget One key item of concern for the City is a firm's ability to meet time and budget requirements. Our Team has reviewed the scope of services requested for this project and has developed a solid plan for staffing this project. Both Pegasus and CPH and our subconsultants have the personnel and resources immediately available to carry the Ocoee West Sanitary Transmission Project to successful completion. Our key Team individuals have the time available to complete this project and are ready to get started. The key benefit to our Team is that the same personnel that start the project will be the same ones who will see the project Tab 2 1 Page 5 Pe,gmm_ RFQ #1401 - ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT �J sac <> through completion. Given our firm's size and location, the City will benefit with the same engineers and professionalism both firms have each provided to the City on previous projects. In summary, we trust our Team has demonstrated why we are uniquely qualified to provide these design services for Ocoee. Our Team members are located a short distance from the City with offices that includes engineers, designers, surveyors, environmental scientists and administrative personnel. Both Pegasus and CPH are currently completing design services for other clients, but are actively seeking work. As a result, our Team is available and has the capacity to perform new projects. We are committed to meeting all budget and schedule requirements. Pegasus and CPH are each proud of the reputation they have earned for cost effective, quality- engineering services through a philosophy of strong project management. Tab 2 1 Page 6 JPeagli RFQ #1401 — ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT RFQ #1401 Engineering Services for Ocoee West Sanitary Transmission Project 44whN 3. PROJECTED WORKLOADS 3. PROJECTED WORKLOADS / AVAILABILITY Based on the currently committed and projected workloads of our Pegasus -CPH Team's key personnel, following is a listing of the projected availability of each key Team member. We assure the City that our Team has more than adequate personnel resources to complete this project within the City's desired schedule. Furthermore, our Project Manager, Fursan Munjed, P.E., is a Principal of Pegasus and has the authority to make additional resources available should the need arise. A. Pegasus Engineering, LLC Fursan Munjed, P.E. Beth Whikehart, P.E. Keith Johnson, P.E. Sean Beck, Sr. Designer Juan Fong, P.E. B. CPH, Inc. David Mahler, P.E. Jay Morris, P.E. Mason Gardberg, E.I. Tom Galloway, PSM C. Other Subconsultants Availability 25% 55% 35% 40% 20% 30% 50% 60% 30% Both Southeastern Surveying & Mapping Corp. and PSI, Inc. have assured our Pegasus -CPH Team senior management that both firms have more than adequate resources to complete any requested services for this project on a timely basis within designated schedules. Tab 3 1 Pagel JPegaSUS RFQ #1401 — ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT RFQ #1401 N O to Engineering Services for Ocoee West Sanitary Transmission Project Licenses, etc. t �-. for O c >(?P 4. LICENSES Pegasus Engineering State of Florida Board of Professional En Aae t,1., Pegasus E LLC i —h-,,d under the prwioo f5 6i'41 Flv -ida Soarur orfcr rngloeerTg rrndwt n,6c publxth —gh a N4- Fnginecr, duly hurred vM, Cl.,— 11, lk S kp b -� I` x 4rtif are aFAwhoe'rotos Cs i,�tia Ni ��ry 1•turu i State of Florida Board of Professionol Engineers an r tho Beth K. IN kehart, P.E. Is licensed as a Professional Engineer under Chapter 471, Florida Stotutes I ,-- azaz2cu Pr o; s„ e,a : n.,: :-Nz 5a5> +s 6"" State of Florida Boord of Professionol Engineers Ana , tl- Keith Andrew Johnson, P.E. Is licensed as a Professionol Engineer under Chapter 471, (lorida Statutes rrpirmi,m. 2i520' -5 PE.'..v Wr Audis N,,: 2.620t53E1G) 6Ys.3 CPH State of Florida Boord of Professionol Engineers Attest. that CPH Inc. V i i ovthorucd under the pr— - ianr d Seutvn 7 1.023, Fbrida Srurusn. to oflc, rnbine«ing wrvico v the publ'K through o Noreai.-I Fnir er, duly Icmud w& Chapter 4'% dared. Statute.. rp t'I^n 27X_01�IK <Y< CertirKOfC Or Auth.,i —in J.IS ktv o r VourL of Prefissional 1z:ginrrrs James R. Mogis Jr., P.E. is ucenaen es r, Qworessrorvaa cacneen crroea c nv rtn an. r.ovo.. s *. n, res Exria� non. 2125f20t3 t• = I.�c Nc� .S!IDIT No 225201312155 623" State of Florida Boord of Professionol Engineers Fursan S. Munjed, P.E. Is licensed as a Professional Engineer under Chopter 471, } lorlda Statutes avd., v��� ns.xns?rca s�.1an State of Florida &xird of Professionol Engineers Juan Fong Jr., P.E. Is --d as o I'r, ly s r,nal Cnginrer undo " p— ..? L r -do Scorntu State of Florida Board of Professionol Engineers David Elton Mahler, P.E. d e Is licensed as a Profess anal Engineer unctr Chopter 471, Florida Statutes E ^.� PC, Tab 4 1 Pagel PegaSUS RFQ #1401 — ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT N 4. LICENSES Southeastern Surveying and Mapping Corp. PS/ State of Florida Board of Professional Engineers A--h., Professional Service Industries, Inc 4 'h,, P—�, f S:6 son T1.ids S—,.- fifer .-i- the P.blk through , flami—I Elgi­d,[, I -&, (].par 471, F6,i& S-111 E. Audi, ,z: 2 2 2 0 1' G I.. ? 2'001 ao&— or A.,h.ri-i- ilk, State of Florida Board of Professional Engineers A,,—,0- Robert Allan Trompke, P.E. 'A 1 11 Is licensed as a Professional Fri under Chapter 471, Horido Statutes - Tab 4 1 Page 2 Pe RFQ #1401 — ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT l , , Engineering Services for Ocoee West Sanitary Transmission Project i i pegasum ENGINEERING YRS OF EXP 22 PROFESSIONAL REGISTRATION Professional Engineer 1997 Florida, No. 51446 EDUCATION B.S. Civil Engineering 1990 University of Central Florida Graduate Work in: Transportation Systems Engineering' University of Central Florida PROF. AFFILIATIONS Institute of Tianspc rtation Engineers �} � Amerz n Socx ty opHi�hway Engirt s,ASH)�) ,, � are � �Prci atzx, r Fursan Munjed, P.E. Principal -in- Charge / Sr. Project Manager Mr. Munjed has over 22 years of public infrastructure engineering experience with primary emphasis on the design of transportation related systems. His responsibilities have included the project management, planning and design of minor and major roadways across Florida, including drainage and utility improvements. His assignments include the preparation of preliminary and final construction plans, technical reports, permit applications, bidding documents, construction administration services, right -of -way negotiations and testifying at order- of-take hearings. Mr. Munjed has served as the I?.ngineer -of- Record on numerous projects and has extensive experience in the preparation of roadway plans, signing and pavement marking plans, signalization plans, temporary traffic control plans, traffic operation reports, safety analysis, and pavement design reports. Mr. Munjed is proficient with related computer software packages including Microstation, Geopak, Highway Capacity Software, Synchro, Guide Sign Program, and FDOT Level- of-Service Software. Southwest Development Utility Improvements, Phases I & II — served as Sr. Project Manager for design of 7,200 feet of water mains and 6,900 feet of force mains. Maguire Rd Preliminary Engineering, Final Design & Construction Phase Services - prepared final construction documents to widen an existing 2 -mile, 2 -lane road to 4 -lane divided urban arterial section with enclosed drainage system, and a bridge over the Florida Turnpike. The project included roadway, enclosed drainage, signing and pavement markings, signals, structural plans, and maintenance of traffic plans. Old Winter Garden Road and Professional Parkway Preliminary Engineering, Final Design and Construction Phase Services - Conducted preliminary engineering analysis and prepared final construction documents to widen an existing 2 -mile, 2 -lane road to 4 -lane divided urban arterial section with enclosed drainage system. The project included roadway, enclosed drainage, signing and pavement markings, signals, and traffic phasing plans. Orlando Avenue and Bluford Avenue Intersection Improvements - prepared final construction plans for the intersection improvements including roadway plans, signing and pavement marking plans, signalization plans and drainage plans. CITY OF WINTER GARDEN Daniels Road Final Design &Construction Phase Services - prepared final construction documents to widen an existing 2 -lane road to 4 -lane urban arterial section with enclosed drainage system, and a bridge over the Florida Turnpike. The project included roadway, enclosed drainage, signing and pavement markings, signals, structural plans, and maintenance of traffic plans. Roper Rd Final Design & Construction Phase Services - prepared final construction plan to reconstruct Roper Road as a two - lane roadway. The project included roadway plans, drainage plans, signing and pavement marking plans, utility adjustment plans, and utility relocation plans. FURSANMUNJED, P.E. Page 2 9 1h St, Story Rd, and Plant St Alignment Studies - prepared alignment studies for the widening of these roadways from a two -lane section to a four -lane urban typical section in order to determine future right -of -way needs, cost, and stormwater treatment and attenuation requirements. Division St Roadway, Drainage & Utility Improvement Project - prepared final construction plans for the reconstruction of Division St as a two -lane roadway including stormwater and utility improvements. ORANGE COUNTY, FLORIDA Forsyth Rd Preliminary Engineering Study & Widening Design - completed traffic planning and design tasks for 2.8 miles of a 2 -1ane road being widened. Continuing Studies Contract - conducted and managed roadway alignment studies, bridge studies, and traffic studies including Taylor Road Study, Reams Road Alignment Study, Parks and Recreation Bridge Evaluation Study, Intersection Analysis and Signal Warrant Analysis Studies, and Oakridge Road and Pine Hills Road Pedestrian Crossing Safety Evaluation. International Dr Resort Area Directional Signage & Parking Management - Design Build Project. Prepared construction and communication plans for the directional signing project which included 17 Dynamic Message Signs and over 100 static guide signs along I- Drive, SR528, Universal Boulevard in the vicinity of the Orange County Convention Center. The project included signing plans, maintenance of traffic plans, structural plans, communication plans, and power service connection plans. The project also included post design services, shop drawing review and preparation of as -built drawings. OSCEOLA COUNTY, FLORIDA Pleasant Hill Road / Reedy Creek Bridge Widening - completed traffic study and design for 0.9 mile segment of road being designed for widening to 6- lanes. SEMINOLE COUNTY, FLORIDA Continuing Contract for Minor Roadways Projects. Preliminary engineering, traffic studies, final design and permitting for minor roadways and designed over 50 intersection improvement projects. Red Bug Lake Road - Final design and permitting for the widening of 2.25 miles to a six -lane roadway. The project included roadway, drainage, signing and pavement marking, signalization, and utility coordination. Seminole Towne Center Infrastructure Improvements - The improvements included modification to the interchange of State Road 46 and Interstate 4, widening of State Road 46, the design of Towne Center Boulevard and St. Johns Parkway. The project included roadway, drainage, signing and pavement marking, signalization, signal communication, maintenance of traffic, and utility coordination. Oviedo Marketplace Infrastructure Improvements - The improvements included the design of Oviedo Market Place Boulevard including the bridge over State Road 417 and Bear Gully Canal, widening of State Road 426, intersection improvements at SR426 and Red Bug Lake Road, and intersection improvements at SR434 and Mitchell Hammock Road. The project included roadway, drainage, signing and pavement marking, signalization, signal communication, maintenance of traffic, and utility coordination. Red Bug Lake Road and Tuskawilla Road Intersection Improvements. Final design and permitting for the intersection improvements to include lane additions, extension of queue or storage length, replacement of the traffic signal with a decorative mast arm structure, and the addition of decorative crosswalks. County Road 46A Final Design and Permitting. Preliminary engineering study and final design and permitting for the widening of 1.8 miles of a 2 -lane rural section to a 4 -lane divided urban typical section. The project included roadway, drainage, signing and pavement marking, signalization, signal interconnect/ communication, and utility coordination. Chapman Road Final Design. final design and permitting for the widening of 1.6 miles of a two -lane section to a four -lane divided urban typical section. The project included roadway, drainage, signing and pavement marking, signalization, signal interconnect /communication, and utility coordination. Pegasus ENGINEERING Beth Whikehart, P.E. Design Team Leader Ms. Whikehart has 12 years of experience focused primarily on utility pipeline design and stormwater engineering including the planning, design, and permitting of multiple utility pipeline projects. Her pipeline design experience includes development of plans and specifications for gravity sanitary sewers, force mains, water mains, and reclaimed water mains. She also has experience with trenchless designs including horizontal directional drilling and slip - lining. Her post design experience includes review of shop drawings, RFIs, and change orders. Sr. Engineer, Southwest Development Utility Improvements Phases I & II, ar Ocoee, Florida, 2013 to present. Ms, Whikehart has served as the Sr. Engineer responsible for preparation of the final construction plans and permitting services for Phases I and II of the Southwest Development Utility Improvements Project. hid �� The project consists of locating a new water main and force main along Roberson �� �` r' �� and Windermere Road to provide water and wastewater services for future development. The Phase I utility improvements consist of approximately 3,400 feet of 8 -inch ductile iron pipe (DIP) water main and 3,100 feet of 4 -inch PVC force main installation. The Phase II utility improvements consist of approximately 3,800 feet of 8 -inch ductile iron pipe (DIP) water main and 2,500 feet of 6 -inch PVC force main installation. The project also includes 340 feet of directional drill pipe installation. Sr. Engineer, Avalon Road (County Road 545) & Tilden Road Intersection Improvements, Winter Garden, Florida, 2013 to present. Ms. Whikehart is responsible for preparation of final utility plans for the widening of the Avalon Road/ Tilden Road intersection. The limits of the project are approximately 3,100 feet along Avalon Road from East Davenport Road to Long Beam Way. The utility improvements consist of relocating the existing 24 -inch reclaimed water transmission line in order to prevent conflicts with proposed roadway and drainage improvements. Since the original service area for the reuse main has been reduced, the existing 24 -inch pipe is being relocated and replaced with 16 -inch PVC pipe. Sr. Engineer, Central Beach Water Main Improvements Project, Utilities Commission City of New Smyrna Beach, Florida, 2013 to present. Ms. Whikehart has recently served as the Sr. Engineer responsible for preparation of design plans, specifications, and cost estimate. The Central Beach Water Main Improvements consist of upgrading approximately 10,000 linear feet of water mains with 6 -inch PVC (polyvinyl chloride) water mains, including service replacement and appurtenances. Ms. Whikehart was also responsible for the preparation of four (4) Volusia County Health Department (VCHD) General Permits for Water Main construction required for the 4 separate sections of water main. In an effort to minimize disruption to residents, the project was designed in conjunction with the City of New Smyrna Beach's Phase III Flood Mitigation improvements. The utility improvements were designed on a fast -track schedule to catch -up with the City's stormwater project (which was at 90% when the utility design commenced). Sr. Engineer, Central Beach Sanitary Sewer Replacement & Rehabilitation & Force Main Interceptor Project, Utilities Commission City of New Smyrna Beach, Florida, 2013 to present. Ms. Whikehart has recently served as the Sr. Engineer responsible for preparation of design plans, specifications, and cost estimate. The Gravity Sanitary Sewer Replacement & Rehabilitation improvements consist of replacing approximately 8,500 linear feet of VCP (vitrified clay pipe) with PVC (polyvinyl chloride), including lateral replacement and installation of 40 new manholes; and reconditioning approximately 12,000 linear feet of VCP using the trenchless cured -in place pipe (CIPP) method. The Force Main Interceptor improvements consist of constructing approximately 3,000 linear feet of 12 -inch force main. In an effort to "Engineering a Higher Standard" 301 West State Road 434, Suite 3 Winter Springs, FL 32708 0407 - 992 -916o 0 Fax 4 30 www.pegasusengineering.net Beth Whikehart, P.E. Page 2 minimize disruption to residents, the project was designed in conjunction with the City of New Smyrna Beach's flood mitigation improvements. The utility improvements were designed on a fast -track schedule to catch -up with the City's stormwater project which was at 90% when the utility design work commenced. Sr. Engineer, Plant Street Segment II Project, Winter Garden, Florida, 2012 to 2014. Ms, Whikehart served as the Sr. Engineer for the Plant Street Segment II Roadway Improvements Project for the City of Winter Garden. Engineering design responsibilities included design and permitting of approximately 5,700 feet of 12 -inch water main replacement, 4,500 feet of 8 -inch gravity sewer replacement, and 750 feet of 6 -inch and 20 -inch force main replacement. Post design responsibilities included reviewing and responding to shop drawings, RFIs, and change orders related to the utility improvements. Sr. Engineer, Various Roadway Restoration Projects, City of Winter Garden, Florida, 2013 to 2014. The City of Winter Garden is currently working to restore many of the streets located in the historical downtown area. The improvements include roadway repair, water and sewer replacement, and stormwater system installation. Ms. Whikehart performed technical reviews on multiple projects including the Reconstruction of Vineland Road, Reconstruction of North Dillard Street (Phase 3), Reconstruction of North Highland Avenue, and Reconstruction of South Woodland Street. She also prepared FDEP water and wastewater permit applications for each project. Project Manager, Dakin Avenue Box Culvert Design /Tohopekaliga Water Authority Utility Improvements Project, Kissimmee, Florida, 2007 to 2009. Ms. Whikehart served as the Project Manager for the Tohopekaliga Water Authority's (TWA) Dakin Avenue Box Culvert and Utility Improvements Project. As part of the City of Kissimmee's downtown revitalization/ redevelopment initiative, the City of Kissimmee wanted to have a portion of infrastructure improvements designed, including the rehabilitation of the Dakin Avenue box culvert. This box culvert serves as the primary stormwater conveyance system in the downtown area. The existing box culvert had numerous utilities that were constructed through the box culvert. To improve the conditions in the box culvert, utility improvements were added to the project including: relocating existing water mains, and designing protection ramps or conflict structures for existing sanitary sewers. Project Engineer, Wastewater System Improvements Project, Jacksonville, Florida, 2005 to 2006. Ms. Whikehart worked as Project Engineer on the JEA's Scott Mill Hill Wastewater System Improvements Project. Her task was to incorporate drainage improvements into a neighborhood septic tank phase out project. The objective of the project was to address maintenance issues and upgrade drainage system components to meet the city's design criteria. The first step was field reconnaissance, followed by completion of a drainage assessment memo, then design of improvements and cost estimation. Design components included roadside ditches, channels, and culverts. Project Engineer, Water and Sewer Improvements Project, Jacksonville, Florida, 2002 to 2003. Ms. Whikehart worked as Project Engineer on the Sans Souci Water and Sewer Improvements Project for the Jacksonville Electric Authority. Ms. Whikehart performed services including water, sewer, drainage, and channel restoration design and preparation of bid documents. Project Engineer, Briar Creek Sewer System Relief Improvements Project, Charlotte, North Carolina, 2002 to 2005. Ms. Whikehart served as Project Engineer for the Briar Creek Sewer Improvement Project for Charlotte - Mecklenburg Utilities in Charlotte, North Carolina. This project includes sewer improvements to the existing Briar Creek trunk sewer system consisting of approximately 100,000 linear feet of gravity sewer (12 to 72 inches in diameter). The project minimizes sanitary sewer system overflows and provides adequate hydraulic capacity for existing and future flows. The project is divided into 4 phases. Engineering services included preliminary design, right -of -way acquisition, and public relation services for all 4 phases of the project. Ms. Whikehart also provided final design and permitting services for the first phase of improvements. "Engineering a Higher Standard" 30. West State Road 434, Suite 309, Winter Springs, FL 327o8 •407- 992-9i6o •Fax4 www.pegosusengineering.net Pe RUN ENGINEERING YRS OF EXP 21 PROFESSIONAL REGISTRATION Professional Engineer 1997 Florida, No. 51932 Juan Fong, P.E. Maintenance of Traffic Engineer Mr. Fong has over 21 years of transportation engineering experience, with primary emphasis on the design of roadway and traffic systems. His responsibilities have included the project management, planning and design of minor, major and complex roadways across Florida, with his largest completed roadway project as Project Manager and Engineer -of- Record was the County Road 481 Widening in Citrus County with a construction cost of over $40 Million. IIis assignments have included the preparation of preliminary and final construction plans, technical reports, permit applications, bidding documents, construction administration services, right -of -way negotiations and testifying at order -of- take hearings. Mr. Fong has served as the Engineer -of- Record on numerous projects and has extensive experience in the preparation of roadway plans, signing and pavement marking plans, signalization plans, traffic control plans, traffic operation reports, safety analysis, and pavement desiL-n. CITRUS COUNTY, FLORIDA CR 486 Phase II Preliminary Engineering and Final Design CR 491 Phase II, III & IV Final Design Croft Ave Segment 2 Preliminary Engineering and Final Design I Iernando I- lementary Access Improvements POLK COUNTY, FLORIDA Berkley Road Segment 1 Final Design Berkley Road Segment 2, Preliminary Engineering and Final Design Pace Road, Preliminary Engineering and Final Design CR 655 (Berkley Road) Segment 4 and CR 559A (Auburndale Cutoff Rd), Preliminary Engineering and Final Design ORANGE COUNTY, FLORIDA Reams Road Corridor Alignment Study Forsyth Road Final Design CITY OF ORLANDO, FLORIDA John Young Parkway Segment 2 and Wetlands Mitigation. Alden Road Corridor/ Alignment Study & Preliminary Design. FDOT EXPERIENCE (DISTRICTS 1, 2, 3, 5 and 71 Multiple Roadway Intersection and Trail Projects for Multiple FDO'f Districts CITY OF OCOEE, FLORIDA SEMINOLE COUNTY, FLORIDA Maguire Road Final Design Multiple Sidewalk Projects as a Continuing Consultant Continuing Consultant °Pegasus ENGINEERING YRS OF EXPERIENCE 12 PROFESSIONAL REGISTRATION Prof. Engineer 2007 Florida, No. 65623 EDUCATION B.S. Civil Engineering 2001 University of Central Florida Keith Johnson, P.E. Engineer Mr. Johnson has over 12 years of public infrastructure engineering experience. He has extensive experience in the design and preparation of roadway plans, as well as utility coordination and completing utility adjustment construction plans and permitting for water, sewer and reuse systems. He has developed specifications, cost estimates, bidding documents, and has provided post- design services. He also has extensive experience in designing pedestrian facilities consistent with ADA requirements. He has also assisted with public involvement, field observations, and construction progress meetings, maintaining detailed project records, and in software installation. Mr. Johnson is also responsible for Electronic Delivery, PEDDS and Specifications on FDOT projects. • Berkley Rd. - Phase I, Final Design 5 -lane Widening & Utilities Design • Berkley Rd. - Phase II & III Final Design Multi -Lane Widening & Utilities Design CITRUS COUNTY, FLORIDA • CR 486 Final Design Multi -Lane Widening & Utilities (Phases II, III, & IV) including water mains & gravity sanitary sewers & force mains • Turkey Oak Dr. Milling /Resurfacing /Widening & Utilities Design VOLUSIA COUNTY • CR 415 ROW Corridor Analysis • 10th St. Preliminary Engineering Analysis (at City of New Smyrna Beach I Edgewater joint city limits) • Volusia Ave. Widening / Paving CITY OF OCOEE, FLORIDA • Maguire Rd. - Final Design 4 -Lane Widening, Bridge Over Turnpike • White Rd. Improvements • Professional Pkwy / Old Winter Garden Rd. Widening SEMINOLE COUNTY, FLORIDA • Sidewalk Program Continuing Consultant • Northern Way w /Pedestrian Bridge (2.0 miles) • Palm Springs Ave. (1.0 mile) • North St. / Seminole Ave. (2.0 miles) • Country Club Rd. (0.8 miles) • W. Lake Brantley Dr. w /Pedestrian Bridge (0.5 miles) • Shetland Ave. & Citrus Ave. (1.5 miles) • Traffic Signal & Intersection Improvements Continuing Contract (over 50 signalization and projects) intersection improvement "Engineering a Higher Standard" 301 West State Road 434, Suite 309, Winter Springs, FL 32708 0407 -992 -9160 0 Fax 407-358-5155 www. pegasusengineering. net POLK COUNTY. FLORIDA I E. Mahler, P.E. /Design Team Leader ando Office. Mr. Mahler is a Project Manager /Project he specializes in relocation of existing utilities associated lnd development and roadway design and permitting for ment facility improvements, SCADA systems, collection s utility line extension and relocation projects for both S.R. 50 Utility Relocation Project • 13 miles of water distribution system and wastewater collection and transmission system relocations and installations within the S.R. 50 Corridor • FDOT /JPA contract • New facilities as well as relocations and removal • 5.5 miles of 8, 12, 16, 20 & 24" diameter watermain • 7.7 miles of 4, 8, 12, 16, 20 and 30" diameter forcemain • 2.84 miles of gravity collection mains • Triplex Master Pump Station S.R. 426 Utility Relocation Project • FDOT widening project for 1.2 miles of S.R. 426 • Relocation of the City's 10" watermain with a 16" watermain • Additional 12" watermain designed to provide interconnect to another city • 4,000 feet of gravity sewer collection system with sewer lines ranging from 8" to 15" • New master lift station designed to accommodate existing and future flows from the area. • Installed 1,300 feet of 10" forcemain including a 270 foot directional drill Lake Alfred WWTF Upgrade and Expansion • Replaced a 0.600 MGD trickling filter facility with a new 1.0 MGD modified activated sludge process \X"\N'TF • New pretreatment headworks • New microscreen filtration • Trickling filter tank converted to 260,000 gallon equalization basin • Reconfiguration of chlorine contact basin to meet Class 1 reliability. Valencia Water Control District • Performs the duties of District Engineer, which includes various projects for the 7- square mile District. • Services performed in connection with master drainage System and related business. Lake Alfred Echo Drainage • Constructed new inlets, storm sewer, and stormwater ponds in order to alleviate flooding • Design consisting of stormwater modeling and permitting through SWFWMD, Polk County and FDOT • Assisted City with securing CDBG funding ay" R. Morris, Jr., P.E. Sr. Project Engineer i our Environmental Engineering Department, and has ms, wastewater collection systems , and pumping systems reas of expertise also includes preparation of water and tl specifications and project manuals, client management, vastewater projects, he has also been responsible for jects. Mr. Morris has also assisted clients with obtaining Orange County Utilities -S.R. 50 Utility Relocation (Phases 1, 2, and 3) • The projects combined include approximately 14 miles of water and sewer system installations and relocations • T he size of the utihty lines range from 4" to 30" and include water mains, gravity collection system and force main • The project also included the addition of a master triplex pump station in the Phase 1 portion of the project. AD three phases are Utility Work by Highway Contractor Agreements. Toho Water Authority - Poinciana Boulevard and U.S. 17 -92 Water Main • Approximately 4.1 miles of a 24" potable water transmission main • Over 3,600 lineal feet of a 30" directional drill • Special permitting requirements included CSX, FDOT, and Osceola County right -of -way of permits City of Oviedo — S.R. 426 • Design of 5,000 LF of gravity sewer, 4,000 LF of water main, 1,500 LF of force main as well as a duplex pump station • Utility Work by Highway Contractor Agreement project between the City of Oviedo and FDOT Orange County Utilities- Hidden Springs Reclaimed Water Re -pump Facility • 3,000 gpm high service reclaimed pump station. This project includes the retrofit of potable water mains to be converted for reclaimed use SR 520 54" Potable Water Transmission Main Phases I & II, City of Cocoa • Included a total of 7.1 miles of 54" potable water transmission lines • Required permitting, production of the project manual, contract documents, and cost estimating construction observation and all administrative tasks Orange County Utilities - Northwest Water Reclamation Facility Reclaimed Water Re -pump Facility • High service reclaimed pump station with 2 million gallon ground storage tank. • Over 2,000 LF of 24" reuse water main • Pond and site improvements • Electrical control building Mason Gardberg, E.I. / ProjecrEnglneer �rironmental Engineering Department, and has experience 'water collection systems, and pumping systems in both expertise also includes preparation of wastewater permit cifications and project manuals, client management, utility Orange County Utilities - S.R. 50 Utility Relocation (Phase 3) Plan Preparations • Removal and /or relocation of approximately 38,345 LF of existing force main ranging in size from 4" to 30" along State Road 50 from Dean Road to Old Cheney Highway as part of an FDOT roadway widening project. • Removal and /or relocation of approximately 53,032 LF of existing water main ranging in size from 4" to 24" along State Road 50 from Dean Road to Old Cheney Highway as part of an FDOT roadway widening project. Wastewater Permit Renewals • Casselberry WRF • Eustis Eastern WWTF • Mount Dora WWTF No. 1 • Oviedo WRF • Winter Springs West WWTF • Valley Mobile I Iome Park WWTF Toho Water Authority — Demolition of the Kissimmee West WTP & Poinciana WWTP No. 1 • Demolition of an existing WWTP and WTP Toho Water Authority — Lift Station # 6 Rehabilitation and Reconfiguration • Reconfigure yard piping through a new 8' x 10' collection structure, piping, and new manholes. • Replacement of the existing 900 LF of gravity sewer main and replacement of existing manholes. Toho Water Authority — Boggy Creek Road Intersection Utility Improvements • Installation of 2,150 LF of 16 -inch DI water main and 2,100 LF of PVC 16 -inch force main. Toho Water Authority — Hydraulic Modeling for Neptune Force Main System and for Fells Cove System • Utilization of Bentley SewerCAD • Modeling the existing system with the addition of future developments to determine the appropriate modifications for the system. alloway, PSMIDirector of Surveying and Mapping irveying and mapping profession, and has a Bachelor of Florida. His experience ranges from working in the field Technician, Project Manager and Survey Manager. Mr. irveying Division of CPH since 2001. Mr. Galloway has CPI I. Fie also directs the firm's High Definition Laser City of Sanford — Boundary, Topographic and As -built Surveys, Construction Stakeout and High Definition Laser Scanning • First Street Strectscape Project • Multiple Waste Water Treatment Plants • Pine Avenue Water Main • Multiple Lift Stations • Magnolia Avenue Streetscape Volusia County School Board — Boundary, Topographic and As -built Surveys, Construction Stakeout and High Definition Laser Scanning • Multiple School sites throughout Florida U.S. Navy - Vertical control and sanitary sewer design build survey on the Island of Guam Walmart Stores — Boundary, Topographic and As -built Surveys, High Definition Laser Scanning, Construction Layout, Sketch and Descriptions, Wetlands and Platting • Multiple Walmart sites throughout Florida • Multiple Walmart sites throughout Puerto Rico Florida Department of Agriculture — Boundary and Topographic Survey and High Definition Laser Scanning • Immokalee Farmers Market Newland Communities • 15 -mile Control & Route Survey - ROW Maps for Ilillsborough County Martin County School Board — Boundary, Topographic and As -built Surveys, Construction Stakeout and High Definition Laser Scanning • Multiple School Sites throughout Martin County SunTrust Banks — Boundary, Topographic and As -built surveys, Construction Layout, Sketch and Descriptions and Platting • Multiple SunTrust sites throughout Florida RFQ #1401 Engineering Services for Ocoee West Sanitary Transmission Project m e 10 6 41SR zuwr c >cc> 6. SIMILAR PROJECTS 6. SIMILAR PROJECTS Following is a listing of representative similar projects where Pegasus and CPH have provided pipeline engineering services for other utility providers within the past five (5) years: A. Pegasus Similar Projects 1. Southwest Development Utility Improvements City of Ocoee Utilities The 2 -phase project along Roberson Road and Windermere Road consists of 7,200 feet of ductile iron water main, 3,100 feet of 4 -inch PVC force main and 2,500 feet of 6 -inch PVC force main. The project includes 120 feet of 8 -inch HDPE directional drill and 220 feet of 6 -inch PVC directional drill. David Wheeler, P.E., City Engineer City of Ocoee 150 North Lakeshore Drive Ocoee, Florida 34761 407 - 905 -3100 (office) / 407 - 905- 3151(fax) / dwheeler @ci.ocoee.fl.us 2. Plant Street Seqment 11 Widening & Utility Improvements City of Winter Garden The utilities improvements associated with this roadway widening project included 5,700 feet of 12 -inch water mains, 4,500 feet of 8 -inch PVC gravity sewers, and 750 feet of 6 -inch and 20 -inch force mains. Arthur Miller, P.E., City Engineer City of Winter Garden 300 West Plant Street Winter Garden, Florida 34787 407 -656 -4111 (office) / 407 - 877 -2363 (fax) / amiller @cwgdn.com 3. County Road 486 Widening & Utility Improvements — Phase IV Citrus County Department of Public Works and Department of Water Resources The utilities improvements associated with this roadway widening project consisted of a total of 16,000 feet of 6 -inch and 8 -inch PVC water mains, and 7,800 feet of 12 -inch PVC force mains. Ken Cheek, P.E., Director of Water Resources Citrus County 3600 West Sovereign Path, Suite 291 Lecanto, Florida 34461 352 -527 -7650 (office) / 352 - 527 -7644 (fax) / ken.cheek @bocc.citrus.fl.us Pe 85u5 Tab 6 1 Page 1 9 . °...•• - RFQ #1401 — ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT WV 6. SIMILAR PROJECTS 0('0( >e 4. Sarno Lakes Drainage Improvements Brevard County The utilities portion of the project included relocating an 8 -inch DIP water main at Aurora Road and Cibola Drive; relocating a 6 -inch PVC water main at Harlock Road and White Road; and relocating a 20- inch PCCP water main at Aurora Road and John Rodes Boulevard to accommodate the $5.4 Million FEMA funded drainage improvements. The utility adjustments also included bends, line stops, service saddles, butterfly valves, and adaptors. Jennifer Spagnoli, P.E., Utilities Engineer City of Melbourne Public Works and Utilities Department 2885 Harper Road Melbourne, Florida 32904 321 - 674 -5761 (office) / 321 - 674 -5765 (fax) /jspagnoli@melbourneflorida.org 5. Central Beach Sanitary Sewer Replacement Rehabilitation & Force Main Project Utilities Commission of New Smyrna Beach Pegasus services included design and permitting of 8,500 feet of 8 -inch PVC gravity sewers to replace old 8 -inch RCP pipe, including 90 new manholes. The project also includes use of trenchless technology pipe rehabilitation of 12,000 feet of VCP using cured -in -place pipe (CIPP) method. The force main design included 2,800 feet of 12 -inch force main. Dana Hale, P.E., Civil Engineer Utilities Commission City of New Smyrna Beach 200 Canal Street New Smyrna Beach, Florida 32168 386 - 424 -3037 (office) / 386 - 409 -4720 (fax) / dhale @ucnsb.org 6. Central Beach Water Main Improvements Utilities Commission of New Smyrna Beach Pegasus design services included design and permitting of 10,000 feet of 6 -inch PVC water mains. Dana Hale, P.E., Civil Engineer Utilities Commission City of New Smyrna Beach 200 Canal Street New Smyrna Beach, Florida 32168 386 - 424 -3037 (office) / 386- 409 -4720 (fax) / dhale @ucnsb.org Tab 6 1 Page 2 Pegasus RFQ #1401 — ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT !D 0 Nu �-. «(:«e 6. SIMILAR PROJECTS 7. Westside Emergency Flood Management System (WSEFMS) City of DeBary The West Side Emergency Flood Management System is a $6.6 Million FEMA funded flood protection project consisting of three (3) permanent stormwater pump stations and 6 -miles of stormwater force mains (ranging in size from 16- inches to 36- inches). Dan Parrott, City Manager City of DeBary 16 Colomba Road DeBary, Florida 32713 386 - 668 -2040 (phone) / 386 - 668 -4122 (fax) / dparrott @debary.org Scott Mays, P.E., Utility Engineer Volusia County Water and Utility Services Group 123 West Indiana Avenue Deland, Florida 32720 386 - 943 -7027, Ext. 12076 (office) / 386- 804 -7870 (fax) / smays @volusia.org B. CPH Similar Proiects 1. SR 50 Sta. 445.00 to Sta. 500.00 Utility Relocations Project (SR 417 to Dean Road) Orange County Utilities Department This project was the second phase of the FDOT's highway improvements along SR 50 from SR 417 to Dean Road which included widening the roadway and storm system improvements. To accommodate the FDOT roadway improvements, approximately 1.1 miles of existing OCU water and wastewater mains had to be relocated. The relocation within FDOT right -of -way consisted of approximately 2,200 LF of 12 -inch and 5,150 LF of 20 -inch water main and 5,000 LF of 24 -inch force main. The project also had 600 lineal feet of 30 -inch directional drill, 200 lineal feet aerial crossing, and multiple water and wastewater service reconnections. Christa Gandenberger, P.E. Orange County Utilities Department 9150 Curry Ford Road Orlando, Florida 32825 407 - 254 -9941 (office) / 407 - 254 -9999 (fax) / christa.gandenberger @ocfl.net Tab 6 1 Page 3 P @98BU5 RFQ #1401 - ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT 6. SIMILAR PROJECTS 0('0 2. International Drive and Universal Boulevard Force Main Orange County Utilities Department This project included the design of 10,100 LF of 24 -inch force main along the County and FDOT rights - of -way at Universal Boulevard, Point Plaza Avenue, across from International Drive, Interstate 4 and Turkey Lake Road. Elizabeth O'Reilly Orange County Utilities Department 9150 Curry Ford Road Orlando, Florida 32825 407 - 254 -9734 (office) / 407 - 254 -9799 (fax) / elizabeth.oreilly @ocfl.net 3. Osceola Parkway /FL. Turnpike Water Main Crossing Toho Water Authority Provided 1,400 LF of 24 -inch water main with a 30 -inch casing under the Florida Turnpike utilizing a single horizontal directional drill (HDD) installation. This HDD installation spanned nearly the entire length of the project with a total length of 1,400 LF. Edwin Matos, P.E. Toho Water Authority 951 Martin Luther King Jr. Blvd. Kissimmee, FL 34741 407 - 944 -5024 (office) / 407 - 944 -4264 (fax) / ematos @tohowater.com 4. Investors Row Force Main Replacement Orange County Utilities Department The project consisted of furnishing and installing approximately 3,133 LF of 16 -inch AWWA C -905 PVC force main by open cut; approximately 261 LF of jack and bore of the 16 -inch force main across John Young Parkway; a 520 LF 16 -inch directional drill across a drainage canal; and removal and disposal or abandonment of the existing DIP force main. Pierre Cadely, E.I. Orange County Utilities Department 9150 Curry Ford Road Orlando, Florida 32825 407 - 254 -9733 (office) / 407 - 254 -0799 (fax) / pierre.cadely @ocfl.net Tab 6 1 Page 4 P8[Ja35U5 RFQ #1401 — ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT [*]Am= RFQ #1401 Engineering Services for Ocoee West Sanitary Transmission Project Equipment List c�c: cap 7. EQUIPMENT LIST A. Pegasus Engineering Equipment List Computer Equipment Hardware 15 Dell Computer Workstations 4 Laptop Computers 1 Dell File Server 1 Back -Up System 1 Dell Color Printer 1 Hewlett- Packard Laser Jet Printer 1 Panasonic 10X Digital Camera 1 Savin Copier/ Scanner/ Printer 1 Hewlett- Packard T1100 Color Plotter 2 Lanier Color Copiers / Scanner Printers B. CPH Equipment List Conventional Survey Equipment List: • 1 Sokkia SET 500 Total Station • 7 Topcon GPT 2005 Total Stations • 1 Topcon GPT 2002 Total Station • 1 Topcon GPT 3103 Total Station • 4 Topcon GPT 3005 Total Stations • 1 Nikon AS2 — Automatic Level • 12 Topcon AT -G4 — Automatic Levels • 2 Topcon AT -24A — Automatic Level • 1 Sokkia B20 — Automatic Level • 1 Trimble DR200+ — Robotic Total Station • 1 GPT Topcon 8005 — Robotic Total Station • 1 Spectra Precision Focus 10 — Robotic Total Station Transportation Equipment List: • 3 — 2005 Dodge Ram 1500 Series • 1— 2006 Dodge Ram 1500 Series • 1— 2005 Ford F -150 Series • 1 — 2010 Ford F -150 Series • 2 — 2003 Chevrolet Silverado 1500 Series • 1— 2004 Chevrolet Silverado 1500 Series • 1— 2008 Chevrolet Silverado 1500 Series • 1— 2011 Chevrolet Silverado • 1 -10' John Boat Software 1 2003 Windows Server 15 Windows 7 Workstations 5 Bentley Microstation 5 Geopak 15 Microsoft Office Suites 15 Adobe Acrobat 2 AutoCAD 1 Arc Info GIS GPS Field Survey Equipment List: • 6 Topcon HiPer Pro — GPS — Glonass Enabled • 1 Trimble 5700 —GPS • 1 Trimble R6 — GPS — Glonass Enabled Digital Level Survey Equipment List: • 2 Topcon DL 101C Digital Level Laser Scanner Survey Equipment List: • Leica ScanStation2 — High Definition 3d Laser Scanning System • Nikon D5000 — Digital Camera • 1— 12' John Boat • 1— 22' Bay Boat Office Software: • Autocad Civil 3D 2012 • Autodesk Autocad 2012 • Arcview Arcmap Version 9.3 • Microsoft Office Suite 2003 — 2010 • Cyclone 7.3 • CP Tab 7 1 Page 1 PBg35U5 RFQ #1401 — ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT !J s 0( 0(> 7. EQUIPMENT LIST Technical Resources: ✓ Approximately 250 Workstations ✓ Windows Server 2000 ✓ Wide Area Networks - VPN via Cisco Routers ✓ High Speed Internet Access ✓ Windows Exchange Server ✓ High Speed e -mail, FTP, and WEB services on- line ✓ 10/100 Ethernet LANs in all offices ✓ Microsoft Office Professional ✓ Powerful large format printing capabilities in all offices ✓ High Security and Virus protection company- wide ✓ ACAD Civil 3D 2012 and ACAD 2009, Arc GIS, Microstation, Autoturn 7, Land Desktop 3, Microstation, Autoturn 7 ✓ WaterCAD, Ponds, Advanced Inter Connected Pond Routing (ICPR), Hydraflow, Modret, ArcView, MColor and many others ✓ Topcon GPT -2005 Total Station with prism /non prism feature ✓ Topcon GPT -3005 Total Station with prism /non prism feature ✓ Topcon AT -G4 Automatic Levels ✓ Topcon Recon 200C w /64MB Field computers with Survey Pro software ✓ FDOT approved setup for traffic cones, traffic signs, survey vests and hardhats ✓ Geopack C. Southeastern Surveying and Mapping Corp. Equipment List Field Equipment 8 Allegro Data Collectors 1 TDS NOMAD 2 TDS Recon Data Collectors 2 Survey Towers 15' High 3 Topcon AT F2 Automatic Levels 19 Topcon GPT Total Stations 1 Topcon GTS -901A Robotic Total Station 4 Wild NA2 Automatic Levels 1 Topographic Scanner Lifts 26 GA -52cx Schonstedt Magnetic Locators 16 Fisher FPID 2100 Magnetic Metal Locators 1 Leica DNA10 Digital Level 9 CST Levels 4 Pentex AFL Automatic Levels 1 Riegl USA VZ -400 Laser Scanner 3 Sokkia SDL30 Digital Levels 31 Topcon TopSury Data Collectors 15 Topcon Total Stations 3 Sokkia Total Stations 6 Sokkia B2 Levels 8 Sokkia B20 Automatic Levels Field Support Equipment 7 All- Terrain Vehicles w /trailers 68 FleetBoss GPS Modules (Fleet Maintenance & Tracking) 1 13' Big'O Air boat with trailer 1 18' open boat with trailer 2 Jon Boats with trailer 1 Pond Prowler 1 12' Canoe 1 12' Skiff w /trailer and 1 -14' Skiff w /trailer 3 Bicycles equipped for asset inventory tasks 2 Ruggedized Ricoh Caplio 500 SE -B Camera with Onboard GPS's 5 Kodak Digital Cameras 21 Olympus TG -830 iHS Digital Cameras 10 Cannon Power Shot Cameras 2 Fujitsu Digital Cameras 1 Honda (9.9) Outboard Motor 1 Johnson (15 -HP) Outboard Motor 1 Briggs and Stratton (5 HP) Outboard Motor 1 Force (15 -HP) Outboard Motor Tab 7 1 Page 2 Pe l mmtm RFQ #1401 - ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT 7. EQUIPMENT LIST 0(0e(? GPS /GIS Equipment 4 Garmin E -TREX Legend -CX 1 Garmin GPS MAP 60 CX Recon Receiver 5 Garmin GPS III "Plus" Reconnaissance Receivers 11 Airlink CDMA Modems 29 Topcon 1-1 /1-2 GPS +Receivers 20 Topcon Data Collectors 3 PDL RTK Rover Modems 4 TDS Ranger Data Collectors with Survey PRO 5 Trimble TSCE Data Collectors 8 Trimble Pro -XR GPS Unit 4 TSC1 Data Collectors 3 Topcon GPS +Reference Station Receiver 3 Trimble 4000 SSE GPS Receivers 1 Trimble 4000 SSI GPS Receivers 2 Magellan Meridian Reconnaissance GPS Rec 2 VoCarta Field Voice Activated Asset Inventory Systems 1 Point Grey Lady Bug 5 Spherical Camera 1 Garmin GLO Bluetooth GPS Communications Equipment 93 (150) MHZ Portable 5 watt Radio Systems 110 Android Cellular Smart Phones Vehicles 57 Ford F150's 3 Ford Explorer 2WD 5 Ford Explorer 4WD's 11 Ford Ranger 2WD's 2 Ford Ranger 4WD's 3 Ford Escapes 2WD XLT's 1 Ford Escape 4WD's XLT 1 Ford E250 Series Van 5 Ford 450 Series Flat Beds 1 Ford Expedition 4WD 1 GMC Box Truck 1 Toyota Tacoma 4WD 1 Dodge Ram 1500 Series 3 Chevy Silverado 4WD Printers /Plotters /Scanners 4 Color Digital /Laser Printers /Scanners 2 Digital Printer/ Copier/ Scanners 5 Fax/Scanners 15 Network Laser Printers 1 Color Wide Format Plotter 2 Business Color Printers 6 Wide Format Printer/ Desktop Color 6 Desktop Color Ink Jet Printers Hydrographic Equipment 1 Seafloor Systems Inc. 200 KHZ Echo Sounder Utility Designation /Location Equipment 6 185 Sullair Diesel Compressors 2 Conquest GPR Units (Concrete Inspection) 5 Noggin Ground Penetrating Radar Units 1 Metro Tech model 9860 Locators 3 Metro Tech Model 810 Line Locators 1 Metro Tech 10 watt transmitter 1 Pipehorn model 100 Locator 5 Pneumatic Hammers 7 Pneumatic Tamps 12 VIVAX Prol-oc 2 Locators 1 500' Sonde Reel 1 Radiodetection 18A Sonde - Range 0' - 12' 1 Dig Trak Sonde Standard - Range 0' - 50' 6 Utilivac Vacuum Excavation Systems 8 Fisher FPID 2100 Magnetic Metal Locators 2 Water Probe Systems 2 RD 500 Plastic Water Pipe Locator 1 Closed Circuit TV /VIDEO 360❑, Pan and Zoom Capabilities and 2 CCTV, Pan and Tilt Rovers with Laser Profiler 1 Pipe Thickness Testing Gauge 10 LMX Ground Penetrating Radar Units Tab 7 1 Page 3 pega5u5 RFQ #1401 — ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT X__. /6r tic 0 7. EQUIPMENT LIST Computer Equipment 50 Dell Precision Workstations with DVD / CD Re- writable Drives 30 Dell Business Desktops with CD Re- writable Drives 6 Latitude Laptops 2 ThinkPad Laptops 2 Mini Dell Laptops 4 Dell Field Download Stations 1 HP Z -Book Laptop 1 ASUS N76V Laptop 2 PowerEdge 860 File and Database Servers Cnft %A /a rP Acrobat Acrobat Professional Adobe (Illustrator, Reader) Adobe Photo Shop Elements AutoCAD 2000 /LDD2 /LDD3 /2006 -2014 AutoDesk Civil 3D 2006 -2014 Bentley GEOPAK for V8 CAiCE (v.10.5, Visual PE 9 and PE 10) Cartegraph v.8.1 CEFB v.12.17.98 Corpscon Version 6 EFBR NT ESRI (ArcEditor 10.1 and Arclnfo 10.1) FDOT Electronic Field Book Processor FDOT 3 wire Level Adjustment Program Hector Vector NT Hitachi - Recognizer v.2.0 for ACAD Hitachi - Tracer v.3.0 for ACAD InterVideo WINDVD 4.0 Mapinfo v.2.0 D. PSI Equipment List • FLPIER — structural and pile analysis • SPILE — pile capacity analysis • SPT — axial load analysis software • PONDS —pond analysis • MODRET— pond analysis • EMBANK — settlement analysis • D647 — drilled shaft lateral analysis • SETTLEG —settlement analysis 1 PowerEdge 2950 GPS Application and Data Server Transmitter 4 HP Proliant DL 380 Domain and Application Servers 1 Proliant 3000 Remote Access Server 1 HP Proliant DL120 SQL Server 1 Public File Transport Server (FTP Server for SSMC) 2 Ultrium LTO Autoloader Tape Backups 1 APC Server Uninterruptible Power Systems 1 R1500XR Uninterruptible Power System (UPS) Microsoft Office Suite 2003, 2007, 2010, 2013 MicroPAVER v.6.1.6 MicroStation V8 w /FDOT 2004 MicroStation V8i w /FDOT 2010 MircroStation V8 - XM w /FDOT 2008 Sokkia Pro Link StarNet v.6 StarLev v.6 TDS Foresight DXM Terra Sync v.2.40 Topcon (Link, PC -CDU, CE -CDU, Pinnacle, Tools) Riscan Pro Stadic LiDAR v1.8 Trimble (Geomatics Office, GPS Survey, Pathfinder Office) Roxio Easy CD Creater VoCarta Processing Manager VoCarta VoCab Builder Microsoft Dynamics NAV Lady Bug CapPro • LPILE — lateral load analysis • CSHTWAL — sheet pile analysis • RE -STAB6 — retaining wall analysis • RSS — slope stability software • SHAFTUF — drilled shaft analysis • COYLE — pile analysis • REWAL — mechanically stabilized earth wall • CPTINTRI —cone penetrometer Tab 7 1 Page 4 Piema " RFQ 41401 — ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT 7. EQUIPMENT UST • SET -SAND — sand settlement analysis PL -AID — single pile analysis using SPT & CPT data LABORATORY EQUIPMENT Soil Equipment 3 — Automatic Rainhart Proctor Machines 2 — Fine Aggregate Sieve Shakers (8" & 12 ") 2 — Sets of Automatic Liquid Limit Devices 6 — Ovens 10 — Electronic Balances 1— Aggregate Crusher 1— Muffle Furnace 1— LA Abrasion Machine 2 — Automatic Rainhart LBR Presses 3 — Sample Splitters 1— Gilson Coarse Aggregate Sieve Shaker 2 — Triaxial Permeability /Shear Testing Panels 55 — LBR Molds Concrete Equipment 1— 500,000 lb. Digital Forney Compression Machine 2 — Rainhart Beam Breaking Machines 3 — Concrete Compression Machines 250- 400,000 pounds 44 — Beam Molds 1— Soil Test Pavematic Compression Machine 1— Temperature or Humidity Controlled Moist Cure Room (Capacity 3,000 cylinders) Asphalt Equipment 1— NCAT Oven 2 — Automatic Marshall Hammers 1— Automatic Marshall Press 2 —Vacuum Asphalt Extraction Apparatuses 2 — Bulk Specific Gravity Water Tanks Specialized Equipment 1— Linear Shrinkage of Concrete Test Equipment (20 molds) 1— Time of Set of Concrete Equipment FIELD EQUIPMENT Soil Equipment 19 — Troxler Nuclear Density Gauges 30 — Speedy Moisture Test Kits 5 — Wind Screens Miscellaneous Hand Augers, Post Hole Diggers, Shovels, Sand Cone Equipment in each pick -up. Concrete Equipment 6 — Roll -A- Meters (Air Test) 6 — Pressure Meters (Air Test) 2 — Winsor Probes 3 —Swiss Hammers 2 — Flow Cones 2 — Electric Concrete Vibrators Miscellaneous Slump Kits, Wheelbarrows with covers, Thermometers, in each pick -up Asphalt Equipment 1— Marshall Hammer 2 — Portable Core Rigs Specialized Equipment Traffic Safety Equipment (Attenuator Truck, Arrow Board, Signs, etc.) 2 — Pile Driver Analyzers 1— Pile Integrity Tester 1— Survey Level and Equipment 2 — R -Meter Metals Equipment 2 — Radiographic Cameras and Truck - Mounted Dark Rooms 2 — Ultrasonic Flaw Detectors 10 — Magnetic Particle Test Devices 1— Set Coatings Discontinuity Test Equipment 4 — Coatings Thickness Magnetic Gauges 1— Coatings Thickness Ultrasonic Gauge Tab 7 1 Page 5 Pega5u5 RFQ #1401 — ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT RFQ #1401 Engineering Services for Ocoee West Sanitary Transmission Project MDA 0 0 8. REFERENCES Listed below are three references for Pegasus Engineering, LLC and three references for CPH, Inc. A. Pegasus Engineering, LLC Dana Hale, P.E., Civil Engineer Utilities Commission City of New Smyrna Beach 200 Canal Street New Smyrna Beach, Florida 32168 386 - 424 -3037 (office) / 386 - 409 -4720 (fax) / dhale @ucnsb.org Arthur Miller, P.E., City Engineer City of Winter Garden 300 West Plant Street Winter Garden, Florida 34787 407 - 656 -4111 (office) / 407 - 877 -2363 (fax) / amiller @cwgdn.com Ken Cheek, P.E., Director of Water Resources Citrus County 3600 West Sovereign Path, Suite 291 Lecanto, Florida 34461 352 - 527 -7650 (office) / 352 - 527 -7644 (fax) / ken.cheek @bocc.citrus.fl.us B. CPH, Inc. Elizabeth O'Reilly Orange County Utilities Department 9150 Curry Ford Road Orlando, Florida 32825 407 - 254 -9734 (office) / 407 - 254 -9799 (fax) / Elizabeth.oreilly @ocfl.net Edwin Matos, P.E. Toho Water Authority 951 Martin Luther King Jr. Blvd. Kissimmee, FL 34741 407 - 944 -5024 (office) / 407 - 944 -4264 (fax) / EMatos @tohowater.com Christa Gandenberger, P.E. Orange County Utilities Department 9150 Curry Ford Road, Orlando, Florida 32825 407 - 254 -9941 (office) / 407 - 254 -9999 (fax) / christa.gandenberger @ocfl.net Tab 8 1 Page 1 Peya5u5 RFQ #1401 - ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT RFQ #1401 *Talffluoffil Engineering Services for Ocoee West Sanitary Transmission Project i #I I i i Following is a listing of the distance in miles and the time required to reach City Hall for each of the firms shown on our Pegasus -CPH Team's Organizational Chart. B. Company Information / Signature Sheet Included in this section is the completed and notarized form for Pegasus Engineering, LLC. C. Receipt of Any Addenda Issued Addendum No. One (1), dated September 3, 2014 All respondents shall acknowledge this addendum in your qualification package by completing the section below and including in Section 11- Firm's Office Location & Other Forms. Respondent. Pe ga�stig'Engineering, LLC 7 r. Signature: Name: Fursan Munied l/1 { Title: Principal -in- Char Tab 9 1 Page 1 Pegasus RFQ #1401 — ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT Pegasus Engineering 301 West State Road 434, Suite 309 21.2 miles 34 minutes Winter Springs, Florida 32708 407 - 992 -9160 CPH, Inc. 1117 East Robinson Street 14.3 miles 23 minutes Orlando, Florida 32801 407 - 425 -0452 - - - - - -- --- - - - - -- Southeastern Surveying and Mapping Corp. 6500 All American Boulevard 10.80 miles 17 minutes Orlando, Florida 32810 O 407 - 292 -8580 PSI, Inc. 174833 rd Street 14.03 miles 20 minutes Orlando, Florida 32839 O 407 - 304 -5560 B. Company Information / Signature Sheet Included in this section is the completed and notarized form for Pegasus Engineering, LLC. C. Receipt of Any Addenda Issued Addendum No. One (1), dated September 3, 2014 All respondents shall acknowledge this addendum in your qualification package by completing the section below and including in Section 11- Firm's Office Location & Other Forms. Respondent. Pe ga�stig'Engineering, LLC 7 r. Signature: Name: Fursan Munied l/1 { Title: Principal -in- Char Tab 9 1 Page 1 Pegasus RFQ #1401 — ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT ISM, W/ 0(U�� 9 OFFICE LOCATIONS & O THER D. MBE CERTIFICATION Pegasus Engineering, LL[ is a certified MBE by Orange County and is also certified as a MBE firm by the State of Florida bee copies of certificates below). ~~ -~' ,m;Anycx,`mumxu, "°""""°"°""^°"""" E. SUMMARY OF LITIGATION Pegosus Engineering, LLC (Prime Consultant) Pegasus Engineering, LL[ has never experienced any claims, bid or contract disputes filed bxoragainst PeQasus,or|itiQationagainsttheservicesprovidedbyourfi/no. ` Taus | Page z fpe-qTM-I! RFQ #1401 - ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT SuI,u/*.� 1 r°'fi— ill,. Pega Engineering. uc x° 09, 12,20 ° 0911 2�201 5 Pegasus Engineering, LL[ has never experienced any claims, bid or contract disputes filed bxoragainst PeQasus,or|itiQationagainsttheservicesprovidedbyourfi/no. ` Taus | Page z fpe-qTM-I! RFQ #1401 - ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT COMPANY INFORMATION /SIGNA'T'URE SHEET RFQ #1401 FAILURE TO COMPLY WITH THESE RFQ INSTRUCTIONS WILL RESULT IN DISQUALIFICATION OF YOUR QUALIFICATION PACKAGE. PLEASE SIGN BELOW ATTESTING THAT YOU HAVE READ AND UNDERSTAND ALL RFQ INSTRUCTIONS AND THAT YOU UNDERSTAND THAT THE SUCCESSFUL RESPONDENT WILL BE REQUIRED TO ENTER INTO A LEGALLY BINDING CONTRACT WITH THE CITY OF OCOEE. Pegasus En ing eering, LLC _ COMPANY NAME 4 07- 992 -9160 TELEPI IONE (INCLUDE: AREA CODE,) 407 - 358 -5155 FAX (INCLUDE AREA CODE) f ursan(a)peRasusen ink eering E-MAIL ADDRESS t LITHO RIZED SIGNATUR (manual) Fursan Munjed, P .E. , Princ NAME /TITLE (PLEASE PRINT) IF REMITTANCE ADDRESS IS DIFFERENT FROM PURCHASE ORDER ADDRESS, PLEASE INDICATE BELOW: 301 West State Road 43 S uite 3 09 STREET ADDRESS W inter Sprint s, _ Flo r id a 3270 CITY STATE ZIP FEDERAL ID # 26- 0806410 Individual X _Corporation Partnership Other (Specify Sworn to and subscribed before me this 9th_ day of_ Septemb , 20 14 . Personally Known X or Produced Identification Notary Public - State of Florida (Type of Identification) County of Seminole Signature of Notary Public Priscilla Villanueva Printed, typed or stamped Commissioned name of Notary Public PRISCILLA VILLANUEVA ! MY COMMISSION #FF090519 EXPIRES April 27, 2018 (407) 398 -0153 FloridallotaryServlce.com RFQ 91401 — ENGINEERING SERVICES FOR OCOFF WEST SANITARY TRANSMISSION PROJECT 14 Mayor S. Scott Vandergrift City Manager Robert Frank September 3, 2014 Commissioners John Grogan, District 1 Rosemary Wilsen, District 2 Rusty Johnson, District 3 Joel F. Keller, District 4 ADDENDUM NO: ONE (1) CITY OF OCOEE RFQ 41401 ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT This addendum consists of two 2 pages, and shall modify and become a part of the original RFQ documents for Engineering Services for Ocoee West Sanitary Transmission Project. Respondents shall acknowledge receipt of this Addendum in the space provided on this Addendum. Failure to do so may subject the Respondent to disqualification. The RFQ due date remains the same. The following Documents have been posted to Dcmandstar: I. Pre- Submittal Conference Sign -in Sheet 8/19/14 2. Presentation at Pre - Submittal Conference 8 /19/14 3. Bluford Avenue Stormwater and Utility improvements Project Drawings Amendments and /or Clarifications to the RFQ documents are as follows: Clarification #1 Firm shall be considered "FIRM /TEAM" when referenced within Request for Qualifications (RFQ) #1401. "FIRM /TEAM" shall include all sub - consultants to support prime Consultants work. Clarification #2 Incidental to and in support with, the City has cause two portions of the project (pre - staged work) to be design and permit and shall, if in the best interest of the City and other mutual parties, cause the construction of those portion of the project before /or during the Consultant design efforts. Consultant shall be required to coordinate with City and others all pre- staged work. Clarification 0 As indicated in Table "Evaluation Criterion" Page 12 responders to the RFQ should include a "Project Approach ". Failure to provide a project approach will result in no points awarded for that category. Amend #1: "C. Scope of Services" Original: The selected Consultant will assist the City by supplying sanitary sewer transmission design, coordination, permitting, and bidding services needed to support the PROJECT. It is anticipated that both geotechnical and professional land survey services will be needed in support of the design of the PROJECT, Consultant will be tasked with preparing a detailed scope and necessary support services, where the City will procure those services utilizing ongoing professional contracts. Shall be replaced with: The selected Consultant will assist the City by supplying sanitary sewer transmission design, coordination, permitting, and bidding services needed to support the PROJECT which shall include al need sub- consultant service to support the efforts of the Consultant City of Ocoee • 150 N Lakeshore Drive - Ocoee, Florida 34761 phone: (407) 905 -3100 • fax: (407) 905 -3194 • www.ocoee.org Amend #2: 9. Firm's Qualifications" Original: • List of all firm's employees, their qualifications, and their role in providing the desired City services, • Firms and employee's certifications and registration with regulatory agencies, professional organizations, etc, • List firm's sub- consultants, their qualifications, and their role in this project. • List of firm's other current or recently completed similar services within the past two 2 years with other public or private agencies. • List and quantity of firm's (and firm's sub- consultants' if applicable) equipment including survey instruments, computers, plotters, vehicles, etc. • List of at least three (3) client references to include organization name, contact person, telephone number (s), and e -mail address. • Project Manager education, experience and any special consideration • Key Project Members education, experience and any special consideration • Firm's Project organization and coordination structure Shall be replaced with: • List of all firm's employees, their qualifications, and their role in providing the desired City services. • Fil and employee's certifications and registration with regulatory agencies, professional organizations, etc. • List firm's sub - consultants, their qualifications, and their role in this project. • List of firm's other current or recently completed similar services within the past FiVC (5)y with other public or private agencies. • List and quantity of firm's (and firm's sub - consultants' if applicable) equipment including survey instruments, computers, plotters, vehicles, etc. • List of at least three (3) client references to include organization name, contact person, telephone number (s), and e -mail address. • Project Manager education, experience and any special consideration • Key Project Members education, experience and any special consideration • Firm's Project organization and coordination structure 1 6 ( c Tolbert, CPPB Purchasing Agent cc: Evaluation Committee All respondents shall acknowledge this addendum in your qualification package by completing the section below and including in Section II- Firm's Office Location & Other Forms. Respondent:_Pe sus Engineeritny, LLC,, SignatruV-- - - `' � 3- - -- Name: Fursan Mi ned Title: Principa -in- Charg RFQ 1401 — Addendum 111 2 Pegasus 301 West State Road 434, Suite 309 Winter Springs, Florida 32708 Phone: 407 - 992 -9160 /Fax: 407 - 358 -5155 www.pegasusengineering.net R FQ #1401 September 9, 2014 at 2:00 pm ENGINEERING SERVICES FOR Ocoee West Sanitary Transmission Project ... { h September 9, 2014 In �consufbng rs Joy ce Tolbert, Purchasing Agent City of Ocoee 150 N. Lakeshore Drive Ocoee, Florida 34761 RE: Request for Qualifications (RFQ) #1401; Ocoee West Sanitary Transmission Project Dear Ms. Tolbert and the City of Ocoee Selection Committee: Inwood Consulting Engineers, Inc. (Inwood) is pleased to present one "original" Statement of Qualifications (SOQ) document, one physical copy of the SOQ, and four electronic copies of the SOQ on four separate CDs. Inwood's headquarters are in nearby Seminole County, and we are strategically located to offer the City of Ocoee (City) excellent personal service. Inwood's utility staff members are available for your project. We have spent many hours researching and developing our project approach. And, because we have completed eight prior projects for the City, we have a very good understanding of the West Sanitary Transmission Project's needs and challenges. In addition, we have good relationships with many of the key stakeholders along this transmission route. Having worked with the City on previous utilities and transportation projects, we are excited about the opportunity to work on this project. We have reviewed the RFQ scope of services and attended the pre -bid meeting, and Inwood acknowledges the terms provided and agrees that we can meet or exceed all of the City's requirements. Inwood's approach to completing the services for this contract will consist of well planned and well managed processes that will best meet the needs of the City. I will serve as Project Manager, and I have served in a similar role on many diverse projects throughout the state of Florida for more than 24 years. I am authorized to represent Inwood on contractual matters and will be the primary point of contact for the City. I can be reached at: Inwood Consulting Engineers, Inc. 3000 Dovera Drive, Suite 200 Oviedo, Florida 32765 Ph. (407) 971 -8850; (321) 303 -6256 (cell); Fax (407) 971 -8955 dcoleman@inwoodinc.com By submitting this SOQ, we declare that it is in all respects fair and in good faith, without collusion or fraud. The Inwood Team would consider it a privilege to work with the City again and will serve the City with diligence. Thank you for the opportunity to demonstrate Inwood's qualifications and for your consideration of our submittal. Very truly yours, INWOOD CONSULTING ENGINEERS, INC. David G. Coleman, PE Principal /Project Manager Inwood Consulting Engineers, Inc. 1 3000 Dovera Drive, Suite 200 1 Oviedo, FL 32765 1 407.971.8850 Table of Contents Page 1. Firm's Qualifications a. List of all of firm's employees, their qualifications, their roles in providing desired City services ........... 1 -1 b. Firm's and employees' certifications and registration with regulatory agencies, professional organizations, etc .............................. 1-2 c. Firm's subconsultants, their qualifications, their roles in this project .. ............................... 1 -4 d. Firm's other current or recently completed similar services within the past 5 years with other public or private agencies .................................. ............................... 1 -9 e. List and quantity of firm's (and subconsultants if applicable) equipment including survey instruments, computers, plotters, vehicles .................... ............................... 1 -15 f. List of at least three (3) client references to include organization name, contact person, telephone number (s), and e -mail address .................... ............................... 1-18 g. Project Manager's education, experience, and any special consideration ........................... 1 -19 h. Key Project Members' education, experience and any special consideration ........................ 1 -20 i. Firm's project organization and coordination structure ........... ............................... 1 -23 j. Project Understanding /Project Approach ..................... ............................... 1-24 11. Firm's Office Location and Other Forms a. List the location of all offices (firm and sub - consultants) involved with this project and approximate distance (in miles) and time (in hours) to City Hall ....................... . ............ 11 -1 b. Company Information /Signature Sheet p. 14 ................... ............................... 11-2 c. Receipt of any addenda issued .............. ............................... • • • . • • . . • • • . • ... -3 d. MBE Certification ............................................ ...........................II -5 e. Summary of Litigation, if none please so state .................. ............................... 11-5 0 m.sultin,g engineers I. Firm's Qualifications !\ 1rwvvv 44 p consubag engrneers 1. Firm's Qualifications a. List of all of firm's employees, their qualifications, their roles in providing desired City services Inw ood Key Personnel Licensure/Training Role Education: B.S., Civil Engineering, University of Florida, 1990 Project David Coleman, PE License: Professional Engineer, Florida, 1995, No. 49469 Manager Certification: Qualified Stormwater Management Inspector Education: M.S., Environmental Engineering, University of Florida, 1975 B.S., Engineering Science and Mechanics, University of Principal - Alex Hull, PE Florida, 1974 in- Charge License: Professional Engineer, Florida, 1979, No. 21769 Education: Master of Engineering, Civil Engineering, University of Florida, 1998 Quality Co -Co Wu, PE B.S., Civil Engineering, National Taiwan University, 1983 Control License: Professional Engineer, Florida, 1991, No. 44198 Certification: Advanced Maintenance of Traffic (MOT), 2013 Education: B.S., Mechanical Engineering, University of Central Florida, 2003 Deputy Project David Ledgerwood, PE License: Professional Engineer, Florida, 2009, No. 70585 Manager/ Certification: Utility Coordination Certification, Florida Utility Coordination Project Engineer Committee Education: B.S., Civil Engineering, University of Central Florida, 1992 Maintenance of Derek Dean, PE License: Professional Engineer, Florida, 1997, No. 51905 Traffic Certification: Advanced Maintenance of Traffic (MOT), 2005 Education: B.S., Environmental Engineering, University of Central Florida, 2010 License: Engineer Intern, Florida, 2010, No. 1100014454 Engineering Ashley Bixler, El, CFM Certifications: Certified Floodplain Manager, 2014, No. US -14 -07773 Support Qualified Stormwater Management Inspector, 2013, No. 28442 Education: B.S., Civil Engineering, Georgia Institute of Technology, 2007 B.S., Business Management, Georgia Institute of Railroad Geoff VanBueren, PE Technology, 2001 Coordination/ License: Professional Engineer, Florida, 2012, No. 74786 Permits Certification: Advanced Maintenance of Traffic (MOT), 2011 Education: B.S., Community and Regional Planning, Iowa State Laura Clark, AICP University, 2003 Public Public Involvement License: American Institute of Certified Planners, Florida, 2011, Involvement No. 025014 Design /CADD Jack Montanez Education: CADD, ITT Technical Institute, 2007 Support b. Firm's and employees' certifications and registration with regulatory agencies, professional organizations, etc. Inwood Consulting Engineers, Inc. State of Florida Board of Professional Engineers Attests that Inwood Consulting Engineers Inc tai is authorized under the provisions of Section (71.023, Florida Statutes, to offer engineering services to the public through a Professional Engineer, duly licensed under Chapter 471, Florida Statutes. Expiration, 2/28 /2015 CA Lic. No: Audit Nu: 2282W 500870 Certificate of Authorization 7074 State of Florida Board of Professional Engineers Attests that Alexander Blue Hull IV., P.E. Is licensed as a Professional Engineer under Chapter 471, Florida Statutes &p —,iom 2/2812016 PT* l ie. No: Audit No: 228201509205 21769 State of Florida Board of Professional Engineers Attests that Co -Co Wu, P.E. Is licensed as a Professional Engineer under Chapter 471, Florida Statutes &piratiotr. 2;28 /2015 P.E. Li, No: Audit No: 228201509625 44198 State of Florida Board of Professional Engineers Attests that David K. Ledgerwood, P.E. Is licensed as a Professional Engineer under Chapter 471, Florida Statutes Expiration: 2/28/2015 P_E. Lie No: Audit No: 228201514478 70585 State of Florida Board of Professional Engineers Attests that David G. Coleman, P.E. Is licensed as a Professional Engineer under Chapter 471, Florida Statutes &pirotiore 2/28/2015 PT Lie No: Audit No: 228201526386 49469 State of Florida Board of Professional Engineers Attests that Derek Dante Dean, P.E. Is licensed as a Professional Engineer under Chapter 471, Florida Statutes &pirotion: 2/28/2015 P.E. Lit. No: Audit No: 228201504735 51905 State of Florida Board of Professional Engineers Attests that Geoffrey Charles Van Bueren, P.E. Ak Is licensed as a Professional Engineer under Chapter 471, Florida Statutes Expiration: 2128/2015 P.E. Lk. No: Audit No: 228201510836 74786 Inwood Consulting Engineers, Inc. - continued Laura E. Clad:, MCP rr r State of Florida Department of State I certify from the r - I -t tins ff 'e teal INWOOD CONSUL'rNG ENGINEERS, MC. is corpcm[i n rgmrized under the laws of the State of Flrn9drt filed w November 12 1991 The document number ofthis corporation is P93000079443 - I fimher ceru� dull said c iii —to i has paid all tees due this office through December 31, 2014, that its most recent annual tepoe/tmiform business rcpon was filed on February 26, 2014, mid its .antis is active. I further certify that said corporation tuts not filed P.nicles of Dlmolml,, G(.rn .urJrrrMy Lwd wd ter G— SmJ Ifik' St— of Florida a Ta166aarr, ar CoP",, Air LLr Tn`rNV -eta th dale fFlbrua , '014 ■ Secretary of State To.awemwm wncernr r m r W,../�.h. .w.: Ill, and feet rmm.. nee v.stru.i.ms elaplaYM. hnps'. /efile sw.Ga.org /cenvan'er.h�nJ ASSOCIATION OF STATE FLOODPLAIN MANAGERS, INC. CERTIFICATION BOARD OF REGENTS Ashley A. Bixler, CFM ASFPM CERTIFIED FLOODPLAIN MANAGER ! - cFNr 11ie rnetiean `Z"raff u� Safety Services Association a Co -co W u gas '/tended Florida Advanced Refresher Tramin9 course � 9 vso /2013 a «ni o � M q ' K ......e.e..Ft v...— _.�v. Ina, our. un unr h AMERICAN TRAFFIC SAFETY SERVICES ASSOCIATION � SAFER ROARS SAVE LIVES This is to affirm that ID 437 Derek Dean has satisfactorily completed the Florida Advanced Refresher Work Zone "Traffic Control Course Date Complete: 09J13 /2012 StahlS: PASS Location: Kissimmee Instructor: Mi. Richard Cabrera Date Refresher Course Required: 09/13/2016 (fertificate of (nualifitation Tills crrtffleo fbnt Geoff VanBueren b,n sap.�0a „ / »J� Il .nnri ../eArF. f7odAn ttnl'n .rd L,><or Advanced Maintenance of Traffic .�..,,� 0U do, -rt --- a s -I(y_ .II NavemGer_. 20.1. aRe T2*CTT rrio,i art 16 J �.,_- c. Firm's subconsultants, their qualifications, their roles in this project fieolecnnical Hill Enulronmental consultanis. Inc. Geotechnical and Environmental Consultants, Inc. Geotechnical and Environmental Consultants, Inc. (GEC) based in Orlando, Florida, with offices in Kissimmee, is well -known in the consulting industry for its leadership and specialized expertise. Established in 1991, GEC is celebrating 23 years serving the entire state of Florida. GEC is privately owned and managed by Gary Kuhns, PE, GEC President and Chief Engineer; Dan Stanfill, PE, Senior Vice President; Mike Byerly, PE, Vice President; and Chris Meyer, PE, Vice President. • City of Clermont Greater Hills Water Treatment Plant • Lake Grove Water /Wastewater Treatment Plant • City of Lady Lake Wastewater Treatment Plant Expansion • City of Clermont East Side Waste Water Treatment Facility Expansion • City of Clermont Sunburst Lane Water Treatment Plant Expansion • Lake County Lake Grove Water /Wastewater Treatment Plant • Lake County Dora Pines Water Treatment Plant Improvements • Orange County Northwest Water Reclamation Facility/ Phase III Expansion GEC utilities engineering experience serving Central Florida clients includes: Seminole, Orange, Osceola, Brevard, and Lake Counties, Orlando Utilities Commission (OUC), Osceola TOHO Water Authority, as well as the Cities of Orlando, Kissimmee, St. Cloud, Maitland, Cocoa, Apopka, Sanford, and Daytona Beach. GEC core professional services include geotechnical engineering, environmental consulting, ground penetrating radar (GPR), and construction materials testing for public works infrastructure and utilities projects throughout Florida. GEC's Representative Experience: • City of Apopka NW Cities Reclaimed Water Main • Orange County Western Regional Water Transmission Line • Orange County Barnett Park Wastewater Collection System • City of Orlando I -Drive Improvements /Sewer Lift Station Improvements • Brevard County Force Main and Lift Station, Barefoot Bay • Orange County (14 Pump Stations) • Orange County Iron Bridge Master Pump Station • City of Orlando Lake Nona Pump Station and Force Main • Orange County Tangelo Park Subdivision Wastewater Collection System Improvements • City of Orlando Reclaimed Water Distribution System Expansion /Consery II • Seminole County Black Hammock Water Main Phase II Post Design Services • City of Sanford Water and Reuse Water Pipeline Extensions • City of Deltona Water and Sewer Distribution Improvements ,Southeast �n� :Suriire fn Y 9r� /z f�J t II1 1<<.4 Southeastern Surveying and Mapping Corporation Founded in 1972, Southeastern Surveying and Mapping Corporation (SSMC) is an independent, employee -owned Land Surveying, Subsurface Utility Location and Geographic Information Systems (GIS) company that serves the Southeast region's leading private and public organizations. Traditional Land Surveying by SSMC applies experience and a complete surveyor's toolkit including Terrestrial Mobile and Static LiDAR, GPS systems, electronic field books and proprietary data collection format, and graphic production using MicroStation, ESRI ArcGIS, AutoCAD Land Development, AutoDesk Civil 3D, Revit, CAiCE, and GEOPAK tools to deliver compatible data in ready -to -use form to our clients and team members. SSMC's Subsurface Utility Designation services using Ground Penetrating Radar (GPR), Location services (Test Holes) and Coordination using safe Vacuum Excavation are performed by SSMC's trained /experienced/ equipped staff on a daily basis. SSMC's Utility Division additionally offers Closed Circuit Television (CCTV) with Laser Profiling Pipe Inspection Services; Concrete Imaging; and Materials Thickness Services (Ultrasonic Testing) services. Geographic Information Systems are created and maintained by SSMC's GIS Division, since 1989. This division has years of experience designing, developing digital maps and collecting data for their associated databases. Additionally, the GIS Division offers Mobile Imaging for Pavement Mapping and Condition Assessment. The SSMC team prides itself on its repeat public sector and private sector clients (some for 42 years) that they work with demonstrating their team's continued ability to control costs, produce a quality product, and meet deadlines. c. Firm's subconsultants, their qualifications, their roles in this project (continued) SSMC's Representative Experience: City of Ocoee • Continuing Professional Surveying and Mapping Services Contract (to include Subsurface Utility Designation /Location /Mapping Services), City of Ocoee (Ongoing since 1990), select project experience: - 1210 Russell Dr. Pipe Replacement (1 ac.), Utility Location 2014 - Bluford Ave, & Orlando St. Intersection Improvements, Utility Designation /Location 2013 - Lakewood Ave, Delaware St & 7th St Utility Improvements 2013 - Bluford Ave Drainage Improvements - Additional Area (2,200 LF), Utility Coordination for Drainage Improvements 2012 - Fountains at Tivioli Place, Plat Review 2014 - Arden Park South (98.5 ac.), Plat Review 2013 - Basking Ridge Court Cemetery (1 ac.), Boundary Survey 2013 - Bluford Ave. & Orlando St. Intersection Improvements, Utility Designation /Location 2013 - Bluford Ave. Drainage Improvements - Area /ROW, Topographic Survey, (10) Descriptions /Sketches 2013 f A qP tS Barnes, Ferland and Associates, Inc. (MBE) Barnes, Ferland and Associates, Inc. (aka BFA Environmental) is an environmental /utility engineering, hydrogeological consulting and surveying and mapping firm that specializes in natural resource management, permitting and design solutions. Services include solid and hazardous waste management; hydrogeological and wellfield development; environmental and contamination assessment; disaster debris management; water resources management and permitting, water, wastewater and reuse master planning. BFA also provides our clients with comprehensive services related to the utility coordination, survey, subsurface exploration, protection and utility relocation of existing utilities located within State, County and City rights -of -way subject to roadway widening and improvements. BFA is a certified minority /disadvantaged business with more than 10 state and local government agencies. BFA is DBE certified with FDOT in Florida, DBE certified with Louisiana DOTD, and HUB Certified with SWUC in North Carolina, and a graduate of the SBA 8(a) program. We are committed to providing reliable, responsive, cost - effective and high quality environmental services to both our large and small clients. City of Altamonte Springs • Cranes Roost Pump Station & Force Main Upgrades, Utility Designation /Location, as Sub - Consultant 2014 • SR 434 Median Improvements; Utility Verification 2013 • Gateway Dr. Ext. Final Design (1.68 mi), Utility Designation, (20) Test Holes, as Sub - Consultant 2012 • Altamonte Station Parking Garage Concept (3ac.), Topographic Survey Active • Galloway Dr. Realignment, Design Survey, Utility Location, as Sub - Consultant Active City of Apopka • 6th St. (Alabama Ave. to US 441) (4,300 LF), Utility Location /Coordination 2014 City of Casselberry • Forest Brook Force Main Replacement, Utility Designation /Location, as Sub - Consultant 2014 • Stormwater /Storm Drain Rehabilitation, CCTV Inspection, as Sub - Consultant 2014 City of Clermont • Force Main Route Survey (6 mi.), Utility Designation/ Location, as Sub - Consultant 2014 BFA is a Florida firm with its main headquarters in Orlando, Florida, and satellite offices in West Palm Beach and Miami, Florida; New Orleans, Louisiana; and Rutherfordton, North Carolina. BFA currently has a professional staff of 18 engineers, hydrogeologists, designers, environmental scientists, surveyors, and three administrative personnel. Much of BFA's success is due to the quality and experience of their staff. The Principals of the company maintain a "hands - on" approach and staff projects with highly experienced and trained individuals. BFA's Professional Engineers, Geologists, and Surveyors have a comprehensive understanding of current and pending regulations and new technologies, BFA can provide a full range of environmental engineering services from water resource development through the disposal of wastewater effluent. • Master Planning for Comprehensive Water, Wastewater, Reclaimed Water, Solid Waste and Stormwater Utility Systems • Hydraulic Modeling and Analysis • Regulatory Audit and Compliance • Water Quality Compliance Evaluations • Design and Construction Management for Water Supply, Treatment, Storage, High Service Pumping and Distribution Systems • Design and Construction Management for Wastewater Collection, Transmission, Treatment, Effluent Disposal and Residuals Management Systems • Design and Construction Management for Reclaimed Water Facilities • Design and Construction Management for Solid Waste Facilities • Facility Valuation Determinations • Utility System Rate and Charge Determinations • Financial Planning including Funding Assistance through State Revolving Fund (SRF) • Program and Rural Utility Service as well as Conventional Financing BFA's Representative Experience: • City of Ocoee: Continuing Survey and Mapping Services: Plat reviews, Topographic Surveys, Boundary Surveys, Legal Descriptions, Specific Purpose Surveys, Construction Staking • Orange County Utilities: Lee Vista Blvd to Innovation Way (2013): Topographic Survey and Control Survey of a 5 -mile large pipeline corridor • Orange County Utilities: Apopka Sweetwater and Ramir Subdivisions (2012): Topographic Survey, Control Survey and SUE services, designation and excavation of utilities • Orange County Utilities: Park Manor Water and Sewer (2011): Topographic Survey of over 7 miles of the Park Manor development. Excavated over 100 utilities. • City of Orlando: Marks Street (2013): Topographic Survey, Control Survey and SUE services • Florida DOT District 5: Pineda Causeway: Performed underground utility Designation and excavations for engineering design, Prepared sketches and test hole reports. • Florida DOT District 5: State Road 200: Underground utility Designation for engineering design. • Florida Turnpike Enterprise: U.S. 27 Interchange — Designation and excavations of underground utilities for the design of new interchange. Prepared sketches and test hole reports. Aclus Engineering, LLC (MBE) Aclus Engineering, LLC is a civil and environmental engineering firm located in Orlando, which provides engineering services to the private and public sectors in Central Florida. Aclus' engineering services include water, municipal wastewater, industrial wastewater, reuse, stormwater, construction, funding assistance and other general consulting services. Daniel Magro, PE, is a Principal with Aclus Engineering and has 14 years of experience in the civil and environmental engineering of water, reclaimed water, and wastewater projects providing preliminary planning, detailed design, permitting, and construction services. Mr. Magro has been responsible for many municipal water and wastewater projects in the Central Florida area, overseeing efforts in civil, mechanical, electrical, geotechnical, architectural, and structural engineering. The most notable projects completed by Mr. Magro include design and rehabilitation of water /wastewater treatment plants ranging in size from 1.0 to 8.0 MGD, and municipal water distribution, sewer collection, sewer pumping /transmission systems, Representative Experience: • Polk Commerce Centre Utility Master Plan, Auburndale, FL, 2013: Prepared a water, wastewater, and reuse master plan for the City's new Polk Commerce Center utility service area. • Water Main Extensions, Avon Park, FL, 2012: Project Manager for design and permitting of 12.5 miles of new 6, 8 and 10 inch water mains within service area. Northeast Water System Improvements, Lake Hamilton, FL 2009: Project Manager for design, permitting, and construction administration for the replacement of 7,500 feet of 6, 8 and 12 inch water mains within an 80 unit residential neighborhood. Obtained $750,000 grant from the CBDG program. Main Street Water Line Improvements, Lake Hamilton, FL, 2009: Project Manager and engineer for the design, permitting, and construction administration for replacement of 2,700 feet of 12 inch directional bore water main piping. Obtained grant /loan funding of $400,000 from SRF ARRA stimulus funds. • US 27 Water /Wastewater Line Relocations, Dundee, FL, 2008: Project Manager for the design, permitting, and construction administration of 4,000 feet of 8, 10 and 14 inch water and force main utility relocations as a result of a FDOT road widening project. c. Firm's subconsultants, their qualifications, their roles in this project (continued) '• CS_o_ut ieist1'n 5urveying�" \-\ Education: SCC, Continuing Education for Licensing Requirements SUE & James Petersen, PSM Mean High Water Surveying Training FDEP Methodology Surveying License: PSM, Florida, 1990, No. 4791 Services Education: Dutchess Community College Liberal Arts Coursework Numerous FDOT and Equipment Training Seminars SUE & Darryll DeMarsh, GPRT Certification: Ground Penetrating Radar (GPR) Certified Confined Space Safety Awareness Training Surveying Services Maintenance of Traffic (MOT) Trained and Certified Geotecholcal and Enulronolenlal consultants, Inc. Education: M.S., Civil Engineering, University Christopher Meyer, PE of Florida, 1994 Bachelor of Science, Civil Engineering, University of Florida, 1991 Geotechnical Engineer License: Professional Engineer, Florida, No. 49328 Southeastern Surveying and Mapping Corp. .,aLB is ., u Professional Surveyor and Mapper Business License t al 11 rte .1 ll \It— 11 aOtt,eVAlco Lw Geotechnical and Environmental Consultants State of Florida Board of Professional Engineers Artcscs chat Geotechnical & Environmental Consultants, Inc. A is outhorhed under the provisions of .023, Florida Statutes, to offer engineering services t o the public through a Professional Fngineer, duly licensed under Chapter 471, Florido Smtutes. Expiratian� 22.9/3(115 CA Lie. No: Audit N. 228201 iO3438 Certificate of Authorization 5882 n.rxn twnrr t �.. 1 41191 w.d.r ht�a F �i i.1i .UO A ter Iv ai+....s $,1y¢G31M1 Professional Surveyor and Mapper license t"', 11c P— nl I lift, 17111-..l., SUUIu J 11ES 1, 1DDI PF.TF.RSFh l .213 Cn1PPEK —u. \tAI[LAYII, tI, 12l't >SI I',t atHiCl (_nHl State of Florida Board of Professional Fngineers Attests that Christopher Paul Meyer, P.E. ,AK Is licensed as a Professional Engineer under Chapter 471, Florida Statutes Expiration: 2128/2015 P.E. Lic. Nn Audit No: 228201515797 49328 Aclus Engineering Barnes, Ferland and Associates State of Florida Board of Professionol Engineers A'. Cf` 9 Sh(I Aclus Engineering LLC �s achor zed under c pro nF Sea n 471023, FI.,;do Smu ctes m offer ng n ing scn,cas a the public ehroug o Profusion.I Engineer, dale ilceescd andcr Chopt ­ 471, Fordo 3wuaes. E proc S u? cJA 01 ( AudrN 2S2i,1'0¢n C of Am horrrof�on ;ti ^,r, State of Ftorida Board of Professional Fngineers a.tex„ t1­ Daniel Magro, P.E. e� Is licensed os o Professionol Engineer under Chopter 471, Florido Stotutes rz uan� 2,2a201b P.F. L" No: paa A,,dit No: 22S20IS1fi726 64'£18 State of Florida Board of Professional Engineers A,,C ,S 6 thal Barnes, Ferland And Associates, Inc. o mhar and under the pru txians of Sec n 71.023, n. id* Soaruttr, ra offer ­g­ mg a kl w the public through a Profc..tonal Engi—, duly V--d aoder Chapter 471, rlorda Sro .0 E p _ N 21,15 CA tic. N. A ,f No. 228 A <U WA C—ifk— d Autho6-6on t>g'N) Fmiessional Suneyor and Mapper Mew (m.i.rn su 1 hYL�.VI'(XK Hn .( al 1 ­fl Ro Aclus Engineering, LLC (MBE) Education: Master of Science, Environmental Engineering, University Permitting/ of Central Florida, 2005 bid- ability and Daniel Magro, PE Bachelor of Science, Chemical Engineering, Florida Institute uctability of Technology, 2001 reviews reviews License: Professional Engineer, Florida, No. 64708 �3FA Barnes, Ferland and Associates, Inc. (MBE) William Miller, PLS Certification: PLS, Florida, No. LS 5010 Survey Training /Certification: OSHA Hazwopper Certificate OSHA Confined Space Certification Subsurface Ron Smith, SUE Crew Maintenance of Traffic (Intermediate Level) Utility Leader Metro Tech Locator American Red Cross First Aid Exploration Ground Penetrating Radar (Sensors and (SUE) Software) Aclus Engineering Barnes, Ferland and Associates State of Florida Board of Professionol Engineers A'. Cf` 9 Sh(I Aclus Engineering LLC �s achor zed under c pro nF Sea n 471023, FI.,;do Smu ctes m offer ng n ing scn,cas a the public ehroug o Profusion.I Engineer, dale ilceescd andcr Chopt ­ 471, Fordo 3wuaes. E proc S u? cJA 01 ( AudrN 2S2i,1'0¢n C of Am horrrof�on ;ti ^,r, State of Ftorida Board of Professional Fngineers a.tex„ t1­ Daniel Magro, P.E. e� Is licensed os o Professionol Engineer under Chopter 471, Florido Stotutes rz uan� 2,2a201b P.F. L" No: paa A,,dit No: 22S20IS1fi726 64'£18 State of Florida Board of Professional Engineers A,,C ,S 6 thal Barnes, Ferland And Associates, Inc. o mhar and under the pru txians of Sec n 71.023, n. id* Soaruttr, ra offer ­g­ mg a kl w the public through a Profc..tonal Engi—, duly V--d aoder Chapter 471, rlorda Sro .0 E p _ N 21,15 CA tic. N. A ,f No. 228 A <U WA C—ifk— d Autho6-6on t>g'N) Fmiessional Suneyor and Mapper Mew (m.i.rn su 1 hYL�.VI'(XK Hn .( al 1 ­fl d. Firm's other current or recently completed similar services within the past 5 years with other public or private agencies Project 1 MONTGOMERY /WHITE ROAD RCW INTERCONNECT CITY OF OCOEE, FLORIDA Owner's Name and Address City of Ocoee, Capital Improvement Program, 150 North Lakeshore Drive Ocoee, FL 34761 construction services. Preliminary: Inwood developed critical preliminary engineering concepts for various pipeline alignment alternatives through the complicated corridor. The preliminary engineering design alternatives were drawn in CAD and submitted to the City for review. Cost estimates for various options were provided. Alternatives took into account a number of major utilities located on the project including, overhead electric/ communications, overhead transmission power, pressure mains, and buried communications. Inwood prepared numerous alternative alignments to reduce the impacts to the surrounding utilities. The final alignment was agreed upon which allowed the final design to begin. Final Design: Inwood performed the final design that included preparing and revising utility plan, profile, and details sheets, The final design required the callouts of connecting feeder and looped pipes, tie -in to existing services and placing air relief valves at appropriate locations. The project contained two areas where special attention was required. The first was the crossing of Clark Road. Clark Road is a fairly large signalized intersection with limited right -of -way and major utilities including Progress Energy Transmission poles. The second location was a wetland /lake area located just west of Clark Road. This area consisted of limited right -of -way and existing transmission poles. Both locations were directionally bored to avoid impacting the existing utilities and minimize the maintenance requirements at the Clark Road intersection. Inwood submitted three phased submittals at 60 %, 90% and Final Plans. Each submittal consisted of plans, specification, cost estimates, and responses to previous submittal review comments. Permitting Services: Inwood assisted the City in obtaining the Right -of -Way Utilization permit for crossing County roadways. Construction engineering and inspection services: Inwood attended the pre- construction meeting and provided periodic construction observation. Construction Cost: $970,000 Contract Completion: April 2012 I iIod v ting engineers Project 2 MARKHAM WOODS ROAD UTILITIES - PHASE II SEMINOLE COUNTY, FLORIDA Owner's Name and Address Seminole County Environmental Services, 500 West Lake Mary Boulevard Sanford, Florida 32773 Preliminary Engineering: Inwood provided preliminary design and redesign for the improvements of the water, sewer and reclaimed mains. Inwood prepared alternatives to the original alignments based on meetings with the County and their General Engineering Consultant (GEC). Inwood provided preliminary engineering to develop the final design alignment and concept to be carried forward, Final Design Services: Inwood provided final design and redesign of 3,860 LF of 24 -inch DIP reclaimed water main, 7,710 LF of 20 -inch DIP reclaimed water main and 6,860 LF of 12 -inch PVC water main. Inwood prepared plan, profile and detail sheets for the 50 %, 90% and 100% submittals, technical specifications and construction contract documents Permitting Services: Inwood obtained two separate FDEP construction permits for the potable water main portion of the project. An FDEP permit was not required for the reclaimed water main as the project was within the County's Reclaimed Water Service Area Boundary. Construction Administration: Inwood provided construction administration services for this project. Inwood prepared conformed documents, responded to the contractor's request for information, performed periodic site inspections, attended construction progress meetings, prepared record drawings and obtained FDEP "clearance for use" Certifications. Construction Cost: $4,007,910 Contract Completion Date: October 2009 1nwooCI� con =ulting engineer= for the project. A significant portion of this project was constructed via trenchless technology (directional bore). Project 3 DESIGN /BUILD SR 37 BRIDGE REPLACEMENT — JACK & BORE CROSSING CSX RAILROAD POLK COUNTY, FLORIDA Owner's Name and Address Florida Department of Transportation, 801 North Broadway Avenue Bartow, FL 33830 The SR 37 Design Build project required substantial coordination efforts with multiple agencies to acquire the necessary permits (including CSX Transportation, SWFWMD, ACOE, the City of Mulberry, and FDEP). The coordination efforts with CSX were necessary to jack and bore 100 LF of 48 -inch steel casing pipe beneath the railroad from SR 37. The permit was required to gain access to the property and perform the necessary construction operations. The permitting process took approximately five months to complete with multiple rounds of review and correspondence. The permit was obtained on time and the project began construction activities as scheduled. Final Design: Inwood's design was done in accordance with CSXand theAmerican Railway Engineering and Maintenance - of -Way Association ( AREMA) guidelines and standards to include the installation of a 42 -inch steel casing. The steel casing was designed to meet all loading requirements, corrosion protection, spacers, and casing seals. Ultimately, the casing was upsized to a 48 -inch steel pipe due to reduction in cost caused by its availability in the market. Permitting Services: Inwood prepared CSX permit applications, prepared application drawings, attended pre - application meetings, and responded to CSX review comments and requests for additional information. The CSX permit for the project was obtained in February 2013. Construction engineering_ and inspection services: Inwood closely coordinated with the Contractor and CSX representatives with bore pit locations and pit configuration. Inwood performed site visits, responded to the Contractor's requests for information (RFI), and provided interpretation of CSX and AREMA standards. Contract Completion: June 2014 Inwood I consulting engineers Project 4 ROUSE ROAD WATER & WASTEWATER UTILITY IMPROVEMENTS —SECTION 1 ORANGE COUNTY, FLORIDA Owner's Name and Address Orange County Utilities 9150 Curry Ford Road Orlando, FL 32825 Description of Services Provided Summary of Work: Orange County Utilities (OCU) contracted with Inwood to provide the preliminary and final design, permitting and construction services for utility improvements on the Rouse Road Section 1 project from Lake Underhill Road to south of East Colonial Drive (SR 50). OCU constructed the new facilities in conjunction with the Public Works roadway widening project along Rouse Road, The project consists of the relocation of approximately 7,900 LF of 24 -inch DIP transmission water main and 70 LF of jack and bore of 42 -inch steel casing. The project also includes the replacement of over 800 LF of 8 -inch and 10 -inch gravity sewer mains and the refurbishing of 21 existing manholes. All improvements and relocations were designed and installed within publicly owned County and State right -of -way. In the same capacity as his proposed role, Mr. Coleman was the Project Manager, Engineer of Record, and performed the day -to -day management of the project. He oversaw all tasks and activities during design, permitting, and construction. Preliminary: Preliminary design services were provided for the improvements of the transmission water main and gravity sewer mains including alternatives to the alignments based on meetings with the County Project Manager and County inspection reports. Initial alternatives included directional bore of the new 24 -inch water main under the existing SR 408 bridge and ramps to minimize impacts and restoration. Open -cut installation was used in lieu of directional bore due to coordination with the Orlando - Orange County Expressway Authority (OOCEA) for crossing and installation in the publicly owned SR 408 right -of -way. Final Design: Inwood completed final design services for approximately 7,900 LF of 24 -inch DIP transmission water main, 70 LF of jack and bore of 42 -inch steel casing, replacement of over 800 LF of 8 -inch and 10 -inch gravity sanitary sewer, and the refurbishing of 21 existing manholes. Permitting: Florida Department of Environmental Protection (FDEP) drinking water and wastewater general permits were obtained for the project. An FDOT Utility Permit was also prepared and obtained for the proposed 24 -inch transmission water main crossing under the SR 408 bridge within the right -of -way. The FDOT Utility Permit required extensive coordination with the OOCEA, who handles the review and approval of FDOT Utility Permits within SR 408 right -of -way. Construction Services: Inwood oversaw construction administration services including routine site visits, responding to Contractors' requests for additional information, reviewing shop drawings, witnessing pressure tests, reviewing change order requests, reviewing bacteriological test reports, and obtaining final FDEP clearance to place the water main into operation. Construction Completion: June 2014 in:�P onsf od v ltin g engineers Project 5 CHAPMAN ROAD UTILITIES RELOCATIONS — FROM SR 426 TO SR 434 SEMINOLE COUNTY, FLORIDA Owner's Name and Address Seminole County Environmental Services, 500 West Lake Mary Boulevard Sanford, FL 32773 -741 Description of Services Provided Summary of Work: Inwood completed the preliminary design, final design, permitting, and construction administration services for the utilities improvements design necessitated by the Seminole County Public Works' Chapman Road widening project. The utility relocation engineering services were accomplished through a Joint Project Agreement between Seminole County Environmental Services and Seminole County Public Works. The project included utility relocation design for approximately 6,500 LF of 16 -inch DIP water main and over 6,800 LF of 12 -inch PVC force main. The project was designed and installed within County -owned right -of -way. Preliminary Design Services: Inwood developed critical preliminary engineering concepts for various pipeline alignment alternatives. The preliminary engineering design alternatives were drawn in CAD and submitted to the County for review. Preliminary cost estimates for these options were provided. Tapping assemblies were recommended, since the water main is a primary transmission main through the corridor, and shut downs of the existing service were not desirable. The final alignment /concepts were approved, which allowed the final design move forward. Final Design Services: The final design of the 6,500 LF of 16 -inch DIP water main and 6,800 LF of 12 -inch PVC force main was completed and included preparing the utility plan, profile, tabulation of quantities, general notes, and details sheets. Since the utilities would be installed by the roadway Contractor, the phasing of construction was closely reviewed and considered during design. The project also contained large areas of muck removal, which was a considerable factor when analyzing the project construction phasing. Plans, specifications, and estimates were prepared and submitted at 60 %, 90 %, 100% and Final intervals. Inwood closely coordinated with the County's Program Managers, who reviewed and distributed project submittals and served as project management for the County. Permitting Services: Inwood prepared and obtained general permits from the FDEP drinking water and wastewater Sections for construction of the new water and force mains. The FDEP Wastewater construction permit included coordination with the City of Orlando since the system was pumped to the City's Iron Bridge Regional Treatment Plant. Though a Right -of -Way Utilization permit was not required during the design phase, utility plans were also submitted to the Seminole County Right -of -Way Department for review and approval. Construction Phase Services: Construction administration services were provided for this project, including review of shop drawings, responding to contractor requests for information, performing periodic site inspections, witnessing pressure tests, attending construction progress meetings, and preparing final record drawings. Construction services also included close coordination with Seminole County Environmental Services' Inspectors and the roadway project CEI firm. Construction Completion Date: July 2013 ln�pd rs Project 6 WEST TOWN PARKWAY EXTENSION — LAUREL STREET TO ORANGE AVENUE SEMINOLE COUNTY, FLORIDA Owner's Name and Address City of Altamonte Springs, 225 Newburyport Avenue Altamonte Springs, FL 32701 Description of Services Provided Summary of Work: This project included the extension of West Town Parkway from the intersection of Laurel Emu= Street and West Town Parkway and extended northeast to Orange Avenue. In conjunction with the roadway work, the City also included the installation of 900 LF of new 12 -inch sanitary sewer system, 2500 LF of 12 -inch water main, and 2400 LF of 20 -inch reclaimed water main. Since the connection points of the new water and reclaimed water main extensions was outside the limits of the roadway construction, the project also included more than 1200 LF of directional bore to minimize the impacts to the existing roadway and avoid a large existing concrete box culvert. Preliminary: Inwood developed critical preliminary engineering concepts for various pipeline alignment alternatives and manhole placement through the corridor. The preliminary engineering design alternatives were drawn in CAD and submitted to the City for review. Cost estimates for various options were provided. The final alignment was agreed upon which allowed the final design to begin, Final Design: Inwood performed the final design that included preparing and revising utility plan, profile, and details sheets. The final design required the callouts of connecting feeder and looped pipes, tie -in to existing services and placing air relief valves at appropriate locations. Other than the intersection with the West Town Parkway extension project, there was not any roadway improvements proposed on Orange Avenue. With limited right -of -way, Inwood proposed to install the new mains along Orange Avenue using directional bore method. This minimized impacts to the roadway and existing utilities and also allowed the mains to be installed under a large existing concrete box culvert. Inwood submitted four phased r r submittals at 60 %, 90 %, 100% and Final Plans. Each submittal consisted of plans, specification, cost estimates, and responses to previous submittal review comments. Permitting Services: Inwood prepared and obtained FDEP drinking water and wastewater permits for the installation of the water and sanitary sewer mains. An FDOT Utility Permit was also prepared and obtained by Inwood for the connection of the new mains within the SR 434 right -of -way. Inwood also coordinated with Seminole County Right -of -Way Department on the directional bore of the new water and reclaimed water mains along Orange Avenue and addressed all county concerns. Construction engineering and inspection services: Inwood oversaw construction administration services including routine site visits, responding to Contractors' requests for additional information, reviewing shop drawings, witnessing pressure tests, reviewing change order requests, reviewing bacteriological test reports, obtained final FDEP clearance to place the water and wastewater mains into operation, and prepared final project record drawings. Contract Completion Date: August 2013 I/Iwood ► ransulting engineers e. List and quantity of firm's (and subconsultants if applicable) equipment including survey instruments, computers, plotters, vehicles Inwood Consulting Engineers, Inc. Vehicles 2 Ford F150 Trucks Field Equipment 1 GoPro Video Camera 1 Camera with GPS locator Steel Probes Tape Measures Printers/Plotters/Scanners 1 Color Digital Printer /Scanner 2 Color Wide Format Plotters 2 Business B/W Printers Computer Equipment DELL Precision 380 Workstations Dual Core CPU with 8 GB of RAM Software Bentley GEOPAK for V8 MicroStation V8 w /FDOT 2004 MicroStation V8i w /FDOT 2010 MircroStation V8 - XM w /FDOT 2008 Microsoft Excel 2013 Microsoft Project 2013 Microsoft PowerPoint 2013 Microsoft Word 2013 Adobe Standard Roxio CD Creator Southeastern Surveying & Mapping, Inc. Communications Equipment 10 Android Cellular Smart Phones Vehicles 57 Ford F150's 5 Ford Explorer 4WD's 1 Ford Escape 4WD XLT 5 Ford 450 Series Flat Beds 3 Chevy Silverado 4WD Printers /Plotters /Scanners 4 Color Digital /Laser Printers /Scanners 2 Digital Printer / Copier/ Scanners 6 Wide Format Printer / Desktop Color 6 Desktop Color Ink Jet Printers 1 Color Wide Format Plotter 2 Business Color Printers Utility Designation /Location Equipment 6 185 Sullair Diesel Compressors 1 Dig Trak Sonde Standard - Range 0'- 50' 5 Noggin Ground Penetrating Radar Units 8 Fisher FPID 2100 Magnetic Metal Locators 3 Metro Tech Model 810 Line Locators 5 Pneumatic Hammers 7 Pneumatic Tamps 1 Radiodetection 18A Sonde - Range 0' -12' 12 VIVAX ProLoc 2 Locators 6 Utilivac Vacuum Excavation Systems 1 500' Sonde Reel 2 Water Probe Systems 10 LMX Ground Penetrating Radar Units Field Equipment 8 Allegro Data Collectors 3 Topcon AT F2 Automatic Levels 19 Topcon GPT Total Stations 1 Topographic Scanner Lifts 16 Fisher FPID 2100 Magnetic Metal Locators 4 Pentex AFL Automatic Levels 1 Riegl USA VZ -400 Laser Scanner 31 Topcon TopSury Data Collectors 3 Sokkia Total Stations 6 Sokkia B2 Levels Field Support Equipment 7 All- Terrain Vehicles w /trailers 2 Jon Boats with trailer 1 Pond Prowler 5 Kodak Digital Cameras Computer Equipment 50 Dell Precision Workstations with DVD / CD Re- writable Drives 30 Dell Business Desktops with CD Re- writable Drives 4 Dell Field Download Stations 1 Proliant 3000 Remote Access Server 2 PowerEdge 860 File and Database Servers 1 APC Server Uninterruptible Power Systems 1 PowerEdge 2950 GPS Application and Data Server Transmitter 1 Public File Transport Server (FTP Server for SSMC) 4 HP Proliant DL 380 Domain and Application Servers 1 HP Proliant DL120 SQL Server 2 Ultrium LTO Autoloader Tape Backups 1 R1500XR Uninterruptible Power System (UPS) Southeastern Surveying & Mapping, Inc. - Continued Software Acrobat Acrobat Professional Adobe (Illustrator, Reader) Adobe Photo Shop Elements AutoCAD 2000 /LDD2 /LDD3 /2006 -2014 AutoDesk Civil 3D 2006 -2014 Bentley GEOPAK for V8 CAiCE (00.5, Visual PE 9 and PE 10) Cartegraph v.8.1 CEFB v.12,17.98 Corpscon Version 6 EFBR NT ESRI (ArcEditor 10.1 and Arclnfo 10.1) FDOT Electronic Field Book Processor FDOT 3 wire Level Adjustment Program Hector Vector NT Hitachi - Recognizer v.2.0 for ACAD Hitachi - Tracer v.3.0 for ACAD InterVideo WINDVD 4.0 Microsoft Office Suite 2003, 2007, 2010, 2013 Micro PAVER v.6.1.6 MicroStation V8 w /FDOT 2004 MicroStation V8i w /FDOT 2010 MircroStation V8 - XM w /FDOT 2008 Sokkia Pro Link StarNet v.6 StarLev v.6 TDS Foresight DXM Terra Sync v.2,40 Topcon (Link, PC -CDU, CE -CDU, Pinnacle, Tools) Riscan Pro Stadic LiDAR v1.8 Trimble (Geomatics Office, GPS Survey, Pathfinder Office) Roxio Easy CD Creater Mapinfo v.2.0 Microsoft Dynamics NAV Barnes, Ferland and Associates, Inc. Land Surveying Equipment Nikon DTM -310 Total Station (1) Carlson Explorer w /software Topcon FC -2500 Data Collector (1) Wooden tripods (3) ES -105 Topcon TTL Station Nikkon AS -2 Automatic Level (1) Topcon GR -3 GPS Receivers (2) Schoenstedt Metal Locators (2) Philladelphia Level Rod (1) SUE Equipment Trailers (2) Utilivac System (2) Sullair Pogo Tamper (2) Carlson Software Packages (2) Metrotech 810 & RD 400 Pipe / Cable Locators LMX100 Ground Penetrating Radar Sullair 183 Compressor (2) Sullair Jackhammer (2) Topcon GPS Unit (GR -3) w/ accessories Standalone License AutoCAD MAP Metrotech vLocPro2 — Locator Geotechnical and Environmental Consultants, Inc. Date Placed in Model Received Service Manufacturer Equipment Received 1.11 -92 1 -11 -92 AND Digital Scale EP -20KP 3806616 New 8 -17 -99 O.O.S. AND Digital Scale GF -1200 14610520 New 3 -1 -02 3 -1 -02 Ohaus Digital Scale EORW60 F047119500842 New 11 -3 -96 11 -3 -96 Despatch Convection Oven LDB1 -69 -4 155648 New 1 -1 -92 1 -1 -92 Tempcon Oven N8620 -10SP 0182 -109 New 7 -20 -92 O.O.S. Cress Muffle Furnace C1006H 9107 New 3.22 -07 4 -2 -07 Thermolyne Muffle Furnace F6020C 1249070236371 New 1 -2.09 1 -2 -09 Durham Geo Liquid Limit Device S -271 684 New 10 -1 -92 10 -1 -92 Orion pH meter 290A 002857 New 10 -1 -01 10 -1 -01 Genesesy 20 Spectro Meter 4001/4 3SGG265002 New 9 -29 -92 9 -29 -92 Nilsson Resistivity Meter 400 40 -377 New 4 -1 -06 4 -20 -06 Atkins Digital Therm. 39658 -K CT031006032- 39658 -K New 7 -21 -03 7 -21 -03 Rainhart Sieve Shaker 635 3521758 New 5 -11 -92 5 -11 -92 Humbolt Sample Splitter H -3985 2/91 New 9 -1 -92 9 -1 -92 Hamilton Beach Mixer 936 -2 71159360002 New 1 -1 -92 Out of Bouyoucon Scale Hydrometer 152H 74265 New Service 11 -24 -92 11 -24 -92 Fisher Scientific Hot Plate 11- 5000 -4H 692920805615 New 8 -6 -01 8 -6 -01 DGE Sample Extruder M -410 1796670001 New 8 -14 -01 8 -14 -01 GeoTac Load Frame Sigma -1 1127 New 10 -8 -01 10 -8 -01 Durham Geo Soil Lathe S -57628 SL -1 New 4 -1 -04 4 -1 -04 Mitutoyo Digital Caliper CD -8 "CS 04077870 New 4 -24 -06 4 -26 -06 Fowler Dial Caliper 52- 008 -018 -0 48457873 New Arista Stopwatch SW -1 New 1 -2 -09 1 -2 -09 Humboldt Penetrometer B62120 -0 -16 083391432 New 9 -20.08 11 -25 -08 Ohaus Digital Scale EP4102P M316112921229 New 7 -31 -10 8 -7 -10 Rainhart Sieve Shaker 657 3521750 New 8 -8 -11 8 -9 -11 HACH pH Meter MM110 126004 New f. List of at least three (3) client references to include organization name, contact person, telephone number (s), and e-mail address 1. ORGANIZATION: CITY OF OCOEE MONTGOMERY/WHITE RCW MAIN 150 North Lakeshore Drive, Ocoee, FL 34761 Contact: Al Butler, Dir. of Support Services, City of Ocoee 407 - 905 -3100 x 1543, abutler @ci.ocoee.fl .us Summary of Work: The Montgomery /White Road RCW Interconnect project included the directional bore of approximately 6,000 feet of 16 -inch and 2,100 feet of 4 to 12 -inch reclaimed water main. The project provided interconnects of the City's existing systems and allowed for reclaimed water service for surrounding neighborhoods. Utility services included preliminary engineering, final design, permitting, and construction services. 2. ORGANIZATION: ORANGE COUNTY UTILITIES ROUSE ROAD UTILITY IMPROVEMENTS 9150 Curry Ford Road, Orlando, FL 32825 Contact: Claudia Paz, Project Manager 407 - 254 -9707, Claudia.Paz @ocfl.net Summary of Work: Orange County Utilities (OCU) contracted with Inwood to provide the preliminary and final design, permitting, and construction services for utility improvements on the Rouse Road - Section 1 project from Lake Underhill Road to south of East Colonial Drive (SR 50). OCU constructed the new facilities in conjunction with the Public Works roadway widening project along Rouse Road. The project consists of the relocation of approximately 7,900 LF of 24 -inch DIP transmission water main and 70 LF of jack and bore of 42 -inch steel casing. The project also includes the replacement of over 800 LF of 8 -inch and 10 -inch gravity sewer mains and the refurbishing of 21 existing manholes. All improvements and relocations were designed and installed within publicly owned county and state right -of -way. 3. ORGANIZATION: SEMINOLE COUNTY ENVIRONMENTAL SERVICES CHAPMAN ROAD WIDENING 500 West Lake Mary Boulevard, Sanford, FL 32773 -741 Contact: James Monahan, PE, Project Manager 407 - 665 -2039, jmonahan02 @seminolecountyfl.gov design for approximately 6,500 LF of 16 -inch DIP water main and more than 6,800 LF of 12 -inch PVC force main. The project was designed and installed within County -owned right -of -way. 4. ORGANIZATION: CITY OF ALTAMONTE SPRINGS WEST TOWN PARKWAY EXTENSION 225 Newburyport Avenue, Altamonte Springs, FL 32701 Contact: Karen McCullen, PE, BCEE, Senior Engineering Project Manager 407 - 571 -8335, KMcCullen @altamonte.org Summary of Work: This project included the extension of West Town Parkway from the intersection of Laurel Street and West Town Parkway and extended northeast to Orange Avenue. In conjunction with the roadway work, the City also included the installation of 900 LF of new 12 -inch sanitary sewer system, 2,500 LF of 12 -inch water main, and 2,400 LF of 20 -inch reclaimed water main, Since the connection points of the new water and reclaimed water main extensions was outside the limits of the roadway construction, the project also included over 1,200 LF of directional bore to minimize the impacts to the existing roadway and avoid a large existing concrete box culvert. 5. ORGANIZATION: FLORIDA DEPARTMENT OF TRANSPORTATION SR 37 DESIGN -BUILD 801 North Broadway Avenue, Bartow, FL 33830 Contact: Richard Howard, PE, FDOT PM 863 - 519 -2769, RichardHoward @dot.state.fl.us Summary of Work: The SR 37 Bridge Replacement was an FDOT design -build project located at the North Fork of the Alafia River improvement project consists of the widening of the existing two lane rural roadway to a 4 -lane divided low - speed (45 mph) urban roadway. A 48 -inch jack and bore crossing of the CSX Railroad was designed and permitted as part of the project. The 9 -month process of coordination and permitting associated with the CSX railroad crossing was key to this project. Summary of Work: Inwood oversaw the preliminary design, final design, permitting, and construction administration services for the utilities improvements design necessitated by the Seminole County Public Works' Chapman Road widening project, Inwood provided utility relocation engineering services necessitated by the roadway and drainage improvements project accomplished with a Joint Project Agreement between Seminole County Environmental Services and Seminole County Public Works, The project included utility relocation g. Project Manager's education, experience, and any special consideration Inwood has assembled a strong team that has a vast amount of experience performing the requested engineering services throughout the state. This varied experienced is detailed throughout this SOQ. Regardless of the size and scope of this project, our staff's attention to detail and a clear understanding of the City's needs will ensure timely and cost - effective results. David Coleman, PE, Principal and co- founder of Inwood, will serve as the Project Manager and key point of contact for the City. Mr. Coleman's common sense approach and his ability to communicate clearly have allowed him to successfully coordinate many complex projects for more than 24 years. Mr. Coleman, Inwood's proposed Project Manager, has managed nearly 50 miles of utility pipeline transmission projects in his career. Education: B.S., Civil Engineering, 1990. Some of Mr. Coleman's specific experience for special consideration follows: UCF /Seminole County 20 -inch Force Main Design (Seminole County Public Works) September 1999 - September 2000 — Project Manager responsible for all aspects of the project. The project included utility design services and construction engineering and inspection (CEI) services for a 4,680 LF of 20 -inch force main and 1,100 LF of directional bore 20 feet below the Little Econlockhatchee River using 20 -inch high density polyethylene pipe. This project was completed on a fast track design basis. Markham Woods Road Utilities - Phase I & Phase II (Seminole County Environmental Services) February 2008 December 2008 — Project Manager responsible for overall completion of the project. Utility design, permitting, and construction services for the construction of over 37,300 feet of 12 -inch potable water main, and 24 -inch reclaimed water main on Markham Woods Road from Lake Mary Boulevard to Markham Road and on Markham Road to Lake Markham Road. Montgomery/White Road RCW Interconnect (City of Ocoee) January 2010 — March 2011— Utility Project Manager responsible for utility design, estimates, permitting and construction services. The Montgomery /White Road RCW Interconnect project included the directional bore of approximately 6,000 feet of 16 -inch and 2,100 feet of 4- to 12 -inch reclaimed water main. West Town Parkway Utilities (City of Altamonte Springs) December 2009 - January 2013 — Utility Project Manager responsible for utility design, estimates, permitting, and construction services. The project began at the intersection of Laurel Street and West Town Parkway and extended northeast to Orange Avenue, a distance of 0.340 miles, The proposed roadway typical section was a two -lane divided urban roadway with 12 -foot travel lanes, 4 -foot bike lanes, and a raised 22 -foot grassed median. Sidewalks and landscaping were provided on both sides of the roadway. Stormwater runoff was collected in curb inlets and roadside swales and piped to a dry retention pond. Utility improvements included a new 12 -inch sanitary sewer system, 2,300 LF of 12 -inch water main (515 LF installed by directional bore), and 2,300 LF of 20 -inch reclaimed water main (450 LF installed by directional bore). SR 64 Final Design — Lena Road to Lorraine Road, Manatee County, Florida (FDOT District One) June 1999 — December 2010 — Utility Project Manager responsible for utility design, estimates, permitting, and construction services. The project was the final design and permitting to widen 2.8 miles of SR 64 from a two -lane rural road to a six -lane urban facility. Included in the design were bridge culvert replacements, signalized intersections, retention facilities, utility relocations, lighting and landscaping. The project had 10 UAOs that existed along the alignment that required relocation. Under a Joint Participation Agreement (JPA), Inwood was also responsible for the utility design for Manatee County's facilities located within the project. This included the relocation of more than 15,000 LF of DIP water main and more than 5,000 LF of 12 -inch PVC force main, Services for Manatee County include utility design, cost analysis, permitting, and construction services. h. Key Project Members' education, experience and any special consideration Alex Hull, PE, Principal -in- Change Alex Hull, PE, Principal and co- founder of Inwood, will serve as the Principal -in- Charge for this project. In his 40 years of experience he has served as Principal -in- Charge and Project Manager on numerous transportation and utility projects throughout the state. Mr. Hull will be in direct communication with the Project Manager to ensure that project schedules are being met and resources are available. Education: M.S., Environmental Engineering, 1975; B.S., Engineering Science and Mechanics, 1974. Concise Relevant Experience. Consumers /Lake Hayes Water Transmission Main — (Seminole County Environmental Services) September 2000 - December 2000. Principal -in- Charge responsible for plans production and staff allocation. Approximately 20,000 total of 24 -inch and 30 -inch pipe and connections to existing water mains. The project also includes the acquisition of easements from existing property owners. CR 516 (Palm Bay Road) Design — Minton Road to Robert J. Conlan Boulevard, Brevard County (FDOT District Five) September 2007 — December 2011. QC Officer responsible for shop drawing review. This project included final engineering design and permitting to widen approximately five miles of CR 516 from a four -lane suburban to a six -lane divided urban arterial roadway. A bridge widening over 1 -95, signalized intersections, retention facilities, utility relocations and noise barrier walls were included services. David Ledgerwood, PE, Deputy Project Manager/ Project Engineer David Ledgerwood, PE, Project Engineer will serve as Deputy Project Manager and the Project Engineer. He will provide utility design, staff direction and subconsultant communication for this project. Mr. Ledgerwood has provided utility design and management services on project utility systems throughout the state of Florida since 2004. Education: B.S., Mechanical Engineering, 2003. City of Winter Park Wastewater Reclamation (Winter Park, Florida) March 2009 — November 2009. Principal -in- Charge responsible for plans production and staff allocation. The design of a 0.75 mgd wastewater treatment plant modification and reclaimed water distribution system. Co -Co Wu, PE, Quality Control Co -Co Wu, PE, Chief Engineer, will provide QA/QC services for this project. Since 1989, Mr. Wu has provided engineering design services on a variety of projects. He serves as Inwood's full -time QA /QC Manager on all design projects focusing on standards compliance, constructability and consistency. Education: M.S., Civil Engineering, 1988; B.S., Civil Engineering, 1983. Concise Relevant Experience: West Town Parkway Extension (Cityof Altamonte Springs) December 2009 - January 2013. QC Officer responsible for quality control of construction plans, This project includes the extension of West Town Parkway and utility design services. The project begins at the intersection of Laurel Street and West Town Parkway and extends northeast to Orange Avenue, a distance of 0.340 miles. The proposed roadway typical section will be a 2 -lane divided urban roadway with 12 -foot travel lanes, 4 -foot bike lanes, and a raised 22 -foot grassed median. Sidewalks and landscaping will be provided on both sides of the roadway. Stormwater runoff will be collected in curb inlets and roadside swales and piped to a dry retention pond. A new sanitary sewer and watermain will also be designed to serve future demand along the new alignment. Concise Relevant Experience: MontgomerylWhite Road RCW Interconnect (City of Ocoee) January 2010 — March 2011. Project Engineer responsible for utility design, estimates, permitting and construction services. The Montgomery/White Road RCW Interconnect project included the directional bore of approximately 6,000 feet of 16 -inch and 2,100 feet of 4- to 12 -inch reclaimed water main. West Town Parkway Utilities (City of Altamonte Springs) December 2009 -January 2013. Project Engineer responsible for utility design, estimates, permitting, and construction services, The project began at the intersection of Laurel Street and West Town Parkway and extended northeast to Orange Avenue, a distance of 0.340 miles. The proposed roadway typical section was a two -lane divided urban roadway with 12' travel lanes, 4' bike lanes, and a raised 22' grassed median. Sidewalks and landscaping were provided on both sides of the roadway. Stormwater runoff was collected in curb inlets and roadside swales and piped to a dry retention pond. A new sanitary sewer and water main was also designed to serve future demand along the new alignment. Utility improvements included a new 12 -inch sanitary sewer system, 2,300 LF of 12 -inch water main (515 LF installed by directional bore), and 2,300 LF of 20 -inch reclaimed water main (450 LF installed by directional bore). SR 64 Final Design— Lena Road to Lorraine Road, Manatee County, Manatee County (FDOT District One) June 1999 — December 2010. Engineering Intern responsible for utility design, estimates, permitting, and utility coordination relating to FDOT roadway improvement project. The project was the final design and permitting to widen 2.8 miles of SR 64 from a two -lane rural road to a six -lane urban facility. Included with this roadway widening project was significant utility relocations services including a 42 -inch water main. The utility services involved the relocation of the County's water and sewer facilities which consisted of over 5,000 feet of 42- inch potable water main and more than 500 feet wastewater force main ranging from 6 inches to 14 inches in diameter. Rouse Road Utilities Design and Bidding (July 2002 — July 2008). Engineering Intern responsible for utility design specifications, estimates, and construction services. This project was the utility design, permitting, and construction services for the relocation of over 88,700 feet of potable water main, gravity sewer, and wastewater force main. The project required the relocation of two wastewater pump stations and modifications to a third pump station in conjunction with roadway widening and drainage improvements from Lake Underhill Road to north of Corporate Boulevard. Derek Dean, PE, Maintenance of Traffic Derek Dean, PE, Associate Principal, will provide Maintenance of Traffic evaluation and design services for this project. He has served as Project Manager on roadway and transportation projects throughout Florida since 1992. He is Inwood's subject matter expert on Traffic Control Plans and is certified by FDOT in Work Zone compliance. Education: B.S., Civil Engineering, 1992. Concise Relevant Experience: SR 415 Final Design — Reed Ellis Road to Acorn Lake Road, Volusia County (FDOT District Five) August 2005 — August 2014. Project Engineer responsible for maintenance of traffic and signing and pavement marking plans. This project involved the reconstruction of a 5.3 -mile two -lane undivided rural highway to a four -lane divided urban arterial with a 22 -foot median. The project also included a four -foot bike lane, a 12 -foot wide multi -use asphalt trail, and a 12 -foot noise wall. Palm Bay Road Design — Minton Road to Robert J. Conlan Boulevard, Brevard County (FDOT District Five) September 2007 — December 2011. Senior Engineer responsible for traffic control plans, signal and signing and pavement marking plans. This project included final engineering design and permitting to widen approximately five miles of CR 516 from a four -lane suburban to a six -lane divided urban arterial roadway. A bridge widening over 1 -95, signalized intersections, stormwater retention facilities, utility relocations and noise barrier walls were included services. Ashley Bixler, El, Engineering Support Ashley Bixler, El, Engineering Support will provide utility coordination, plans production, specifications preparation and design support for the project. Education: B.S., Environmental Engineering, 2010. Concise Relevant Experience: Evergreen Park Drainage Improvements (Orange County Public Works) March 2008 — October 2011. Engineering Intern responsible for plans preparation. The project involved the design and permitting of a swale with concrete overflow weirs to provide better stormwater conveyance for the western portions of the Evergreen Park Subdivision. Wakulla Way Canal Restoration Alternatives Evaluation (Orange County Public Works) April 2012 — April 2013. Engineering Intern responsible for report and plans preparation. The project involves development and comparison of alternatives to correct chronic erosion of the canal banks near Wakulla Way. Geoff VanBueren, PE, Project Engineer Geoff VanBueren, PE, Project Engineer will provide railroad permitting and coordination for this project. Mr. VanBueren recently completed similar services on Inwood's SR 37 project in Polk County. He was instrumental in permitting a 48 -inch jack and bore crossing of the CSX railroad in Mulberry. His recent experience is vital to the success of this project. Education: B.S., Business Management, 2001; B.S., Civil Engineering, 2007. Concise Relevant Experience: Design /Build SR 37 Bridge Replacement — Jack & Bore Crossing CSX Railroad FDOT District One) August 2012 — Ongoing. Engineering Intern /Project Engineer responsible for railroad coordination and permitting The SR 37 Design Build project required substantial coordination efforts with multiple agencies to acquire the necessary permits (including CSX Transportation, SWFWMD, ACOE, the City of Mulberry, and FDEP). The coordination eff orts with CSX were necessary to jack and bore 100 LF of 48 -inch steel casing pipe beneath the railroad from SR 37. The permit was required to gain access to the property and perform the necessary construction operations. The permitting process took approximately nine months to complete with multiple rounds of review and correspondence. The permit was obtained on time and the project began construction activities as scheduled. Clarke Road Intersection Modifications (City of Ocoee) January 2010 —April 2011. Engineering Intern responsible for design modifications to accommodate additional intersection improvements including coordination with municipal clients, permitting agencies, private developers and utility companies within a compressed schedule. This project included roadway design, signalization plans, signing and pavement marking plans as well as cost estimates and contract documents. Laura Clark, AICP, Public Involvement Laura Clark, AICP, Transportation Planner will provide Public Involvement services for this project. Ms. Clark's key areas of expertise include PD &E Studies, ETDM, sociocultural effects evaluation, MPO Long Range Transportation Plan (LRTP) Updates, development and comprehensive plan review, Developments of Regional Impact, and public and stakeholder involvement. Education: B.S., Community and Regional Planning, 2003. Concise Relevant Experience: Work Program Public Hearing Support (FDOT District Five) 2009 - 2011. Assistant Project Manager /Transportation Planner for the District Five Work Program Public Hearings Contract. Responsibilities include providing overall task coordination including the development of videos and website to inform the public of upcoming meetings and highlighted projects. Chapman Road Design — SR 426 to SR 434 — Phase 1 (Seminole County Public Works) August 2006 — September 2007. Transportation Planner responsible for coordination of meeting logistics and public notification through newsletter mail -outs and brochures. Project involved plans update and production of construction plans for the reconstruction of Chapman Road. Jack Montanez, Design /CADD Technician Jack Montanez, CADD Technician will provide design and CADD support for this project. He has been providing CADD, and other graphic services since 2007 for civil engineering design projects for the FDOT and municipal government clients throughout Florida. Education: CADD coursework. i. Firm's project organization and coordination structure Inwood's team structure and key personnel are illustrated in the following organizational chart. More information regarding our project understanding, project approach, and management plan follow this page. i i Geoff VanBueren, PE Laura Clark, AICP Railroad Coordination/ Public Involvement (9) Permits (8)a SUBCONSULTANTS PERMITTING /BID- ABILITY AND GEOTECH SURVEY CONSTRUCTABILITY REVIEWS GEC Southeastern Surveying & Mapping Corp. Aclus Engineeing, LLC (MBE) Christopher Meyer, PE (22) James Petersen, PSM (35) Daniel Magro, PE (13) Darryl] DeMarsh, GPRT (20) SURVEY /SUE Barnes, Ferland and Associates, Inc. (MBE) William Miller, PLS (31) Ron Smith ( # ) Years of Experience j. Project Understanding The Inwood team has thoroughly reviewed the City's RFQ No. 1401, Engineering Services for Ocoee West Sanitary Transmission Project and has an excellent understanding of the scope of the project. The City is seeking a qualified firm /team to provide engineering services for the construction of approximately 21,400 feet of 12 -inch to 20 -inch diameter transmission force main and a regional master lift station to reroute half of the existing flows, relieve overloaded collection systems along SR 50, and increase overall conveyance capacities to the City's Wastewater Treatment Facilities (WWTF). Since the design of the master lift station will be performed by the City, coordination with the connection of the transmission force main to the master lift station is required. There are also several locations where existing or designed systems will connect to the new transmission main. Along with a thorough review of the RFQ, the Inwood team has also walked the project corridor and reviewed the following documents: • Ocoee West Wastewater Utility Plan, August 2008 (REI) • Western Force Main Route Evaluation — Revision #2, June 3, 2011 (REI) • Bluford Avenue Stormwater and Utility Improvements Project, July 2013 • Florida Central Railroad (FCR) Facility Encroachment Application Package /Requirements, April 1, 2009 Based on the information presented at the pre - proposal meeting, the City has already secured a FCR railroad crossing permit on the project, and the selected firm will be responsible for the remaining crossings. Inwood is very familiar with permitting through CSX and similar railroad entities. We recently prepared and obtained a permit through CSX for a 48 -inch steel casing to convey stormwater to a pond on our SR 37 design /build project in Polk County, Florida. The process included coordination with numerous local entities and took nearly 5 months to obtain. We are also currently preparing a CSX Facility Encroachment Permit for a new pump station adjacent to the Sunrail Station in Lake Mary, Florida; so we are very knowledgeable about the procedures, regulations, and requirements of local railroad entities. We have assembled our team to provide all of the required services including survey, geotechnical investigation, utility design, permitting, and bidding assistance. Since Inwood has completed a number of utility projects with the City under our Continuing Engineering Contract, we have a very good understanding of the City's planning needs, design standards and overall project management. From our past project experience and research of this project, our team has extensive knowledge to successfully complete the West Sanitary Transmission Poject on schedule and under budget. n Our approach to the project will begin with meeting with the City to discuss the project, determine specific areas of concern, and understand all City expectations. Following the Project Initiation Meeting with the City, the Inwood Team will start collecting all available information including, but not limited to, records, maps, aerials, reports, all easements, right -of -way records, roadway plans, record drawings, soils investigation reports, and all codes pertinent to execution of the Project. As stated above, we have already begun this process in preparation of this proposal. One of the first things we did was to pull a utility design ticket for the corridor through Sunshine 811 to identify the utility /agency owners (UAO's) located on the project. Utility coordination is going to be a very important aspect to the overall success of this project. Both David Coleman and David Ledgerwood have been performing utility coordination services on City, County, and FDOT projects throughout the state for over 10 years. In fact, David Ledgerwood is certified in utility coordination through the Florida Utility Coordination Committee. Inwood has also completed a number of City of Ocoee engineering design projects in the area giving our team a very good understanding of the utilities that will be encountered along the corridor. • Final Conceptual Downtown Ocoee Sewer Plan - Project Approach Analytical Results, March 18, 2014 (REI) Preliminary Desig Potential utility crossing location at FCR Railroad and Bluford Avenue From our Sunshine 811 design ticket, six UAO's were identified along the transmission force main route. We began contacting the UAO's to identify the facility types, material, and location. Some of the facilities noted in our research are the City's potable water main along Bluford Avenue, Duke Energy's pole line throughout the project, and Lake Apopka Natural Gas main located at Wurst Road. The City also maintains an existing gravity sanitary sewer main along the north side of Wurst Road and an above ground storage facility along the south side of Wurst Road. Along with the existing facilities, we are aware of future facilities including the City's future downtown sewer plan. This plan was closely reviewed and instrumental in determining the best preliminary location for the transmission force main along Bluford Avenue. Our evaluation of this area can be seen in Figure 1 of this proposal. Once the major utilities were identified on the project, we prepared a set of aerial plans and performed a site investigation. We collected information on available right -of- way, traffic conditions, drainage structures, and noted any potential issues with the installation of the new transmission force main. One of the biggest concerns that we noted was the limited right -of -way and higher traffic volumes located around the downtown area. This area has several small businesses, Ocoee Middle and Elementary Schools, and serves as a southern route for traffic to access State Road 50. Our peak traffic times were approximately between 8:30 a.m. to 9:15 a.m, in the morning and 3:00 p.m. to 4:15 p.m. in the afternoon. A detailed maintenance of traffic plan will be required in the downtown area to minimize the impacts to the local businesses and schools. Once all our researched information was compiled, we prepared a preliminary alignment that addressed the issues we noted during our evaluation of the corridor. Based on our evaluation of the corridor, horizontal directional drill is the best way to construct this project.This methodof installation is similar to the City's approach on our Montgomery /White reclaimed water main project and offers the least disruptions to the local residents, businesses, schools, and traffic. Our proposed preliminary alignment accounts for daylighting, bore pits, pipe lay -out, and for HDPE pipe assembly /welding locations. An overview of our alignment can be seen in Figures 1 and 2 of this proposal, Not included in the figures is the directional drilling of 180 feet of 12 -inch force main crossing State Road 50 to connect separate systems and provide the City with alternative routing of existing flows. Columbus St. to Franklin St. Further north, our proposed alignment starts with a new 16- inch force main connecting to the existing 12 -inch force main located at Maguire Road and continues east along the south side of Columbus Street, where it ties into a future 16 -inch gate valve designed and constructed by others. There is limited right -of -way and a large roadway cross drain located along the south side of Columbus Street, but the side offers space for HDPE pipe lay -out during the directional drill process and, more importantly, will not impact operations to the Ocoee Fire Station located on the corner of Columbus Street and Bluford Avenue. The Bluford Avenue Stormwater and Utility Improvements project continues from this point and travels north along the east side of Bluford Avenue to just past East Delaware Street, where it terminates with a 16 -inch gate valve. Our proposed alignment continues from this point north along the east side of Bluford Avenue to just past City Hall and then crosses over to the west side of the road. The area in front of the schools provides longer distances for HDPE pipe lay -out and avoids the residential homes and limited right -of -way along the west side of Bluford Avenue. Placement along the east side for this segment of pipe also avoids the future construction of the downtown sewer plan shown in Figure 1 of this proposal. Our proposed alignment continues along the west side of Bluford Avenue to Franklin Street, where it transitions from 16 -inch to 20 -inch in diameter. This is also the point where a 12 -inch force main tees off the transmission main and continues down the north sides of Franklin Street and Lee Street and connects to the City's existing 12 -inch force main located on Ocoee Apopka Road, By staying on the north side of these two roads, we are able to utilize open areas adjacent to the shopping plaza and a large undeveloped parcel on Lee Street for HDPE pipe lay- out and maintain access to residential homes. This segment of 12 -inch force main will require the jack and bored 24 -inch steel casing for the crossing of FCR's railroad. Franklin St. to Master Pump Station From Franklin Street, the 20 -inch force main continues north along the west side of Bluford Avenue, crossing Silver Star Road and up to the FCR railroad. Cross drain on Columbus St. to be avoided FCR Typical for pipelines crossing railroad Though directional drilling with steel pipe is permitted under a variance for FCR railroad crossings, we recommend the jack and boring of a 34 -inch steel casing under the FCR railroad. This will reduce time needed during the FCR permitting process for the crossing and provide the City with access to the main in the case of required maintenance. After crossing the railroad, the force main continues along the north side of Rewis Street and then heads north along the east side of North Lakewood Avenue, where it connects to the new Master Pump Station. Master Pump Station to WWTP The 20 -inch force main will exit the pump station and continue north along the east side of North Lakewood Avenue to Wurst Road. Due to areas of limited right -of -way, existing power poles, and the city's existing gravity sanitary sewer system, our preliminary alignment is proposed along the south side of Wurst Road and on AD Mims Road. The south side of the road also allows for continual access for the small businesses and Springs Lake Elementary School located on the north side of the road. There is also a third crossing of the FCR railroad at the end of Wurst Road before turning onto AD Mims Road. The information provided in this approach is based on Inwood's initial evaluation of the corridor. Once Inwood has received the official notice to proceed, the information outlined here will be reevaluated and further data collection and research will be performed and compiled in a Preliminary Design Report (PDR) for the City's review. The PDR will include conceptual plans, pipeline layouts, permit requirements, preliminary opinion of engineer's cost estimate, conclusions, and final recommendations based on the findings. Inwood's Project Manager, Project Engineer and other selected team members will meet with the City to discuss the PDR and collect the City's review comments. Following the meeting and collection of review comments, Inwood will revise, finalize and provide two (2) hard copies and one digital copy in PDF of the final PDR. Once all the City's comments regarding the PDR have been reviewed and addressed, Inwood will commence with the Final Design phase of the project. Final Design The initial stages of the project Final Design will start with the survey collection. As a part of the Inwood Team, Southeastern Survey and Mapping Company (SSMC) will perform the survey of the right -of -way corridor, all existing utilities, existing drainage, and topographical features. In addition, Barnes Ferland and Associates (BFA) will provide soft dig locate services to verify the depths of the major utilities and project connection points identified in the PDR. Based on the accepted preliminary alignment from the PDR, survey will be performed on only the side of the road that the proposed work is being constructed on. This will reduce time needed for survey collection and also provide a cost savings to the City. Geotechnical and Environmental Consultants (GEC) will perform a geotechnical investigation to facilitate design of the proposed force main. The geotechnical investigation report will be provided and will include information related to soil boring logs and classifications, existing groundwater levels and estimated seasonal high levels, pipe trench preparation, backfill and corrosion protection recommendation, dewatering discharge recommendation and other concerns, The report will also determine potential ground water contamination points along the utility corridor route. If potential contamination points are suspected, groundwater sampling will be performed and t t�_......_...._.. rat -_. _......_.w__.......... tay - ..__.__.. t f Y t f_ qi Sealed casings for Ilarrw yo)g subslpnc s t shall be oroneriv vealwl t • • • - • • . y CROSSSU'TIO.NVIEW B Track � eau eats teJ�� Ih1-- i cis gF14. ! ;- _ -. __._. . . .............................. ............. SannPle "R" ....... 4".. . PIPELINE PROFILE VIEW B A -A FCR Typical for pipelines crossing railroad Though directional drilling with steel pipe is permitted under a variance for FCR railroad crossings, we recommend the jack and boring of a 34 -inch steel casing under the FCR railroad. This will reduce time needed during the FCR permitting process for the crossing and provide the City with access to the main in the case of required maintenance. After crossing the railroad, the force main continues along the north side of Rewis Street and then heads north along the east side of North Lakewood Avenue, where it connects to the new Master Pump Station. Master Pump Station to WWTP The 20 -inch force main will exit the pump station and continue north along the east side of North Lakewood Avenue to Wurst Road. Due to areas of limited right -of -way, existing power poles, and the city's existing gravity sanitary sewer system, our preliminary alignment is proposed along the south side of Wurst Road and on AD Mims Road. The south side of the road also allows for continual access for the small businesses and Springs Lake Elementary School located on the north side of the road. There is also a third crossing of the FCR railroad at the end of Wurst Road before turning onto AD Mims Road. The information provided in this approach is based on Inwood's initial evaluation of the corridor. Once Inwood has received the official notice to proceed, the information outlined here will be reevaluated and further data collection and research will be performed and compiled in a Preliminary Design Report (PDR) for the City's review. The PDR will include conceptual plans, pipeline layouts, permit requirements, preliminary opinion of engineer's cost estimate, conclusions, and final recommendations based on the findings. Inwood's Project Manager, Project Engineer and other selected team members will meet with the City to discuss the PDR and collect the City's review comments. Following the meeting and collection of review comments, Inwood will revise, finalize and provide two (2) hard copies and one digital copy in PDF of the final PDR. Once all the City's comments regarding the PDR have been reviewed and addressed, Inwood will commence with the Final Design phase of the project. Final Design The initial stages of the project Final Design will start with the survey collection. As a part of the Inwood Team, Southeastern Survey and Mapping Company (SSMC) will perform the survey of the right -of -way corridor, all existing utilities, existing drainage, and topographical features. In addition, Barnes Ferland and Associates (BFA) will provide soft dig locate services to verify the depths of the major utilities and project connection points identified in the PDR. Based on the accepted preliminary alignment from the PDR, survey will be performed on only the side of the road that the proposed work is being constructed on. This will reduce time needed for survey collection and also provide a cost savings to the City. Geotechnical and Environmental Consultants (GEC) will perform a geotechnical investigation to facilitate design of the proposed force main. The geotechnical investigation report will be provided and will include information related to soil boring logs and classifications, existing groundwater levels and estimated seasonal high levels, pipe trench preparation, backfill and corrosion protection recommendation, dewatering discharge recommendation and other concerns, The report will also determine potential ground water contamination points along the utility corridor route. If potential contamination points are suspected, groundwater sampling will be performed and tested in accordance with FDEP Rules Chapter 62 -621 and an FDEP permit for the discharge of Produced Ground Water from any Non - contaminated Site Activity will be procured. A report will be provided and will include recommendations to remedy the discharge of contamination when dewatering. The report will be included in the specifications submitted for bidding the project. Following the survey collection and evaluation of all available maps, records, as- builts, existing utilities, and geotechnical information, the final design, plans preparation, and calculations will commence. Final design services will include preparation and submittal of the construction documents at the 60 %, 90 %, and 100% level of completion following Inwood's internal QA /QC and independent constructability reviews. Since the City will be designing the master pump station, Inwood will closely coordinate all connections of the transmission force main to the new pump station. This coordination will be similar to our Pioneer Key Phase I project where Inwood designed the utilities infrastructure and the City designed the subdivision pump station. This project will be designed in accordance with the City's current manual of standards and specifications, FDEP requirements, FCR Railroad requirements, FDOT, and all agencies having jurisdiction over the project. The project will also be designed to serve the project needs related to flows and pressures at the point of delivery. Maintenance of traffic will be reviewed along with the preparation of traffic control plans, including a major emphasis on maintaining pedestrian traffic, to ensure that the proposed transmission force main can be constructed in the areas of limited right -of -way. Our MOT plan will also include details for maintaining all pedestrian access to the schools and local businesses. All construction activities will be proposed in a manner that maintain existing sidewalk traffic or provide plans for temporary sidewalks /paths to allow for local students and parents to walk to the schools. A complete set of 60% construction documents will include plan and profile sheets including survey, existing utilities, new utilities, proposed connections to the existing utilities, all applicable construction details, all sections of draft technical specifications and an opinion of the probable construction cost. Three (3) sets of the drawings and specifications and a digital copy of a PDF file will be provided at the 60% stage. Inwood will meet with the City to discuss and receive the 60% review comments. Upon the completion of the 60% review submittal, Inwood will prepare the 90% design and will submit three (3) copies of "bid- ready" construction drawings, specifications, list of all the 60% review comments and Inwood actions, bid schedule, an engineer's opinion of the probable construction cost, geotechnical report, and one digital copy as a single PDF file for the review by the City. The Inwood team will meet with the City to discuss and receive review comments. BFA will perform utility locates (soft -digs) for potential utility conflicts identified in the 60% design. In addition, Inwood will prepare the permit packages with FDOT, FCR and FDEP. Our Team will incorporate all 90% review comments and will prepare the 100% package. The 100% submittal will include four (4) signed and sealed and two (2) unsigned hard copy sets of construction drawings and technical specifications, a digital copy of the drawings and specifications as a single PDF and a copy of the drawings in AutoCAD Release 14 format to the City. Specifications will be submitted in Microsoft Word format. Quality Assurance /Quality Control Inwood Consulting Engineers is fully committed to meeting all of The City of Ocoee's needs and providing high - quality utility design engineering services. Much of this commitment is fulfilled by our staff's adherence to Inwood's Quality Assurance /Quality Control (QA /QC) Plan, which ensures compliance with the requirements and deliverables identified within the project's scope of services. Throughout the course of a project, QA /QC reviews will be conducted at every submittal to the City in order to ensure the quality of the documentation, methods, training, and maintain the standards set by the Project Manager. Inwood requires all sub - consultants to provide copies of their own QA /QC plan for review or adopt Inwood's plan for use on any assigned tasks. Because a successful QA /QC plan requires adequate time commitment, all Inwood project schedules are developed with hours specifically dedicated to QA /QC. Over the course of time, we have learned that the QA /QC process provides a secondary benefit to projects in the form of increased project awareness for both field and office staff. The added expertise provided by QA /QC staff paired with "a fresh set of eyes" often results in an increased project awareness of additional project issues or considerations. Before any project deliverable is submitted to the City, that deliverable is reviewed by an independent QA /QC reviewer. The QA /QC reviewer is generally a senior level staff member with relevant expertise in the project scope, but is not actively involved in the preparation of the product being reviewed. This process consists of the reviewer documenting their comments and corrections followed by the preparer documenting their concurrence or dispute of those comments and corrections. The QA /QC review process generally includes a QA /QC stamp, which accompanies every deliverable throughout the QA/QC process. After the submittal has gone through Inwood's internal QA /QC process, the documents will then be reviewed for constructability by Daniel Magro, PE with Aclus Engineering. Once all comments have been addressed, the construction documents will be submitted to the City for review. Public Involvement Assistance Public involvement is a very important aspect of any project. It allows a direct interaction between the people working on a project and the people directly affected by it. Acceptance of a proposed project by the public largely depends on the project team's ability to clearly communicate ideas and concepts, as well as actively listen to the concerns of the affected property owners and address those concerns, where feasible. Inwood has developed a reputation for providing excellent public involvement services. Our staff has extensive experience with the public and has provided some form of public involvement on all types of projects. Inwood currently holds the FDOT District Five Community Awareness Contract to assist the Department with public involvement services for many different types of projects throughout the district. Some of the key stakeholders we have identified on this project include: Ocoee Elementary school, Ocoee Middle School, Spring Lake Elementary school, Ocoee Fire Department, 6 church locations, local residents, and numerous businesses. Inwood has the knowledge and capabilities to assist the City in notifying the local community of the project, project schedule, and what to expect during construction. Some of the tools we utilize to clearly convey ideas and concepts to the public include high - resolution aerial imagery and 3 -D renderings; audio - visual slide shows; automated presentations with voice over's or project videos; live webcasts of public meetings/ hearings; meeting handouts; notification of stakeholders and government officials through newsletters, e -mail and mail - outs. Inwood welcomes the opportunity to assist the City with public involvement activities associated with this project. Permitting Permitting will entail preparing, submitting all required permit application packages, responding to RAI's, and providing all necessary services to obtain the required permits for the project. Permits may include, but are not limited to the following: • FDOT Right -of -way Utilization Permit • FDEP Domestic Wastewater Permit • FCR Facility Encroachment Permit Our Project Manager, David Coleman will respond to all requests for additional information to secure all permits. Inwood will pay all fees to the regulatory agencies and will be reimbursed by the City. Bidding Assistance Services After construction plans are finalized, Inwood will provide assistance to the City for bidding the project for construction. Inwood will provide sets of plans and specifications in the format and number required by the City. Inwood will attend the pre -bid conference, respond to written questions from bidders, prepare addenda, clarify or expand bidding documents, attend bid opening, prepare bid tabulation, evaluate three (3) lowest bids, check references, provide recommendation and attend required bid protest meetings. If required, Inwood will provide required documents to re -bid the project. Management Plan Inwood has assembled a collection of talented individuals and firms with extensive experience. The Inwood Team is eager and well prepared to undertake the challenges of this project. David Coleman, PE, will lead this project team and will be involved in the day -to -day decision - making throughout the duration of the project. He will serve as the City's primary point of contact. Mr. Coleman's strong project management skills will ensure that a quality product is produced, that the work product is delivered on or ahead of schedule, and that the lines of communication are always open. Mr. Coleman is a Principal of Inwood, and the City can rely on him for the duration of the contract. To ensure timely completion of work products, Mr. Coleman will fully utilize the resources of his staff. David Ledgerwood, PE, will be the Project Engineer and will work directly with Mr. Coleman on a day -to -day basis. Mr. Coleman and Mr. Ledgerwood have been performing in this capacity on past and current projects for the past 10 years. Their interaction and communication enable all projects to continue seamlessly if one person is out of the office. Mr. Coleman coordinates with subconsultants and often delegates in -house staff assignments to Mr. Ledgerwood. Mr. Ledgerwood is an excellent communicator and constantly keeps project issues at the forefront of key individuals' attention via email and phone calls. Scheduling and Monitoring Plan. At the beginning of this project, the scope of work will be divided into smaller work assignments with responsible individuals assigned to each task with intermediate and final completion dates assigned to each task. Project schedules will be developed using Microsoft Project. The schedules will be set to allow sufficient independent QA /QC and constructability review time prior to submitting work products to the City. Schedules will also be established with sufficient float time, while maintaining the required completion date so unexpected delays in the critical path items will not cause a schedule overrun —we will start as soon as we are given notice -to- proceed and will work diligently on the project deliverables to achieve early submittal dates, Communication will be maintained with the City and with subconsultants through weekly telephone calls, emails, and monthly progress reports. Progress meetings will be planned on the City's schedule, We have developed an overall schedule for this project, which can be seen on the following page of this proposal. Also included in this schedule are Inwood's internal QA /QC review, independent constructability review, and two -week City review periods for each submittal phase. Preliminary Design Layout Survey and Data Collection Final Design & Reviews mom Railroad Coord. /Permitting G Permitting — Bidding and Award Construction to be 8 Month Design, Permittingand Bidding 2014 2015 2016 Oct -Dec Jan -Mar Apr -Jun July -Sep Oct -Dec Jan -Mar RFQ #1401 - City of Ocoee Engineering Services Ocoee West Sanitary Transmission Project I Page 1 -30 RFQ #1401 - City of Ocoee Engineering Services Ocoee West Sanitary Transmission Project I Page 1 -31 • 0 le 20° f fvlr �! V W 4 , . ° N LAKEWOOD LIVE, son C= •, i J ¢p t f' �'` ' W W to wz _ ,A�, "" ' • W . P A t f PETERS H _ ;,� 3 °,� + .CENTRAL PARK a • " LAKE MOXIE"' ¢ s R ! PEACH LAKE 4 . , 9� 11 9 b * 3 ♦ �� ,p n `a 3 Le •° M .�., F 0� _ CSX Railroad `w Ex 0 FP S� Existing Pump Station Existing Gravity SPRING LAKE "J W ' -4 d 11 N II. Firm's Office Location & Other Forms II. Firm's Office Location and Other Forms a. List the location of all offices involved with this project and approximate distance (in miles) and time (in hours) to City Hall. EMIN 0 LE Inwood Consulting SSMC* &. Engineers* �* 29.1 miles 10.8 miles ; Ket (30 min.) Ocoee City Hall Aclus* 15 miles (20 min.) GEC* 19.3 miles (25 min.) BFA* 14.8 miles (20 min.) O RANGE *All of our team offices are within 30 miles of the City of Ocoee's City Hall. b. Company Information /Signature Sheet COMPANY INFORMATION /SIGNATURE SHEET RFQ #1401 FAILURE TO COMPLY WITH THESE RFQ INSTRUCTIONS WILL RESULT IN DISQUALIFICATION OF YOUR QUALIFICATION PACKAGE. PLEASE SIGN BELOW ATTESTING THAT YOU HAVE READ AND UNDERSTAND ALL. RFQ INSTRUCTIONS AND THAT YOU UNDERSTAND THAT THE SUCCESSFUL RESPONDENT WILL BE REQUIRED TO LINTER INTO A LEGALLY BINDING CONTRACT WITH THE CITY OF OCOEE. Inwood C onsulting Engineers, Inc. COMPANY NAME C AUTHORIZED SIGNATURE (manual) 407- 971 -8850 TELEPHONE (INCLUDE AREA CODE) 407 - 971 -8955 FAX (INCLUDE AREA CODE) d cole man inwo odin c .com E -MAIL ADDRESS IF REMITTANCE ADDRESS IS DIFFERENT FROM PURCHASB ORDER ADDRESS, PLEASE INDICATE BELOW: David G. Colem P /Princi al NAME /TITLE (PLEASE PRINT) 3000 Dovera Drive STREET ADDRESS Oviedo, FL 32765 CITY STATE ZIP FEDERAL ID # 59- 321 Individual Corporation Partnership Other (Specify) Sworn to and subscribed before me this 9th day of Septem 2014 Personally Known__ X , or Produced Identification (Type of Identification) Notary Public - State of Florida County of Seminole aSQ S i Y A CS r ._ Signature of Notary Public Tasha L. McGraw Printed, typed or stamped Commissioned name of Notary Public TASHA L MCGRAW MY COMMISSION 0 EE879379 ' EXPIRES February 28. 2017 407 3960163 RFQ #1401 — ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT 14 c. Receipt of addenda Ms s'oI, S. Scott Varulergrift. City \/ I mnavetl Roheit frank September 3, 2014 't r-er orida Com missioners John Grog all, District I Rosemwy \-Nilsen District 2 Rusty Johnson District 3 Joel F. Keller, District 4 ADDENDUM NO: ONE (1) CITY OF OCOEE RFQ #1401 ENGINEERING SERVICES FOR OCOEE WEST SANITARY TRANSMISSION PROJECT This addendum consists of two (2) pages, and shall modify and become a part of the original RFQ documents for Engineering Services for Ocoee West Sanitary 'Transmission Project. Respondents shall acknowledge receipt of this Addenda n in the space provided on this Addendum, Failure to do so may subject the Respondent to disqualification. The RFQ due date remains the same. The following Documents have been posted to Demandstar: 1. Pre - Submittal Conference Sign -in Sheet 8/19/14 2. Presentation at Pre-Submittal Conference 8/19/14 3. Bluford Avenue Stormwater and Utility Improvements Project Drawings Amendments and /or Clarifications to the RFQ documents are as follows: Clarification #1 Firm shall be considered "FIRM /TEAM" when referenced within Request for Qualifications (RFQ) 41401. "FIRM /TEAM" shall include all sub - consultants to support prime Consultants work. Clarification #2 Incidental to and in support with, the City has cause two portions of the project (pre - staged work) to be design and permit and shall, if in the best interest of the City and other mutual parties, cause the construction of those portion of the project before /or during the Consultant design efforts. Consultant shall be required to coordinate with City and others all pre - staged work. Clarification 43 As indicated in Table "Evaluation Criterion" Page 12 responders to the RFQ should include a "Project Approach ". Failure to provide a project approach will result in no points awarded for that category. Amend #1: "C. Scope of Services" Original: The selected Consultant will assist the Cih' by supplying sanitary sewer transmission design, coordination, permitting, and bidding services needed to support the PROJECT. It is anticipated that both geotechnieal and professional land survey services will be needed in support of the design of the PROJECT. Consultant will be tasked with preparing a detailed scope and necessary support services, where the City will procare those services utilizing ongoing professional contracts. Shall be replaced with: The selected Consultant will assist the City by supplying sanitary sewer transmission design, coordination, permitting, and bidding services needed to support the PROJECT w hich shall incl ude all need sub-co service to sup tine effom of the Consultant. City of Ocoee • 150 N Lakeshore Drive - Ocoee, Florida 34761 phone: (407) 905-3 100 - fax: (407) 905 -3194 • www.ococc.org Amend 42: "1. Firm's Qualifications" Original: • List of all firm's employees, their qualifications, and their role ui providing the desired City services, • Firms and employee's certifications and registration with regulatory agencies, professional organizations, etc, • List firm's sub - consultants, their qualifications, and their role in this project. • List of firm's other current or recently completed similar services within the past two 2 years with other public or private agencies. • List and quantity of firm's (and firm's sub - consultants' if applicable) equipment including survey instruments, computers, plotters, vehicles, etc. • List of at least three. (3) client references to include organization name, contact person, telephone number (s), and e -mail address. • Project Manager education, experience and any special consideration • Key Project Members education, experience and any special consideration • Firm's Project organization and coordination structure Shall be replaced with: • List of all firm's employees, then qualifications, and their role in providing the desired City services. • Firm's and employee's certifications and registration with regulatory agencies, professional organizations, etc. • List firm's sub - consultants, their qualifications, and their role in this project. • List of firm's other current or recently completed similar services within the past five 5 ears with other public or private agencies. • List and quantity of firm's (and firm's sub- consultants' if applicable) equipment including survey instruments, computers, plotters, vehicles, etc. • List of at least three (3) client references to include organization name, contact person, telephone number (s), and e -mail address. • Project Manager education, experience and any special consideration • Key Project Members education, experience and any special consideration • Firm's Project organization and coordination structure i e R ce" Tolbert, CPPB Purchasing Agent cc: Evaluation Committee All respondents shall acknowledge this addendum in your qualification package by completing the section below and including in Section II- Firm's Office Location & Other Forms, Respondent. In wood Consulting E ngineers . c. __ Name: David G. Coleman, PE Title: Prind I Proje� ana er__ RTQ 1401 — Addendum 0 2 d. MBE Certification Aclus Engineering, LLC ('H I'l- le I C111 I" 1�111-10(1 I—Bf I I 111 1-1101 Al-10 If T [I Il 111�1 11TF,11-1�1� ...... . . .. ........... . ... A .... ...... ...... .... . ........ ... Y'�I, h 11111111.KI s--ly 0 R, NU ACLUS I.N(;INI.I:IUN(;, INC. MINORI I Y BUSINESS FN I ERPRISE Sl A I ,01 YI AM I DA ( I -H 1 Ft M PRIM SNION At, t:N(; JNI t,k Barnes, Ferland and Associates, Inc. Minority, Women & Florida Veteran Business Certification Barnes, Ferland and Associates, Inc. e. Summary of litigation Inwood Consulting Engineers, Inc. is not and has never been involved in any litigation. is c, -Ider the provietons of 257 and 2GL Florica Statutes fcr a period f-In, '0 0611T2013 06/17/2015 SERVICES O-S QS e. Summary of litigation Inwood Consulting Engineers, Inc. is not and has never been involved in any litigation. Inwood ► consulting engineers 3000 Dovera Drive, Suite 200 Oviedo, FL 32765 407 - 971 -8850 www.inwoodinc.com • rid • UIDA