Loading...
Item #07 Approval of a Construction Manager Agreement with Collage Design & Construction Group, Inc., (d/b/a The Collage Companies) for Pre-Construction Services Related to the Lakeshore Center Expansion Project at a Cost of $26,675. t I Ocoee florlda AGENDA ITEM COVER SHEET Meeting Date: January 16, 2018 Item # Reviewed By: Contact Name: Al Butler, Director Department Director: Contact Number: 407-554-7063 City Manager: tiMO Subject: Approval to execute a construction manager agreement wit Collage Design & Construction Group, Inc., d.b.a., The Collage Companies, for pre-construction services related to the Lakeshore Center Expansion project at a cost of$26,675. Background Summary: The Lakeshore Center Expansion project is being designed by Rhodes + Brito, architects, under a continuing services contract with the city. Given the complexity of the project, procurement of a construction firm to build the facility was undertaken using the construction manager at risk method (CM at Risk), as provided in §255.103, Florida Statutes. This relatively new way of hiring a contractor uses the same qualifications-based approach (Request for Qualifications, or RFQ) used for hiring licensed professionals, such as architects and engineers. This selection method was used because it requires the contractor to be involved in the design of the building, which provides two benefits. First, the contractor can provide input to the design process that could lower the difficulty and cost of construction. Second, the extensive interaction with the plans prior to providing the city with a price for the construction work allows the builder to become very familiar with the plans and for the city to avoid issues related to typical low-bid procurements. Failure of the contractor to understand the plans was a source of continuing difficulty with the building's original construction. Seven firms responded to the CM at Risk RFQ solicitation and the three top-ranked firms, based on their written submissions, were invited to make personal presentations to the selection committee, which made a final ranking of firms. The Ocoee City Commission adopted the selection committee's rankings, with The Collage Companies being the top-ranked firm. Staff has negotiated a basic contract and a price for pre-construction services, where the contractor interacts with the architect and other designers to develop a final set of construction documents. After the plans are completed, The Collage Companies will be asked to provide a price for the construction work and a guaranteed completion date. Section 255.103, Florida Statutes, allows the city to select one of two possible construction pricing options: guaranteed maximum price (GMP) and lump sum price (LSP): "At the option of the governmental entity, the construction management entity, after having been selected and after competitive negotiations, may be required to offer a guaranteed maximum price and a guaranteed completion date or a lump-sum price and a guaranteed completion date, in which case, the construction management entity must secure an appropriate surety bond pursuant to §255.05 and must hold construction subcontracts" [s. 255.103(2), Florida Statutes]. Thus, it is staffs position that the city is free to alter the chosen method of price negotiation up until the time those negotiations are concluded. In its RFQ, the city indicated that it intended to use GMP; however, subsequent to the solicitation being concluded, staff determined that it would be to the city's advantage to use LSP. The advantages to the city of the GMP approach is that it allows the possibility for cost savings if the cost of construction is less than what was anticipated. A shared contingency fund is used to address cost overruns. The disadvantage is that the city has to supervise the procurement of subcontractors and suppliers, which can impose a significant time demand on staff, who are also trying to manage other, less well-defined projects. The advantage of the LSP approach is that it sets a fixed expectation on the price to be paid by the city, and only the contractor bears responsibility for securing subcontractors and suppliers. Under the present situation, where there is high demand for qualified subcontractors and there are several simultaneous projects being managed, it may be in the city's best interest to go with LSP, as there is little chance for prices to go down during construction. Accordingly, the proposed contract contains the language needed for the simpler LSP construction pricing option. Should it ultimately be determined by the parties that a GMP approach is warranted, then the proposed contract published in the RFQ can be utilized to produce the final agreement for construction. Issue: Should the City Commission authorize the Mayor to execute the CM at Risk agreement with Collage Design & Construction Group, Inc., d.b.a., The Collage Companies, for pre-construction services related to the Lakeshore Center Expansion project at a cost of$26,675? Recommendation: Staff recommends that the City Commission authorize the Mayor to execute the attached services agreement with Collage Design & Construction Group, Inc., d.b.a., The Collage Companies, for pre- construction services related to the Lakeshore Center Expansion project at a cost of $26,675. This work will hire the contractor to participate in the pre-construction phase of the work and sets the stage for the contractor to make a price offer, at which time the staff will return to the City Commission for approval of the required contract addendum. The proposed contract supports the LSP approach for construction. This means that several sections of the GMP contract version published in the RFQ have been removed. Should staff decide at a later date to use the GMP approach, additional contract language can be included at the time the construction phase addendum is presented to the City Commission. Because the contractor's review of the contract is still underway, staff additionally recommends that the City Attorney be allowed to make changes in the specific wording of the agreement within the context of the overall presentation of terms and conditions. Attachments: • Proposed CM at Risk services agreement with pre-construction phase pricing. • Pre-construction phase proposal from the selected contractor. Financial Impact: The proposed expenditure of up to $26,675 is included in the Lakeshore Center Expansion project funded by the 2017 General Fund Capital Bond Issue. Any proposed addendum to add the construction phase of work to the agreement will require further action by the City Commission. Type of Item: (please mark with an x'9 Public Hearing For Clerk's Dept Use: Ordinance First Reading x Consent Agenda Ordinance Second Reading Public Hearing Resolution Regular Agenda x Commission Approval Discussion&Direction X Original Document/Contract Attached for Execution by City Clerk Original Document/Contract Held by Department for Execution Reviewed by City Attorney Reviewed by Scott Cookson N/A Reviewed by Finance Dept. ---12,s\312S2_ N/A AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER AT RISK FOR LAKESHORE CENTER EXPANSION PROJECT THIS AGREEMENT made the day of in the year 20 by and between COLLAGE DESIGN AND CONSTRUCTION, INC., d.b.a., THE COLLAGE COMPANIES ("Construction Manager"), a Florida corporation, and the CITY OF OCOEE, a Florida municipal corporation, ("City"or"Owner"). ARTICLE 1 THE CONSTRUCTION TEAM AND EXTENT OF AGREEMENT The Construction Manager accepts the relationship of trust and confidence established between it and the Owner by this Agreement. Construction Manager covenants with the Owner to furnish its best skill and judgment and to cooperate with the Architect of Record in furthering the interests of the Owner. Construction Manager agrees to furnish efficient business administration and superintendence and use its best efforts to complete the project in the best and soundest way and in the most expeditious and economical manner consistent with the interest of the Owner. 1.1 The Construction Team The Construction Manager, the Owner, and the Architect of Record, and any supporting design professions, called the "Construction Team," shall work jointly during design and through final construction completion and shall be available thereafter should additional services be required. The Architect and the Construction Manager shall communicate through the Owner, except as may otherwise be provided in this Agreement or when direct communications have been specifically authorized by the Owner. The Construction Manager shall copy the Owner on all correspondence sent to or received from the Architect or any of its consultants of which the Owner was not copied. The specific representatives of the Construction Team are shown in Exhibit "A" attached. 1.2 Extent of Agreement This Agreement for Pre-construction and Construction Management Services for the Project between the Owner and the Construction Manager supersedes any prior negotiations, representations, or agreements. When drawings, specifications, and other descriptive documents defining the work to be included in the Lump Sum Price(LSP) are complete, an Amendment to the Agreement shall be signed by the Owner and Construction Manager acknowledging the LSP and the drawings, specifications, and other descriptive documents upon which the LSP is based. To expedite the preparation of this LSP Amendment by the Owner, the Construction Manager shall obtain two (2) sets of dated drawings, specifications, and other documents upon which the LSP is based from the Architect via the Owner. The Construction Manager shall acknowledge on the face of each document of each set, that it is the set upon which it based its LSP and shall send one set of the documents to the Owner along with its LSP proposal, while keeping one set for itself. See Exhibits "J" and "K". In addition, the Construction Manager shall supply one electronic set of digitally dated and signed drawings, specifications, and other documents upon which the LSP is based, which is to be used for acquiring related building construction permits from the City. The electronic document set must include a statement that it has the same contents as the paper set. This Agreement shall not be superseded by any provisions/revisions of the documents for construction and may be amended only by written instrument signed by both Owner and Construction Manager. 1.3 Definitions A. Project—The Project is the total work to be performed under this Agreement. The Project consists of permitting and construction for RFQ No. 1801 - Construction Manager at Risk for Lakeshore Center Expansion. B. Owner—City of Ocoee, a political subdivision of the State of Florida. C. Construction Manager — Collage Design and Construction, Inc., d.b.a., The Collage Companies. D. Architect of Record—Rhodes+Brito, Architects. E. Owner's Representatives — Director of Support Services for the City. During the construction phase, the Architect of Record may serve as Owner's Representative. F. Lump Sum Price—The Construction Manager's latest lump sum price. G. Guaranteed Delivery Date — The Construction Manager's latest guaranteed delivery date. H. Contract Documents — This Agreement, the Plans, Specifications, related Construction Documents, RFQ #1801 and all addenda, Construction Manager's Response to RFQ #1801, all written proposals from the Construction Manager, and or any other documents incorporated herein by reference. The general intent of the Contract Documents is to include all items necessary for the proper execution and completion of the scope of the Work by the Construction Manager. All Work mentioned or indicated in the Contract Documents shall be performed by the Construction Manager as part of this Agreement unless it is specifically indicated in the Contract Documents that such Work is to be done by others. In the event the Drawings or the Specifications disagree in themselves or with each other, the Construction Manager shall provide the better quality or better quantity of Work unless otherwise directed by a written addendum to the Agreement. In the event of discrepancies among the Contract Documents, the documents shall be construed according to the following priorities: Highest Priority- Change Order Second Priority- Amendments to drawings and specifications — later date to take precedence Third Priority- Construction Management Agreement Fourth Priority- Specifications Fifth Priority- Drawings Sixth Priority- Request for Qualifications Solicitation Document and all addenda, and all written proposals and responses from Construction Manager. I. Punch List — List of items of work to be completed and deficiencies to be corrected, which items shall not affect the attainment of Substantial Completion. Such items shall be complete or otherwise disposed of prior to final acceptance/completion. J. Schedule of Values —The schedule to be used as a basis for progress payments to be made to the Construction Manager by the Owner during performance of the Work, based on the then current percentage of progress of construction of the Project, subject to the review of the Architect. K. Substantial Completion Date — The date, certified by the Architect, that the Project, or designated portion thereof, is sufficiently complete, in accordance with the Construction Documents and a Certificate of Completion issued, so that the Owner can reasonably utilize the Project, or designated portion thereof, for its intended use. Additionally, complete all items referred to as necessary for Substantial Completion, as defined in Article 2.10 (h) and in the Construction Documents. L. Substantial Completion — The Project, or designated portion thereof, is sufficiently complete, in accordance with the Construction Documents and a Certificate of Completion issued and as certified by the Architect, so that the Owner can reasonably utilize the Project, or designated portion thereof, for its intended use. Additionally, complete all items referred to as necessary for Substantial Completion, as defined in Article 2.10(h) and in the Construction Documents. The only remaining work to be performed is the Punch List. M. General Conditions — Those items that are not specific to any trade and are required for the construction of the Project. Examples of General Conditions items include daily cleanup and safety rails. [Reference 9.2(16)] N. Project Improvements — Shall mean the improvements comprising the utility, stormwater, building, site civil, and landscape improvements for the Lakeshore Center Expansion Project, as identified in RFQ #17_, to be constructed and installed by the Construction Manager pursuant to this Agreement and the Construction Contract. O. Underground Facilities — All pipelines, conduits, ducts, cables, wires, manholes, vaults, tanks, tunnels or other such facilities or attachments, and any encasements containing such facilities which have been installed underground to furnish any of the following services or materials: electricity, gases, steam, chilled water, telephone or other forms of communications, cable television, sanitary sewage, stormwater drainage removal,potable water, traffic, and control systems. P. Final Completion—The following items have been completed or satisfied: 1. Construction of the Project is totally complete (all work as defined in the Contract Documents), and certified as such by the Owner and Architect. 2. The Project is suitable for full use as determined by the Owner and Architect. 3. All Punch list items have been completed or otherwise disposed of or accounted for to the Owner's satisfaction and approval. 4. A Final Certificate of Completion and all other permits and approvals required have been legally and validly issued. 5. Construction Manager's executed Final Releases of Lien have been delivered to the Owner. 1.4 Owner's Construction Budget Owner's funds budgeted and requested for construction of the Project: The Owner's Construction Budget is estimated at $2.5 million, including all Construction Manager fees, costs of the work, and the Owner's and Construction Manager's construction and interface contingencies, as defined in Articles 8 and 9. This acknowledgment of the Owner's budgeted funds is not to be construed as the Construction Manager's LSP. An LSP will be offered by separate documentation, as outlined in Article 7. ARTICLE 2 CONSTRUCTION MANAGER'S SERVICES The services which the Construction Manager shall provide include, but are not limited to, those described or specified herein. The services described or specified shall not be deemed to constitute a comprehensive specification having the effect of excluding services not specifically mentioned. 2.1 Project Management Information System (PMIS) General: 1. Commencing immediately after contract award, the Construction Manager shall implement and shall utilize throughout the life of this Agreement all subsystems of the Project Management Information System hereinafter referred to as PMIS. 2. The reports, documents, and data to be provided shall represent an accurate assessment of the current status of the Project and of the Work remaining to be accomplished and it shall provide a sound basis for identifying variances and problems and for making management decisions. It shall be prepared and furnished to the Owner and the Architect monthly. 3. If requested by the Owner, the Construction Manager shall conduct a comprehensive workshop for participants designated by the Owner and additional seminars as required, to provide instruction. This workshop and the seminars shall facilitate each participant's and the Owner's representatives' use and understanding of PMIS; shall support, in part, the function of organizing in concert with the Architect for the design and construction of the Project; and shall establish, with the full concurrence of the Owner and the Architect, procedures for accomplishing the management control aspect of the Project. 4. The PMIS shall be described in terms of the following major subsystems: A. Narrative Reporting, on a monthly basis, B. Schedule Control, on a monthly basis, C. Cost Control, and estimating, D. Project Accounting, E. Accounting and Payment, and F. Action Reports. 2.2 Narrative Reporting Subsystem 1. The Construction Manager shall prepare written reports as described hereunder. No other PMIS narrative reports shall be required. All reports shall be in 8.5" X 11" format, unless directed otherwise by the Owner. 2. The Narrative Reporting Subsystem shall include the following reports: A. A Monthly Executive Summary that provides an overview of current issues and pending decisions, future developments and expected achievements, and any problems or delays, including code violations found by Permitting Authority. B. A Monthly Cost Narrative describing the current construction cost estimate status of the Project. C. A Monthly Scheduling Narrative summarizing the current status of the overall project schedule. This report shall include an analysis of the various project schedules, a description of the critical path, and other analyses as necessary to compare planned performance with actual performance. D. A Monthly Accounting Narrative describing the current cost and payment status of the entire project. This report shall relate current encumbrances and expenditures to the LSP. E. A Monthly Construction Progress Report during the construction phase summarizing the work of the various subcontractors. This report shall include information from the weekly job site meetings as applicable such as general conditions, long lead supplies, current deliveries, safety and labor relations programs permits, construction problems and recommendations, and plans for the succeeding month. F. A Daily Construction Diary during the construction phase describing events and conditions on the site, as well as, identifying the number of crews, men per crew, and heavy equipment on the project each day. 3. The reports outlined in subsection 2A through E, above, shall be bound with applicable computer reports and submitted monthly during design and construction phases and shall be current through the end of the preceding month. Copies shall be transmitted to the Owner and the Architect and others designated by the Owner's Representative with the monthly pay requisition. Additional copies of the report outlined in subsection 2A shall be bound separately and distributed monthly, as directed by the Owner's Representative. 4. The report outlined in subsection 2F, above, shall be maintained at the site available to the Owner and Architect. A bound copy of the complete diary shall be submitted to the Owner at the conclusion of the Project. 2.3 Schedule Control Subsystem: 1. Master Project Schedule - Within fifteen (15) days of award of this Agreement, the Construction Manager shall submit to the Owner for approval, a Master Project Schedule covering the planning and design approvals, construction, and Owner utilization of the Project. This schedule shall serve as the framework for the subsequent development of all detailed schedules. The Master Project Schedule shall be produced and updated monthly throughout the project. No revisions, activity additions, activity deletions, or logic changes to the Master Project Schedule or any other schedule previously approved by the Owner, shall be made without the Owner's approval. 2. Within ten (10) days after the date of the Owner's issuance of a Notice to Proceed for construction, the Construction Manager shall prepare and electronically submit to the Owner's Representative for approval a construction schedule in sufficient detail to graphically depict the activities contemplated to occur as a necessary incident to performance of the work required to complete the project, showing the sequence in which the Construction Manager proposes for each such activity to occur and duration (dates of commencement and completion, respectively) of each such activity. The Owner shall determine whether the construction schedule developed and submitted by the Construction Manager meets the requirements stated above and such determination shall be binding on the Construction Manager. Failure of the Construction Manager to develop and submit a construction schedule as aforesaid shall be sufficient grounds for the Owner to find the Construction Manager in substantial default and certify that sufficient cause exists to terminate this Agreement or to withhold any payment. Following development and submittal of the construction schedule, as aforesaid, the Construction Manager shall, at the end of each calendar month occurring thereafter, update the construction schedule to show the actual progress of the work performed and the occurrence of all events which have affected the progress of performance of the work already performed or will affect the progress of the performance of the work yet to be performed in contrast with the planned progress of performance of such work, as depicted on the original construction schedule and all updates thereto as reflected in the updated construction schedule last submitted prior to submittal of each such monthly update. Each such update to the construction schedule shall be submitted to the Owner in duplicate. Failure of the Construction Manager to update, revise, and submit the construction schedule as aforesaid shall be sufficient grounds for the Owner to find the Construction Manager in substantial default, and certify that sufficient cause exists to terminate this Agreement or to withhold payment to the Construction Manager until a schedule or schedule update acceptable to the Owner is submitted. No revisions, activity additions, activity deletions, or logic changes shall be made without the Owner's approval, which shall not be unreasonably withheld. 3. When required by the Owner, the Construction Manager shall prepare and incorporate into the schedule database, at the required intervals, the following schedules: A. Subcontractor Construction Schedules (Sub-networks) - Upon the award of each sub-contract, the Construction Manager shall jointly, with the subcontractor, develop a schedule which is more detailed than the pre-bid schedule included in the specifications, taking into account the work schedule of the other subcontractors. The construction schedule shall include as many activities as necessary to make the schedule an effective tool for construction planning and for monitoring the performance of the subcontractor. The construction schedule shall also show pertinent activities for material purchase orders, shop drawing schedules and material delivery schedules. B. Completion Schedule - The Construction Manager shall jointly develop with the Architect and Owner a detailed plan, inclusive of punch lists, final inspections, maintenance training and turn-over procedures, to be used for ensuring accomplishment of a smooth and phased transition from construction to public use. The Completion Schedule shall be produced and updated monthly from its inception through final Owner acceptance. 4. All schedules will be provided to the Owner on electronic Flash Drive media in a format acceptable to the Owner. The Construction Manager will provide the Owner with the appropriate software, if necessary, to read the data. The cost of providing the licenses and software shall be part of the cost of construction and included as part of Article 9, Cost of the Work. 2.4 [Deleted] 2.5 [Deleted] 2.6 Project Manual When directed by the Owner, the Construction Manager shall provide the following: 1. Upon award of contract, the Construction Manager shall develop a draft comprehensive Project Manual describing the services set forth in this Agreement for Owner's approval. This shall provide a plan for the control, direction, coordination and evaluation of work performed throughout the project, including identification of key personnel, responsibilities of Construction Manager, Owner, and Architect; work flow diagrams; and strategy for bidding the work. The Project Manual shall be updated as necessary with the Owner's approval throughout the design, construction and Owner utilization phases. Two copies of the Project Manual and any updates shall be submitted to the Owner and Architect. In developing the Project Manual, the Construction Manager shall coordinate with the Owner and the Architect. 2. Contents of Project Manual - The Project Manual shall describe in detail the procedures for executing the work and the organizations participating. The Project Manual shall include as a minimum the following sections: A. Project Definition - The known characteristics of the project or sub- projects shall be described in general terms which will provide the participants a basic understanding of the project or sub-projects. B. Project Goals - The schedule, budget, physical, technical and other objectives for the project shall be defined. C. Project Strategy - A narrative description of the project delivery methods shall be utilized to accomplish the project goals. D. Project Work Plan - A matrix display of the program of work to be performed by the Construction Manager, the Architect and the Owner during each phase of the project. E. Project Organization - A summary organization chart showing the interrelationships between the Owner, the Construction Manager and the Architect, and other supporting organizations and permitting review agencies. Detailed charts, one each for the Construction Manager, the Architect, and the Owner showing organizational elements participating in the project shall be included. F. Responsibility Performance Chart - A detailed matrix showing the specific responsibilities and interrelationships of the Owner, the Architect, Construction Manager, and subcontractors. The Responsibility Performance Chart shall indicate major responsibility, and minor responsibility, for each specific task required to deliver the project. The Construction Manager shall develop a similar chart for the personnel within its own organization, as well as for its subcontractors, who are assigned to the project, and also for the personnel of the Owner and the Architect from data supplied by each. G. Flow Diagrams - These charts shall display the flow of information and the decision process for the review and approval of shop drawings and submittals, progress and change orders. H. Written Procedures - The Construction Manager will provide written procedures for communications and coordination required between Construction Team members throughout the project. Procedures shall cover such items as correspondence, minutes, reports, inspections, team meetings, technical reviews, design reviews, and other necessary communications. 2.7 Design and Review and Recommendations The Construction Manager shall perform the services described in this Article. The services to be provided under Paragraph 2.7 constitute the Pre-construction Phase services. The parties acknowledge the Construction Phase may commence before the Pre- construction Phase is completed, and, to a certain extent, both phases shall proceed concurrently. The parties acknowledge that the Owner may choose not to proceed with the Construction Phase or any portion of the construction in its sole discretion, and Owner may terminate the Agreement for its convenience per Paragraph 14.3. 1. Preliminary Evaluation - The Construction Manager shall provide a preliminary evaluation of the Owner's program and Project budget requirements, each in terms of the other. 2. Consultation -The Construction Manager will jointly schedule and attend regular meetings with the Owner and Architect. The Construction Manager will consult with the Owner regarding site use and improvements, and the selection of materials, building systems, and equipment. The Construction Manager will provide recommendations on construction feasibility; actions designated to minimize adverse effects of labor or material shortages; scheduling and time requirements for procurement, installation, and construction completion; and factors related to construction cost including estimates of alternative designs or materials, preliminary budgets, and possible economies, including providing value engineering options. The Construction Manager's fundamental role and responsibility during and throughout the progress of the Pre-construction Phase of the Project shall include examination of the contract documents with written communication(s) to the Owner, Owner's Representative, and Architect of any gaps, redundancies, and conflicts that have the potential to adversely affect the cost, schedule, and constructability of the Project. 3. Phased Construction - The Construction Manager shall make recommendations to the Owner regarding the phased issuance of Drawings and Specifications to facilitate phased construction of the Work, taking into consideration such factors as economies of scale, time of performance, availability of labor and materials, and provisions for temporary facilities. The Owner may choose to terminate this Agreement before commencing any part of the Construction Phase. 4. Review Reports - Within ten (10) days after receiving the Construction Documents for each phase of the project, the Construction Manager shall perform a specific review thereof, focused upon factors of a nature encompassed in Paragraph 2.7(1) and 2.7(2) above and on factors set out in Paragraph 2.7. Promptly after completion of the review, Construction Manager shall submit to the Owner, with copies to the Architect, a written report covering suggestions or recommendations previously submitted; additional suggestions or recommendations, as Construction Manager may deem appropriate; all actions taken by the Architect with respect to same; any comments Construction Manager may deem to be appropriate with respect to separating the work into separate contracts; alternative materials; and all comments called for under Article 2.7(3) . THE CONSTRUCTION MANAGER SHALL WARRANT, TO THE BEST OF CONSTRUCTION MANAGER'S KNOWLEDGE, WITHOUT ASSUMING ANY ARCHITECTURAL OR ENGINEERING RESPONSIBILITY, THAT THE PLANS AND SPECIFICATIONS ARE CONSISTENT, PRACTICAL, FEASIBLE, AND CONSTRUCTIBLE. CONSTRUCTION MANAGER SHALL WARRANT THAT THE WORK DESCRIBED IN THE PLANS AND SPECIFICATIONS FOR THE VARIOUS SUBCONTRACTOR BIDDING PACKAGES IS CONSTRUCTIBLE WITHIN THE SCHEDULED CONSTRUCTION TIME. The recommendations and advice of the Construction Manager concerning design alternatives shall be subject to the review and approval of the Owner and Owner's professional consultants. Construction Manager shall not assume in any way the responsibilities of the Architect; in particular, the responsibility of assuring that the Drawings and Specifications, which are identified in Exhibit "I", are in accordance with applicable laws, statutes, ordinances, Building Codes, Rules, and Regulations. However, if the Construction Manager recognizes that portions of the Drawings and Specifications are at variance therewith, the Construction Manager shall promptly notify the Architect, via the Owner, in writing regarding the identified variances. 5. Long-lead Procurements - The Construction Manager shall review the design for the purpose of identifying long-lead procurement items (machinery, equipment, materials and supplies). When each item is identified, the Construction Manager shall notify the subcontractors, the Owner and the Architect of the required procurement and schedule. Such information shall be included in the bid documents and made a part of all affected sub-contracts. The Construction Manager shall keep itself informed of the progress of the respective subcontractors or suppliers manufacturing or fabricating such items, and advise Owner and Architect of any problems or prospective delay in delivery. The Construction Manager may recommend to the Owner a schedule for procurement of the long-lead time items, which will constitute part of the Work as required to meet the Project Schedule. If such long-lead items are procured by the Owner, they shall be procured on terms and conditions acceptable to the Construction Manager. Upon the Owner's acceptance of the Construction Manager's LSP proposal, all contracts for such items shall be assigned by the Owner to the Construction Manager, who shall accept responsibility for such items as if procured by the Construction Manager. The Construction Manager shall assist in expediting the delivery of long-lead time items. 6. Planning Separate Contracts - Without assuming any design responsibility, the Construction Manager shall review the design with the Architect and make recommendations to the Owner with respect to dividing the work in such manner as will permit the Construction Manager to take bids and award separate construction sub-contracts on the current schedule while the design is being completed. The evaluation shall take into consideration such factors as natural and practical lines of severability, sequencing effectiveness, access and availability constraints, total time for completion, construction market conditions, availability of labor and materials, community relations, and any other factors pertinent to saving time and cost by overlapping design and construction that are authorized by the Owner. 7. Interfacing A. The Construction Manager shall take such measures as are appropriate to provide that all construction requirements will be covered in the separate subcontracts for procurement of long lead items, the separate construction subcontracts and the general conditions items performed without duplication or overlap, sequenced to maintain completion of all work on schedule. Particular attention shall be given to provide that each bid package clearly identifies the work included in that particular separate subcontract, its schedule for start and completion and its relationship to other separate contractors. B. Without assuming any design responsibilities of the Architect, the Construction Manager shall include in the reports required under Article 2.7(4) comments on overlap with any other separate subcontracts, omissions, lack of correlation between drawings, and any other deficiencies noted, in order that the Owner and Architect may arrange for necessary corrections. 8. Job-Site Facilities - The Construction Manager shall arrange for all job- site facilities necessary to enable Construction Manager, Owner's Representatives and Architect to perform their respective duties in the management, inspection, and supervision of construction. 2.8 Construction Phase 1. Construction Manager's Staff- The Construction Manager shall maintain sufficient off-site support staff, and competent full time staff at the Project site authorized to act on behalf of the Construction Manager to coordinate, inspect and provide general direction of the work and progress of the subcontractors and it shall provide no less than those personnel during the respective phases of construction that are set forth in Exhibit "B" to this agreement. Construction Manager shall not change any of those persons named in Exhibit "B" unless mutually agreed to by the Owner and Construction Manager. In such case, the Owner shall have the right of approval of the qualifications of replacement personnel. Such approval will not be unreasonably withheld. 2. Lines of Authority - The Construction Manager shall establish and maintain lines of authority for this personnel, and shall provide this definition to the Owner and all other affected parties, such as the code inspectors of the Permitting Authority, the subcontractors, the Architect and the Owner's representatives, to provide general direction of the work and progress of the various phases and subcontractors. Owner, Owner's Representative, and Architect may attend meetings between the Construction Manager and its subcontractors; however, such attendance shall not diminish either the authority or responsibility of the Construction Manager to administer the subcontractor. 3. Schedule and Project Manual Provisions - The Construction Manager shall provide subcontractors and the Owner, its representatives and the Architect with copies of the Project Manual (total number of copies not to exceed 10) developed and updated as required by Article 2.6 expanded for each Construction Phase, employing their respective milestones, beginning and finishing dates, their respective responsibilities for performance, and the relationships of their work with respect to subcontractors and suppliers. Construction Manager shall also continue to provide current scheduling information, direction and coordination regarding milestones, and beginning and finishing dates. Construction Manager is also responsible for performance and the relationships of the Construction Manager's work to the work of its subcontractors and suppliers to enable them to perform their respective tasks so that the development of construction progresses in a smooth and efficient manner in conformance with the overall project schedule. The schedule shall include all phases of the construction work, material supplies, long lease procurement, approval of shop drawings, change orders in progress, schedules for change orders, and performance testing requirements. Construction Manager shall advise the Owner, its representatives and the Architect of their required participation in any meeting or inspection giving each at least one week notice unless such notice is made impossible by conditions beyond its control. Construction Manager shall hold job- site meetings at least once each month with the Construction Team or more frequently as required by work progress, to review progress, discuss problems and their solutions and coordinate future work with all subcontractors. 4. Solicitation of Bids A. Without assuming responsibilities of the Architect, the Construction Manager shall prepare invitations for bids, or requests for proposal when applicable, for all procurement of long-lead items, materials and services, and Subcontractor contracts. B. The Construction Manager shall be responsible for coordinating with the Architect and preparing all information that is the responsibility of the Construction Manager for bidding of the separate bid packages. C. As part of such preparation, the Construction Manager shall review the specifications and drawings prepared by the Architect. Ambiguities, conflicts, lack of clarity of language, use of illegally restrictive requirements, and any other defects in the specifications or in the drawings noted by the Construction Manager shall be brought to the attention of the Owner and Architect in written form. The Construction Manager is solely responsible for reviewing and comparing the Contract Documents with each other and shall immediately report to the Architect any and all errors, inconsistencies or omissions. In the event the Construction Manager performs any Work with the knowledge that it involves an error, inconsistency or omission in the Contract Documents, the Construction Manager shall be responsible for such erroneous, inconsistent, or omitted Work. The Construction Manager is also responsible for taking such field measurements as are necessary in order to verify field conditions and to compare such field measurements and conditions with the Contract Documents. Any and all errors, inconsistencies or omissions shall be immediately reported to the Architect. The Construction Manager and the Owner's Representative shall mutually agree when and if to conduct a pre-bid conference with prospective bidders and the Architect. In the event questions are raised which require an interpretation of the bidding documents or otherwise indicate a need for clarification or correction of the invitation, the Construction Manager shall transmit these to the Owner and the Architect, and upon receiving clarification or correction in writing, the Construction Manager shall prepare an addendum to the bidding document, and issue same to all of the prospective bidders. D. The Construction Manager is required to enter into written agreements with each subcontractor who will perform any portion of the Work on the Project. The subcontract agreement shall incorporate the terms of the Contract Documents, and the terms of this Agreement, and be assignable to Owner. Further, where appropriate, the Construction Manager shall require each subcontractor to enter into similar agreements with sub-subcontractors and material suppliers. Before entering any agreement with a subcontractor, Construction Manager shall confirm that the subcontractor is properly licensed by the State, Orange County, and any applicable municipality, for the portion of the Work to be performed on the Project, and shall supply such information or proof of licensing, in writing, to Owner. 5. Bonds - In accordance with the provisions of Section 255.05, Florida Statutes, the Construction Manager shall provide to the Owner, on forms furnished by the Owner and attached as Exhibit "L", a 100% Performance Bond and a 100% Labor and Material Payment Bond each in an amount not less than the total construction cost as defined in Article 9 and inclusive of the construction fee. To be acceptable to the Owner as Surety for Performance Bonds and Labor and Material Payment Bonds, a Surety Company shall comply with the following provisions: A. The Surety Company shall have a currently valid Certificate of Authority, issued by the State of Florida, Department of Insurance, authorizing it to write surety bonds in the State of Florida. B. The Surety Company shall have currently valid Certificate of Authority issued by the United States Department of Treasury under Sections 9304 to 9308 of Title 31 of the United States Code. C. The Surety Company shall be in full compliance with the provisions of the Florida Insurance Code. D. The Surety Company shall have at least twice the minimum surplus and capital required by the Florida Insurance Code at the time the bond is issued. 1. The Surety Company shall have at least the following minimum ratings in the latest issue of Best's Key Rating Guide. Contract Amount Policy Holder's Rating Required Financial Rating $500,000 to$1,000,000 A Class IV $1,000,000 to $2,500,000 A Class V $2,500,000 to $5,000,000 A Class VI 2. The Surety Company shall not expose itself to any loss on any one risk in an amount exceeding Ten Percent (10 %) of its surplus to policyholders, provided: a. In the case of the surety insurance company, in addition to the deduction for reinsurance, the amount assumed by any co-surety, the value of any security deposited, pledged or held subject to the consent of the surety and for the protection of the surety shall be deducted. b. Any risk or portion of any risk being reinsured shall be deducted in determining the limitation of the risk as prescribed in this section. These minimum requirements shall apply to the reinsuring carrier providing authorization or approval by the State of Florida, Department of Insurance to do business in this state has been met. 6. Quality Control - The Construction Manager shall develop and maintain a written program, acceptable to the Owner and Architect, to assure quality control of the construction. Construction Manager shall supervise the work of all subcontractors providing instructions to each when their work does not conform to the requirements of the plans and specifications and Construction Manager shall continue to exert its influence and control over each subcontractor to ensure that corrections are made in a timely manner so as to not affect the efficient progress of the work. Should disagreement occur between the Construction Manager and Architect over acceptability of work and conformance with the requirements of the specifications and plans, the Owner shall be the final judge of performance and acceptability, subject to the dispute provisions of this Agreement. 7. Subcontractor Interfacing - The Construction Manager shall be the single point of interface with all Subcontractors for the Owner and all of its agents and representatives including the Architect. When health and safety are threatened, the Construction Manager shall act immediately to remove the threat to health and safety. Construction Manager shall also carefully review all shop drawings and then forward the same to the Architect for review and actions. The Architect shall transmit them back to the Construction Manager, who will then issue the shop drawings to the affected subcontractor for fabrication or revision. The Construction Manager shall maintain a suspense control system to promote expeditious handling. Construction Manager shall request the Architect to make interpretations of the drawings or specifications requested of him by the subcontractors and shall maintain a suspense control system to promote timely response. Construction Manager shall advise the Owner and Architect when timely response is not occurring on any of the above. 8. Permits - The Construction Manager shall secure all necessary permits from the Permitting Authority and all necessary utility connection permits, the cost of which will be considered a direct cost item, but not subject to Construction Manager profit, as described in section 8.3. There is no cost for permits required from the City. 9. Job Site Requirements A. The Construction Manager shall provide for each of the following activities as a part of its Construction Phase Cost: 1. Maintain a log of daily activities, including manpower records, heavy equipment on site, weather, delays, major decisions, etc. 2. Maintain a roster of companies on the project with names and telephone numbers of key personnel. 3. Establish and enforce job rules governing parking, clean-up, use of facilities and worker discipline. 4. Provide labor relations management for a harmonious, productive project. 5. Provide a safety program for the project to meet OSHA requirements. Monitor for subcontractor compliance without relieving them of responsibilities to perform work in accordance with the best acceptable practice. 6. Provide a quality control program as developed under Article 2.8(6) herein above. 7. Miscellaneous office supplies that support the construction efforts, which are consumed by its own forces. 8. Travel to and from its home office to the project site, as the project requires. B. The Construction Manager shall provide personnel and equipment or shall arrange for separate subcontracts to provide each of the following as a direct cost item: 1. Schedule the services of independent testing laboratories for the necessary testing of materials to ensure conformance to contract requirements, if the Owner does not provide for these services. 2. The printing and distribution of all required bidding documents and shop drawings, including the sets required by the Permitting Authority's inspectors. 10. Job Site Administration - The Construction Manager shall provide, as part of its job site fee,job site administrative functions during construction to assure proper documentation, including but not limited to such things as the following: A. Job Meetings - Hold weekly progress and coordination meetings to provide for an easy flowing project. Implement procedures, assure timely submittals, expedite processing approvals and return of shop drawings, samples, etc.; Coordinate and expedite critical ordering and delivery of materials, work sequences, inspection and testing, labor allocation, etc.; Review and coordinate each subcontractor's Work; Review and implement revisions to the Schedule; Monitor and promote safety requirements. In addition, a regular monthly project status meeting will be held between the Architect, Owner and Construction Manager. Use the job site meeting as a tool for planning of work and enforcing schedules and for establishing procedures, responsibilities, and identification of authority for all to clearly understand. Identify party or parties responsible for follow up on any problems, delay items or questions and identify a course for solution. Revisit each pending item at each subsequent meeting until resolution is achieved. Require all present to make any problems or delaying event known to those present for appropriate attention and resolution. B. Shop Drawing Submittals/Approvals - Provide staff to check shop drawings and to implement procedures to be approved by Owner for submittal and transmittal to the Architect and Owner of such drawings for action, and closely monitor their submittal and approval process. C. Material and Equipment Expediting - Provide staff to closely monitor material and equipment deliveries, important checking and follow-up procedures on supplier commitments of all subcontractors. D. Payments to Subcontractors - Develop and implement a procedure for review, processing, and payment of applications by subcontractors for progress and final payments. E. Document Interpretation - Refer all questions for interpretation of the documents prepared by the Architect to the Architect via the Owner. F. Reports and Project Site Documents - Record the progress of the project. Submit written progress reports to the Owner and the Architect including information on the subcontractors' work, and the percentage of completion. Keep a daily log available to the Owner, the Architect and the Permitting Authority inspectors. G. Subcontractors' Progress - Prepare periodic punch lists for the subcontractors' work, including unsatisfactory or incomplete items and schedules for their completion. H. Substantial Completion - Ascertain when the work, or designated portions thereof, are ready for the Owner's and the Architect's substantial completion inspection. Prior to the Owner's and Architect's pre-substantial completion inspection, the Construction Manager shall issue a list of incomplete items. After the Owner's and the Architect's inspection, the Construction Manager shall prepare a schedule for the completion of the list indicating completion dates for the Owner's review. The Owner and the Architect will issue a certificate of substantial completion when the work on the Construction Manager's pre-substantial completion punch list has been accomplished, to the best of the Construction Manager's ability (See Exhibit"C"). After the Construction Manager has notified the Architect that the project is substantially compete, and the Architect agrees that all Contract Documents and each pay item is complete, the Architect shall notify the Construction Manager and the Owner, in writing, that the project has attained substantial completion. Architect, Owner, and Construction Manager will perform the semifinal inspection within seven (7) day of substantial completion. As part of the semi-final inspection, representatives of the Owner will perform a joint review of the project. The Architect will generate a final project condition report, with resolutions of discrepancies if any, and provide a copy to the Owner and Construction Manager. If, at the semifinal inspection, all construction provided for and contemplated by the Agreement is found complete to the Architect's satisfaction, such inspection shall constitute the final inspection, as prescribed herein. If, however, any work is found unsatisfactory, in whole or in part, the Architect shall compile a "punch list" of work to be completed. A copy of the "punch list" will be furnished to the Construction Manager, with the indication that the work so noted must be completed. Time shall continue to be charged on the project. Any "punch list(s)" furnished to the Construction Manager prior to final inspection and acceptance shall state that it is not to be construed as the "final" list. It shall also state that items damaged beyond the control of the Construction Manager and prior to the final inspection must be corrected prior to final acceptance. It shall also state that the Construction Manager is still responsible for maintenance, including mowing, of the Project(s) until final acceptance. I. Final Completion - Monitor the Subcontractors' performance on the completion of the project and provide notice to the Owner and Architect that the work is ready for final inspection. Secure and transmit to the Owner, through the Architect, all required guarantees, affidavits, releases, bonds and waivers, manuals, record drawings, and maintenance books, including the Final Completion form shown in Exhibit"D". J. Start-Up - With the Owner's personnel, direct the checkout of utilities, operations, systems and equipment for readiness and assist in their initial start-up and testing by the trade contractors. K. Record Drawings/As-Built Drawings - The Construction Manager shall monitor the progress of its own forces or its Subcontractors on marked up field prints. The Construction Manager shall record all deviations from original drawings. Final payment will not be made until the requirements of this paragraph have been met. During the progress of the work, the Construction Manager shall record on all field sets of drawings the exact locations, as installed, of all underground and otherwise concealed conduit, pipe and duct lines which were not installed exactly as shown on the contract drawings. Upon completion of the work, this data shall be recorded to scale on electronic files of the contract drawings. Where changes are to be recorded, the drawing shall be erased before the changes are made. Where the work was installed exactly as shown on the contract drawings the drawing shall not be distributed other than being marked "As-Built." In showing the changes the same legend shall be used to identify piping, etc., as was used on the contract drawings. Each sheet shall bear the date and name of the subcontractor submitting the drawings. The Construction Manager shall review the completed as-built drawings and ascertain that all dates furnished on the drawings are accurate and truly represent the work as actually installed. When manholes, boxes, underground conduits, inverts, etc., are involved as part of the work, the Construction Manager shall furnish true elevations and locations, all properly referenced by using the original benchmark used for the institution or for this project. The drawings including those unchanged and changed shall be submitted to the Architecting and the Owner when completed, together with two sets of blue line or black line prints for certification. Upon completion and prior to final inspection, the following must be provided to the Architect and Owner: 1. Test results, as required. 2. Maintenance Bond for facilities to be conveyed to the Owner. 3. As-built drawings shall be submitted after final inspection and prior to acceptance for water, wastewater and drainage systems, both on and off-site. These drawings shall be based upon field surveys, and will show all boundary, rights-of-way, easement and lot lines, and shall be certified by a Registered Professional Land Surveyor in accordance with Chapter 62-817, F.A.C. Note: Digital format drawings (AutoCAD, Revit, and PDF). a. Location of all sanitary manholes and cleanouts, the service end of all laterals, and the elevation of all inverts and manhole tops. b. Location, size and invert elevation of all drainage pipes. c. Location of all water mains, valves, and joints, and the elevation of all fittings. d. CAD files should be in State Plane Coordinates (SPC) Feet, East Zone - Florida, North American Datum (NAD) 1983 and NAVD 1988, with the latest amendments. 11. Administrative Records - The Construction Manager may be required to maintain at the job site on a current basis, files and records such as, but not limited to the following: Contracts or Purchase Orders Shop Drawing Submittal/Approval Logs Equipment Purchase/Delivery Logs Contract Drawings and Specifications with Addenda Warranties and Guarantees Payment Request Records Meeting Minutes Lab Test Reports Insurance Certificates and Bonds Contract Changes Purchase Orders Material Purchase Delivery Logs Technical Standards Design Handbooks "As-Built"/Record Drawing Operating&Maintenance Instruction Daily Progress Reports Monthly Progress Reports Correspondence Files Transmittal Records Inspection Reports Punch Lists PMIS Schedule and Updates Suspense(Tickler) Files of Outstanding Requirements Project Manual Job Photographs Schedules (original, updated, and as-built) The project records shall be available at all times to the Owner and Architect for reference or review. 12. Owner Utilization The Construction Manager shall: A. Provide services during the design and construction phases, which will provide a smooth and successful Owner utilization of the project. Provide consultation and project management to facilitate Owner utilization and provide transitional services to get the work, as completed by the contractors, subcontractors, "on line" in such conditions as will satisfy Owner operational requirements. B. Conduct the Construction Manager's preliminary punch list inspection and coordinate the completion of all punch list work to be done with Owner utilization requirements in mind. Videotape all major equipment startup procedures and deliver videotapes as part of the closeout documents. C. Catalog operational and maintenance requirements of equipment to be operated by maintenance personnel and convey these to the Owner in such a manner as to promote their usability. Provide operational training, in equipment use, for building operators. D. Secure required guarantees and warranties, assemble and deliver same to the Owner in a manner that will facilitate their maximum enforcement and assure their meaningful implementation. The Owner may take control of portions of the project providing the above items discussed in this paragraph have been completed and the Substantial Completion, Start- Up, Record Drawing, and Warranty requirements specified in paragraphs 2.8(10) and 2.8(13) have been completed to the Owner's satisfaction for the portions to be occupied, excluding the requirements for a warranty inspection nine months after Owner Utilization. 13. Warranty Where any work is performed by the Construction Manager's own forces or by subcontractors under contract with the Construction Manager, the Construction Manager shall warrant that all materials and equipment included in such Work will be new except where indicated otherwise in Contract Documents, and that such Work will be of good quality, free from improper workmanship and defective materials and in conformance with the Drawings and specifications. With respect to the Work, the Construction Manager further agrees to correct all work found by the Owner to be defective in material and workmanship or not in conformance with the Drawings and Specifications for a period of one year from the Date of Substantial Completion or partial utilization of any portion of the building, whichever comes first, or for such longer periods of time as may be set forth with respect to specific warranties contained in the trade sections of the Specifications. The Construction Manager shall collect and deliver to the Owner any specific written warranties given by others as required by the Contract Documents. Also, the Construction Manager shall conduct, jointly with the Owner and the Architect, a warranty inspection approximately eleven(11)months after the date of Owner Utilization. 14. Uncovering and Correction of the Work A. In the event the Construction Manager covers a portion of the Work contrary to the request of the Architect or prior to an inspection by the Architect, the Construction Manager must if requested in writing uncover the Work, and then shall be required to replace the work at the Construction Manager's sole expense, without any change to the contract time. B. The Project is subject to and shall be constructed in accordance with the Florida Building Code and to all applicable codes referenced therein. C. The Construction Manager shall promptly correct any and all Work rejected by the Architect and any and all Work which fails to comply with the requirements of the Contract Documents. The Construction Manager shall bear all of the costs for correcting such Work, including any compensation for the Architect's services. D. If within one (1) year after the date of final completion of the Work or after the date for commencement of warranties, any of the Work is found to be not in accordance with the requirements of the Contract Documents, the Construction Manager shall promptly return to the Project and correct the deficient Work upon receipt of written notification from the Owner to do so. The obligation set forth in this subparagraph shall survive acceptance of the Work under this Agreement and any termination of the Agreement. The Owner shall give such written notice promptly after discovery of the deficient Work. This one (1) year Construction Manager warranty described in this subparagraph does not impact or impair any manufacturer's warranty or the Owner's ability to make any other claim against the Construction Manager as allowed under Florida law. E. The Construction Manager shall immediately remove from the Work Site any and all portions of the Work which are not in compliance with the requirements of the Contract Documents. In the event the Construction Manager fails to correct any non-conforming Work within a reasonable time, the Owner may correct such non-conforming Work, the cost of which shall be the Construction Manager's responsibility. In the event the Owner corrects the non-conforming Work, the Owner in its sole discretion may remove, store or sell for salvage any salvageable materials or equipment related to or a part of the non-conforming work at the Construction Manager's expense. If the Construction Manager fails to reimburse the Owner for such expenses within 7 days after written notice, the Owner may take any and all action it deems appropriate in order to obtain reimbursement of its expenses under this subparagraph. Any action taken by the Owner under this subparagraph shall not in any respect serve to limit in law or equity the Owner's ability to place any other claim against the Construction Manager. F. The Owner has the discretion to accept work that is not in compliance with the requirements of the Contract Documents. In this event, the Owner shall reduce its decision to writing, which shall include any reduction, if any, to the Contract Sum as a result of the acceptance of non- conforming Work. Any such adjustment to the Contract Sum shall apply whether or not final payment has been made under this Agreement. 15. Site Conditions A. Field Measurements. Before undertaking each part of the construction, Construction Manager shall carefully study and compare the Contract Documents and check and verify pertinent figures shown thereon and all applicable field measurements. Construction Manager shall promptly report in writing to the Owner any conflict, error or discrepancy which Construction Manager or any of its Subcontractors or Suppliers may discover and shall obtain a written interpretation or clarification from Owner before proceeding with any Work affected thereby; provided, however, Construction Manager shall not be liable to the Owner for failure to report any conflict, error or discrepancy unless Construction Manager or any of its Subcontractors or Suppliers had actual knowledge thereof or should reasonably have known thereof. B. Physical Conditions (Including Underground Facilities) 1. The Contract Documents may identify reports of explorations and tests of subsurface conditions at the site, and those drawings of physical conditions in or relating to existing surface or subsurface structures or Underground Facilities owned by Owner which are at or contiguous to the site, that have been utilized by the design professional in preparation of the Contract Documents. Construction Manager shall have full responsibility for physical conditions, and Underground Facilities owned by Owner or others, shown or indicated in the Contract Documents. 2. The information and data shown or indicated in the Contract Documents with respect to Underground Facilities owned by others or at contiguous to the site is based on information and data furnished to Owner or the design professional by the owners of such Underground Facilities or by others. The Owner shall not be responsible for the accuracy or completeness of any such information or data, and the Construction Manager shall have full responsibility for reviewing and checking all such information and data. 3. If the Contract Documents necessitate amending to order changes in the Work due to Underground Facilities owned by the Owner or others, whether they be shown or indicated or newly discovered, Owner shall authorize the required changes in the Work by Change Order. If those Underground Facilities owned by the Owner or others cause or will cause delays in the performance or extend completion of all or part of the work, Construction Manager shall absorb all related delay, extension or acceleration costs, however caused; except that if Owner and Construction Manager agree that the delays require a change in Contract Time, Owner shall authorize the necessary change in Contract Time. However, an extension in Contract Time, when and if so granted shall be Construction Manager's sole and exclusive remedy with respect to Owner for any delay, disruption, interference, inefficiency, acceleration, extension or hindrance and associated costs, however caused, resulting from variance in the location or configuration of Underground Facilities owned by the Owner or others shown or indicated, or from newly discovered Underground Facilities owned by the Owner or others. 4. Unless it prejudices Work already excavated and uncovered, Construction Manager shall schedule layout, excavation and uncovering of Work or Underground Facilities a sufficient time in advance to allow the Owner's Architect of Record's review, and the possible amending or supplementing of the Contract Documents. C. Special Requirements for Underground Facilities Construction Manager shall have full responsibility: a) for field locating any and all Underground Facilities including utilities shown or indicated as to depth and alignment in advance of excavation; b) for identifying the owner of any newly discovered Underground Facility and promptly notifying that owner and Architect of that discovery; c) for shoring, blocking and protecting Underground Facilities including utilities shown, indicated or discovered; d) for coordination, scheduling and sequencing the Work with the owners of all Underground Facilities shown, indicated or discovered; e) for repairing any damage to the satisfaction of those owners, to the extent that the damage was due to Construction Manager's failure to adhere to the requirements of this section, or to the fault or negligence of Construction Manager; and 0 for the safety and protection of any affected Work, and for repairing any damage done to the work. Except as otherwise provided in this section, all costs involved and time required to perform these responsibilities shall be considered as having been included in the Contract Sum and in the Construction Manager's schedule for the performance of the Work within the Contract Time, even if the Contract Documents need amending to authorize minor deviations or changes in the Work due to those Underground Facilities including utilities. 16. Maintenance of Traffic A. Construction Manager shall be responsible for the proper maintenance control and detour of traffic in the area of construction, during the course of construction. All traffic control and maintenance procedures shall be in accordance with the requirements of either the Florida Department of Transportation, City of Ocoee, or the local municipality, within their respective area of jurisdiction. It shall be the Construction Manager's responsibility, prior to submitting its LSP, to determine the requirements of these agencies so that its Proposal reflects all costs to be incurred. No claims for any increase to the LSP will be considered for costs incurred in the proper maintenance, control, detour and protection. B. Traffic shall be maintained at all times where practical, and as more particularly specified hereinafter. No traffic shall be detoured without prior knowledge and approval of the respective traffic control agency having jurisdiction. The Construction Manager shall notify such agencies 48 hours in advance of such time it proposes to detour such traffic. 17. Fencing On all Work which included fencing and where the ENGINEER determines it to be necessary for maintaining the security of adjacent property, or for protection of pedestrians who are likely to gain access to the Work from adjacent property, the CONTRACTOR shall erect appropriate temporary security fence as a first order of business. Temporary fencing shall be installed at temporary construction easement areas on all commercial and residential properties appropriate to secure the Work area and protect persons and domestic animals. At all times, the CONTRACTOR shall conduct the Work under secure temporary fencing. Permanent fencing shall be addressed as required by the Plans and Specifications. ARTICLE 3 OWNER'S RESPONSIBILITIES 3.1 Owner's Information The Owner shall identify its requirements for the project. 3.2 Owner's Representative The Owner shall designate, in writing, any additional representatives authorized to act on the Owner's behalf with respect to the Project who were not previously defined in Article 1.3, together with the scope of his/her respective authority. In no event shall any delegation of authority be contrary to State or County laws or codes. Such designations as of the date hereof are set forth on Exhibit "F" hereto. Functions that this Agreement provides will be performed by the Owner can be delegated by the Owner only by written notice to the Construction Manager from the Owner. Exhibit "F" may be amended from time to time by the Owner pursuant to written notice of and acceptance by the Construction Manager of such amendment. The Construction Manager shall be entitled to rely on directions (and it shall be required to follow directions) from the Owner's Representative designated on Exhibit "F" or an amendment to Exhibit "F" within the authority conferred by the Owner in this Agreement or any Amendment or Change Order to this Agreement. Owner hereby authorize the Owner's Representative to: (1) act as the Owner's agent and execute documents associated with this Project. Examples of these documents are Construction Manager's Contingency Authorizations, Notices of Commencement, Certificates of Substantial Completion, and permits from applicable agencies; (2) administer, coordinate, interpret and otherwise manage the contractual provisions and requirements of this Agreement; (3) negotiate a duly authorized Change Order on behalf of the Owner; and (4) issue a duly authorized purchase order, memorandum, letter or other instrument covering the services and work to be provided pursuant to this Agreement. Directions and decisions made by Owner's Representatives shall be binding on the Owner. The Owner's Representative does not have the authority to authorize work beyond the scope of the LSP. The Owner additionally authorizes the City Manager, in conjunction with the Owner's Representative, to authorize changes in the work up to the limits designated in the City of Ocoee Purchasing Code. Said work shall be funded from the Owner's Contingency and shall not cause an increase to the overall project budget. Any changes above the City's Purchasing Code limits will need City Commission approval. 3.3 Architect's Agreement The Owner has retained an Architect for design and to prepare construction documents for the Project. The Architect's services, duties and responsibilities are described in the Agreement between the Owner and the Architect, a copy of which will be furnished to the Construction Manager. The Agreement between the Owner and the Architect shall not be modified without written notification to the Construction Manager. The Agreement may include a provision for the Architect to also serve as Owner's Representative. In such a case, the Architect shall have all the responsibilities and duties of both roles. 3.4 (Intentionally omitted.) 3.5 (Intentionally omitted.) 3.6 Cost of Surveys &Reports The services, information, surveys and reports required by the above paragraphs shall be furnished with reasonable promptness in accordance with the approved schedule at the Owner's expense, and the Construction Manager shall be entitled to rely upon the accuracy and completeness thereof. 3.7 Project Fault Defects If the Owner becomes aware of any fault or defect in the Project or non-conformance with the drawings and specifications, Owner shall give prompt written notice thereof to the Construction Manager and Architect. 3.8 (Intentionally omitted.) 3.9 Lines of Communication The Owner and the Architect, through the Owner, shall communicate with the subcontractors or suppliers only through the Construction Manager so long as such method of communication is effective in maintaining project schedules and quality. 3.10 Permitting&Code Inspections The Owner recognizes and coordinates with the appropriate Permitting Authority and expects the Construction Manager to do the same. ARTICLE 4 PERMITS, FEES AND NOTICES 4.1 Unless otherwise provided in the Contract Documents, the Construction Manager shall secure and pay for the permits, which are customarily secured by a General Contractor in performing site work, utility, and roadway construction. 4.2 The Construction Manager shall comply with and give notices, as required by laws, ordinances, rules, regulations and lawful orders of public authorities bearing on performance of the Work. 4.3 It is not the Construction Manager's responsibility to ascertain that the Contract Documents are in accordance with applicable laws, statutes, ordinances, Building Codes and Rules and Regulations. However, if the Construction Manager observes that portions of the Contract Documents are at variance therewith, the Construction Manager shall promptly notify the Architect and Owner in writing, and necessary changes shall be accomplished by appropriate modification. 4.4 If the Construction Manager performs Work knowing it to be contrary to laws, statutes, ordinances, Building Codes, and Rules and Regulations without such notice to the Architect and Owner, the Construction Manager shall assume full responsibility for such Work and shall bear the attributable costs. 4.5 Cost for all re-inspections of work performed by the Construction Manager found defective and subsequently repaired, shall be borne by the Construction Manager, unless such cost is not a result of negligence on the part of the Construction Manager. ARTICLE 5 SUBCONTRACTS 5.1 Definition A subcontractor is a person or organization who has a direct contract with the Construction Manager to perform any of the work at the site. Nothing contained in the Contract Documents shall create any contractual relation between the Owner or Architect and any subcontractor. 5.2 General Requirements Subject to Article 9 and, in accordance with Article 2.8(4), the Construction Manager shall request and receive proposals from qualified subcontractors and suppliers. 5.2.1 Required Subcontractors' Qualifications and Subcontract Conditions: 1. Subcontractual Relations - The Construction Manager shall require each Subcontractor to assume all the obligations and responsibilities that the Construction Manager owes the Owner under the Agreement, to the extent of the work to be performed by the subcontractor. The subcontracts shall be made in writing and shall preserve and protect the rights of the Owner and Architect under the Contract Documents with respect to the Work to be performed by the subcontractor so that the subcontracting thereof will not prejudice such rights. Where appropriate, the Construction Manager shall require each subcontractor to enter into similar agreements with its sub- subcontractor(s) and supplier(s). 2. Insurance requirements for subcontractors shall be no more stringent than those requirements imposed on the Construction Manager by the Owner. 3. The Construction Manager shall make available to each proposed Subcontractor, prior to the execution of the Subcontract, copies of the Contract Documents to which the Subcontractor will be bound by this Article 5. 5.2.2 All subcontracts shall provide: 1. LIMITATION OF REMEDY -NO DAMAGES FOR DELAY The subcontractor's exclusive remedy for delays in the performance of the subcontract caused by events beyond its control, including delays claimed to be caused by the Owner or Architect or attributable to the Owner or Architect and including claims based on breach of contract or negligence, shall be an extension of its contract time and shall in no way involve any monetary claim. 2. The subcontract shall require the subcontractor to expressly agree that the foregoing constitute its sole and exclusive remedies for delays and changes in the work and thus eliminate any other remedies for claims for increase in the contract price, damages, losses or additional compensation. 3. Each subcontract shall require the Owner to be added as an additional insured on the subcontractor's general liability policy for the project. 5.3 Responsibilities for Acts and Omissions The Construction Manager shall be responsible to the Owner for the acts and omissions of its employees, agents, subcontractors, their agents and employees, and all other persons performing any of the work or supplying materials under a contract to the Construction Manager. ARTICLE 6 SCHEDULE, TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION 6.1 Time is of the essence of the performance of this Agreement. At the time a LSP is established, as provided for in Article 7, a project substantial completion date, a project final completion date, and an Owner utilization date for completion of the project in accordance with the master project schedule shall also be established by the Construction Team. The Construction Manager agrees to complete the construction in accordance with the agreed upon substantial completion date, final completion date and Owner utilization date. The Construction Manager acknowledges that failure to complete the project within the construction time set forth in the approved schedule will result in substantial damages to the Owner. Construction Manager hereby expressly waives and relinquishes any right which it may have to seek to characterize the liquidated damages, set out in this paragraph 6.1 below, as a penalty, which the parties agree represents a fair and reasonable estimate of the Owner's actual damages at the time of contracting if Construction Manager fails to achieve Substantial Completion or Final Inspection within the Contract Time. Further, the parties acknowledge that it would be extremely difficult, if not impossible, to ascertain Owner's actual damages with any degree of certainty in the event Construction Manager fails to achieve either Substantial Completion or Final Inspection within the Contract Time. In the event the Construction Manager does not achieve Substantial Completion within the Contract Time, including approved extensions, the Construction Manager shall pay the Owner, as liquidated damages and not as a penalty, the sum of$500 per day for each calendar day the actual time of performance exceeds the authorized Contract Time before substantial completion. Liquidated damages shall be $700 per day from Substantial Completion to final completion. The most important scheduled event to occur during the period of construction is the annual Founders' Day Celebration, generally set for the first weekend of November. No work will be permitted during the week prior to Founder's Day. Founders' Day is an annual event and the required week-long work stoppage must be incorporated into the CMR schedule. Any project element begun before the Founders' Day week must be completed prior to the work stoppage, as it will not be possible to leave work in progress during the week of work stoppage due to the large crowds expected. Liquidated damages in the amount of $1,500 per day will be imposed on any work not conforming to this requirement. No additional mobilization/ demobilization charges will be allowed for the Founders' Day shutdown. Any such costs must be included in the Base Bid Item for Mobilization/Demobilization. 6.2 The date of Owner Utilization shall occur as described in Article 2.8(12) herein above. Warranties called for by this Agreement or by the Drawings and Specifications shall commence on the Date of Substantial Completion, unless otherwise agreed to, in writing, between the Owner and Construction Manager. ARTICLE 7 LUMP SUM PRICE FOR CONSTRUCTION 7.1 When the design documents are sufficiently complete to establish the scope of work for the project or any portion thereof, as generally defined by a design document listing to be provided by the Architect and Construction Manager upon execution of this Agreement, which is to be used only as a guide in developing for the Owner's approval, the specifications and plan data necessary to establish a Lump Sum Price; or at such time thereafter designated by the Owner; the Construction Manager will establish and submit in writing to the Owner, for its approval an LSP, guaranteeing the price to the Owner for the construction cost of the project or designated part thereof. The Construction Manager acknowledges multiple LSPs may be required for the portions of the project to support the project phasing and schedule. Such LSP will be subject to modification for changes in the project as provided in Article 10. Costs which would cause the LSP to be exceeded will be paid by the Construction Manager without reimbursement by the Owner. 7.2 Intentionally omitted. 7.3 At the time of submission of an LSP, the Construction Manager will verify the time schedule for activities and work, which were adopted by the Construction Team and used to determine the Construction Manager's LSP. ARTICLE 8 CONSTRUCTION MANAGER'S COMPENSATION In consideration of the performance of this Agreement, the Owner agrees to pay the Construction Manager as compensation for its services, costs or fees, as set forth in Article 8.1(1) and 8.1(2) as follows. 8.1 Design Phase/Pre-construction - For the performance of the Preconstruction services set forth under Articles 2.3, 2.4, 2.6, 2.7 and for profit and overhead related to these services, the Construction Manager shall be paid a not to exceed fixed fee of $26,675.00. The Design Phase/Pre-construction Costs shall be paid according to the percent complete of the design phase in each calendar month. The Construction Manager's personnel to be assigned during this phase and their duties and responsibilities to this project and the duration of their assignments are shown on Exhibit "E". 8.2 Construction Phase — For the Construction Manager's performance of the Construction Phase Work, the Owner shall pay Construction Manager the Lump Sum Price, as it may have been amended by any approved Change Order(s). To the extent the Cost of the Work exceeds the LSP, the Construction Manager shall bear such costs in excess of the LSP without reimbursement or additional compensation from the Owner. ARTICLE 9 COST OF THE WORK FOR CONSTRUCTION PHASE SERVICES !DELETED] ARTICLE 10 CHANGES IN THE PROJECT 10.1 Change Orders The Owner, without invalidating this Agreement, may order Changes in the Project within the general scope of this Agreement consisting of additions, deletions, or other revisions, with the LSP and the Construction Completion Date being adjusted accordingly. All changes in the Project that the Construction Manager alleges will result in a material increase in its cost or time of construction shall be authorized by a Change Order signed by the Owner before the change is implemented. Construction Manager's claims for additional time shall be accompanied by detailed dates, correspondences, notices, and other data to prove the claim as required by Article 16. 1. A Change Order is a written order to the Construction Manager signed by the Owner issued after the execution of this Agreement, authorizing a Change in the Project, the change in the LSP, or the Construction Completion date. Each adjustment in the LSP resulting from a change order shall clearly separate the amount attributable to the Cost of the Work. A change order must be in writing. No course of conduct, verbal discussions or dealings between the parties can be a basis for any claim to change the LSP or contract time. 2. The increase or decrease in the LSP resulting from a change in the Project shall be determined in one or more of the following ways: (Should any costs be required for design of an Alternative System that would be advantageous to the project and result in a deductive change order, the Construction Manager shall include the cost of the redesign services of the Architect so that the Owner can make proper assessment of the cost of such change. Payment for such additional services shall be made by the Owner.) a. by mutual acceptance of a lump sum properly itemized and supported by sufficient substantiating data to permit evaluation by the Architect and Owner; b. by quantity and unit prices stated in the Agreement or subsequently agreed upon; c. by the method provided in Subparagraph 10.3 3. If none of the methods set forth in Clause 10.2 is agreed upon, the Construction Manager, provided Construction Manager receives a written order signed by the Owner, shall promptly proceed with the Work involved. The cost of such Work shall then be determined on the basis of the reasonable expenditures and savings of those performing the Work attributed to the change. However, in the event a Change Order is issued under these conditions, the Construction Manager shall establish an estimated cost of the work and the Construction Manager shall not perform any work whose cost exceeds that estimate without prior written approval by the Owner. In such case, and also under Article 10.2 above, the Construction Manager shall keep and present, in such form as the Owner may prescribe, an itemized accounting together with appropriate supporting data of the increase in the Cost of the Work as outlined in Article 9. The amount of decrease in the LSP to be allowed by the Construction Manager to the Owner for any deletion or change which results in a net decrease in cost will be the amount of the actual net decrease. 4. Should concealed conditions encountered in the performance of the Work below the surface of the ground, which are either at material variance with the conditions indicated by the Drawings, Specifications, or Owner furnished information or at material variance with those conditions ordinarily found to exist in geographic area in which the Project is located, then the LSP and the Construction Completion date shall be equitably adjusted by Change Order upon Construction Manager's adherence to the claim procedures outlined in Article 16 of this Agreement . No adjustments in Contract Time or LSP will be allowed to the extent the concealed or unknown condition should have been reasonably discovered by Construction Manager during pre-construction or pre-proposal review. The only exception to the prohibition of adjustments to time or LSP will be where organic soils on the site when encountered differ significantly, greater or less, than the quantities estimated in providing the LSP. The Construction Manager will propose the methodology and assumptions employed to establish the quantity of materials with the LSP submission; however such methodology and assumptions must be approved by the Owner. In the event the Construction Manager encounters organic soil conditions significantly ("significant" to be determined at LSP) different from its interpretation of the geotechnical reports, and which is materially at variance with the quantities derived through the application of Construction Manager's methodology and assumptions, as approved by the Owner, the Construction Manager must immediately notify the Owner, and the Owner will consider mitigation strategies, which may involve adjustments in contract time or LSP. 5. In the event the Construction Manager encounters on the site material reasonably believed to be asbestos or polychlorinated biphenyl (PCB) which has not been rendered harmless, petroleum waste, biohazardous substances, radioactive waste or any other substance falling within the category of hazardous or toxic waste under the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) or any other state or federal environmental statute or regulation, hereinafter collectively referred to as "hazardous waste," the Construction Manager shall immediately stop Work in the area affected and report the condition to the Owner in writing. Owner shall thereafter as soon as reasonably possible conduct a thorough investigation to determine if the suspected material in the affected area is in fact hazardous waste and shall certify to Construction Manager that such material is not hazardous waste or if such material is in fact hazardous waste that such hazardous waste has been abated and that it is safe to return to the affected area and resume work. The Construction Manager may require the Owner to furnish copies of reports of tests conducted by a qualified testing laboratory acceptable to Construction Manager verifying the absence of such hazardous waste before Construction Manager will be required to resume work. The Contract time and amount shall thereafter be equitably adjusted to account for the time lost due to the encountering of the hazardous waste and the reasonable cost associated therewith pursuant to the procedures for changes orders. The Construction Manager shall, through an analysis of network schedule, have the burden to prove the need for such time delays and associated costs. 6. The Construction Manager shall not be required to perform any work relating to hazardous waste without consent pursuant to the changes clause herein. 10.2 Claims for Additional Cost or Time All claims for additional cost or time shall be made by request for a Change Order submitted as provided in Article 16. As used in this subparagraph, "cost" shall mean the estimated or actual net increase or decrease in cost to the Construction Manager, subcontractor, or sub-subcontractor for performing the work covered by the change, including actual payments for materials, equipment rentals, expendable items, wages and associated benefits to workmen and to supervisors employed full time at the site, insurance bonds and other provable direct costs, including any administrative, accounting, or other indirect or overhead costs, or any wages or benefits of supervisory personnel not assigned full time to the site, or any amount of profit or fee to the Construction Manager, subcontractor or sub-subcontractor. If the Construction Manager is delayed at any time in the progress of the work by any act or neglect of the Owner or the Architect or of any employee of either or by any separate Construction Manager employed by the Owner or by any changes ordered in the work by labor disputes, fire, or unusual delay in transportation, unavoidable casualties or any causes beyond the Construction Manager's control or by delay authorized by the Owner pending resolution of disputes, and such delay extends the completion date, then the dates for completion may be equitably adjusted. Only delays that are determined to extend the critical path for the schedule for constructing the project will result in a time extension. Neither the Owner nor the Construction Manager shall be considered to own the schedule float time. 10.3 Minor Changes in the Project The Owner will have authority to order minor changes in the Project not involving an adjustment in the LSP or an extension of the Construction Completion Date and not inconsistent with the intent of the Drawings and Specifications. Such changes shall be effected by written order. The Documentation of changes shall be determined by the Construction Team, included in the Project Manual and displayed monthly in the PMIS. Changes shall be approved by the Owner and Architect. 10.4 Emergencies In any emergency affecting the safety of persons or property, the Construction Manager shall act at its discretion to prevent threatened damage, injury or loss. Any increase in the LSP or extension of time claimed by the Construction Manager on account of emergency work shall be determined as provided in Article 10. ARTICLE 11 DISCOUNTS [DELETED] ARTICLE 12 PAYMENTS TO THE CONSTRUCTION MANAGER 12.1 Monthly Statements Based upon Applications for Payment submitted to the Owner by the Construction Manager, the Owner shall make progress payments on account of the LSP to the Construction Manager as provided below and elsewhere in the Contract Documents. Each Application for Payment shall be based on a schedule of values to be submitted by the Construction Manager for the Owner's approval at the time the LSP Amendment is entered. The schedule of values, as approved by the Owner, shall be attached to the LSP Amendment as an Exhibit. The schedule of values shall allocate the entire LSP among the various portions of the Work. The schedule of values shall be prepared in such form and supported by such data to substantiate its accuracy as the Owner may require. This schedule of values, after approval by the Owner, shall be used as a basis for reviewing the Construction Manager's Applications for Payment. Applications for Payment shall indicate the percentage of completion of each portion of the Work as of the end of the period covered by the Application for Payment. Subject to other provisions of the Contract Documents, the amount of each progress payment shall be computed as follows: 1. Take that portion of the LSP properly allocable to completed Work as determined by multiplying the percentage completion of each portion of the Work by the share of the LSP allocated to that portion of the Work in the schedule of values, less retainage in the amount set forth below; 2. Add that portion of the LSP properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the completed construction(or, if approved in advance by the Owner, suitably stored off the site at a location agreed upon in writing), less retainage in the amount set forth below; 3. Subtract the aggregate of previous payments made by the Owner; and 4. Subtract amounts, if any, for which the Owner has withheld or nullified as otherwise allowed by this Agreement. If the Owner's Representative determines that the pay request exceeds the amount that may reasonably be due to the Construction Manager for the work done to date, the Owner's Representative shall return the pay request to the Construction Manager with its reasons for rejection within five (5) days of receipt. Otherwise, the pay request shall be forwarded to the Owner for payment. Any pay request forwarded upon recommendation or acquiescence by the Owner's Representative may be reviewed by the Owner and may be returned to the Construction Manager for modification within the timeframe established in applicable Florida Statutes. Ten percent (10%) retainage shall be held on all payments until the contract is fifty percent (50%) complete; except, when approved by the Owner, certain suppliers and subcontractors may be paid the entire amount due when such payment is generally the practice of the industry. At 50% completion, the Owner may approve a reduction of the retainage from 10% to 5% at its discretion. As a condition to the application for the monthly partial pay requisition, the Construction Manager agrees that all as-built information will be recorded within thirty(30) days after receipt of information that a change to the Construction Documents has occurred. 12.2 Final Payment Final payment constituting the unpaid balance of the LSP, shall be due and payable as described in Article 12.4 after Final Completion, provided that the Project be then finally completed, that the Construction Manager has verified by its signature that it has completed all items specified on the attached Exhibit "H" and that this Agreement has been finally performed. However, if there should remain work to be completed, the Construction Manager, the Owner, and the Architect shall list those items prior to receiving final payment and the Owner may retain a sum equal to 200% of the estimated cost of completing any unfinished work and portion of the Construction Manager's retainage, provided that said unfinished items are listed separately and the estimated cost of completing any unfinished items are likewise listed separately. Thereafter, Owner shall pay to Construction Manager, monthly, the amount retained for each incomplete item after each of said items is completed. 12.3 Payments to Subcontractors The Construction Manager shall promptly, within ten (10) days after receipt of payment from the Owner, pay all the amount due to subcontractors less a retainage of ten percent (10%) until the project is fifty percent (50%) complete, and, based on Construction Manager's evaluation of the subcontractor's acceptable performance, the Owner may approve a reduction in retainage from 10% to 5% thereafter. If there should remain items to be completed, the Construction Manager, the Owner, and Architect shall list those items required for completion and the Construction Manager shall require the retainage of a sum equal to 200% of the estimated cost of completing any unfinished items, provided that said unfinished items are listed separately and the estimated cost of completing any unfinished items likewise listed separately. Thereafter, the Construction Manager shall pay to the subcontractors, monthly, the amount retained for each incomplete item after each of said items is completed. Before issuance of final payment without any retainage, the subcontractor shall submit satisfactory evidence that all payrolls, material bills and other indebtedness connected with the Project have been paid or otherwise satisfied, warranty information is complete, as-built markups have been submitted and instruction for the Owner's operating and maintenance personnel is complete. Final payment may be made to certain select subcontractors whose work is satisfactorily completed prior to the total completion of the Project only upon approval of the Owner. 12.4 Construction Manager's Payment Rights Payment for construction services shall be governed and in accordance with Florida Prompt Payment Act Statute 218.735, Timely Payment for Purchases of Construction Services. 12.5 Payments for Materials and Equipment Payments will be made for material and equipment not incorporated in the work but delivered and suitably stored at the site or another location that is insured to protect the Owner's assets subject to prior written approval and acceptance by the Owner on each occasion. 12.6 Withholding Payments To Subcontractors The Construction Manager shall not withhold payments to subcontractors if such payments have been made to the Construction Manager. Should this occur, the Construction Manager shall return such moneys to the Owners, adjusting pay requests and project bookkeeping as required. However, this provision shall not apply should payments to Subcontractors be withheld as a result of procuring normal process paperwork in accordance with the Construction Managers contract with said Subcontractor. The Construction Manager shall, if requested by the Owner, notify the Owner in writing as to the reason for withholding payment. ARTICLE 13 INSURANCE, INDEMNITY AND WAIVER OF SUBROGATION 13.1 Indemnity The Construction Manager agrees to indemnify and hold the Owner and its agents and employees harmless from all claims of liability, damages, losses and costs, including but not limited to reasonable attorney's fees, to the extent that they are caused by the negligence, recklessness, or intentional wrongful misconduct of the Construction Manager or persons employed or utilized by the Construction Manager in the performance of this Agreement. 13.2 Construction Manager's Insurance 1. The Construction Manager shall not commence any construction work in connection with this Agreement until it has obtained all of the following types of insurance and such insurance, naming the City of Ocoee as additional insured, and has been approved by the Owner, nor shall the Construction Manager allow any subcontractor to commence work on its subcontract until all similar insurance required of the subcontractor has been so obtained and approved. All insurance policies shall be with insurers qualified and doing business in Florida with an A.M. Best & Company rating of no less than A. 2. Worker's Compensation Insurance - The Construction Manager shall take out and maintain during the life of this Agreement Worker's Compensation Insurance for all its employees connected with the work of this Project and, in case any work is sublet, the Construction Manager shall require the subcontractor similarly to provide Worker's Compensation Insurance for all of the latter's employees unless such employees are covered by the protection afforded by the Construction Manager. Such insurance shall comply with the Florida Worker's Compensation Law. In case any class of employees engaged in hazardous work under this Agreement at the site of the Project is not protected under the Worker's Compensation statute, the Construction Manager shall provide adequate insurance, satisfactory to the Owner, for the protection of employees not otherwise protected. Employers' liability shall be set at $1,000,000/1,000,000/1,000,000. 3. Construction Manager's Public Liability and Property Damage Insurance - The Construction Manager shall take out and maintain during the life of this Agreement Comprehensive General Liability and Comprehensive Automobile Liability Insurance as shall protect him from claims for damage for personal injury, including accidental death, as well as claims for property damages which may arise from operating under this Agreement, whether such operations are by himself or by anyone directly or indirectly employed by him, and the amount of such insurance shall be minimum limits as follows: a. Construction Manager's Comprehensive General, $1,000,000 Each ($2,000,000 aggregate) Liability Coverages, Bodily Injury Occurrence, & Property Damage Combined Single Limit b. Automobile Liability Coverages, $1,000,000 Each Bodily Injury & Property Damage Occurrence, Combined Single Limit c. Excess Liability, Umbrella Form $2,000,000 Each Occurrence, Combined Single Limit Insurance clause for both Bodily Injury and Property Damage shall be amended to provide coverage on an occurrence basis. The Products and Completed operations portions of the General Liability and Excess Liability policies shall extend for a period of ten (10) years after the Final Acceptance of the Project by the Owner. 4. Subcontractor's Public Liability and Property Damage Insurance - the Construction Manager shall require each of its subcontractors to procure and maintain during the life of the subcontract, insurance of the type specified above or insure the activities of its subcontractors in its policy, as specified above. 5. (Intentionally omitted.) 6. "XCU" (Explosion, Collapse, Underground Damage) - The Construction Manager's Liability Policy shall provide "XCU" coverage for those classifications in which they are excluded. 7. Broad Form Property Damage Coverage, Products & Completed Operations Coverages - The Construction Manager's Liability Policy shall include Broad Form Property Damage Coverage, Products and Completed Operations Coverages. 8. Contractual Liability Work Contracts - The Construction Manager's Liability Policy shall include Contractual Liability Coverage designed to protect the Construction Manager for contractual liabilities assumed by the Construction Manager in the performance of this Agreement. 9. Indemnification Rider a. In any and all claims against the Owner or the Architect or any of their agents or employees by any employee of the Construction Manager, any subcontractor, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable, the indemnification obligations under this Paragraph shall not be limited in any way by any limitation on the amount or type of damages, compensation or benefits payable by or for the Construction Manager or any subcontractor under workers' or workmen's compensation acts, disability benefit acts or other employee benefit acts. b. The obligations of the Construction Manager under this Article 13.2.9 shall not extend to the liability of Architect, its agents or employees, arising out of(1) the preparation or approval of maps, drawings, opinions, reports, surveys, change orders, designs or specifications, or (2) the giving of or the failure to give directions or instruction by Architect, its agents or employees, providing such giving or failure to give is the primary cause of the injury or damage. 10. Builder's Risk Coverage - The Construction Manager shall take out and maintain during the life of this Agreement a "Builder's Risk Policy" completed value form, issued to provide coverages on an "all risk" basis including theft. This coverage shall not be lapsed or canceled because of partial utilization by the Owner prior to final acceptance of the Project. The Owner may elect to take out and maintain this insurance coverage. Should the Owner purchase said insurance, the insurance policy shall have a deductible for each occurrence of$5,000.00. The Construction Manager shall be responsible for losses up to the amount of the deductible. 11.Certificate of Insurance - The Owner shall be furnished proof of coverage of Insurance as follows: Certificate of Insurance form and the actual policies (if requested) will be furnished to the Owner. These shall be completed and signed by an authorized Resident Agent. This Certificate shall be dated and show: a. The name of the insured Construction Manager, the specific job by name and job number, the name of the insurer, the number of the policy, its effective date, and its termination date. b. Statement that the Insurer will mail notice to the Owner and a copy to the Architect at least fifteen (15) days prior to any material changes in provisions or cancellation of the policy. c. Certificate of Insurance shall be in the form as approved by Insurance Standards Office (ISO) and such Certificate shall clearly state all the coverages required in this Section commencing at 13.2 and ending with 13.3(4). 12. Owner is to be named as an Additional Insured under all policies except for Worker's Comp. 13. The insurance evidenced by the certificate shall be primary and non-contributory to any other insurance of the certificate holder. 13.3 Waiver of Subrogation 1. The Owner and the Construction Manager waive all rights against each other, for damages caused by perils covered by insurance provided under Article 13.2 to the extent they are covered by such insurance except such rights as they may have to the proceeds of such insurance held by the Owner and Construction Manager as trustees. The Construction Manager shall require similar waivers from all subcontractors and their sub-subcontractors. 2. The Owner and Construction Manager waive all rights against each other for loss or damage to any equipment used in connection with the Project and covered by any property insurance. The Construction Manager shall require similar waivers from all subcontractors and their sub-subcontractors. 3. The Owner waives subrogation against the Construction Manager on all property and consequential loss policies carried by the Owner on adjacent properties and under property and consequential loss policies purchased for the Project after its completion. 4. If the policies of insurance referred to in this Article require an endorsement to provide for continued coverage where there is a waiver of subrogation, the Owner of such policies will cause them to be so endorsed. Failure to obtain proper endorsement nullifies the waiver of subrogation. 13.4 Insurance as Additional Remedy Compliance with the insurance requirements of this Agreement shall not limit the liability of the Construction Manager, its subcontractors, sub-subcontractors, material suppliers, employees, or agents to the Owner or others. Any remedy provided to the Owner, or the Owner's officers, employees, agents or assigns, by the insurance shall be in addition to and not in lieu of any other remedy available under the Agreement or otherwise. 13.5 No Waiver by Approval/Disapproval Neither approval by the Owner nor failure to disapprove the insurance furnished by the Construction Manager shall relieve the Construction Manager of its full responsibility to provide the insurance as required by this Agreement. ARTICLE 14 TERMINATION OF THE AGREEMENT AND OWNER'S RIGHT TO PERFORM CONSTRUCTION MANAGER'S OBLIGATION 14.1 Suspension by the Construction Manager If the Project is stopped for a period of thirty (30) days under an order of any court or other public authority having jurisdiction or as a result of an act of government, such as a declaration of a national emergency making materials unavailable, through no act or fault of the Construction Manager, or if the Project should be stopped for a period of sixty (60) days by the Construction Manager for the Owner's failure to make payments thereon, then the Construction Manager may submit a Claim pursuant to Article 16 for an equitable adjustment to the Project Schedule as well as to the LSP for mobilization and re-mobilization costs. 14.2 Owner's Right to Perform Construction Manager's Obligations and Termination by Owner for Cause The Owner may terminate this Agreement for any of the following reasons: 1. If the Construction Manager is adjudged as bankrupt, or if it makes a general assignment for the benefit of its creditors, or if a receiver is appointed on account of its insolvency, or if it persistently or repeatedly refuses or fails, except in case for which extension of time is provided, to supply enough properly skilled workmen or proper materials and fails to maintain an established schedule (failure to maintain schedule shall be defined as any activity on the critical path that falls forty-five (45) days or more behind schedule) which has been adopted by the Construction Team, or if it fails to make prompt payment to subcontractors for materials or labor, or persistently disregards laws, rules, ordinances, regulations, or orders of any public authority having jurisdiction, or otherwise materially breaches this Agreement. 2. The Owner may, without prejudice to any right or remedy and after giving the Construction Manager and its surety, seven (7) days written notice, during which period Construction Manager fails to cure the violation, terminate the employment of the Construction Manager and take possession of the site and of all materials, equipment, tools, construction equipment and machinery thereon owned by the Construction Manager, accept assignment of the subcontracts, and may finish the Project by whatever method Owner may deem expedient In such case, the Construction Manager shall not be entitled to receive any further payment until the Project is finished nor shall it be relieved from its obligations assumed under Article 7. Reasonable terminal expenses incurred by the Owner may be deducted from any payments left owing the Construction Manager. In the event the costs for completing the Work, including compensation for any Architect services and expenses, exceed the unpaid balance of the Contract Sum, the Construction Manager shall pay the difference to the Owner. This obligation for payment shall survive termination of this Agreement. However, no such notice is required of the Owner if the furnishing of such notice would be futile. 14.3 Termination by Owner for its Convenience 1. The Owner may, at any time, terminate or suspend this Agreement in whole or in part for the Owner's convenience and without cause. Owner will not incur liability for the issuance of a stop work order. 2. Upon receipt of written notice from the Owner of such termination for the Owner's convenience, the Construction Manager shall: a. Cease operations, as directed by the Owner in the notice; b. Take actions necessary, or that the Owner may direct, for the protection and preservation of the Work; and c. Terminate all existing subcontracts and purchase orders and not enter into further subcontracts and purchase orders, except for Work directed to be performed prior to the effective date of termination stated in the notice. 3. In case of such termination for the Owner's convenience, the Construction Manager shall be entitled to receive payment for any non-deficient Work executed up to the date of said termination. ARTICLE 15 ASSIGNMENT AND GOVERNING LAW 15.1 Neither the Owner nor the Construction Manager shall assign its interest in this Agreement without the written consent of the other except as to the assignment of proceeds. 15.2 This Agreement shall be governed by the Laws of the State of Florida. Venue shall lie exclusively in Orange County, or federal court in Orlando, Florida. The parties waive all rights to trial by jury. ARTICLE 16 NOTICE OF CLAIM: WAIVER OF REMEDIES 16.1 The Owner's liability to the Construction Manager for any claims arising out of or related to the subject matter of this Agreement, whether in contract or tort, including, but not limited to, claims for extension of construction time; for payment by the Owner of the costs, damages or losses because of changed conditions under which the work is to be performed; or for additional work; shall be governed by the following provisions: 1. All claims must be submitted as a Request for Change Order in the manner as provided herein; 2. The Construction Manager must submit a Notice of Claim to Owner within twenty(20) days of the Construction Manager becoming aware of the occurrence, or the event, giving rise to the claim; and 3. Within ten (10) days of submitting its Notice of Claim, the Construction Manager shall submit to the Owner its Request for Change Order, which shall include a written statement of all the details of the claim, including a description of the work affected. The Construction Manager agrees that the Owner shall not be liable for any claim that the Construction Manager fails to submit as a Request for Change Order as provided in this paragraph. 16.2 After receipt of a Request for Change Order, the Owner, in consultation with the Architect, shall deliver to the Construction Manager its written determination of the claim. The City Manager has authority to execute changes orders up to the limits designated in the City of Ocoee Purchasing Code. Above said limits, the City Commission must authorize the change order. 16.3 For work the Construction Manager performs with its own forces, and in addition to the adjustments provided for in Article 8, the Construction Manager's exclusive remedy for delays in performance of the construction caused by events beyond its control, including delays claimed to be caused by or attributable to the Owner or the Architect, including claims based on breach of contract or negligence, shall be a claim submitted in compliance with Article 16.1 above, for an extension of the scheduled construction time. In the event of a change in such work, the Construction Manager's claims for adjustments in the contract sum are limited exclusively to its actual costs for such changes plus 5% for overhead and profit. The Construction Manager expressly agrees that the foregoing constitutes its sole and exclusive remedy for delays and changes in such work, and eliminates any other remedies for claim, for increase in the contract price, delays, changes in the work, damages, losses or additional compensation. 16.4 In the event the Construction Manager's work on the Project is delayed, the Construction Manager's sole and exclusive remedy is an extension of the construction completion date regardless of whether delay is caused by any act or neglect of the Owner, Architect, or is attributable to the Owner or Architect. 16.5 The Construction Manager specifically waives any objection to the use of an LSP for the Construction Phase of the Work and acknowledges that Section 255.103(2), Florida Statutes, provides that the point at which a final decision is made by the City as to whether to use the LSP or GMP pricing option is at the end of the Pre-construction Phase and prior to the execution of any addendum necessary to enter into the Construction Phase of the Work. The instant Agreement has been drafted to support the LSP approach, as that is the method adopted for the Pre-construction Phase of the Work. Should the decision be made by the City to use the GMP approach, additional language may be added to the Agreement via addendum to support the GMP approach. The basic content of this additional language was contained in the sample contract that was part of the original Request for Qualifications solicitation, which shall serve as the basis for any such addendum. ARTICLE 17 DISPUTES 17.1 Harmony The Construction Manager is advised and hereby agrees that it will exert every reasonable and diligent effort to assure that all labor employed by the Construction Manager and his Subcontractors for work on the project shall work in harmony with and be compatible with all other labor being used by building and construction contractors now or hereafter on the site of the project. The Construction Manager further agrees that this provision will be included in all subcontracts of the Subcontractors as well as the Construction Manager's own contract; provided, however, that this provision shall not be interpreted or enforced so as to deny or abridge, on account of membership or non-membership in any labor union or labor organization, the right of any person to work as guaranteed by Article 1, Section 6 of the Florida Constitution. 17.2 Dispute Resolution 1. All claims, disputes and other matters in question (hereinafter referred to as a "Controversy") between the parties to this Agreement arising out of or relating to this Agreement or the breach thereof shall be initially submitted to mediation by a mediator mutually acceptable to both parties. Otherwise, if the parties cannot agree on a mediator, mediation shall be in accordance with the Construction Mediation Rules of the American Arbitration Association ("AAA"). Construction Manager shall require pre-suit mediation in all of its subcontracts for this Project. 2. Should either the Owner or the Construction Manager feel it necessary and appropriate to take any legal action to enforce any of the terms or conditions of this Agreement between said parties, then each party shall be responsible for its own attorney's fees and costs associated with such litigation. ARTICLE 18 (Intentionally omitted.) ARTICLE 19 PUBLIC RECORDS 19.1 The Construction Manager must comply with public records laws, specifically to: This paragraph will survive termination of this Agreement. The City of Ocoee (City) is a public agency subject to Chapter 119, Florida Statutes. The Contractor agrees to comply with Florida's Public Records Law. Specifically, the Contractor shall: 1. Keep and maintain public records required by the City to perform the service. 2. Upon request from the City's custodian of public records, provide the City with a copy of the requested records or allow the records to be inspected or copied within a reasonable time at a cost that does not exceed the cost provided in chapter 119, Florida Statutes, or as otherwise provided by law. 3. Ensure that public records that are exempt or confidential and exempt from the public records disclosure requirements are not disclosed except as authorized by law for the duration of the contract term and following completion of the contract if the Contractor does not transfer the records to the City. 4. Upon completion of the contract, Contractor agrees to transfer at no cost to the City all public records in possession of the Contractor or keep and maintain public records required by the City to perform the service. If the Contractor transfers all public record to the City upon completion of the contract, the Contractor shall destroy any duplicate public records that are exempt or confidential and exempt from public records disclosure requirements. If the Contractor keeps and maintains public records upon completion of the contract, the Contractor shall meet all applicable requirements for retaining public records. All records stored electronically must be provided to the City, upon request from the City's custodian of public records, in a format that is compatible with the information technology systems of the City. 5. A Contractor who fails to provide the public records to City within a reasonable time may be subject to penalties under section 119.10, Florida Statutes. IF THE CONTRACTOR HAS QUESTIONS REGARDING THE APPLICATION OF CHAPTER 119, FLORIDA STATUTES, TO THE CONTRACTOR'S DUTY TO PROVIDE PUBLIC RECORDS RELATING TO THIS CONTRACT, CONTACT THE CUSTODIAN OF PUBLIC RECORDS AT 407-905-3100, EXTENSION 1022, CCDL@ci.ocoee.fl.us, WITH AN OFFICE LOCATED AT 150 NORTH LAKESHORE DRIVE, OCOEE, FLORIDA 34761. ARTICLE 20 ACCOUNTING RECORDS AND AUDIT 20.1 The Construction Manager shall keep full and detailed accounts and exercise such controls as may be necessary for proper financial management under this Agreement; the accounting and control systems shall be satisfactory to the Owner. The Owner and the Owner's accountants or other duly authorized representatives or agents shall be afforded access to the Construction Manager's records, books, correspondence, instructions, Drawings, receipts, subcontracts, purchase orders, vouchers, memoranda, and other data relating to this Project for audit purposes, and the Construction Manager shall preserve these records, documents and data for a period of ten(10) years after final payment, or for such longer period as may be required by law. The Construction Manager shall require all of its subcontractors likewise to retain such records, documents and data. If the Construction Manager receives notification of a dispute or the commencement of litigation regarding the Project within this four-year period, the Construction Manager shall continue to maintain all Project records until final resolution of the dispute or litigation. 20.2 Upon seven (7) calendar days' written notice, from the date of this Agreement to the last date described in the preceding Article 20.1, the Construction Manager shall make its records available during normal business hours to the Owner or its authorized representative(s). Owner and its authorized representative(s) shall be entitled to inspect, examine, review and copy the Construction Manager's records at the Owner's reasonable expense, within adequate work space at the Construction Manager's facilities. Such rights to inspect, examine, review and copy shall extend to the records and documentation of subcontractors. Failure by the Construction Manager to supply substantiating records shall be reason to exclude the related costs from amounts which might otherwise be payable by the Owner to the Construction Manager pursuant to this Agreement. 20.3 This Article, "Accounting Records and Audit," including all access, inspection, copying, auditing, reimbursement and repayment rights shall survive the termination of this Agreement. ARTICLE 21 MISCELLANEOUS 21.1 Limitation of Liability. The Owner shall be liable only to the extent of its interest in the Project, and no elected official, officer, director, partner, agent, or employee of the Owner shall ever be personally or individually liable with respect to this Agreement or the Work. Any subcontract entered into by the Construction Manager shall include the forgoing limitation, which shall be effective in the event the Owner ever succeeds to the Construction Manager's rights and obligations under a subcontract. 21.2 Unless the context of this Agreement otherwise clearly requires, references to the plural include the singular, references to the singular include the plural, the term "including" is not limiting, and the terms "hereof', "herein", "hereunder", and similar terms in the Contract Documents refer to the Contract Documents as a whole and not to any particular provision thereof,unless stated otherwise. 21.3 Gender. Unless the context clearly indicates to the contrary, pronouns having a neuter, masculine or feminine gender shall be deemed to include the others. 21.4 Entire Agreement. This Agreement and the Construction Documents incorporated herein by reference constitute the entire Agreement between the parties with respect to the matters covered by this Agreement. All prior negotiations, representations and agreements not incorporated in this Agreement are cancelled. This Agreement can be modified or amended only by a written document duly executed by the parties or their duly appointed representative. 21.5 Binding Effect. Each and all of the covenants, terms, provisions and agreements contained in this Agreement shall be binding upon and inure to the benefits of the parties and their respective assigns, successors, subsidiaries, affiliates, holding companies and legal representatives, as allowed in this Agreement. 21.6 Notices. All notices shall be in writing, and may be served by (a) depositing the same in the United States mail addressed to the party to be notified, postpaid, and registered or certified with return receipt requested, (b) by delivering the same in person to such party, (i) personal delivery, or (ii) overnight courier, or (c) by facsimile transmission provided that a copy is sent on the same day, by 5 p.m., by either of the methods described in (a) or(b). Notice deposited in the mail shall be deemed to have been given on the third day next following the date postmarked on the envelope containing such notice, or when actually received, whichever is earlier. Notice given in any manner shall be effective only if and when received by the party to be notified. All notices to be given to the parties shall be sent to or delivered at the addresses or facsimile numbers set forth below: If to Owner: CITY OF OCOEE Director of Support Services 150 North Lakeshore Drive Ocoee, FL 34761 Telephone: 407-554-7063 and to CITY OF OCOEE Purchasing Agent 150 North Lakeshore Drive Ocoee, FL 34761 Telephone: 407-905-3100 ext. 1516 Construction Manager: THE COLLAGE COMPANIES Rob Maphis, VP of Operations, COO 585 Technology Park Lake Mary, FL 32746 Telephone: 407-829-2257 By giving the other party at least fifteen (15) days' written notice, each party shall have the right to change its contact person and/or address and specify as its new address any other address in the United States of America. 21.7 Waiver. No consent or waiver, express or implied, by either party to this Agreement to or of any breach or default by another in the performance of any obligations shall be deemed or construed to be consent or waiver to or of any other breach or default by that party. Except as otherwise provided in this Agreement, failure on the part of any party to complain of any act or failure to act by another party or to declare the other party in default, irrespective of how long such failure continues, shall not constitute a waiver of the rights of that party. 21.8 Captions. The headings used for the various portions of this Agreement and the Construction Documents are inserted only as a matter of convenience, and for reference, and in no way define, limit or describe the scope or the intent of this Agreement, any section of this Agreement, or any section of the Contract Documents. 21.9 Severability. In the event the provisions of this Agreement are determined by a Court of competent jurisdiction to be illegal or unenforceable, then such unenforceable or unlawful provision shall be excised from this Agreement, and the remainder of this Agreement shall continue in full force and effect. Notwithstanding the foregoing, if the result of the deletion of such provision will materially and adversely affect the rights of a party, such party may elect, at its option, to terminate this Agreement in its entirety. 21.10 Cumulative Remedies. All rights, powers, remedies, benefits, and privileges are available under any provision of this Agreement to any party, is in addition to and cumulative of any and all rights, powers, remedies, benefits and privileges available to such party under all other provisions of this Agreement, at law or in equity. 21.11 Approval. Whenever any review or approval is required by any party, such party agrees that such review or approval will be promptly and expeditiously prosecuted to conclusion. 21.12 Further Assurances. The parties agree to execute any and all further instruments and documents, and take all such action as may be reasonably required by any party to effectuate the terms and provisions of this Agreement and the transactions contemplated in this Agreement. 21.13 No Partnership or Joint Venture. It is understood and agreed that nothing contained in this Agreement shall be deemed or construed as creating a partnership or joint venture between the parties or any third party, or cause any party to be responsible in any way for the debts and obligations of the other party. 21.14 No Construction Against Drafter. Each of the parties have been represented by legal counsel who have had ample opportunity to, and have, participated in the drafting of this Agreement. Therefore, this Agreement shall not be construed more favorably or unfavorably against any party. 21.15 Third Party Beneficiary. This Agreement has been made and entered into for the sole protection and benefit of the Owner, and its respective successors, and no other person or entity shall have any right or action under this Agreement. 21.16 Force Majeure. With regard to the performance under this Agreement, a party shall not be deemed to be in default of this Agreement, or have failed to comply with any term or conditions if, for reasons beyond the parties reasonable control, including without limitation acts of God, natural disaster, labor unrest, war, declared or undeclared, the existence of injunctions or requirements for obtaining licenses, easements, permits or other compliance with applicable laws, rules and regulations, such performance is not reasonably possible within such time periods, then the time for such performance shall be extended until removal of such reasons beyond the parties reasonable control, provided that the party commences such performance as soon as reasonably possible and diligently pursues such performance. 21.17 Right to Enter this Agreement. Each party warrants and represents, with respect to itself, that neither the execution of this Agreement nor the performance of its obligations under this Agreement shall violate any legal requirement, result in or constitute a breach or default under any indenture, contract, or other commitment or restriction to which it is a party or by which it is bound. Each party also warrants and represents, with respect to itself, that the execution of this Agreement and the performances and obligations under this Agreement shall not require any consent, vote, or approval which has not been obtained, or at the appropriate time shall not have been given or obtained. Each party agrees that it has or will continue to have throughout the term of this Agreement the full right and authority to enter into this Agreement and to perform its obligation under this Agreement. Upon written request, each party agrees to supply the other party with evidence of its full right and authority. 21.18 Public Entity Crime Information Statement and Department. — Section 287.133(2)(a) of the Florida Statutes states: "A person or affiliate who has been placed on the convicted vendor list following a conviction for a public entity crime may not submit a bid on a contract to provide any goods or services to a public entity, may not submit a bid on a contract with a public entity for the construction or repair of a public building or public work, may not submit bids on leases of real property to a public entity, may not be awarded or perform work as a contractor, supplier, subcontractor, or consultant under a contract with any public entity, and may not transact business with any public entity in excess of the threshold amount provided in Section 287.017, for CATEGORY TWO for a period of thirty-six (36) months from the date of being placed on the convicted vendor list." By signing this Agreement, Construction Manager certifies, to the best of its knowledge and belief, that it and its principals: a) Are not presently debarred, suspended, proposed for debarment, declared ineligible or voluntarily excluded from covered transactions by a federal department or agency. b) Have not, within a five-year period preceding the issuance of RFQ #1801 been convicted of or had a civil judgment rendered against them for commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (federal, state or local) transaction or contract under public transaction; violation of federal or state antitrust statutes or commission of embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements or receiving stolen property. c) Are not presently indicted or otherwise criminally charged by a governmental entity (federal, state or local) with commission of any of the offenses enumerated in the preceding paragraph(b). d) Have not within a five-year period preceding the issuance of RFQ#1801 had one or more public transactions (federal, state or local) terminated for cause or default. Construction Manager agrees to notify Owner within 30 days after the occurrence of any of the events, actions, debarments, proposals, declarations, exclusions, convictions, judgments, indictments, information, or terminations as described in paragraphs (a) — (d) above, with respect to Construction Manager or its principals. 21.19 No Waiver of Sovereign Immunity. Nothing herein is intended to serve as a waiver of sovereign immunity by any agency or political subdivision to which sovereign immunity may be applicable. 21.20 Non-Discrimination. The parties shall not discriminate against any employee or participant in the performance of the duties, responsibilities and obligations under this agreement because of race, color, religion, gender, age, marital status, disability, political or religious beliefs, national or ethnic origin. 21.21 Harmony. The Construction Manager is advised and hereby agrees that it will exert every reasonable and diligent effort to assure that all labor employed by the Construction Manager and its Subcontractors for work on the project shall work in harmony with and be compatible with all other labor being used by building and construction contractors now or hereafter on the site of the project. The Construction Manager further agrees that this provision will be included in all subcontracts of the Subcontractors as well as the Construction Manager's own contract; provided, however, that this provision shall not be interpreted or enforced so as to deny or abridge, on account of membership or non-membership in any labor union or labor organization, the right of any person to work as guaranteed by Article 1, Section 6 of the Florida Constitution. 21.22 Construction Manager's Project Records. The Construction Manager's Project Records shall be maintained as prescribed herein above for the minimum period required by State and Federal Law, and shall be made available to the Owner or its authorized representative at mutually convenient times. 21.23 Consequential Damages. The parties mutually waive all claims for consequential damages, except to the extent paid for by insurance maintained for this project or for liquidated damages otherwise recoverable by the Owner and allowed by this Agreement. SIGNATURE PAGE FOLLOWS IN WITNESS WHEREOF, the parties hereto have executed this Agreement the day and year first above written. CONSTRUCTION MANAGER: THE COLLAGE COMPANIES BY: PRINT NAME: rOB mAPHIS TITLE: vICE President of Operations, COO WITNESSES: NAME: NAME: TITLE: TITLE: OWNER: CITY OF OCOEE,FLORIDA ATTEST: APPROVED: BY: BY: Melanie Sibbitt,City Clerk Rusty Johnson,Mayor (SEAL) FOR USE AND RELIANCE ONLY BY APPROVED BY CITY OF OCOEE THE CITY OF OCOEE,FLORIDA COMMISSION AT A MEETING HELD APPROVED AS TO FORM AND LEGALITY on ,under Agenda Item this day of ,2017 SHUFFIELD,LOWMAN&WILSON, P.A. BY: Scott A. Cookson,City Attorney END OF SECTION TRUTH-IN-NEGOTIATION CERTIFICATE The Consultant hereby certifies that all wage rates, and any and all other unit costs supporting the compensation to be paid to the Consultant pursuant to a Services Authorization for the Services as set forth therein, will be accurate, complete, and current at the date of the Services Authorization's execution. WITNESS: [NAME F FIRM] BY: BY: Print Name: Print Name:Jenter name] Title: Title: renter title] STATE OF FLORIDA } COUNTY OF } PERSONALLY APPEARED before me, the undersigned authori- ty, , [ ] well known to me or [ ] who has produced his/her as identification, and known by me to be the of the corporation named above, and acknowledged before me that he/she executed the foregoing instrument on behalf of said corporation as its true act and deed, and that he/she was duly authorized to do so. WITNESS my hand and official seal this day of , 20_. NOTARY PUBLIC Print Name: My Commission Expires: EXHIBIT A To Be Completed Per Project Assignment Construction Team Representatives Owner City of Ocoee, City Commission City Manager Robert D. Frank Owner's Representative Al Butler, Director of Support Services Architect of Record Rhodes+Brito, Architects Ruffin Rhodes, AIA, Project Managing Principal Donald Williams, Architect Construction Manager The Collage Companies CM Representative Rob Maphis EXHIBIT B SAMPLE: To Be Completed per Project Assignment Construction Manager's Personnel During Construction Phase (TO BE COMPLETED AT FINAL LSP) Duration Name Title (Months) Percentage Off-Site Staff On-Site Staff EXHIBIT C SAMPLE: To Be Completed per Project Assignment CERTIFICATE OF SUBSTANTIAL COMPLETION Project: Construction Manager at Risk for Lakeshore Center Expansion RFQ No. 1801 CONTRACTOR Contract For Contract Date This Certificate of Substantial Completion applies to all Work under the Contract Documents or to the following specified parts thereof: To Owner And To Contractor The Work to which this Certificate applies has been inspected by authorized representatives of OWNER, CONTRACTOR and ARCHITECT, and that Work is hereby declared to be substantially complete in accordance with the Contract Documents on , (Date of Substantial Completion). A tentative list of items to be completed or corrected is attached hereto. This list may not be all- inclusive, and the failure to include an item in it does not alter the responsibility of CONTRACTOR to complete all the Work in accordance with the Contract Documents. When this Certificate applies to a specified part of the Work the items in the tentative list shall be completed or corrected by CONTRACTOR within days of the above date of Substantial Completion. The date of Substantial Completion is the date upon which all guarantees and warranties begin, except as follows: The responsibilities between OWNER and CONTRACTOR for security, operation, safety, maintenance, heat,utilities and insurance shall be as follows: RESPONSIBILITIES: OWNER CONTRACTOR The following documents are attached to and made a part of this Certificate: Executed by OWNER on ,20 (OWNER) By The CONTRACTOR accepts this Certificate of Substantial Completion on: , 20 . (Contractor) By END OF SECTION EXHIBIT D SAMPLE: To Be Completed per Project Assignment Final Completion Forms CONSTRUCTION MANAGER'S AFFIDAVIT OF CONTRACT COMPLETION OWNER: City of Ocoee PROJECT: Lakeshore Center Expansion CONSTRUCTION MANAGER: The Collage Companies CONTRACT FOR: Construction Manager at Risk CONTRACT DATE: CONTRACT AMOUNT: CONSTRUCTION MANAGER'S AFFIDAVIT I solemnly swear and affirm: That the work under the above-named Contract and all amendments thereto have been completed in accordance with the requirements of said Contract: that except as noted on the attached sheet, all costs incurred for equipment, materials, labor, and services against the Project have been paid; that no liens have been attached against the Project; that no Notices of Non-Payment have been served against the Payment Bond issued for this Project; that, except as noted on the attached sheet, no suits are pending by reason of work on the Project under the Contract; that all Workmen's Compensation claims are covered by Workmen's Compensation insurance as required by law; and that all public liability claims are adequately covered by insurance. CONSTRUCTION MANAGER: (Seal) Title: Date: STATE OF: COUNTY OF: Personally appeared before me this day of 20 , known (or made known) to me to be the of , who, being by me duly sworn, subscribed to the foregoing affidavit in my presence. Notary Public Typed My Commission Expires: EXHIBIT E SAMPLE: To Be Completed per Project Assignment Construction Manager's Staff Positions to be Assigned to the Pre-construction/Design Phases Name Title Duration Percentage (Months) Off-Site Staff On-Site Staff EXHIBIT F SAMPLE: To Be Completed per Project Assignment Owner's Representative(s) and Designee(s) Owner's Representative(s) Director of Support Services or other City Manager designee Total Dollar Limit per Occurrence, the City Manager in conjunction with the Owner's Representative(s) is authorized to obligate the Owner: $ (To be determined at Final LSP) EXHIBIT G Partial Payment Request Form APPLICATION AND CERTIFICATE FOR PAYMENT FORM Application No. Progress Payment Final Payment P.O. No.: Contractor: Contract Date: Application Date: For Period Ending City Project Nos.: RFQ #1801 Project Name: Construction Manager at Risk for Lakeshore Center Expansion Construction Start Date: End Date: Construction Days—Total: Elapsed: Remaining: 1. Original Contract Amount $ 2. Sum of Approved Change Orders to Date (from Table) $ 3. Current Contract Amount (Sum of Lines 1 and 2) $ 4. Total of Prior Pay Applications (including retainage) $ 5. Amount of this Pay Application(including retainage; from Bid Item Quantity Spreadsheet) $ 6. Total Earned to Date (Sum of Lines 4 and 5) $ 7. Total of Payments Made by City to Date $ 8. Retainage Held from Prior Pay Applications $ 9. Retainage to Be Held in this Pay Application $ 10. Total Retainage Held to Date (Sum of Lines 8 and 9) $ 11. Total Earned to Date less Retainage(Line 6 minus Line 10) $ 12. Total Earned less Retainage for this Pay Application (Line 5 minus Line 9) $ 13. Total Amount to Be Paid by City for this Application (Line 11 minus Line 7) $ Approved Change Orders Change Date Approved Date Accepted Total Change in Order No. by City by Contractor Contract Price Contractor's Certification The undersigned Contractor hereby swears under penalty of perjury that (1) all previous progress payments received from the Owner on account of Work performed under the contract referred to above have been applied by the undersigned to discharge in full all obligations of the undersigned incurred in connection with Work covered by prior Applications for Payment numbered 1 through inclusive (not applicable for first application.); and (2) all materials and equipment incorporated in said Project or otherwise listed in or covered by this Application for Payment are free and clear of all liens, claims, security interest and encumbrances; (3) all Work covered by this Application for Payment is in accordance with the Contract Documents and not defective as that term is defined in the Contract Documents. Dated , 20 (Contractor) By: (Name) (Title) COUNTY OF STATE OF Before me on this day of , 20_, personally appeared , known to me, who being duly sworn, deposes and says that (s)he is the of the Contractor above mentioned; that(s) he executed the above Application for Payment and statement on behalf of said Contractor; and that all of the statements contained therein are true, correct and complete. Notary Public My Commission Expires Payment shown on Line 13 is recommended by City's Owner's Representative and authorized by the Owner: By: Date: Representative's Authorized Signature By: Date: Owner's Authorized Signature Title EXHIBIT H Final Payment Request Check List Items to be submitted with General Contractor's Request for Final Payment 1. Pay Request(1 copy with original signatures and original seals, noted as FINAL) 2. Final Schedule of Contract Values 3. Consent of Surety to make Final Payment (signed and sealed) 4. Power of Attorney from Surety for Release of Final Payment (signed, sealed and dated same as Consent of Surety) 5. Affidavit of Contract Completion(Exhibit D) 6. Satisfactory Conclusion or Release of Lien from all Subcontractors or laborers who have filed Intent to Lien or have indicated non-payment from the General Contractor 7. Construction Manager's Guarantee of Construction for one (I) year from the date of Substantial Completion 8. Copy of the approval by the Architect and the transmittal to the Owner of Manuals, Shop Drawings, As-Builts (2 sets of digital media (Flash Drives), two sets of prints), brochures, warranties, and list of Subcontractors with telephone numbers and addresses 9. Verification that Owner's personnel has been trained in the operation of their new equipment, attendance lists and videos 10. Other special Warranties are required by Specifications in the name of the Owner 11. Copy of Certificate of Completion EXHIBIT I Contract Drawings & Specifications To be completed at Final LSP EXHIBIT J Schedule of Values To be completed at Final LSP EXHIBIT K Clarifications,Assumptions,Exclusions and Allowances To be completed at Final LSP EXHIBIT L PERFORMANCE BOND KNOW ALL MEN BY THESE PRESENTS that , (hereinafter referred to as "Principal"), and t a corporation organized under the laws of the State of and licensed to do business in the State of , (hereinafter referred to as "Surety"), and held and firmly bound unto the City of Ocoee, Florida, as Obligee, (hereinafter referred to as "Obligee"), in the Penal Sum of , for the payment of which sum well and truly made, Principal and Surety bind themselves, their heirs, personal representatives, successors and assigns,jointly and severally, firmly by these presents. WHEREAS, Principal has by written agreement dated ,entered into a contract, (hereinafter referred to as the "Contract") with Obligee for the construction of RFO #1801 Construction Manager at Risk for Lakeshore Center Expansion (hereinafter referred to as the "Project") in accordance with the plans and specifications prepared by dated ; and NOW, THEREFORE, THE CONDITIONS OF THIS OBLIGATION IS SUCH THAT IF Principal shall well and truly perform all the undertakings, covenants, terms, conditions, and agreements of said Contract including, but not limited to, the making of payments to persons or entities providing labor, materials or services to Principal under the Contract, within the time provided therein, and any extensions thereof that may be granted by the Obligee, and also during the life of any warranty or guaranty required under said Contract, and shall also well and truly perform all undertakings, covenants, terms, conditions, and agreements of any and all duly authorized and modifications of said Contract that may hereafter be made, and shall pay, compensate, indemnify and save harmless the said Obligee of and from any and all loss, damage and expense, or from any breach or default by Principal under the Contract, including, but not limited to, liquidated damages, damages caused by delays in performance of the Principal, expenses, cost and attorneys' fees, including appellate proceedings, that Obligee sustains resulting directly or indirectly from failure of the Principal to perform the Work identified by the Contract, then this obligations shall be null and void; otherwise, it shall remain in full force and effect and Surety shall be liable to Obligee under this Performance Bond. The Surety's obligations hereunder shall be direct and immediate and not conditional or contingent upon Obligee's pursuit of its remedies against Principal, and shall remain in full force and effect notwithstanding (I) amendments or modifications to the contract or contract entered into by Obligee and Principal without the Surety's knowledge or consent; (ii) waivers of compliance with or any default under the Contract granted by Obligee to Principal or by Principal to Obligee without the Surety's knowledge or consent; (iii) the discharge of Principal from its obligations under the Contract as a result of any proceeding initiated under The Bankruptcy Code of 1978, as the same may be amended, or any similar state or federal law, or any limitation of the liability of Principal or its estate as a result of any such proceedings; or (iv) any other action taken by Obligee or Principal that would, in the absence of this clause, result in the release or discharge by operation of law of the Surety from its obligations hereunder. In the event that the Surety fails to fulfill its obligations under this Performance Bond, then the Surety shall also indemnify and save the Obligee harmless from any and all loss, damage, cost and expense, including reasonable attorneys' fees and other legal costs for all trial and appellate proceedings, resulting directly or indirectly from the Surety's failure to fulfill its obligations hereunder. This paragraph shall survive the termination or cancellation of this Performance Bond. The obligations set forth in this paragraph shall not be limited by the Penal Sum of this Bond. Any changes in or under the Contract or the Contract and compliance or noncompliance with any formalities connected with the Contract or the Contract or the changes therein shall not affect Surety's obligations under this bond, and Surety hereby waives notice of any such changes. Further, Principal and Surety acknowledge that the Penal Sum of this bond shall increase or decrease in accordance with approved changes or modifications to the Contract. The said Principal and the said surety agree that this bond shall inure to the benefit of all persons supplying labor and material in the prosecution of the work provided for in the said subcontract, as well as to the Obligee, and that such persons may maintain independent actions upon this bond in their own names. IN WITNESS WHEREOF, the Principal and Surety have executed this instrument under their several seals on the day of , 20_, the name and corporate seal of each corporate party being hereto affixed and these presents fully signed by its undersigned representative, pursuant to the authority of its governing body. Signed, sealed and delivered in the presence of: Principal By: (SEAL) (Official Title) Surety By: (SEAL) (Official Title) NOTES: If Principal and Surety are corporations, the respective corporate seal should be affixed and attached. Surety shall execute and attach a certified copy of Power of Attorney Appointing Individual Attorney-In-Fact for execution of Performance Bond on behalf of Surety. END OF SECTION EXHIBIT M Statutory Payment Bond Pursuant to Florida Statutes, 255.05, et seq. KNOW ALL MEN BY THESE PRESENTS,THAT (hereinafter called the "Principal"), as Principal, and , a corporation organized and existing under the laws of the State of , hereinafter called the "Surety"), as Surety, are held and firmly bound unto the City of Ocoee, Florida, (hereinafter called the "Obligee"), by bond number in the sum of Dollars and Cents ($ ), for the payment of which sum well and truly to be made, the said Principal and Surety bind themselves, and their respective heirs, administrators, executors, successors and assigns,jointly and severally, firmly by these presents. WHEREAS, the Principal has entered into a written Contract with the Obligee dated , 20_ to perform, as Contractor, in accordance with the Contract and Contract Documents, which Contract and Contract Documents are hereby incorporated herein by reference. NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the Principal promptly makes payments to all claimants, as defined in Section 255.05 (1), Florida Statutes, that provide or furnish the Principal with labor, materials, or supplies, used directly or indirectly by Principal in the prosecution of the work provided for in the contract, then this obligation shall be null and void; otherwise it shall remain in full force and effect. The Principal and the Surety agree that this Bond shall inure to the benefit of all claimants, as defined in Section 255.05 (1), Florida Statutes, that provide or furnish the Principal with labor, materials, or supplies, used directly or indirectly by Principal in the prosecution of the work provided for in said Contract, and that any such claimant may maintain an independent action upon this Bond in its own name. The provisions of Florida Statutes, Section 255.05, et seq. are hereby incorporated herein by reference and made a part of this payment bond including, but not limited to, the notice and time limitation provisions in subsection (2). Any action instituted by a claimant under this bond for payment must be in accordance with the notice and time limitation provisions in Section 255.05 (2), Florida Statutes. IN WITNESS WHEREOF, the above bounden parties have executed this instrument under their several seals this day of 20_, the name and corporate seal of each corporate party being hereto affixed and these presents duly signed by its undersigned representative, pursuant to authority of its governing body. (Seal) (Principal) By (Name &Title) (Signature) Witness or Secretary's Attestation (Seal) (Surety) By (Name &Title*) (Signature) Witness or Secretary's Attestation *Attach Power-Of-Attorney END OF SECTION UCOLLAGE CONSTRUCTION • INTEGRATED SERVICES December 22, 2017 DESIGN BUILDERS GENERAL CONTRACTORS CONSTRUCTION MANAGERS CITY OF OCOEE 150 N. Lakeshore Drive com+,meoroQuality Ocoee, FL 34761 TRANSMITTED VIA EMAIL (abutter@ci.ocoee.fl.us) ATTN: Mr. Al Butler, Support Services Director Project: LAKESHORE CENTER EXPANSION PROJECT Subject: Pre-Construction Phase Fee Proposal Dear Mr. Butler: Thank you for taking time to meet with me yesterday to discuss the upcoming Lakeshore Center Expansion project. We are excited for this opportunity and look forward to working with you and the rest of the project team to make this project a success. As requested, we have evaluated the costs associated with Pre-construction Phase services as you described during our meeting. We are pleased to submit this proposal to perform Pre-construction phase services for this project in the amount of$26,675. This proposal is predicated on the understanding that the Pre- construction Phase will coincide with the two remaining phases of the design, as described below. • 60% Construction Documents Phase. Collage is to provide design review and recommendation services for the current (60% CD) set of design documents. Because of the anticipated design phase timeline and need for an accelerated review of this design, the services will not consist of design review reports as described in the CM Agreement. Rather, Collage is to conduct a preliminary evaluation of the design for constructability, schedule, anticipated cost and coordination with other adjacent ongoing projects. THE COLLAGE COMPANIES Collage will meet with the City and design team to discuss the various corpora.office findings and review design recommendations. 585 Technology Park L eMary.Roida32748 • Construction Documents Phase. It is anticipated that the CD design P407.829.25T package will be provided in January 2018, enabling Collage to provide Pre- construction services for that package. Collage will provide the design review and recommendations for this phase of the design, leading up to the www.coIlage-usa.corn development of a construction cost proposal. ■ CG 0020818 THE MOST INFORMED CONSTRUCTION SERVICES COMPANY' Additionally, it is our understanding that the City may desire a lump sum structure OESAGNBUILDERS of agreement for construction phase services in lieu of the Guaranteed Maximum GENERAL CONTRACTORS Price (GMP) approach that is currently described in the CM Agreement. There are a coNSTRUCTIONMANAGERS number of contract requirements that are only applicable in a GMP-based approached and, therefore, those provisions will need to be modified at the time of �t ousop, the amendment. Thank you again for the opportunity to work with you on this project. Please let us know if there are any questions, comments, or if any additional information is required. Sincerely, THE COLLAGE COMPANIES Digitally signed by Rob Maphis ,/ /Vi/ DN:cn=Rob Maphis,cm-The Collage Companies,ou,email=rmaphis@collage- usa.com,c=US Date:2017.12.22 09:59:04-05'00' Rob Maphis Vice President of Operations, COO cc: Brian Walsh Steve Pinyot Keith Kolakowski a THE COLLAGE COMPANES Corporate Canoe 585 TeohnOOQy Park Lake Mary.Florkle 32748 P 407.829.2257 F 407 8292258 S www ooitape-uYMOef a CG CO20818 THE MOST WORMED CONSTRUCT{ON SSRYiCES COMPANY'