Item #05 Approval to Increase the Construction Phase Budget Allocation for the Lakeshore Center Expansion Project to $3,900,000 and the Total Project Budget for All Identified Needs to $4,300,000 Ocoee florida AGENDA ITEM COVER SHEET Meeting Date: May 15, 2018 Item # 5 Reviewed By: ' / Contact Name: Al Butler, Director Department Director: %�"'; Contact Number: 407-554-7063 City Manager: / IIP "I. Subject: Approval to increase the construction phase budget alloc. ion for the Lakeshore Center Expansion project to $3,900,000 and the total project budget for all identified needs to $4,300,000. Background Summary: The Lakeshore Center Expansion project was designed by Rhodes + Brito, architects, under a continuing services contract with the city. Given the complexity of the project, procurement of a construction firm to build the facility was undertaken using the construction manager at risk method (CM at Risk), as provided in §255.103, Florida Statutes. This relatively new way of hiring a contractor uses the same qualifications-based approach (Request for Qualifications, or RFQ) used for hiring licensed professionals, such as architects and engineers. This selection method was used because it requires the contractor to be involved in the design of the building, which provides two benefits. First, the contractor can provide input to the design process that could lower the difficulty and cost of construction. Second, the extensive interaction with the plans prior to providing the city with a price for the construction work allows the builder to become very familiar with the plans and for the city to avoid issues related to typical low-bid procurements. Failure of the contractor to understand the plans was a source of continuing difficulty with the building's original construction. The City Commission awarded the work to the Collage Design & Construction Group, Inc., d.b.a., The Collage Companies, which has completed the pre-construction portion of their work. In accordance with §255.103(2), Florida Statutes, the CM at Risk provided a guaranteed maximum price (GMP) and a guaranteed completion date. The original GMP was $3,492,279, which was used by the City Commission to establish a construction phase budget of $3.6 million. As noted in the related agenda report, "some design details are still being addressed, including changes requested by the city following completion of the construction documents, and the final precise cost of some finish items is not yet known, particularly those items needed later in the project." Subsequent plan changes, construction method selections, value engineering modifications, and inclusion of items previously excluded from the GMP but necessary for the building to be usable have increased the construction cost GMP to $3,854,718. This number includes coverage of some items that are still to be resolved at a "worse-case" level, plus a contractor's contingency of $95,000. Beyond the capital cost of construction, there is also the need to acquire fixtures, furnishings, and equipment (FF&E) that are outside the scope of the work being performed by the CM at Risk. These items include tables, chairs, portable dance floor, some AV equipment, kitchen equipment, and other items needed to utilize the enlarged banquet space to its full capacity. Construction must begin by May 18 if the project is to meet its deadline for exterior construction to be finish before the area is needed for Founders' Day activities November 1. Issue: Should the City Commission increase the authorized budget allocation for construction services related to the Lakeshore Center Expansion project to $3,900,000 and the total project budget to $4,300,000? Recommendation: Staff recommends that the City Commission increase the total project budget to $4.3 million and the budget allocation for construction to $3.9 million. Attachment: Revised GMP construction phase cost estimate from the CM at Risk, The Collage Cos. Financial Impact: The original 2017 General Fund Capital Budget Bond allocation for the Lakeshore Center Expansion project was $4 million for construction; however, this budget must also cover the cost of design and FF&E needs. At the time the construction phase work was awarded at a level of $3.6 million, the unencumbered balance for the project budget was $3,731,316.80 and the total cost of the project was still under the $4 million budget. Although the cost of construction remains less than $4 million, the cost of design services, construction administration, and FF&E collectively push the total cost beyond the existing project budget allocation. Thus, an additional $300,000 is needed in the project budget in order to proceed. The proposed source of the additional budget is the Recreation Impact Fund, which has sufficient funds for this purpose. The budget addition will raise the total project budget to $4.3 million. This funding level is required in order to make the GMP commitment while also reserving funds for FF&E purchases, but should be more than what may ultimately be needed given the possibility of savings that would put the final cost below the GMP. Accordingly, the City Manager should be empowered to make adjustments within the total project budget up to the limits of his purchasing authority and to return funds to their original source or re-allocate unused budget to meet other needs related to Downtown Redevelopment capital projects. Type of Item: (please mark with an 'x') Public Hearing For Clerk's Dept Use: Ordinance First Reading x Consent Agenda Ordinance Second Reading Public Hearing Resolution Regular Agenda x Commission Approval Discussion&Direction Original Document/Contract Attached for Execution by City Clerk Original Document/Contract Held by Department for Execution Reviewed by City Attorney N/A Reviewed by Finance Dept. (L N/A ::COLLAGE CONSTRUCTION • INTEGRATED SERVICES May 4, 2018 DESIGN BUILDERS GENERAL CONTRACTORS CITY OF OCOEE CONSTRUCTION MANAGERS 150 N. Lakeshore Drive Ocoee, FL 34761 Committed to Quality TRANSMITTED VIA EMAIL(abutler@cLocoee.fl.us) ATTN: Mr. Al Butler, Support Services Director Project: LAKESHORE CENTER EXPANSION PROJECT Subject: GMP Proposal Dear Mr. Butler: We are pleased to provide you with a GMP Proposal for the Lakeshore Center Expansion Project. It is based upon the 95% Construction Documents dated 2/14/18, bid clarifications, and alternates. Per your direction we have included several alternates as accepted, and incorporated them into this GMP. Alternates seven (ALT7)through eleven (ALT11) have been migrated to the allowances section, given that the design of these elements is still in progress as we anticipate the 100% document release imminently. Enclosed please find the Summary of Costs including incorporated allowances and alternates, a detailed list of accepted and rejected alternates, a list of Clarifications, Assumptions, Exclusions &Allowances, Document Log, and our most recent schedule. Please do not hesitate to contact me if there are any questions or if any additional information is required. Sincerely, • THE COLLAGE COMPANIES THE COLLAGE COMPANIES Corporate Office - 585 Technology Park Keith Kolakowski lake Maps Florida 32746 Pre-Construction Engineer P 407.829.2257 F 407.829.2258 • www.collage-use.com cc: Brian Walsh Rob Maphis • Steve Pinyot CC 00708,6 TOC'''OST INFORMED CCNSTCUCTrON SERVICES 00001.0:' U COLLAGE CONSTRUCTION / iNTEOR ATE() SERVICES SUMMARY OF COSTS Guaranteed Maximum Price PROJECT: Lakeshore Community Center Expansion LOCATION: Ocoee, FL SQUARE FEET: 6,125 Addition/8,548 Selective Renovation/2,484 Storage Building ARCHITECT: rhodes+brito ESTIMATOR: K. Kolakowski DATE: 5/4/2018 REV: 4 DESCRIPTION QTY UNIT UNIT COST TOTAL COST NOTES COST OF WORK SUB TOTAL BUILDINGS 1 LS — 2,617,163 SUB TOTAL SITE WORK 1 LS — 238,367 GENERAL CONDITIONS 1 LS — 392,660 CONTRACTOR'S CONTINGENCY 1 LS — 95,000 BUILDER'S RISK INSURANCE 1 LS — 10,296 PERFORMANCE&PAYMENT BOND 1 LS — 37,381 SUB TOTAL 3,390,867 CM FEE CM FEE 8 % -- 271,269 TOTAL GUARANTEED MAXIMUM PRICE 3,662,136 ACCEPTED ALTERNATES SUB TOTAL ACCEPTED ADDITIVE ALTERNATES 1 LS — 33,480 SUB TOTAL ACCEPTED VE ALTERNATES 1 LS — -148,666 SUB TOTAL ACCEPTED ALTERNATES -115,186 ALLOWANCES Proposed Accepted 1.AudioNisual Systems $ 193,230 $ 193,230 Previously"ALIT 2.CCN, CATV,Voice/Data Cabling $ 35,098 $ 35,098 I Previously"ALTS" 3. Provide non-carrier HVAC equipment&controls No Cost No Cost Previously"ALT9" 4. Relocate Family RR 101 to bridal locker area(Deleted @ IT Rm) $ 19,440.00 $ 19,440 Previously"ALT10" 5. Expand Office 102 into exist.Family RR 101 No Cost I No Cost Previously"ALT11" 6.Forthcoming 100%document changes $ 50,000.00 I S 50,000 Pending Acceptance 7.Acoustical and drywall modifications for low voltage work $ 10,000.00 $ 10,000 Pending Acceptance _ SUB TOTAL ACCEPTED ALTERNATES 307,768 TOTAL GMP With Accepted Alternates&Allowances: 3,854,718 SQUARE FOOT COST ANALYSIS Building/Area Square Footage Approximate Value Cost/SF New Addition and Renovation 14,673 3,327,215 $ 226.76 Storage Building 2,484 289,136, $ 116.40 Site Work -- 238,367 -- TOTAL PROJECT 17,157 3,854,718. $ 224.67 ICOLLAGE CONSIRUCTiON / INTEGRATED SERVICES ALTERNATES Guaranteed Maximum Price PROJECT: Lakeshore Community Center Expansion LOCATION: Ocoee, FL SQUARE FEET: 6,125 Addition/8,548 Selective Renovation/2,484 Storage Building ARCHITECT: rhodes+brito ESTIMATOR: K. Kolakowski DATE: 5/3/2018 REV: 4 DESCRIPTION QTY UNIT UNIT COST TOTAL COST NOTES ADDITIVE ALTERNATES _ Proposed Accepted ALT1 -Provide material testing&inspection services $ 10,207 Rejected By City ALT2-Provide threshold inspection services $ 7,587 Rejected By Others ALT3-Temporary cooling of existing facility while chiller is offline $ 11,880 $ 11,880 Pending Acceptance ALT4-Temporary utility consumption costs(water,electric) $ 21,600 $ 21,600 Pending Acceptance ALTS-Landscaping& Irrigation $ 36,720 Rejected By City ALT6-Retaining wall-Pending Design Clarifications $ 9,705 Rejected Not Required ALT7-AudioNisual Systems-Pending Clarifications Moved to Allowances Moved to Allowances 1 ALT8 -CCTV, CATV,Voice/Data Cabling Moved to Allowances Moved to Allowances ALT9-Provide non-carrier HVAC equipment&controls Moved to Allowances Moved to Allowances ALT10-Relocate Family RR 101 to bridal locker area(Deleted @ IT Rm) Moved to Allowances Moved to Allowances ALT11 -Expand Office 102 into exist. Family RR 101 Moved to Allowances Moved to Allowances ALT12-Manual control option for areas under lighting control system $ - Rejected Not Required ALT13-Relocate arbor&grape vine to owner decided location $ - Rejected Not Required ALT14-Relocate exist.dumpster to owner decided location $ - Rejected Not Required SUB TOTAL Additive Alternates $ 33,480,00 VALUE ENGINEERING ALTERNATES Proposed Accepted VE1-Alternate Flooring Manufacturers $ (5,225) Rejected VE2-Alternate Light Fixture Package $ (23,760) Rejected VE3-Altemate Horizontal Folding Partition Wall in lieu of Skyfold $ (128,845) $ (128,845) Accepted VE4-Utilize Conan solid surface in lieu of Zodiaq $ (13,044) $ (13,044)Accepted VE5-Maintain IT Rm 117 location&eliminate req'd demo&conduit $ (2,457) $ (2,457) Pending Acceptance VE6-Altemate'retrofit'layout for Mens Room 110 $ (1,620) $ (1,620) Pending Acceptance VE7-Alternate acoustical ceiling manufacturer at Lakeview Room $ (2,700) $ (2,700) Pending Acceptance VE8-Alternate layout of Office 102, Family RR 101 $ - Rejected SUB TOTAL VE Alternates $ (148,666.32) :COLLAGE CONStFUC'IC r. / It C FvrC ; Guaranteed Maximum Price CLARIFICATIONS, ASSUMPTIONS, EXCLUSIONS & ALLOWANCES PROJECT: Lakeshore Community Center Expansion LOCATION: Ocoee,FL SQUARE FEET: 6,125 Addition/8,548 Selective Renovation/2,484 Storage Building ARCHITECT: rhodes+brito ESTIMATOR: K.Kolakowski DATE: 5/4/2018 REV: 4 . .. � ' m t4' +-r,< _.,,..�,� >•� ." � ,� tea= -.. ��. .:� - ' .,,r- „ .� The following is a list of clarifications--where conflicts exist between these clarifications and the contract documents,these clarifications shall take precedence. The GMP is based upon the documents referenced within the attached document log,and does not reflect any permit review comments. Due to ongoing material price increases in the market,this GMP is only valid until May 16th,2018 after which our subcontractors and suppliers are unable to hold their pricing and may need to adjust. DIVISION 1 INDIRECT WORK 1. Builder's Risk Insurance Policy is included 2. Performance and payment bond Is Included 3. The cost of all permits and impact fees are not included and understood to be waived by the City of Ocoee. 4. The owner is providing for the following services:material testing and inspections,threshold inspection.An alternate is provided should the owner elect for Collage to provide these services. 5. Temporary electric and water consumption costs for the existing facility have been offered as an additive alternate for up to 12 months. 6. Temporary cooling costs for the existing facility have been offered as an additive alternate for up to 6 months. 7. Relocation or removal of owner furnishings,fixtures and equipment induding kitchen equipment,audio visual equipment and devices, wifi routers,security camera system,voice and data cables and devices,digital signage and wall mounted monitors,fax machines and telephones,tables,and chairs are excluded and expected to be removed from the building by the owner by April 17th. 8. The clock controller,wireless mics,and all assistive listening buds,chargers,transmitters are assumed to be either left in place,or otherwise relocated at the owners request to the new equipment room by the AV contractor contemplated in Allowance#1. 9. It is our understanding that our staging and new construction areas will take over the existing north parking lot,and parts of the south parking lot,and the city will provide for alternate parking for it's employees. DMSION 2:DEMOLITION 10. Testing,removal and remediation of any existing hazardous materials are not included. 11. The maintenance,trimming or relocation of existing plants to remain is not included. 12. Relocation of the existing arbor&grape vine is excluded,but is offered as an alternate pending owner chosen location and determination of costs including arborist.If decision is not made prior to demolition,arbor and grape vine will be demolished&removed. 13. Cleanout of existing storm structures outside the project limits is not included. 14. Asbestos survey and any required remediation is not included. DMSION 3:CONCRETE 15. No Clarifications DMSION 4:MASONRY 16. No Clarifications DMSION 5:METALS 17. No Clarifications DMSION 6:WOOD AND PLASTICS 18. No Clarifications NICOLLAGE / , Guaranteed Maximum Price CLARIFICATIONS, ASSUMPTIONS, EXCLUSIONS & ALLOWANCES PROJECT: Lakeshore Community Center Expansion LOCATION: Ocoee, FL SQUARE FEET: 6,125 Addition/8,548 Selective Renovation/2,484 Storage Building ARCHITECT: rhodes+brito ESTIMATOR: K.Kolakowski DATE: 5/4/2018 REV: 4 DMSION 7:THERMAL AND MOISTURE PROTECTION 19. New roof system is included as an Englert Series 2500, 16"wide,T high,90-degree seam,24 ga.Galvalume with Permacolor 3500 two-step finish in Patina Green with 35 year material warranty. The finish color is to match the existing roof system,but is not guaranteed to match. 20. Roof deck foam is included as R-19 open cell foam with no thermal barrier required per the Bid Q&A DIVISION 8:DOORS AND WINDOWS 21. No Clarifications DIVISION 9:FINISHES 22. Painting of the exterior of the existing facility,as well as interior exposed block wall at the storage building is included. 23. Janitor Room 134 flooring is included as VCT per P-RFI#010. Quarry tile as shown in that same room on sheet ID101 is not included. DIVISION 10:SPECIALTIES 24. Lockers are included as a custom millwork item. DIVISION 11:EQUIPMENT 25. Portable projection screens indicated on sheet A201 are excluded and considered an owner furnished item. DIVISION 12:FURNISHINGS 26. Draperies DP-1 and DP-2 as shown on the finish schedule are not quantified on the drawings and are therefore not included. DMSION 21:FIRE SUPPRESSION 27. No fire pump is included and the necessary water supply flow and pressure is presumed to be adequate based on the existing system. 28. Removal,replacement or alteration of existing sprinkler heads where no ceiling work is performed is not included. 29. Removal,replacement or modification of existing sidewall fire sprinklers at existing porches and balconies is not included. 30. Temporary Fire protection or fire watch during construction is not included. Temporary fire extinguishers as required by OSHA are included. DIVISION 22:PLUMBING 31. No Clarifications DMSION 23:HEATING VENTILATING AND AIR CONDITIONING(HVAC) 32. Carrier equipment and controls are included as specified but the owner may be"revisiting the HVAC control situation given the current operating staffs issues with the existing Carrier control system. A decision on this matter requires additional consultation with Public Works staff. A non-Carrier control option may be selected if it would offer greater performance and reliability. [The Owner will]need additional information about that"multi-vendor"control choice in order to make a final decision. A no-cost allowance has been included for a York chiller combined with a non-Carrier control option. 33. Owner will retain salvage rights to the existing chiller. 'On-site removal of the existing chiller upon replacement is included.Relocation to an off-site location is not included. DMSION 26,27&28:ELECTRICAL,COMMUNICATIONS,ELECTRONIC SAFETY AND SECURITY 34. Conduit,stubs and backer boxes for low voltage systems have been included as shown in the documents.Voice/Data cabling,CCTV, CATV,Audio Visual systems,and access control systems,devices and cable trays have been offered as an allowance pending further clarification. 35. All relocation of low voltage system cabling 8 devices is excluded and expected to be completed as required by owner by May 16,2018. 36. The eight(8)existing porch fans will remain in place. There will only be three(3)new fans at the new rear porch. IIICOLLAGE CONS1RUC- ON / ,IJ' cpJSED 4`RvIr Cc, Guaranteed Maximum Price CLARIFICATIONS, ASSUMPTIONS, EXCLUSIONS & ALLOWANCES PROJECT: Lakeshore Community Center Expansion LOCATION: Ocoee,FL SQUARE FEET: 6,125 Addition/8,548 Selective Renovation/2,484 Storage Building ARCHITECT: rhodes+brito ESTIMATOR: K.Kolakowski DATE: 5/4/2018 REV: 4 We have excluded a'fully mechanical means of lighting control as the primary mechanism,with electronic or remote control serving as a secondary mechanism." 37. It is our understanding that the existing underground electrical primary feeding the existing City Hall is not in conflict with any of the new work and will remain in place without need for relocation. 38. In accordance with P-RFI 008 the new utility transformer has not been scheduled for installation yet. It is assumed that the owner wfil schedule this with the local utility,and the transformer will be in place and ready to be powered up prior to the removal of the old utility transformer. DIVISION 31,32&33:EARTHWORK,EXTERIOR IMPROVEMENTS,UTILITIES 39. In accordance with the owner's request the retaining wall alternate has been rejected,and it is understood the owner intends to avoid all site retaining walls by means of grading,and relocation of the telephone vault by others. No cost for site retaining walls is included. 40. New Landscaping and Irrigation is not included. Repairs,modifications and alterations of the existing irrigation system are not included. 41. Unforseen soil remediation is excluded. 42. Construction above or around existing underground installations(including telecommunication lines,plumbing services or electric service lines)is included only to the extent shown within the design documents. GMP Estimate does not warrant that utility service provider will allow for construction around existing installations and no provisions have been included to address restrictions or modify design to accommodate the requirements of existing easements. EXCL Permits&Impact Fees Design Services&Reimbursables Temporary Electric Costs (See Add Alternate) AN Systems,Devices,and Data Cabling(See Add Alternate) Testing and Inspections(See Add Alternate) Access Control or Security Systems Threshold Inspection (See Add Alternate) Furniture,Fixtures and Equipment(FF&E) Geotechnical Consultant Asbestos Survey or Abatement Removal of unknown or buried debris Hoods&Fire Suppression Systems = COLLAGE Co„„,„ ... / riv7 EGE67Er ,Ettvi:ts Guaranteed Maximum Price CLARIFICATIONS, ASSUMPTIONS, EXCLUSIONS & ALLOWANCES PROJECT: Lakeshore Community Center Expansion LOCATION: Ocoee,FL SQUARE FEET: 6,125 Addition/8,548 Selective Renovation 12,484 Storage Building ARCHITECT: rhodes+brito ESTIMATOR: K.Kolakowski DATE: 5/4/2018 REV: 4 ALLOVAN The following allowances have been incorporated into the GMP. Originally figured as additive alternates,these items have been accepted by the owner and are elaborated upon here for clarification. The exact scopes of these allowances are yet to be codified in the project documents and therefor their cost of work is yet to be confirmed. 1.AudioNisual Systems:An allowance of$193,230 has been included and is based upon an initial proposal from an audio visual contractor confirmed acceptable to the owner and in accordance with the 95%plans,as well as their anticipated VE savings involving the re-use of select speakers and other audio-visual devices,cabling and equipment. This price does not include complete demolition&replacement of AV systems. 2.CCTV,CATV,Voice/Data Cabling:an allowance of$35,098 has been Included and is based upon an initial proposal from a contractor confirmed acceptable to the owner and in accordance with the 95%plans,as well as anticipated VE savings involving the re-use of select CCTV cameras and cabling where possible. This price does not include complete demolition&replacement of CCTV,CAN or Voice/Data Cabling and systems. 3.Provide non-carrier HVAC equipment&controls:A"No Cost"allowance has been Included,based upon an initial proposal from a qualified mechanical contractor who has advised an anticipated wash in price to provide York equipment(savings)and a 3rd party controls vendor(added cost)in lieu of the specified Carrier equipment and controls. 4.Relocate Family RR 101 to bridal locker area(Deleted©IT Rm):An allowance of$19,440 has been included based upon input from qualified contractors accounting for the additional work involved in the relocation of the Family Restroom 101,in lieu of it's location within the walls of the existing IT Room as indicated in the 95%plans. 5.Expand Office 102 into exist.Family RR 101:A"No Cost"allowance has been included for this scope of work based upon owner sketches which appear to be nearly identical to the 95%set.This does not include unforseen conditions or requested changes encountered in the course of construction that have not been contemplated in this no cost allowance. 6.An allowance of$50,000 has been included for costs associated with changes in the 100%construction design documents that are still being developed. 7.An allowance of$10,000 has been included for removal&replacement of acoustical ceiling systems and drywall modifications that are likely to be required in the course of audio visual system installations,projectors and projector screen install,and voice/data cabling. UCOLLAGE DOCUMENT LOG CONSTRUCTION•INTEGRATED SERVICES Dated: 5/4/2018 Ocoee Lakeshore Center Expansion Sheet Number Description Sheet Issue Date GENERAL CS001 COVER SHEET 2/14/2018 G100 [ON INDEX—MISSING FROM 95%SET] Not Included G001 DRAWING GUIDE,ABREVIATIONS,INDEX 2/14/2018 G002 PARTITION TYPES 2/14/2018 G003 PARTITION DETAILS 2/14/2018 LIFE SAFETY LS101 FIRST FLOOR LIFE SAFETY PLAN 2/13/2018 LS201 [ON INDEX—MISSING FROM 95%SET] Not Included CIVIL C101 GENERAL NOTES 2/14/2018 C102 DEMOLITION AND EROSION CONTROL PLAN 2/14/2018 C103 SWPP NOTES AND DETAILS 2/14/2018 C200 SITE PLAN 2/14/2018 C201 SITE PLAN 2/14/2018 C300 GRADING AND DRAINAGE PLAN 2/14/2018 C400 SITE UTILITY PLAN 2/14/2018 C500 SITE DETAILS 2/14/2018 C600 CITY OF OCOEE STANDARD DETAILS 2/14/2018 LANDSCAPE L001 LANDSCAPE NOTES 2/6/2018 1100 LANDSCAPE PLAN 2/6/2018 L101 LANDSCAPE DETAILS 2/6/2018 L200 IRRIGATION PLAN 2/6/2018 L201 IRRIGATION SPECIFICATIONS 2/6/2018 L202 IRRIGATION DETAILS 2/6/2018 L203 IRRIGATION DETAILS 2/6/2018 STRUCTURAL S001 STRUCTURAL GENERAL NOTES 11/17/2017 5002 STRUCTURAL GENERAL NOTES 11/17/2017 S201 FOUNDATION PLAN 11/17/2017 S202 ROOF FRAMING PLAN 11/17/2017 S203 FOUNDATION AND SLAB ON GRADE PLAN 11/17/2017 (STORAGE BUILDING) S204 ROOF FRAMING PLAN(STORAGE BUILDING) 11/17/2017 S501 SECTIONS AND DETAILS 11/17/2017 5502 SECTIONS AND DETAILS 11/17/2017 1 UCOLLAGE DOCUMENT LOG CONSTRUCTION•INTEGRATED SERVICES Dated:5/4/2018 Ocoee Lakeshore Center Expansion S503 SECTIONS AND DETAILS 11/17/2017 S504 SECTIONS AND DETAILS 11/17/2017 S505 SECTIONS AND DETAILS 11/17/2017 _ 5506 SECTIONS AND DETAILS 11/17/2017 S507 SECTIONS AND DETAILS 11/17/2017 S508 SECTIONS AND DETAILS 11/17/2017 DEMOLITION AD201 DEMOLITION FIRST FLOOR PLAN 2/14/2018 AD221 REFLECTED CEILING DEMOLITION PLAN 2/14/2018 AD261 ROOF DEMOLITION PLAN 2/14/2018 AD301 BUILDING DEMOLITION ELEVATIONS 2/14/2018 AD302 BUILDING DEMOLITION ELEVATIONS 2/14/2018 AD303 BUILDING DEMOLITION ELEVATIONS 2/14/2018 AD503 WALL SECTION DEMOLITION 2/14/2018 ARCHITECTURAL A101 ARCHITECTURAL SITE PLAN 2/14/2018 A111 ENLARGED SITE PLANS 2/14/2018 A112 SITE DETAILS 2/14/2018 A201 FLOOR PLAN 2/14/2018 A202 DIMENSION PLAN 2/14/2018 A203 STORAGE BUILDING FLOOR PLAN 2/14/2018 _ A221 REFLECTED CEILING PLAN 2/14/2018 A240 ENLARGED FLOOR PLANS 2/14/2018 A241 ENLARGED RESTROOM FLOOR PLANS 2/14/2018 A251 ROOF PLAN 2/14/2018 A261 STORAGE BUILDING ROOF PLAN AND DETAILS 2/14/2018 A271 ROOF DETAILS 2/14/2018 A301 BUILDING ELEVATIONS 2/14/2018 A302 BUILDING ELEVATIONS 2/14/2018 A303 STORAGE BUILDING ELEVATIONS 2/14/2018 A401 BUILDING SECTIONS 2/14/2018 A402 BUILDING SECTIONS 2/14/2018 A403 STORAGE BUILDING SECTIONS AND DETAILS 2/14/2018 A501 WALL SECTIONS 2/14/2018 A502 WALL SECTIONS 2/14/2018 A611 EXTERIOR DETAILS 2/14/2018 A612 EXTERIOR DETAILS 2/14/2018 A621 MILLWORK DETAILS 2/14/2018 A622 MILLWORK DETAILS 2/14/2018 A631 CEILING AND GYP BOARD DETAILS 2/14/2018 A701 OPENING SCHEDULES 2/14/2018 A701A STORAGE BUILDING OPENING SCHEDULES 2/14/2018 (STORAGE BUILDING) A702 WALL SECTIONS(STORAGE BUILDING) 2/14/2018 2 ::COLLAGE DOCUMENT LOG CONSTRUCTION■INTEGRATED SERVICES Dated: 5/4/2018 Ocoee Lakeshore Center Expansion A711 OPENING DETAILS 2/14/2018 —� A712 OPENING DETAILS 2/14/2018 A831 RESTROOM ELEVATIONS 2/14/2018 A832 RESTROOM ELEVATIONS 2/14/2018 A833 RESTROOM ELEVATIONS 2/14/2018 A834 INTERIOR ELEVATIONS 2/14/2018 A836 INTERIOR ELEVATIONS 2/14/2018 A837 INTERIOR ELEVATIONS 2/14/2018 INTERIORS 10101 FINISH PLAN&SCHEDULE -- ID102 FLOOR PATTERN PLAN&ELEVATIONS -- ID601 INTERIOR DETAILS -- ID602 INTERIOR ELEVATIONS AND MILLWORK -- MECHANICAL (LAKESHORE COMMUNITY CENTER EXPANSION) M100 LEGEND,ABBREVIATIONS AND GENERAL NOTES 2/14/2018 MD201 HVAC DEMOLITION 2/14/2018 M201 FIRST FLOOR HVAC 2/14/2018 M202 FIRST FLOOR HVAC PIPING 2/14/2018 M501 DETAIL SHEET 2/14/2018 M601 SCHEDULES 2/14/2018 M700 CONTROLS 2/14/2018 (LAKESHORE STORAGE BUILDING) M101 [ON INDEX—MISSING FROM 95%SET] Not Included M203 HVAC NEW WORK PLAN 2/14/2018 M501 [ON INDEX—MISSING FROM 95%SET] Not Included M502 DETAIL SHEET 2/14/2018 M602 SCHEDULES 2/14/2018 PLUMBING (LAKESHORE COMMUNITY CENTER EXPANSION) P100 GENERAL NOTES,ABBREVIATIONS&LEGENDS 2/14/2018 PD201 PLUMBING DEMOLITION 2/14/2018 P201 SANITARY PLUMBING 2/14/2018 P202 DOMESTIC PLUMBING 2/14/2018 P401 ENLARGED PLUMBING PLANS 2/14/2018 P501 PLUMBING DETAILS 2/14/2018 P601 SANITARY PLUMBING RISER 2/14/2018 P602 DOMESTIC PLUMBING RISER 2/14/2018 (LAKESHORE STORAGE BUILDING) P100 [ON INDEX—MISSING FROM 95%SET] P201 [ON INDEX—MISSING FROM 95%SET] P203 STORAGE BUILDING PLUMBING 2/14/2018 3 ::COLLAGE DOCUMENT LOG CONSTRUCTION■ INTEGRATED SERVICES Dated: 5/4/2098 Ocoee Lakeshore Center Expansion ELECTRICAL E001 ELECTRICAL GENERAL NOTES SYMBOLS AND 11/09/2017 LEGEND ED101 ELECTRICAL DEMO SITE PLAN 11/09/2017 E101 ELECTRICAL SITE PLAN 11/09/2017 ED202 ELECTRICAL POWER DEMO FIRST FLOOR PLAN 11/09/2017 ED203 ELECTRICAL LIGHTING DEMO REFLECTED CEILING 11/09/2017 PLAN E202 ELECTRICAL POWER FIRST FLOOR PLAN 11/09/2017 E203 ELECTRICAL LIGHTING REFLECTED CEILING PLAN 11/09/2017 E301 LIGHTNING PROTECTION PLAN 11/09/2017 E401 ELECTRICAL POWER ENLARGED PLAN 11/09/2017 E501 ELECTRICAL ONE LINE DIAGRAM 11/09/2017 E502 LIGHTING CONTROL SYSTEM RISER DIAGRAM 11/09/2017 E601 ELECTRICAL DISTRIBUTION AND EQUIPMENT 11/09/2017 FEEDER E701 ELECTRICAL SCHEDULES 11/09/2017 E702 ELECTRICAL DETAILS 11/09/2017 E801 ELECTRICAL DETAILS 11/09/2017 E802 ELECTRICAL DETAILS 11/09/2017 E803 ELECTRICAL DETAILS 11/09/2017 ES001 SYSTEMS LEGEND 11/09/2017 ES101 SYSTEMS SITE PLAN 11/09/2017 ESD201 SYSTEMS FIRST FLOOR DEMO 11/09/2017 ES201 SYSTEMS FIRST FLOOR PLAN 11/09/2017 ES202 SYSTEMS REFLECTED CEILING PLAN 11/09/2017 ES401 SYSTEMS ENLARGED PLAN 11/09/2017 ES501 FIRE ALARM MATRIX AND RISER DIAGRAM 11/09/2017 ES502 AV MATRIX AND RISER DIAGRAM 11/09/2017 ES601 SYSTEMS BLOCK DIAGRAMS 11/09/2017 ES701 SYSTEMS RACK LAYOUTS 11/09/2017 ES801 SYSTEMS DETAILS 11/09/2017 FIRE PROTECTION FP100 GENERAL NOTES SYMBOLS&ABBREVIATIONS 2/14/2018 FP201 FIRST FLOOR FIRE PROTECTION 2/14/2018 SPECIFICATIONS PROJECT MANUAL-95%CONST. DOCUMENTS 2/14/2018 OTHER BID Q&A RESPONSES 3/7/2018 4 1 c m N m o g- a L . c • a n1 O m o La o' m m `t ° c o 0 Mo I d o.._- @ -r h 1 = !2 z c rt, o 0 va) 0> m N 7 - g E 0 c - c CI "H w 0 W c I 2 y 0 ,0 .ux aE o O CV, 01.-L-...L-...... @ w 2 2 53 0 Z C ° 2 Ep O co W W o O C W g LZ C y y ad y 7 M u1 la, o •E U m 111 y0 Egto Evl �' )73 Io p .� 8 v '. s § E S o • - Q w c E L ti d' .. ul y U 0 E rn ar a m L° m �° $ m o o m m L w Il w a e a c I ' w v� °a m e .g Z U �Ep : r—j Y3 u ca 0 4. 2 `m ° a c m c m O `o v7 E v n x ] v• Yi E m ; c9 v a ao' ' Ea' ai u� w a V C <n ° .y :2) {AQ �j a) LL ..` y N .0 Cl . '� j d CD p fn �.4I. a E E a' a cc N °° d v a 8 IY V a 0 2 ,, m 0 tn a ti in me a Q a a m m as I CO ao COQm CO COrCO ao ao faro !' a aro ,m goo a03 CO 03 co m m CO !CO co co m m m m m i 6 f `'i 4o r i, as 3 3 i. 3. 1 ' o) b1'ca 6) d) o) b b Z a7 m a7 a7 W W •a) a7 G 7 I C 1 c' r co Ih i O Q 0) '0 O N o, N ,r o N N O CO N m N N N ca .n- c'cj 1 O c6 00 O r O 'M M N N 0 Q Q Q Q Q IIC Q CO m CO CO CO Sao CO CO CO m CO CO mm co I 412 :CO CO CO CO m CO I' m CO mmmW C r r m m m m3 '-) 9 O b b C2 m m cccccccs v e r- r. M - 0) ) N 0 o M M W o m O) m O .- �j O t° 0 O N I N N N M m r = O O M •�- N N O N N O 0 i N NO O M O N A .0 U Ki 0 0 0 0 o e o 0 0 0 0 0 0 0 0 0 0 0 o a X ,e o 0 0 0 0 o e x 0 e e e 0 e at I a) a s U) 5� O 0 0 0 0 0 In o 0 O O o O o 0 0 O o O O i0 jo o O o o O o 'O 'b .O o io �O o O .O ` a) tL E 1_ V 0 0 0 0 0 0 1� 0 0 v 0 U i OU ami O W `o m co C .0 g O O O O O O 10 O O N r M O O In O m Ln O In I, CO M )n O O in O O O O O 4 O O O In O T U M di E ! r r ` r i N r N N r r N N N r N aV lV r- 3 U P2 U 0 0 o 0 32 ."' co O N r ii4 ip b LC) to 0 �n O) 0 N 0 CO1n 0 1n P. O ' N N N 0 N N 0 •IN IN !(V b ) a3 L N .- aVr a) F- TSa ' r !r r r , ' r r ! co 3 I i .0 A 0 o Ia 2 EE c m 7z, o> r I I v .E m H .� E v Z i I . o 'O Z • ° U m N m 8 U c cr O .- N la C c y C O fa \ l�i to m U 5 At = E - > iri m i 2 y W o E d > c p 1L y w a m .� o C v a rn v d co y E D w > W ace _ w`o L° v o • U Z > i t G n. w o > L o l o ! o w 7 w g �C C e 4 �j 0 E a c m c ''c� t ° g `m Z c y I� i e O ' ; > a O � V a re N ° $ U 7 ii C L C a) c o o 0d qa 3 0 0 � 0 3 c $ Z v 2 u) c w U �' = Q 0- g . c c ro ru a i. S a a 2 ° 0.6 N 8 m c co,Hc E o d - `° y N a) X II a x c 0 C7 U ° x c rn i a L m a a Z w L w E c q� $ ' ; Qc qlli E7 w i I° a u. ILL ,,-92 E .� U g '° E m L 7' ° a6 W a U COa N N O y /0 U O �j .� d y I. ' ~ L C .0 to co 0 a. O ` ! 2 cn C V U H € a c a2 m 1 n m m c m a3) m_ m S o a 0 3 3 E E ° o o Q . c m d O a) Z aL C CJ LL X Q' 7 z co Q' 2 (n Z In I.L. C IL C 2 W W Z CI Z U CI LL ¢ Q' CD - a) a 1 O 0 co O Q O O 0 O 0 O O 0 ON rn f1t7 O 8 N O 0 n rn O 0 0 rO Or n N O O M m 8 O 8 ? 8 p m O O N O r -O 8 O O O OO O 0 O O O O ON NO N N N M O O O N N O N N O O O N O O O OI -J O O O OOO OO OOOOO r Nr r r N N M r M M .- N CO CO r N N CO r CO r CO CO +■ i 1 1 1 7 1 a J I J 3 1 3 1 l 1 l 1 1 ] 1 1 1 1 1 1 1 1 1 1 1 1 I 1 1 1 1 co I ° ° E U E 5 i. I a m CO g CqQ! - d 1 m $ o f0 C O O p W Qa O m °i N o 3 j' ° 4) d a) M 2 dE) 711 R o m e ,g o ca a • ca D ry c w 2. U N W C Q LL m LL Q E g c - E N m PI o o • et I. g ti m o : ' La c 'c $r m a • m . NU E E O Q H CO CD ora CD 'CO ;CD 0) O) a) a) 0 1 o o x o o aa)) co a) a) A. z z Q z z o 7 L 4 U) C CO M N 1 V N- N- 0 N O O N N O O ,0 a) OD '60m CO CO Co °) o) I •• t O O al C Q av o z z 41 -`° c w O O N N N co N O O N C 1' wx; e e e e e e e e o e 1° CO ba o 0 0 0 0 0 0 0 0 o CO K CO 0 ' w 3 0 `m U 0 c a) cc a E N N N n N N N O O M T U CO a Oxy a Q v 0' 0 ag N N N f_ N N N p p ICS u) L 3a Y �_. ni I J a a R ao ❑ O O E - N a m > c 1:77 C > C _ 0 7° N LL LL LL N • T o ° ❑ p U Q d a) °) m -0 a) a c a. CES 0 a a LL ° cn▪ a'o o u m p``\ a.c• o U > m o c°//� Q_ 1 ID F `c w c 0 C c o d is I o d .� O !e ;w a E i £ c I ca .ILS ;2o 5 U o f a o a) W U if LU c o c r m E E c < � . —°E cm N o) 0 g u L o 0 x ia- IL 0 � 2 Q o Q 2 Oa O O CO N ? O 2 O Cl)N a) N N N 0 O) O co D O O O CD O O a o a) 0)) �I♦ J I n) C) 0 0 0 e') M e�) O) °) ��